Subject: Application for CAMA Major Development Permit for the Proposed
Replacement of Bridge No. 9 on SR 1112 (Mouth of The Creek Rd) in
Beaufort County, North Carolina; TIP No. B-5614; Federal Aid Project
BRZ-1112 (017); Debit $475 from WBS No. 45569.1.1
Dear Mr. Lane:
The Department requests authorization to replace bridge No. 9 on SR 1112 (Mouth of
The Creek Road) over Blounts Creek.
Please see enclosed copies of the Division of Coastal Management Major Permit Forms 1
and 5, permit plans, buffer plans, and utility plans for the above referenced project. This
project calls for a letting date of April 18, 2023 and a review date of February 8, 2023.
The project schedule may be advanced if funding becomes available.
A Categorical Exclusion was completed in November 2021 and distributed shortly
thereafter. Additional copies are available at the NCDOT website:
https://xfer.services.ncdot.aoy/t)dea/EnvironmentalDocs/Documents/STIP B-ProjectsB-
5614 CE Final 11.05.2021 Signed.pdf
NCDOT requests that the proposed work be authorized under a Coastal Area
Management Act Major Permit. Adjacent riparian landowner certified mail return
receipts will be provided once they are received.
Mailing Address:
NC DEPARTMENT OF TRANSPORTATION TELEPHONE: 919-707-6000 Location:
ENVIRONMENTAL ANALYSIS UNIT Customer Service: 1-877-368-4968 CENTURY CENTER, BUILDING B
1598 MAIL SERVICE CENTER 1000 BIRCH RIDGE DRIVE
RALEIGH NC 27699-1598 Website: www.ncdot.gov RALEIGH NC, 27699
A copy of this permit application will be posted on the NCDOT Website at
https://xfer.services.ncdot.gov/pdea/Perm.Apps/. Should you have any questions
regarding this information, please contact Deanna Riffey at (919) 707-6151 or
driffeyAncdot.gov.
Sincerely,
Piz C ' �-
Chris Rivenbark, Eastern Team Lead
Environmental Coordination and Permitting Group
cc: Cathy Brittingham, NCDCM Raleigh
„. STA7Fa
yo.
GW+
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
ROY COOPER J. ERIC BOYETTE
GOVERNOR SECRETARY
September 7, 2022
Jonathan Kassnove & Howard Pinkham
1441 Boyd Galloway Rd
Grimesland, NC 27837
Dear Landowner:
The North Carolina Department of Transportation is planning to replace bridge number 9 on Mouth of The
Creek Road over Blounts Creek. The proposed project will replace the aging existing structure over Blounts
Creek. The project will replace the existing 600-foot bridge with a 962-foot bridge. The additional length
will allow for the replacement of a substandard structure. The bridge replacement will be on new alignment
to the south of the existing bridge while traffic will be maintained on the existing bridge. This project
crosses an Area of Environmental Concern, as defined by the North Carolina Division of Coastal
Management (DCM), and must be approved by the DCM under provisions of the Coastal Area Management
Act (CAMA). One of the prerequisites to this approval is that adjacent riparian landowners be given an
opportunity to comment on the proposal. The full permit application detailing the work planned, including
vicinity map and site drawings, is enclosed for your review.
The attached form is submitted to ensure that you have an opportunity to comment on the proposal. If you
have no objections to the proposal, please return the form with your response within 30 days to this office.
If you do have objections to the project, please forward your comments to:
Mr. Stephen Lane
N.C. Division of Coastal Management
400 Commerce Ave.
Morehead City, NC 28557
Thank you for your cooperation.
Sincerely,
Chris Rivenbark, Eastern Team Lead
Environmental Coordination and Permitting Group
cc: Mr. Stephen Lane, NCDCM
File — TIP B-5614
Mailing Address: Telephone: (919)707-6000 Location:
NC DEPARTMENT OF TRANSPORTATION Customer Service: 1-877-368-4968 1000 BIRCH RIDGE DRIVE
ENVIRONMENTAL ANALYSIS UNIT Website: www.ncdot.gov RALEIGH NC 27699
1598 MAIL SERVICE CENTER
Ra,LEIGH NC 27699-1598
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
Roy COOPER
GOVERNOR
September 7, 2022
Gerard Alpern Parker, Jr.
504 Country Club Dr
Trent Woods, NC 28562
Dear Landowner:
J. ERic BOYETTE
SECRETARY
The North Carolina Department of Transportation is planning to replace bridge number 9 on Mouth of The
Creek Road over Blounts Creek. The proposed project will replace the aging existing structure over Blounts
Creek. The project will replace the existing 600-foot bridge with a 962-foot bridge. The additional length
will allow for the replacement of a substandard structure. The bridge replacement will be on new alignment
to the south of the existing bridge while traffic will be maintained on the existing bridge. This project
crosses an Area of Environmental Concern, as defined by the North Carolina Division of Coastal
Management (DCM), and must be approved by the DCM under provisions of the Coastal Area Management
Act (CAMA). One of the prerequisites to this approval is that adjacent riparian landowners be given an
opportunity to comment on the proposal. The full permit application detailing the work planned, including
vicinity map and site drawings, is enclosed for your review.
The attached form is submitted to ensure that you have an opportunity to comment on the proposal. If you
have no objections to the proposal, please return the form with your response within 30 days to this office.
If you do have objections to the project, please forward your comments to:
Mr. Stephen Lane
N.C. Division of Coastal Management
400 Commerce Ave.
Morehead City, NC 28557
Thank you for your cooperation.
Sincerely,
Chris Rivenbark, Eastern Team Lead
Environmental Coordination and Permitting Group
cc: Mr. Stephen Lane, NCDCM
File — TIP B-5614
Mailing Address: Telephone: (919) 707-6000 Location:
NC DEPARTMENT OF TRANSPORTATION Customer Service: 1-877-368-4968 1000 BIRCH RIDGE DRIVE
ENVIRONMENTAL ANALYSIS UNIT Wehsite: www.ncdot.gov RALEIGH NC 27699
1598 MAIL SERVICE CENTER
RALEIGH NC 27699-1598
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
ROY COOPER
GOVERNOR
September 7, 2022
James & Mary Lewis
211 WIlliamsburg Rd
Washington, NC 27889
Dear Landowner:
J. ERIC BOYETTE
SECRETARY
The North Carolina Department of Transportation is planning to replace bridge number 9 on Mouth of The
Creek Road over Blounts Creek. The proposed project will replace the aging existing structure over Blounts
Creek. The project will replace the existing 600-foot bridge with a 962-foot bridge. The additional length
will allow for the replacement of a substandard structure. The bridge replacement will be on new alignment
to the south of the existing bridge while traffic will be maintained on the existing bridge. This project
crosses an Area of Environmental Concern, as defined by the North Carolina Division of Coastal
Management (DCM), and must be approved by the DCM under provisions of the Coastal Area Management
Act (CAMA). One of the prerequisites to this approval is that adjacent riparian landowners be given an
opportunity to comment on the proposal. The full permit application detailing the work planned, including
vicinity map and site drawings, is enclosed for your review.
The attached form is submitted to ensure that you have an opportunity to comment on the proposal. If you
have no objections to the proposal, please return the form with your response within 30 days to this office.
If you do have objections to the project, please forward your comments to:
Mr. Stephen Lane
N.C. Division of Coastal Management
400 Commerce Ave.
Morehead City, NC 28557
Thank you for your cooperation.
Sincerely,
Chris Rivenbark, Eastern Team Lead
Environmental Coordination and Permitting Group
cc: Mr. Stephen Lane, NCDCM
File —TIP B-5614
Mailing Address: Telephone: (919) 707-6000 Location:
NC DEPARTMENT OF TRANSPORTATION Customer Service: 1-877-368-4968 1000 BIRCH RIDGE DRIVE
ENVIRONMENTAL ANALYSIS UNIT Website: www.ncdot.gov RALEIGH NC 27699
1598 MAIL SERVICE CENTER
RALEIGH NC 27699-1598
ST�7f„
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
Roy COOPER
GOVERNOR
September 7, 2022
Sema E. Lederman
204 Glennview Place
Chapel Hill, NC 27516
Dear Landowner:
J. ERIC BOYETTE
SECRETARY
The North Carolina Department of Transportation is planning to replace bridge number 9 on Mouth of The
Creek Road over Blounts Creek. The proposed project will replace the aging existing structure over Blounts
Creek. The project will replace the existing 600-foot bridge with a 962-foot bridge. The additional length
will allow for the replacement of a substandard structure. The bridge replacement will be on new alignment
to the south of the existing bridge while traffic will be maintained on the existing bridge. This project
crosses an Area of Environmental Concern, as defined by the North Carolina Division of Coastal
Management (DCM), and must be approved by the DCM under provisions of the Coastal Area Management
Act (CAMA). One of the prerequisites to this approval is that adjacent riparian landowners be given an
opportunity to comment on the proposal. The full permit application detailing the work planned, including
vicinity map and site drawings, is enclosed for your review.
The attached form is submitted to ensure that you have an opportunity to comment on the proposal. If you
have no objections to the proposal, please return the form with your response within 30 days to this office.
If you do have objections to the project, please forward your comments to:
Mr. Stephen Lane
N.C. Division of Coastal Management
400 Commerce Ave.
Morehead City, NC 28557
Thank you for your cooperation.
Sincerely,
Chris Rivenbark, Eastern Team Lead
Environmental Coordination and Permitting Group
cc: Mr. Stephen Lane, NCDCM
File — TIP B-5614
Mailing Address: Telephone: (919) 707-6000 Location:
NC DEPARTMENT OF TRANSPORTATION Customer Service: 1-877-368-4968 1000 BIRCH RIDGE DRIVE
ENVIRONMENTAL ANALYSIS UNIT Website: www.ncdot.gov RALEIGH NC 27699
1598 MAIL SERVICE CENTER
RALEIGH NC 27699-1598
IN MP-1
WFLICATION for
Malor Development Pernift
(last revised 12/27106)
North Carolina DIVISION OF COASTAL MANAGEMENT
1. Primary Applicant/ Landowner Information
Business Name
Project Name (if applicable)
North Carolina Department Of Transportation
B-5614
Applicant 1: First Name
MI
Last Name
Deanna
Riffey
Applicant 2: First Name
MI
Last Name
N/A
N/A
N/A
If additional applicants, please attach an additional page(s) with names listed.
Mailing Address
PO Box
City
State
Environmental Analysis Unit, 1598 Mail Service Center
Raleigh
NC
ZIP
Country
Phone No.
FAX No.
27610
USA
919 - 707 -
6151 ext.
-
Street Address (if different from above)
City
State
ZIP
EAU - Centery Center A, 1000 Birch Ridge Drvie
Raleigh
NC
27610-
Email
driffey@ncdot.gov
2. Agent/Contractor Information
Business Name
N/A
Agent/ Contractor 1: First Name
MI
Last Name
Agent/ Contractor 2: First Name
MI
Last Name
Mailing Address
PO Box
City
State
ZIP
Phone No.1
ext.
Phone No 2
ext.
FAX No.
Contractor #
Street Address (if different from above)
City
State
ZIP
Email
<Form continues on back>
252-803-2808 1-888-4RCOAST ., www.nccoastalmanagament.net
Form DCM MP-1 (Page 2 of 5)
APPLICATION for
Major Development Permit
3. Project Location
County (can be multiple)
Street Address
State Rd. #
Beaufort County
Mouth of the Creek Road
1112
Subdivision Name
City
State
Zip
NA
Blounts Creek
NC
27814 -
Phone No.
Lot No.(s) (if many, attach additional page with list)
- ext.
I I I ,
a. In which NC river basin is the project located?
b. Name of body of water nearest to proposed project
Tar -Pamlico River Basin
Blounts Creek
c. Is the water body identified in (b) above, natural or manmade?
d. Name the closest major water body to the proposed project site.
®Natural ❑Manmade ❑Unknown
Pamlico River
e. Is proposed work within city limits or planning jurisdiction?
f. If applicable, list the planning jurisdiction or city limit the proposed
®Yes ❑No
work falls within.
Beaufort County
4.
Site Description
a.
Total length of shoreline on the tract (ft.)
b. Size of entire tract (sq.ft.)
294
236,713
c.
Size of individual lot(s)
d. Approximate elevation of tract above NHW (normal high water) or
NWL (normal water level)
(If many lot sizes, please attach additional page with a list)
15' ❑NHW or ®NWL
e.
Vegetation on tract
Maintained/Disturbed: Lawns, fields, and roadside shoulders are mostly open with scattered trees such as sweetgum, red
maple, and flowering dogwood; Mesic Mixed Hardwood: bald cypress, black gum, green ash, loblolly pine, wax myrtle,
sweetgum, red maple, jewel weed, lizard's tail, netted chainfern, and Japanese honeysuckle; Pine Plantation: loblolly pine,
American holly, sawtooth blackberry, and laurel leaf smilax: Salt Marsh: smooth cordgrass, small spike false nettle,
needlegrass rush, big cordgrass, narrowleaf cattail, alli atorweed, and water willow.
f.
Man-made features and uses now on tract
Features are: SR1112 (Mouth of the Creek Road, Bridge #9, electric and water utility lines, residential homes.
Uses are: transportation, residential, and recreational.
g.
Identify and describe the existing land uses Jacent to the proposed project site.
Land use in the project study area is a combination of maintained roadsides, residential, and undeveloped natural areas.
h.
How does local government zone the tract?
i. Is the proposed project consistent with the applicable zoning?
Residential
(Attach zoning compliance certificate, if applicable)
®Yes ❑No ❑NA
j.
Is the proposed activity part of an urban waterfront redevelopment proposal? ❑Yes ®No
k.
Hasa professional archaeological assessment been done for the tract? If yes, attach a copy. ®Yes ❑No ❑NA
If yes, by whom? NCDOT Archaeology
I.
Is the proposed project located in a National Registered Historic District or does it involve a ❑Yes ®No ❑NA
National Register listed or eligible property?
<Form continues on next page>
m. (i) Are there wetlands on the site? ®Yes ❑No
(ii) Are there coastal wetlands on the site? ®Yes ❑No
(iii) If yes to either (i) or (ii) above, has a delineation been conducted? ®Yes [:]No
(Attach documentation, if available)
52-808-2808 .. 1-888-4RCOAST .. www.nccoastaismanagement.net
Form DCM MP-1 (Page 3 of 5)
APPLICATION for
Major Development Permit
n. Describe existing wastewater treatment facilities.
N/A
o. Describe existing drinking water supply source.
N/A
p. Describe existing storm water management or treatment systems.
NA - no existing storm water management or treatment systems
5. Activities and Impacts
a.
Will the project be for commercial, public, or private use? ❑Commercial ®Public/Government
❑ Private/Community
b.
Give a brief description of purpose, use, and daily operations of the project when complete.
The proposed bridge replacement will provide an updated creek crossing over Blounts Creek for local commuters.
c.
Describe the proposed construction methodology, types of construction equipment to be used during construction, the number of each type
of equipment and where it is to be stored.
A workbridge will be used to build the new structure. Typical construction equipment insluces crane, excavator, dump trucks,
etc.
d.
List all development activities you propose.
A temporary causeway will be built near the north side of the bridge. Once the new roadway is complete, the existing bridge
and causeway will be removed.
e.
Are the proposed activities maintenance of an existing project, new work, or both? new work -- bridge replacement
f.
What is the approximate total disturbed land area resulting from the proposed project? 1.4 ❑Sq.Ft or ®Acres
g.
Will the proposed project encroach on any public easement, public accessway or other area ®Yes ❑No ❑NA
that the public has established use of?
h.
Describe location and type of existing and proposed discharges to waters of the state.
Existing drainage flow directly off of the existing bridge into Blounts Creek, existing bridge approaches have overland flow
which discharges to Blounts Creek. The proposed drainage will be picked up within 2G1's at the end of bridge and will
discharge to proposed grassed swales which eventually tie in with existing drainage features.
i.
Will wastewater or stormwater be discharged into a wetland? ®Yes ❑No ❑NA
If yes, will this discharged water be of the same salinity as the receiving water? []Yes ®No ❑NA
I.
Is there any mitigation proposed? ®Yes ❑No ❑NA
If yes, attach a mitigation proposal.
<Form continues on back>
6. Additional Information
In addition to this completed application form, (MP-1) the following items below, if applicable, must be submitted in order for the application
package to be complete. Items (a) — (f) are always applicable to any major development application. Please consult the application
instruction booklet on how to properly prepare the required items below.
a. A project narrative.
b. An accurate, dated work plat (including plan view and cross -sectional drawings) drawn to scale. Please give the present status of the
proposed project. Is any portion already complete? If previously authorized work, clearly indicate on maps, plats, drawings to distinguish
between work completed and proposed.
c. A site or location map that is sufficiently detailed to guide agency personnel unfamiliar with the area to the site.
252.308-2308 .. 1-833-4RCt3AST .. vbww.nccoastalmanagennent.nat
Form DCM MP-1 (Page 4 of 5)
APPLICATION for
Major Development Permit
d. A copy of the deed (with state application only) or other instrument under which the applicant claims title to the affected properties.
e. The appropriate application fee. Check or money order made payable to DENR.
f. A list of the names and complete addresses of the adjacent waterfront (riparian) landowners and signed return receipts as proof that such
owners have received a copy of the application and plats by certified mail. Such landowners must be advised that they have 30 days in
which to submit comments on the proposed project to the Division of Coastal Management.
Name See Attached List
Phone No.
Address
Name
Phone No.
Address
Name
Phone No.
Address
g. A list of previous state or federal permits issued for work on the project tract. Include permit numbers, permittee, and issuing dates.
N/A
h. Signed consultant or agent authorization form, if applicable.
i. Wetland delineation, if necessary.
j. A signed AEC hazard notice for projects in oceanfront and inlet areas. (Must be signed by property owner)
k. A statement of compliance with the N.C. Environmental Policy Act (N.C.G.S. 113A 1-10), if necessary. If the project involves expenditure
of public funds or use of public lands, attach a statement documenting compliance with the North Carolina Environmental Policy Act.
7, Certification and Permission to Enter on Land
I understand that any permit issued in response to this application will allow only the development described in the application.
The project will be subject to the conditions and restrictions contained in the permit.
I certify that I am authorized to grant, and do in fact grant permission to representatives of state and federal review agencies to
enter on the aforementioned lands in connection with evaluating information related to this permit application and follow-up
monitoring of the project.
I further certify that the information provided in this application is truthful to the best of my knowledge.
Date 7/.2DA Z Print Name tC�J'�✓vbar�
Signature WA r
Please indicate application attachments pertaining to your proposed project.
❑DCM MP-2 Excavation and Fill Information ®DCM MP-5 Bridges and Culverts
❑DCM MP-3 Upland Development
❑DCM MP-4 Structures Information
252.803-2808 .. 1.888.4RCOAST .. www.nccoastalmanagement.net
Nm AtRMFS
BRIDGES and CULVERTS
Attach this form to Joint Application for CAMA Major Permit, Form DCM MP-1. Be sure to complete all other sections of the Joint
Application that relate to this proposed project. Please include all supplemental information.
1.
BRIDGES
❑This section not applicable
a.
Is the proposed bridge:
b.
Water body to be crossed by bridge:
❑Commercial ®Public/Government ❑Private/Community
Blounts Creek
C.
Type of bridge (construction material):
d.
Water depth at the proposed crossing at NLW or NWL:
Modified Bulb Tee (concrete)
12.0
e.
(i) Will proposed bridge replace an existing bridge? ®Yes ❑No
f.
(i) Will proposed bridge replace an existing culvert? []Yes ®No
If yes,
If yes,
(ii) Length of existing bridge: 600'
(ii) Length of existing culvert:
(iii) Width of existing bridge: 24'
(iii) Width of existing culvert:
(iv) Navigation clearance underneath existing bridge: 15'
(iv) Height of the top of the existing culvert above the NHW or
(v) Will all, or a part of, the existing bridge be removed?
NWL:
(Explain) All of existing bridge will be removed
(v) Will all, or a part of, the existing culvert be removed?
(Explain)
g.
Length of proposed bridge: 962'
h.
Width of proposed bridge: 33'
i.
Will the proposed bridge affect existing water flow? ❑Yes ®No
j.
Will the proposed bridge affect navigation by reducing or
If yes, explain:
increasing the existing navigable opening? ❑Yes ®No
If yes, explain:
k.
Navigation clearance underneath proposed bridge: 15'
I.
Have you contacted the U.S. Coast Guard concerning their
approval? ®Yes ❑No
If yes, explain: Coast Guard Permit will be required.
m.
Will the proposed bridge cross wetlands containing no navigable
n.
Height of proposed bridge above wetlands: NA
waters? ❑Yes ®No
If yes, explain:
2.
CULVERTS
®This section not applicable
a.
Number of culverts proposed:
b.
Water body in which the culvert is to be placed:
< Form continues on back>
C. Type of culvert (construction material):
252-808-2808 :; 1-8884RCOAST .; •w N,,v.ncr-oastaimanagamenb.net revised: 101;26 06
Form DCM MP-5 (Bridges and Culverts, gage 2 of 4)
d. (i) Will proposed culvert replace an existing bridge? e. (i) Will proposed culvert replace an existing culvert?
❑Yes [--]No ❑Yes [:]No
If yes,
(ii) Length of existing bridge:
(iii) Width of existing bridge:
(iv) Navigation clearance underneath existing bridge: _
(v) Will all, or a part of, the existing bridge be removed?
(Explain)
If yes,
(ii) Length of existing cuivert(s):
(iii) Width of existing culvert(s):
(iv) Height of the top of the existing culvert above the NHW or
NWL:
(v) Will all, or a part of, the existing culvert be removed?
(Explain)
f. Length of proposed culvert: 9 Width of proposed culvert:
h. Height of the top of the proposed culvert above the NHW or NWL. i. Depth of culvert to be buried below existing bottom contour.
j. Will the proposed culvert affect navigation by reducing or k. Will the proposed culvert affect existing water flow?
increasing the existing navigable opening? ❑Yes []No ❑Yes ❑No
If yes, explain: If yes, explain:
3. EXCAVATION and FILL [-I This section not applicable
a. (i) Will the placement of the proposed bridge or culvert require any b. (i) Will the placement of the proposed bridge or culvert require any
excavation below the NHW or NWL? []Yes ®No excavation within coastal wetlands/marsh (CW), submerged
If yes, aquatic vegetation (SAV), shell bottom (SB), or other wetlands
(WL)? If any boxes are checked, provide the number of square
(ii) Avg. length of area to be excavated: feet affected.
(iii) Avg. width of area to be excavated: ❑CW ❑SAV ❑SB
(iv) Avg. depth of area to be excavated: ❑WL ®None
(v) Amount of material to be excavated in cubic yards:
(ii) Describe the purpose of the excavation in these areas:
C. (i) Will the placement of the proposed bridge or culvert require any
high -ground excavation? ®Yes ❑No
If yes,
(ii) Avg. length of area to be excavated: 16.5
(iii) Avg. width of area to be excavated: 50
(iv) Avg. depth of area to be excavated: 4_5
(v) Amount of material to be excavated in cubic yards: 150
23:2-508-230 :; 1.888-4 ,,.OAST :; re At N,nccoastaimanagement.net revised. 10.26/06
Form DCNI P-5 (Bridges and Culverts, Page 3 of A)
d. If the placement of the bridge or culvert involves any excavation, please complete the following:
(i) Location of the spoil disposal area: To be determined by Contractor
(ii) Dimensions of the spoil disposal area: To be determined by Contractor
(iii) Do you claim title to the disposal area? ❑Yes ®No (If no, attach a letter granting permission from the owner)
(iv) Will the disposal area be available for future maintenance? ❑Yes []No
(v) Does the disposal area include any coastal wetlands/marsh (CW), submerged aquatic vegetation (SAVs), other wetlands (WL), or shell
bottom (SB)?
❑CW ❑SAV OWL ❑SB ®None
If any boxes are checked, give dimensions if different from (ii) above.
(vi) Does the disposal area include any area below the NHW or NWL? ? []Yes ®No
If yes, give dimensions if different from (ii) above.
e. (i) Will the placement of the proposed bridge or culvert result in any f. (i) Will the placement of the proposed bridge or culvert result in any
fill (other than excavated material described in Item d above) to fill (other than excavated material described in Item d above) to
be placed below NHW or NWL? ®Yes ❑No be placed within coastal wetlands/marsh (CW), submerged
If yes, aquatic vegetation (SAV), shell bottom (SB), or other wetlands
(WL)? If any boxes are checked, provide the number of square
(ii) Avg. length of area to be filled: 32'-6" (per bent - there are feet affected.
7 bents) ®CW 335 ❑SAV ❑SB
(iii) Avg. width of area to be filled: T-6" (diameter) ®WL 15,912 ❑None
(iv) Purpose of fill: proposed bridge bents (ii) Describe the purpose of the excavation in these areas:
Proposed Roadway embankment and bridge
approaches.
g. (i) Will the placement of the proposed bridge or culvert result in any
fill (other than excavated material described in Item d above) to
be placed on high -ground? ®Yes [:]No
If yes,
(ii) Avg. length of area to be filled: 1,1 X
(iii) Avg. width of area to be filled: 40'
(iv) Purpose of fill: proposed roadway embankment
14. GENERAL
a. Will the proposed project require the relocation of any existing b. Will the proposed project require the construction of any temporary
utility lines? ®Yes ❑No detour structures? ❑Yes ®No
If yes, explain: The project includes relocation of power If yes, explain:
lines and telecommunitcations.
If this portion of the proposed project has already received
approval from local authorities, please attach a copy of the
approval or certification.
< Form continues on back>
c. Will the proposed project require any work channels? d. How will excavated or fill material be kept on site and erosion
❑Yes ®No controlled?
If yes, complete Form DCM-MP-2. Design Standards in Sensitive Watersheds will be adhered
to throughout construction
252-8 8-2303 :. 1 383-=4 OAST : w,,vw.nccoastalrnananeznent.net revised: 110126/06
Form DC - (Bridges and Culverts, Page 4 of 4)
e. What type of construction equipment will be used (for example,
dragline, backhoe, or hydraulic dredge)?
temporary work bridge, cranes, excavators, bulldozer
g. Will the placement of the proposed bridge or culvert require any
shoreline stabilization? ❑Yes ®No
If yes, complete form MP-2, Section 3 for Shoreline
Stabilization only.
Se,p4erin6er -7 , a 0 a- 2
Date
6 - SCE ► '-(
Project Name If
C[lriS ��J2v�v�ar
Applicant Name
—M ��
C
Applicant Signature
f. Will wetlands be crossed in transporting equipment to project site?
®Yes ❑No
If yes, explain steps that will be taken to avoid or minimize
environmental impacts.
Safety fence and sediment and erosion control devices
will be installed to delineate the work area and minimize
environmental impacts to additional adjacent features.
252-808-2308 :: 1-888-4RCOA6T :: aw tiw,nccoastair7anat3ement.net revises!: i 03 26i06
tt%Pl\V:'1'1'
North Carolina Department of Transportation ..
Slt?rtl tx�vr_11 tfCi'
Highway Stormwater Program
STORMWATER MANAGEMENT PLAN
oterstan 3 W Released August 20211
FOR NCUOT PROJECTS
WBS Elumem: 4 , i t ......_
...-.._-........w......a ........._._
T TIP(Pr No 3 '.t614 Cou, �(les). 5 A l oit ... ... .... _ _ ._ P t. ........ 1 of Z
_._.......,... _ _.,..... _.. - .. .._ . .. . .._.-.m........._ ..
Generat Project information
WBS Element:
45569.11 ITIP Number: B-5614 Project T e: Brid e Replacement Date: 3/28,2022
NCDOT Contact:
David Stunts. PE
Contractor l Desl ner:
Rabi Robot
Address:
1581 Mail Service Center
Address:
940 Main Campus Drive, Suite 500
Raleigh, NC 27699-1581
Raleigh, NC 27606
Phone:
919)707-6442
Phone:
919 829-0328
Email:
dstults ncdot. ov
Email:
notxrllWOb.com
Ci !Town:
Biounts Creek
Court ies :
Beaufort
River Basins :
Tar Pamlico
CAMA County?
Wetlands within Pro ect Limits?
Yes-
Project De$Grt tlon
Project Length (lin. miles or foot):
0.398 rni. Surroundin Land Use: k Sr er'_tcal, Wixjded, Agriculture
;Pro osed Pr 'act
Exisfin Site
Project Built -Upon Area sc.
1.4
12 IuC
Typical Cross Section Description.
2 g 10' lanes with 2' paved shoulders and 1' grass shoulders (.road) and 2 Cq? 10' lanes
2 C� 10' lanes with 2' paved shoulders and 1' grass shoulders
with 5' paved shoulders (bridge)
Annual Avg Daily Traffic (vehlhrlday):
Desi n•'Future < 1000 Year: 2041 Existing 11000 Year: 2021
General Project Narrative:
Project B-5614 involves the replacement of the existing NCDOT Bridge 9060009 on SR 1112 over Blounts Creak in Beaufort County. Bridge 0060009 is a 601.1' timber dock on
(Description of Minimization of Water
1-breams crested bridge with a 15 span arrangement (14@40.0', 1 @41.1') with vertical timber abutments. The proposed bridge is a 960'. 63" Modred Bulb Tee design with a
Quality Impacts)
8 r@120' span arrangement and 4'-0" end caps. According to the effective Flood insurance Rate Map (FIRM), the study area is located in Zone AE in a Coastal Area
Management Act (CAMA) county. As such, the low chord of the proposed bridge was designed to be at or higher than the low chord of the existing bridge per CAMA county
requirements. There are both CAMA wetlands and 404 wetlands OR the project site, impacts to these are noted on the wetland impact summary table. The project site is also
subject to the Tarr Pamlico Buffer Rules and stormwater outfalls were placed outside of the buffer zones and were provided rip -rap pads to help dissipate energy and to reduce
velocity at all proposed outfalls. No deck drains are required for the proposed bridge.
t i1 �St'il ,
Stornhltair,er
(Version 8"00; Released August 2021)
North Carolina Department of Transportation
Highway Stormwater Program
STORMWATER MANAGEMENT PLAN
FOR NCDOT PROJECTS
4,
WBS Element: 1_i_i TIPIPro" No.: ?+ 5514
_._ __. _ __-____--____. .____ _..,_-___ 1 _. _ _
Coui �ies� Beaufort _..._._. ....------
_ _ _.._ ._.T _._.., .___.—
General Project Information
.._... Page 2
................
Waterbody Information
Surface Water Body _
f3lounts l,reek
NCDWR Stream Index No.:
29-9-1-(3)
NCDWR Surface Water Classification for Water Body
Prima Classification:
Class SB
Su lemental Classification:
Nutrient Sensitive Waters INSW
Other Stream Classification:
None
Impairments:
None
Aquatic T&E Species?
Yes Comments:
1131ounts Creek is classified as an anadiomous fish spawning area
NRTR Stream ID:
Buffer Rules in Effect: Tar -Pamlico
Project Includes Bridge Spanning Water Body?
1yes
Deck Drains Discharge Over Buffer? INo
Dissi ator Pads Provided in Buffer? lNo
Deck Drains Dischar a Over Water Body? INo
y, t0w ihor in tip c naval Project Narrative)
(if yes: provide justification in the. •3eneral Project Narrative)
of yes, describe in the General Project Narrative, if no, justify in the
General Project Narrative)
B-5614
Utilities Narrative
July 281h, 2022
COUNTY: BEAUFORT
STIP: B-5614
VHB Engineering NC, P.C.
DESCRIPTION: Project B-5614 involves the replacement of the existing NCDOT Bridge #060009
on SR 1112 over Blounts Creek in Beaufort County.
The utility conflicts for the subject NCDOT Project are listed below:
TIDELAND EMC AND LUMEN — POWER LINES AND TELEPHONE CABLES
Plans include the construction of Tideland EMC temporary and permanent overhead power
lines and Lumen underground telephone cables. The proposed temporary overhead powerline,
which is located from -L- station 11+97 to 17+92 LT will require less than .01 AC of hand clearing
in wetlands. The proposed permanent overhead power lines from -L- 12+02 to 17+91 RT will
require 0.14 AC of hand clearing in wetlands. A portion of this hand clearing is in buffer zones; it
will result in 203 SF of impact in Buffer Zone one and 105 SF of impact in Buffer Zone two.
These proposed power lines and telephone cables will also create additional buffer impacts due
to trenching operations from -L- 17+62 to 18+12 LT. Trenching work will require 834 SF of
impact in Buffer Zone one, and 197 SF in Buffer Zone 2.
BEAUFORT COUNTY WATER
According to the utility coordination, two 8" water lines will be relocated on both sides of the
proposed bridge from station -WL- 5+10 to 8+73 and station -WL2- 5+00 to 8+77. The existing
waterlines within these limits will be abandoned. The proposed waterlines will not create
additional wetland or buffer impacts outside of impacts covered in the Bridge Replacement
environmental permit.