Loading...
HomeMy WebLinkAboutDC00339 - Living Shoreline Precon_Meeting Minutes STATE OF NORTH CAROLINA DEPARTMENT OF TRANSPORTATION ROY COOPER J. ERIC BOYETTE GOVERNOR SECRETARY September 23, 2022 Contract No.: DC00339 WBS Element: 49083.3.1 Federal Aid No.: Federal Provisions Tip No.: M-0540A County: Onslow Subject: Shoreline Stabilization, Environmental Resiliency – PRE-CONSTRUCTION MEETING MINUTES The following items were discussed at the August pre-con meeting (meeting notes in red). Introductions: · Name and Job Title – (See attached sign in sheet) Safety: · All personnel are responsible for safety · Required PPE include – Steel / Composite Toe Boots, Safety Vest, Backup Alarms · Traffic Control will adhere to 1101.02 or TMP plans · Work Zone Traffic Control Certificate Required General Information about Project · Date of Availability: September 19, 2022 · Date of Overall Completion: June 15, 2024 · Project Amount: $1,697,687.00 · Project description: NC 24 CAUSEWAY BETWEEN THE SWANSBORO BRIDGES & CEDAR POINT · Projected start date: October 10th, 2022 Lines of Communication · NCDOT o Resident Engineer:  Daniel Waugh  dgwaugh1@ncdot.gov  910-467-0520 o Project Inspector:  Greg Frame  gframe@sepiinc.com  910-238-9648 · Contractor o Project Manager: Justin Hill o Project Superintendent: Jamie Allen o General Superintendent: Steven Salter · Estimate Period o Preferred Day: End of month Overall Contract ICT · Date of Availability: September 19, 2022 · Completion Date: June 15, 2024 · Liquidated Damages: Two Hundred Dollars ($200.00) per calendar day ICT #1 – All Work Except PVE · Except for that work required under the Project Special Provisions entitled Planting, Reforestation and/or Permanent Vegetation Establishment, included elsewhere in this proposal, the Contractor will be required to complete all work included in this contract and shall place and maintain traffic on same. · The date of availability for this intermediate contract time is September 19, 2022. · The completion date for this intermediate contract time is April 15, 2023. · The liquidated damages for this intermediate contract time are Eight Hundred Fifty Dollars ($ 850.00) per calendar day. ICT #2 – Traffic Restrictions · The Contractor shall not close or narrow a lane of traffic on NC 24 during the following time restrictions: MONDAY THROUGH SUNDAY 6:00AM - 9:00AM & 3:00PM - 6:00PM · In addition, the Contractor shall not close or narrow a lane of traffic on NC 24, detain and/or alter the traffic flow on or during holidays, holiday weekends, special events, or any other time when traffic is unusually heavy, including the following schedules: 1. For unexpected occurrence that creates unusually high traffic volumes, as directed by the Engineer. 2 thru 8 .– See SP page 2 & 3. Restriction included for - Holidays and holiday weekends shall include New Year's, Easter, Memorial Day, Independence Day, Labor Day, Thanksgiving, and Christmas. The Contractor shall schedule his work so that lane closures will not be required during these periods, unless otherwise directed by the Engineer. · The time of availability for this intermediate contract work shall be the time the Contractor begins to install all traffic control devices for lane closures according to the time restrictions listed herein. · The completion time for this intermediate contract work shall be the time the Contractor is required to complete the removal of all traffic control devices for lane closures according to the time restrictions stated above and place traffic in the existing traffic pattern. · The liquidated damages are Eight Hundred Fifty Dollars ($ 850.00) per hour. ICT #3 – Wetland Planting · The Contractor shall complete the required work of Wetland Grass Planting, as shown on the plans, as directed by the Engineer and within any seasonal limitations for the specific task included herein. · The date of availability for this intermediate contract time is April 15, 2023. · The completion date for this intermediate contract time is June 15, 2023. · The liquidated damages are Eight Hundred Fifty Dollars ($ 850.00) per day. PROJECT SPECIAL PROVISIONS - GENERAL PERMANENT VEGETATION ESTABLISHMENT: · Overall Contract time includes 1 year period to warranty Wetland Plantings. · ICT Acceptance will be dependent on Wetland Planting acceptance. · SOD will be monitored during separately. Major Contract Items · Line Item #14: Class II RIP RAP Specialty Items · Line Item # 11-12: Guardrail · Line Item # 16-19: Signing · Line Item # 29-31, 33: Long-Life Pavement Markings · Line Item # 36-37: Permanent Pavement Markers · Line Item # 38-39, 42-43: Erosion Control · Line Item # 45: Planting Price Adjustment · Fuel Price Adjustment o The base index price for DIESEL #2 FUEL is $ 4.5239 per gallon o Items available for fuel price adjustment (Pg. 5) Required Documents to be Submitted · Proof of required insurance (Submitted) · Progress Schedule and Narrative (To be submitted) · List of Subcontractors o DBE Goal: 3% o DBE Commitment: 6.97% o CUF (Commercially Useful Function) Report will be required (SP Pg. 14) o Submit SAF in order need on the project: Will not pay estimate if SAF not in  Committed: 1. Jerry T. Bunn Trucking: $ 118,300.00 o Certified Federal Payrolls o Job Bulletin onsite with all Federal Posters (Possibly on business side of NC24 -TBD) o Wage Interviews – 1 per quarter- Prime and EA subcontractor o Title VI and Nondiscrimination  Submit two subcontracts: DBE / NON-DBE with signatures.  Federal Requirements: 1. Post NCDOT’s Notice of Nondiscrimination and the Contractor’s own Equal Employment Opportunity (EEO) Policy in conspicuous locations accessible to all employees, applicants and subcontractors on the jobsite. 2. Physically incorporate the required Title VI clauses into all subcontracts on federally-assisted and state-funded NCDOT projects, and ensure inclusion by subcontractors into all lower-tier subcontracts. 3. Required Solicitation Language. The Contractor shall include the following notification in all solicitations for bids and requests for work or material, regardless of funding source: “The North Carolina Department of Transportation, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat. 252, 42 US.C. §§2000d to 2000d-4) and the Regulations, hereby notifies all bidders that it will affirmatively ensure that any contract entered into pursuant to this advertisement, disadvantaged business enterprises will be afforded full and fair opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, or national origin in consideration for an award. In accordance with other related nondiscrimination authorities, bidders and contractors will also not be discriminated against on the grounds of sex, age, disability, low-income level, creed/religion, or limited English proficiency in consideration for an award.” USE OF UNMANNED AIRCRAFT SYSTEMS · The Contractor shall adhere to all Federal, State and Local regulations and guidelines for the use of Unmanned Aircraft Systems (UAS). Equipment Idling Guidelines · Exercise reduced fuel consumption and reduced equipment emissions during the construction of all work associated with this contract. Employees engaged in the construction of this project should turn off vehicles when stopped for more than thirty (30) minutes and off-highway equipment should idle no longer than fifteen (15) consecutive minutes. · Sheet 19 for guidelines CARGO PREFERENCE ACT · Privately owned United States-flag commercial vessels transporting cargoes are subject to the Cargo Preference Act (CPA) of 1954 requirements and regulations found in 46 CFR 381.7. Contractors are directed to clause (b) of 46 CFR 381.7 as follows: (see page 21) EROSION AND SEDIMENT CONTROL/STORMWATER CERTIFICATION: · National Pollution discharge Elimination System (NPDES) permit for the work is required. · Provide a certified Erosion and Sediment Control/Stormwater Supervisor, Foreman and Installer to manage the Contractor and subcontractor operations, ensure compliance with Federal, State and Local ordinances and regulations, and manage the Quality Control Program. (To be provided) WORK ZONE INSTALLER: · Provide the service of at least one qualified work zone installer during the setup, installation, and removal of temporary traffic control within the highway right of way. The qualified work zone installer shall serve as crew leader and shall be on site and directing the installation and removal of temporary traffic control. If multiple temporary traffic control installations or removals are occurring simultaneously, then each shall have a qualified work zone installer. (To be provided) · The work zone installer shall be qualified by an NCDOT approved training agency or other approved training provider in the safe and competent set up of temporary traffic control. For a complete listing of approved training agencies, see the Work Zone Safety Training webpage. PROJECT SPECIAL PROVISIONS - ROADWAY NOTES TO CONTRACTOR: · Monitoring for the presence of shellfish species (oysters, clams, mussels, etc.) will be performed just prior to construction along the proposed footprint of the granite sill. Any shellfish that are present will be relocated just offshore of the construction and sill footprint. (Coastal Fed. To survey) (Stroud Engineering to mark limits) · All new rip rap will be granite material. · Borrow material will be classified as dead marine sand, sample will need to be provided to Engineer for approval prior to placement. (Sample of current material and borrow material to be provided by NCDOT) · Grading, handling, moving, placing, shaping of existing limestone Rip Rap to accommodate proposed typical sections will be incidental to LS grading. · Temporary Access plan will be submitted to the Engineer 30 days prior to installation for approval. Construction of earthen causeway will not be allowed for temporary access, except at proposed access points and with approval by the Engineer. · Existing Utilities shall not be disturbed. Contractor shall adhere to all OSHA requirements in regard to Overhead Electrical Lines. Contractor will coordinate with Duke Energy for Rip Rap placement around existing guy wires and poles. 7 days’ notice minimum, with meeting onsite with Duke Representative prior to work. Further guidance and contact information will be provided. (TA Loving to coordinate) · Contractor will install Safety Fence around all Wood poles, Existing hydrants and Telecommunication Pedestals to clearly mark these locations during construction. · Lane closures associated with material deliveries and construction of this project will be incidental to all other items. · The permittee shall limit in-water work between February 1 to June 30 of any year to the maximum extent practicable to protect juvenile fishes that may be in the vicinity and shall also limit in-water work to the maximum extent practicable from April 1 through October 31 to avoid additional impacts to submerged aquatic vegetation (SAV) · The authorized structure and associated activity must not interfere with the public’s right to free navigation on all navigable waters of the United States. No attempt will be made by the Permittee to prevent the full and free use by the public of all navigable waters at or adjacent to the authorized work for reasons other than safety. ADA COMPLIANT PEDESTRIAN TRAFFIC CONTROL DEVICES & PEDESTRIAN TRANSPORT SERVICE: · Pedestrian Transport Service plan narrative, drop-off, pick-up locations will be submitted to the Engineer for approval prior to closing the sidewalk. Drop-off and pick-up locations shall not be located within the work zone, must be located away from traffic and provide ADA accessible access to pedestrians. (Submit transport service plan prior to closing sidewalk) · The Contractor shall provide a Pedestrian Transport Service through and/or around the project when a traversable, firm, stable, and slip-resistant path for pedestrians cannot be maintained through the work area. At minimum, the Pedestrian Transport Service shall be on-call 24 hours per day Monday thru Sunday and operate at no-cost to the users. BURNING RESTRICTIONS: · Open burning is not permitted on any portion of the right-of-way limits. SIDEWALK, CONCRETE CURB & GUTTER · Quantity has been provided to repair existing curb, gutter and sidewalk that has been previously damaged due to erosion. A quantity has been established to replace what is needed for construction access. It is not the intention to replace all onsite. Care should be taken to protect Sidewalk, Curb and Gutter where possible. OYSTER STRUCTURE · Provide subcontractor information and method of construction. (NCDOT aware of pre- qualification requirement – please let us know when submitted so that we can follow up with Central.) TREE PROTECTION FENCE · Place tree protection fence around any to be saved and all utility poles, hydrants, etc. FABRIC INSERT INLET PROTECTION DEVICE (HIGH FLOW) · Insert Inlet Protection Device, of the type specified, in inlet structures (catch basins, drop inlets, etc) in areas where asphalt or concrete may prevent the proper installation of a Rock Inlet Sediment Traps Type C, or as directed. Submit product data to Engineer for approval prior to installation. (To be submitted) WETLAND GRASS PLANTING · The Contractor shall be responsible for taking sufficient soil samples for testing by the North Carolina Department of Agriculture and Consumer Services, Agronomic Division, Soil Testing Section, to determine the soil pH and nutrient content. Samples shall be taken in the presence of the Engineer. Results shall be received by the Engineer directly from the North Carolina Department of Agriculture and Consumer Services. The Contractor shall be responsible for the addition of fertilizer and/or other soil amendments as needed to ensure livability of the wetland grass planting. (Grass plantings are long lead time items -6 months, supplier “Lumber River” ordering material early will be essential to make the planting window.) PROJECT SPECIAL PROVISIONS – PERMITS (Please see permit conditions included in contract, some errors occurred transferring verbiage) CAMA Major Permit Condition(s): · The permittee shall limit in-water work between February 1 to June 30 of any year to the maximum extent practicable to protect juvenile fishes that may be in the vicinity and shall also limit in-water work to the maximum extent practicable from April 1 through October 31 to avoid additional impacts to submerged aquatic vegetation (SAV). · All temporary fill within wetlands and waters of the State where no stone currently exists shall be placed on geotextile fabric to facilitate total removal of the temporary fill upon completion of the project. · Turbidity curtains shall be used where practicable to isolate all in-water work areas from the adjacent waters of the White Oak River, including but not limited to installation and removal of the temporary construction trestle and temporary access ramps, and placement of fill material within or adjacent to wetlands or waters of the State. The turbidity curtains shall be of sufficient length and effectiveness to prevent a visible increase in the amount of suspended sediments in adjacent waters. The turbidity curtains shall be properly maintained and retained in the water until construction is complete. The turbidity curtains shall be removed when turbidity within the curtains reaches ambient levels. · Prior to planting, the permittee shall submit a final planting plan for the authorized Coastal Wetland planting areas in writing to DCM for review and approval. The planting plan shall include a list of proposed species as well as identify different planting zones. DEQ · The permittee shall limit in-water work between February 1 to June 30 of any year to the maximum extent practicable to protect juvenile fishes that may be in the vicinity and shall also limit in-water work to the maximum extent practicable from April 1 through October 31 to avoid additional impacts to submerged aquatic vegetation (SA V). · In accordance with commitments made by the permittee, in order to protect the endangered West Indian Manatee, Trichechus manatus, the permittee shall implement the U.S. Fish & Wildlife Service's · The permittee shall notify the N.C. Division of Marine Fisheries (DMF) Shellfish Sanitation and Recreational Water Quality Section at 252-726-7021 before any fill activity occurs due to the potential for runoff or turbidity that could necessitate the need for a temporary closure within the vicinity. · In accordance with commitments made by the permittee, the permittee shall conduct a survey for shellfish within authorized fill areas prior to construction. · The authorized temporary construction trestle shall be elevated a minimum of 2 feet above the normal high water level of the White Oak River as measured from the low chord of the structure. · Material excavated at the project site may be used in fill areas associated with the project or shall be removed from the site and taken to a high ground location. (Waste site to be submitted) · All construction equipment access shall be through the use of existing high ground areas, temporary construction · trestles and two temporary access ramps. · Construction staging and stockpile areas shall be located staging only in area, upland and not areas, in on any the wetlands authorized or waters of the temporary State outside construction of the trestle, authorized or within impact the areas. · The installation of piles for the temporary construction trestle shall be accomplished by use of pile to utilize driving and/or another the type use of of pile a vibratory installation, hammer. additional Should the authorization permittee from and/or DCM its shall be contractor required. USAMCE · The Permittee shall install and maintain, at his expense, any safety lights and signals prescribed by the U.S. Coast Guard, through regulations or otherwise, on authorized facilities. It is recommended, at a minimum, the completed structure be equipped with reflective structures on both ends to ensure safe navigation within the vicinity of the structure. (Permit requires PVC pipe at 50’ On Center with yellow reflective tape 3’ above mean high water) · The permittee will adhere to the Submerged Aquatic Vegetation (SAV) Monitoring Plan, Version 3, dated May 4, 2022 (attached) with the following modification to the “Section 4 Proposed Mitigation and Monitoring Plan” found on page 9: · The permittee shall employ all sedimentation and erosion control measures necessary to prevent an increase in sedimentation or turbidity within waters and wetlands outside the permit area. This shall include, but is not limited to, the immediate installation of turbidity curtains, silt fencing or similar appropriate devices around all areas subject to soil disturbance or the movement of earthen fill, and the immediate stabilization of all disturbed areas. Additionally, the project must remain in full compliance with all aspects of the Sedimentation Pollution Control Act of 1973 (North Carolina General Statutes Chapter 113A Article 4). Additional items discussed: · Onsite Environmental Meeting with all permitting Agencies scheduled for Oct 6. · No moratorium for this project, permit condition request contractor limit in water work to the extent possible. · Access points are permitted where shown on the plans, no additional access points will be granted. · DIV Environmental will coordinate a separate meeting to discuss implementing NCDOT required actions to meet permit conditions. · Contractor proposes 3 phase construction · Contractor proposes Access Trestle supported on mats vs. pile supported, DEPT and NCDCM has concern about the Mat Supported trestle meeting the permit conditions. Contractor to submit proposal, sketch, and pictures. This method was used to construction living shoreline at CCC in Morehead City. Further discussions to be held. · Contractor request clarification no shifting traffic. Griding vs Water blasting paint markings. DEPT requires water blasting on bridge. Contractor expresses concern about performing traffic shift in one night due to paint not adhering to wet surface. DEPT allows removal of paint/poly on bridge 24 hours prior to traffic shift to allow surface to dry. Remove no more markings than needed. · Contractor request direction on re-striping the entire bridge. DEPT will review budget as this item of work becomes available. · Contractor express concern about deleting center turn lane. Proposes delineators on double yellow line. DEPT will review traffic concerns once temporary traffic pattern is in place to determine if this necessary. Delineators are not currently part of the TMP plans requirements. · Town of Swansboro advises of upcoming events: o Mullet Festival Oct 7 to Oct 9 o Candlelight event - Saturday Nov 12th o Holiday Festival – Friday Nov 25th DC00339 Preconstruction Meeting attendees NAME TITLE FIRM EMAIL / PHONE Daniel Waugh Resident Engineer NCDOT dgwaugh1@ncdot.gov Kyle Champion Assist. Resident Engineer – TEA NCDOT ktchampion@ncdot.gov Josh Allen Engineer of Record SWCA joshua.allen@swca.com Shawn Gurdry Operations Manager PSS sgurdry@performancestriping.com Hannan Sprinkle DWR NCDOT Hydro hannan.sprinkle@ncdenr.gov Brian Lipscomb Engineer - AOR NCDOT blipscomb@ncdot.gov / (919) 745-7553 Jamie Allen Superintendent T. A. Loving jallen@taloving.com / (910) 340-3667 Sarah Zajovits Sandbar Oyster Co. sarah@sandbaroystercompany.com Shane Lofton Engineering Tech NCDOT salofton@ncdot.gov Morgan Rudd Coastal Ecologist Native Shorelines morgan@nativeshorelines.com Lexia Weaver Coastal Scientist NC Coastal Federation lexiaw@nccoast.org / (252) 393-8185 Sean Farrell Division 3 Environmental NCDOT scfarrell@ncdot.gov Anneliese Westphal NCDOT Environmental Specialist NCDOT awestphal@ncdot.gov / (910) 341-2037 Grace Riley NCDOT Intern NCDOT kgriley@ncdot.gov Paula Webb Swansboro Town Manager Town of Swansboro pwebb@ci.swansboro.nc.us Aliette Cuadro Swansboro Deputy Clerk Town of Swansboro acuadro@ci.swansboro.nc.us Dwayne Taylor Chief of Police Town of Swansboro dtaylor@ci.swansboro.nc.us Brad Haste Onslow Maintenance Engineer NCDOT blhaste@ncdot.gov Stephen Lane NCDCM Representative NCDCM Stephen.Lane@ncdenr.gov Tank Bates Director of Public Works – Swansboro Swansboro gbates@ci.swansboro.nc.us / (540) 809-9665 Pawel Jasinski Engineering Tech NCDOT pjasinski@ncdot.gov Justin Hill Project Manager T. A. Loving jehill@taloving.com / (919) 922-0348 Greg Frame CEI - SEPI/TranSystems SEPI/TranSystems gframe@transystems.com / (910) 238-9648