Derita Branch Sanitary Sewer Improvements Project
18. Nature of Activity
A Woman -Owned Small Business
NCDOT DBE/WBE #49220
Established in 19951
The overall purpose of the project is to replace and upsize the existing Derita Branch sewer line.
The main line will be upsized from 8", 12" and 15" lines to 18", 24" and 30" lines. The new lines
will be made of DIP and C-900 DR25 PVC pipes. The line will be installed by open -cut and by boring.
The line is approximately 18,000 feet long, has 5- and 6-foot diameter manholes, and will have a
six -foot -wide trench. The sewer line will be dug in place. Existing aerial sewers and piers will be
removed and the new larger pipe will be laid through wetlands and under Derita Branch and its
unnamed tributaries to the creek. There will no longer be exposed pipe and piers at the creek
crossings. This will reduce the risk of pipe failure from wash outs and sanitary sewer spills. No
structures will be constructed on fill piles or platforms. It is estimated that approximately 3,900
cubic yards of bedding stone will be used around the sewer pipe in the wetlands. This is in order
to support and stabilize the pipe. The remaining portion of the ditch will be filled using native soil
that was dug from the ditch. The top 12 inches of the wetland topsoil will be removed, stockpiled
and replaced. The wetlands will be reseeded with wildlife friendly, native species. In order to
match the preconstruction contours, the excess soil displaced by the pipe and bedding stone will
be hauled off.
In the wetlands, it is estimated that approximately:
Total trench volume = 84,300 CY
Topsoil to be removed, stockpiled and replaced = 1,185 CY
Bedding stone = 3,901 CY
Pipe will displace approximately 1,007 CY
Dirt fill in addition to topsoil = 78,207 CY
Approximately 4,908 CY of soil will need to be hauled off
19. Project Purpose
The overall need is to replace aged and failing infrastructure since the existing sewer is under
capacity. It also has high levels of infiltration and inflow. The existing sewer was built in the
1960's and 1970's and the manholes leak groundwater. The creek has meandered and is putting
the sewer pipe at risk of being exposed and falling into the creek. Construction is projected to
begin in early spring 2023, and the project will take approximately 18 months to complete.
STREAM AND WETLAND DELINEATION AND RESTORATION - RESTORATION PLANTING - RAIN GARDEN, POND, AND WATER QUALITY BMP
INSPECTION AND MAINTENANCE - MITIGATION MONITORING - INVASIVE SPECIES MANAGEMENT - 404/401 WATER QUALITY PERMITTING
THREATENED AND ENDANGERED SPECIES SURVEYS - SITE INSPECTION - NC, SC, & VA LICENSED GROUND PESTICIDE APPLICATORS
SEDIMENT AND EROSION CONTROL DEVICE INSPECTION - SUPPLIER OF NATIVE TREES, SHRUBS, AND PLANTS - NORTH CAROLINA
LICENSED HIGHWAY CONTRACTOR - NC LICENSED LANDSCAPE CONTRACTOR -A WOMAN OWNED SMALL BUSINESS - NCDOT WBE #49220
CELEBRATING A PROUD HISTORY OF ENVIRONMENTAL EXCELLENCE!
20. Reason(s) for Discharge
The backfilling of the sewer trench was described in detail for question 18. Nature of Activity.
Clayey soil and rock will be excavated, removed from the trench and hauled off -site. It is estimated
that approximately 3,900 cubic yards of bedding stone will be used around the sewer pipe in the
wetlands. This is in order to support and stabilize the pipe. The remaining portion of the ditch
will be filled using native soil that was dug from the ditch. The top 12 inches of the wetland topsoil
will be removed, stockpiled and replaced. In order to match the pre -construction contours, the
excess soil displaced by the pipe and bedding stone will be hauled off. The original contours will
be restored. Erosion control devices will be used per state requirements. We do not anticipate
any basins to be constructed.
21. Type(s) of Material Being Discharged and the Amount of Each Type in Cubic Yards.
Clayey soil and rock will be removed and hauled off -site. The new sewer trench will have stone
bedding and native soil backfill as described in question 18. The top 12 inches of the wetland
topsoil will be removed, stockpiled, and replaced. The wetlands will be seeded with wildlife
friendly, native species.
In the wetlands, it is estimated that approximately:
Total trench volume = 84,300 CY
Topsoil to be removed, stockpiled and replaced = 1,185 CY
Bedding stone = 3,901 CY
Pipe will displace approximately 1,007 CY
Dirt fill in addition to topsoil = 78,207 CY
Approximately 4,908 CY of soil will need to be hauled off
22. Surface Area in Acres of Wetlands or Other Waters Filled
In all wetland areas the contractor will clear the trees within the permanent and temporary
easements and install erosion control measures. The contractor will bring in pipe, manholes and
bedding stone, excavate the soil with a backhoe, and place the new pipe and manholes. Excess
materials will be removed from the site and the wetlands will be restored to their original
contours. The area within the temporary easement will self -restore over time and will not need
to be maintained. Erosion control devices will be removed once ground cover is established. This
will occur in all wetland locations on the project.
23. Description of Avoidance, Minimization, and Compensation
The existing sewer crosses Derita Creek and unnamed tributaries many times. The new alignment
will cross the stream fewer times and will reduce operational impacts to the stream. Existing aerial
lines will be buried below the creek bottom. The alignment was selected to avoid streams and
ponds as much as possible and to follow the general drainage basin of the existing sewer.
STREAM AND WETLAND DELINEATION AND RESTORATION - RESTORATION PLANTING - RAIN GARDEN, POND, AND WATER QUALITY BMP
INSPECTION AND MAINTENANCE - MITIGATION MONITORING - INVASIVE SPECIES MANAGEMENT - 404/401 WATER QUALITY PERMITTING
THREATENED AND ENDANGERED SPECIES SURVEYS - SITE INSPECTION - NC, SC, & VA LICENSED GROUND PESTICIDE APPLICATORS
SEDIMENT AND EROSION CONTROL DEVICE INSPECTION - SUPPLIER OF NATIVE TREES, SHRUBS, AND PLANTS - NORTH CAROLINA
LICENSED HIGHWAY CONTRACTOR - NC LICENSED LANDSCAPE CONTRACTOR -A WOMAN OWNED SMALL BUSINESS - NCDOT WBE #49220
CELEBRATING A PROUD HISTORY OF ENVIRONMENTAL EXCELLENCE!
Mitigation will be provided through the purchase of credits from the Charlotte -Mecklenburg
Storm Water Services Umbrella Stream and Wetland Mitigation Bank. Additional on -site
mitigation will be performed to recreate the emergent wetlands that were previously impacted
by sewer line installation and restoring forested wetlands to the portions of the former sewer
right-of-way that are to be abandoned. The purchase of wetland credits and conducting on -site
mitigation is being performed to avoid Individual Permitting and qualify for a Nationwide Permit
#58.
24. Provide any background on any part of the proposed project already completed. Describe the
area already developed, structures completed, any dredged or fill material already discharged,
the type of material, volume in cubic yards, acres filled, if a wetland or other waterbody (in
acres or square feet). If the work was done under an existing Corps permit, identity the
authorization, if possible.
The Phase 1 portion of the project has been permitted (SAW-2021-02426). The Phase I Derita
Branch Tributary Sanitary Sewer Improvements Project corridor alignment starts from the
existing sanitary sewer located in a grassed area next to Little Sugar Creek and north of Cullman
Avenue, within a contaminated industrial site. The corridor extends to the east, parallel to Little
Sugar Creek and crosses perpendicular under Little Sugar Creek and into a forested upland. A
branch line of the sewer crosses Derita Branch to tie to the existing sewer. The sewer corridor
then extends between Derita Branch and existing development to North Tryon Street. The Phase
2 portion of the project extends north from the Phase 1 portion of the project.
25. Addresses of Adjoining Property Owners, Lessees, Etc., Whose Property Adjoins the Waterbody
11
Mecklenburg County ABC Board
3333 N Tryon St Charlotte NC 28206
12
Linda Hudson, trustee of the Ann Harper
Youree trust
200 Atando Ave Charlotte NC 28206
13
Deborah Welch & Kelly Melazzo
Frew Rd Charlotte NC 28206
14
Cathy M Welch
3311 Frew Rd Charlotte NC 28206
15
TPM Properties LP
Eugene Rodney Orr
3816 Mooreland Farms Rd Charlotte NC
28226
16
Frew Road Greenway LLC
PO Box 11936 Charlotte NC 28220
17
Ground Thunder Properties LLC
PO Bos 791096 Charlotte NC 28206
18
Phillip Teller & Amy Li Matlock
510 Johnson Rd Charlotte NC 28206
19
Mecklenburg County
600 E 4" St 11" Floor Charlotte NC 28202
20
Hornet Properties LLC
5154 Kodiak Ct Charlotte NC 28215
21
Mecklenburg County
600 E 4" St 11" Floor Charlotte NC 28202
22
Budd Investment Properties
2325 S Stratford Rd Winston Salem NC
271013
23
Mecklenburg County
600 E 4'h St Charlotte NC 28202
24
BKT Enterprises LP
420 Devega Dr Lexington SC 29073
25
Mecklenburg County C/O Real
estate/Finance Dept
600 E 4" St 11" Floor Charlotte NC 28202
STREAM AND WETLAND DELINEATION AND RESTORATION - RESTORATION PLANTING - RAIN GARDEN, POND, AND WATER QUALITY BMP
INSPECTION AND MAINTENANCE - MITIGATION MONITORING - INVASIVE SPECIES MANAGEMENT - 404/401 WATER QUALITY PERMITTING
THREATENED AND ENDANGERED SPECIES SURVEYS - SITE INSPECTION - NC, SC, & VA LICENSED GROUND PESTICIDE APPLICATORS
SEDIMENT AND EROSION CONTROL DEVICE INSPECTION - SUPPLIER OF NATIVE TREES, SHRUBS, AND PLANTS - NORTH CAROLINA
LICENSED HIGHWAY CONTRACTOR - NC LICENSED LANDSCAPE CONTRACTOR -A WOMAN OWNED SMALL BUSINESS - NCDOT WBE #49220
CELEBRATING A PROUD HISTORY OF ENVIRONMENTAL EXCELLENCE!
26
Mecklenburg County C/O Real
estate/Finance Dept
600 E 4th St 11th Floor Charlotte NC 28202
27
Ermer Real Estate Holdings LLC
4143 Merlane Dr Charlotte NC 28206
28
KT Tradings LLC
9222 Monroe Rd Charlotte NC 28270
29
Wesley Nathan Fox & Audrey G Fox
4000 Wilson Ln Charlotte NC 28206
30
F9 Properties, LLC P/K/A Ano LLC
4840 Reagan Dr Charlotte NC 28206
31
Pinnacle Towers Inc C/O PMB 353
4017 Washington Rd McMurray PA 15317
32
Ameritruck Real Estate Holdings LLC
4725 N 1-85 Service Rd Charlotte NC 28269
33
Cannon Ave — Charlotte LP
24151 Ventura Blvd Ste 150 Cakabasas CA
91302
34
Tforce Freight Inc F/K/A Overnite
Transportation Co Inc
5200 Graham St Charlotte NC 28203
35
Ameron Property Management LLC
PO Box 480700 Charlotte NC 28269
36
Grant F Harris, Executor for the Estate of
Peggy P. Harris
5146 Princess St Charlotte NC 28206
37
Michael P Williams
5142 Princess St Charlotte NC 28269
38
Caralee Brenna Murphy & Everett Murphy
5209 Princess St Charlotte NC 28269
39
City of Charlotte
600 East 4th St Charlotte NC 28202
40
Lifespan, Inc. F/K/A St. Marks Center, Inc.
1801 Oak St Charlotte NC 28206
41
H C Smith
PO Box 775 Wadesboro NC 28170
42
Greg Adam Fishman
5411 Dutchess St Charlotte NC 28269
43
Louis G. Ratcliffe Inc F//K/A Sugaw
Corners, LLC
N. Graham St Charlotte NC 28206
44
Zippy Land Holdings LLC
5701 N Graham St Charlotte NC 28269
54
Emmanuel Loaeza Diaz & Karina Lizbeth
Sifuentes Garcia
824 W Craighead Rd Charlotte NC 28206
53
IZMIR, LLC
3101 N. Tryon St Charlotte, NC 28206
56
Greenhouse Corners, LLC
5630 N. Graham St. Charlotte, NC 28269
STREAM AND WETLAND DELINEATION AND RESTORATION - RESTORATION PLANTING - RAIN GARDEN, POND, AND WATER QUALITY BMP
INSPECTION AND MAINTENANCE - MITIGATION MONITORING - INVASIVE SPECIES MANAGEMENT - 404/401 WATER QUALITY PERMITTING
THREATENED AND ENDANGERED SPECIES SURVEYS - SITE INSPECTION - NC, SC, & VA LICENSED GROUND PESTICIDE APPLICATORS
SEDIMENT AND EROSION CONTROL DEVICE INSPECTION - SUPPLIER OF NATIVE TREES, SHRUBS, AND PLANTS - NORTH CAROLINA
LICENSED HIGHWAY CONTRACTOR - NC LICENSED LANDSCAPE CONTRACTOR -A WOMAN OWNED SMALL BUSINESS - NCDOT WBE #49220
CELEBRATING A PROUD HISTORY OF ENVIRONMENTAL EXCELLENCE!