HomeMy WebLinkAboutNCC223390_Site Plan or Location Map_20220930STAGE 4 CONSTRUCTION SEQUENCE 1. CONTINUE TO MAINTAIN EROSION CONTROL DEVICES. 2. THE CONTRACTOR SHALL CONTINUE TO CONDUCT SELF -INSPECTIONS OF THE EROSION AND SEDIMENT CONTROL MEASURES AND COMPLETE THE FOLLOWING COMBINED SELF -INSPECTION FORM FOUND ON THE DEMLR WEBSITE; (HTTP:HDEQ.NC.GOV/ABOUT/DIVISIONS/ENERGY-MINERAL-LAND-RESOURCES/EROSION-SEDIMENT-CONTROL/FORMS). COMPLETE INSPECTIONS FORMS SHALL BE KEPT ON -SITE AND AVAILABLE FOR INSPECTION AT ALL TIMES. IT IS RECOMMENDED THAT A COPY BE KEPT IN A PERMITS BOX. SELF -INSPECTIONS FOR STABILITY AND FUNCTION OF EROSION AND SEDIMENTATION CONTROL MEASURES ARE TO BE PERFORMED AT LEAST ONCE EVERY SEVEN CALENDAR DAYS AND WITHIN 24 HOURS OF EACH RAINFALL EVENT OF GREATER THAN 0.5 INCH. ANY NEEDED REPAIRS SHALL BE MADE IMMEDIATELY TO MAINTAIN MEASURES AS DESIGNED. ALL EROSION AND SEDIMENTATION CONTROL MEASURES SHALL BE MAINTAINED AS SPECIFIED IN THE CONSTRUCTION DETAILS ON THIS PLAN. A RAIN GAUGE SHALL BE INSTALLED AT THE PROJECT SITE FOR MONITORING. 3. A COPY OF THE EROSION AND SEDIMENT CONTROL PERMIT, A HARD COPY OF THE PLAN, AND ALL SELF -INSPECTION RECORDS MUST BE KEPT ON -SITE, PREFERABLY IN A PERMITS BOX, AND ACCESSIBLE AT ALL TIMES FOR INSPECTION. 4. CONTINUE SITE FINE GRADING. INSTALL ADDITIONAL EROSION CONTROL MEASURES AS REQUIRED. 5. BEGIN CURB AND GUTTER, CONCRETE, PAVEMENT AND BUILDING CONSTRUCTION. 7. CONTINUE STORM DRAINAGE SYSTEM, OTHER SITE UTILITY, AND PUBLIC UTILITY EXTENSION CONSTRUCTION. INSTALL INLET PROTECTION AROUND ALL INLETS AND "SILT SACKS" INSIDE OF INLET AS STORM DRAINAGE SYSTEM IS CONSTRUCTED. ONCE SUB -BASE HAS BEEN ADDED TO ALL PAVED AREAS, REMOVE INLET PROTECTION AROUND INLETS AND MAINTAIN "SILT SACKS" INSTEAD. CONTRACTOR SHALL UTILIZE AN 8'x10' SILT BAG FOR ANY UTILITY TRENCH DEWATERING OPERATIONS. 8. RESEED/STABILIZE DISTURBED AREAS IMMEDIATELY AFTER GRADES HAVE BEEN ACHIEVED. TEMPORARY VEGETATIVE COVER SHALL BE PROVIDED WITHIN 7 DAYS ON PERIMETER AREAS AND SLOPES GREATER THAN 3:1. TEMPORARY VEGETATIVE COVER SHALL BE PROVIDED WITHIN 14 DAYS ON ALL OTHER AREAS. PERMANENT GROUNDCOVER SHALL BE ESTABLISHED IN 15 WORKING DAYS OR 90 CALENDAR DAYS, WHICHEVER IS SHORTER. \q HOWEVER, NPDES GROUNDCOVER REQUIREMENTS TAKE PRECEDENCE. i 9. CONTINUE TO MAINTAIN EROSION CONTROL MEASURES UNTIL VEGETATIVE COVER HAS BEEN ESTABLISHED OVER ALL DISTURBED AREAS AND SITE HAS BEEN STABILIZED. REMOVE EROSION CONTROL MEASURES ONLY AFTER FINAL INSPECTION AND APPROVAL BY INSPECTOR. 10. WHEN THE PROJECT IS COMPLETE, THE PERMITTEE SHALL CONTACT DEMLR TO CLOSE OUT THE E%SC PLAN. AFTER DEMLP INFORMS THE PERMITTEE OF THE PROJECT CLOSE OUT, VIA INSPECTION REPORT, THE PERMITTEE SHALL VISIT deq.nc.gov/NCGO1 TO SUBMIT AN ELECTRONIC NOTICE OF TERMINATION (e-NOT). A $100 ANNUAL - - - \ GENERAL PERMIT FEE WILL BE CHARGED UNTIL THE e-NOT HAS BEEN FILLED OUT. 460 465 468 \ \ 467 \ \ \ \ v A A Ad] V / v BLDG 2 v 23 2 \V v FFE=468.00S� �v \ \ �� 0vv /v 2// 1 00 I I 4j4o0 2 I01 3 / 1 sF sF-^ W W W 3 / O �� SF�G S� SF_ SF� W / / / / SF� 1% 7 467 - - - 4 $ 469 470 iw / 0 n v �P �� �� / / / / \\ 20 / �7 A 21v v 09 0 V / �9� ® LffiI / m BLDG/300 v v A FFE �471.20 14 10 < 1 \ WELL F LSF F �- ` \ \ \ F- S - - - _ \ v \ SF� SF - - - - - - - - P �i F )USE A SF _ P - A o A v SF_ SF - - - _P_ - - - - -- _�- SF -TF sF � ��-P -s�� sF --'� SF AV A 461.99 111V v - - - s SF- sF--SF s�'L� \ 461.20 (INV) \ aF�sF --_ _W - _ _ sF--sF s�� v - �� T -- T - T - T==- _ AS V T - - M FM _ _ F- T 46g.p2 a 46g - \ V / - - _- -- - T - - T - - TT p F II FM M -i -F1b1- F�-CnT-iINV �8 FM F� rIV' SF� SF_ SF SF -SF- SF- SF� SF SF- SF- SF F4W- - - _ _ \ PAVED D�W SF� SF_ - = T �L- �P FM \ sF\ sF sF-y sF- SF � sF� sF� 7� \ \ �7N� \\ \\ \\ \ \ l \ - FM__ _ sF \ - V / _ CONTROL NAIL/ WAD 83-2011 �_ N = 942,452.374 ( sft) sF� F 98 E = 2,162,483.407 ( sft) STORM DIsF� s lz sF� ��� 7 � �I� s�� ELEV. = 468.79 ( NAVD-88) 467.53 TOP)) sF� F�� F� �� 465.10 (( INV) FICj SF �- \ / IUD sF` \ - - I O \ / .- _ � - / /IT T Aso- PR 1302 qD SF l• e�lC R SF� SF A4 r ��, N 5a5�• SF� v M 40 SF 7 ' PAVE �F v EM �FM sF�v I / SF�= / CI ONTROL NAIL/ WAD 83-2011 pABNEY RD CH SITE DATA m OWNER/: RED OAK APARTMENTS, LLC a o DEVELOPER 6749 LAKE DALE WAY CLEMMONS, NORTH CAROLINA27012 PHONE: (336) 880-3300 FAX: (336) 454-6190 MATT RAAB email: matt.raab@wynnefieldproperties.com p�L�NRD ENGINEER: ALLIED DESIGN, INC. SITE 4720 KESTER MILL ROAD WCREEK RD WINSTON-SALEM, NC 27103 RE�OPKRO PHONE: (336) 765-2377 uSNWY15s FAX: (336) 760-8886 HiL�SipEWAY STEVE M. CAUSEY, P.E. e email: scausey@allied-engsurv.com �o TEMPORARY SKIMMER SEDIMENT BASIN #1 DISTURBED AREA=4.85 AC DRAINAGE AREA=4.85 AC REQ'D VOLUME=8,730 CF Q10=CxlxA (0.35x5.5 IN/HRx4.85 AC)=9.3 CFS REQ'D SURFACE AREA=Q10x325 9.3x325=3,023 SF SURFACE AREA LENGTH=130' SURFACE AREA WIDTH=78' WEIR LENGTH=8.8' (REQUIRED) WEIR LENGTH=10' (PROVIDED) OUTLET STRUCTURE UTILIZED FOR WEIR BOTTOM OF BASIN=455.00 SURFACE AREA=461.00 TOP OF DAM=462.00 DEPTH OF STORAGE=6.0' SURFACE AREA PROVIDED=3,058 SF SURFACE AREA ELEVATION=455.68 VOLUME PROVIDED=8,768 CF VOLUME ELEVATION=457.30 2.0" SKIMMER W/ 1.50" ORIFICE DEWATERING TIME=4.13 DAYS 3:1 SIDE SLOPES 10' EMBANKMENT WIDTH 4 %a5 VICINITY MAP NOT TO SCALE NOTE: DIVERSION BERMS MAY REQUIRE ADDITIONAL CUT OR FILL IN ORDER TO PROPERLY DIVERT RUNOFF. 4 olk� EROSION CONTROL LEGEND ALL SYMBOLS NOT SHOWN EVERY SHEET TEMPORARY CONSTRUCTION ENTRANCE/EXIT. - SF- SF- TEMPORARY SEDIMENT FENCE. SgfflSF_ TEMPORARY SEDIMENT FENCE WITH STONE - STABILIZATION. ?)) TEMPORARY DIVERSION BERM. TREE LINE. TEMPORARY SKIMMER SEDIMENT BASIN. TEMPORARY COIR, JUTE, OR BURLAP BAFFLES. TEMPORARY EMERGENCY SPILLWAY. �y TEMPORARY SKIMMER DEVICE. j${ OUTLET STABILIZATION PAD. CTEMPORARY STONE CHECK DAM. TEMPORARY WIRE AND STONE INLET FILTER. INLET FILTER SHALL STAY IN PLACE UNTIL CURB AND SUBBASE IS INSTALLED. ONCE CURB AND SUBBASE IS INSTALLED FILTER SHALL BE REMOVED AND "SILT SACK" SHALL REMAIN. - - - - DISTURBED LIMITS. TEMPORARY 18" CPP SLOPE DRAIN, SLOPE DRAINS SHALL BE INSTALLED/RE-INSTALLED ON SLOPES AT 8' INTERVALS MEASURED VERTICALLY. TEMPORARY ON -SITE CONCRETE WASHOUT ®� STRUCTURE WITH LINER NEAR CONSTRUCTION ENTRANCE. PROVIDE CLEARLY MARKED SIGNAGE NOTING DEVICE LOCATION. POSSIBLE TEMPORARY STOCKPILE/STORAGE/STAGING AREA. TEMPORARY EROSION CONTROL MATTING FOR TEMPORARY DIVERSION BERM. PROVIDE CHANNEL LINING NAG S75 WITH STAPLE PATTERN D. EXISTING STUMPING/GRUBBING/STRIPPING. O# DIVERSION BERM NUMBER. �# SWALE NUMBER. GRAPHIC SCALE 20 40 so ( IN FEET ) 1 inch = 40 ft. 160 M 0 Z N � Q Z_ J U 0 U E Q 0 � o J Q 4.O p r- � N .W z � J Z N co a � W 00 a) W -6 w �Q - co= Z_ w U) co r- 70 O U)ZC(o � a) J Y 0 Co . 0- LL FIRM LICENSE C-1891 0%111111:i'J'pf ESSRp, iy 701 ��s•'FHc � Ems' f rr M . C P 4y I- U Z Z J J J O Lu Q U ¢O Q 0� a Y 0 O Z Q Q p Z O Q O Or- W Lu LU Z LLI I..L = 0 U04 Q 0 > U) N N 0 0 O Z U m Z Wbi m 0 w Y O Q w d 0 0 U z O w w w w o Q W z W z W Df U 0 z 0 z z w = z O U O w o H H LL O w � Lu 0_ a a w O W 0 O W 0 a 0 LL 0 W C Ln W S2 (n W ir (n W ir W Q N N N N N N O0 , O , '� , , WO O z M<1 C) o STAGE 5 EROSION CONTROL PLAN ya��l C2.7