Loading...
HomeMy WebLinkAbout20140944 Ver 1_Updated_Impact_Tables_20141016CAROLINA ECOSYSTEMS, INC. October 14, 2014 3040 NC 42 West, Clayton NC 27520 P:919- 606 -1065 — F:919 -585 -5570 Ms. Karen Higgins 1617 Mail Service Center Raleigh, NC 27699 -1617 RECEIVED RE: Response to Additional Info Request for Project # 14 -0944 OCT 16 2014 South Fork Basin Improvements DENR -LAND QUALITY Forsyth County, North Carolina STORMWATER PERMITTING Dear Ms. Higgins; Carolina Ecosystems, Inc. (CEI) has been in discussion with Sue Homewood of the Winston - Salem Regional Office related to the above referenced project. The purpose of this letter is to provide responses to Ms. Homewood's questions as well as revised plans and permit information for review and issuance of a 401 Certification for this project. A copy of this information is also being provided to the US Army Corps of Engineers for their review and possible modification of the 404 Permit for this project. The sections below summarize our discussion points (in bold) regarding the South Fork Basin Improvements PCN, along with our team's responses (in italics). Also, a stream impact table with additional information, a map showing the permanent stream crossings in relation to access points for maintenance, and revised figures and plans from the original PCN have been attached. Within the stream impact table, new columns have been highlighted with a bold outline, and revised information is shown in red. On the major crossings (e.g. South Fork Muddy and Salem Creeks), was boring/drilling evaluated? If so, please provide additional justification on why it is not practical. Trenchless methods, while often non - invasive to the surface waters, often require large construction areas, cost exceedingly more than conventional open -cut methods, and still pose some risk of disturbing the bottom of the creek or stream. The presence of rock can complicate the trenchless method as well. The designers always consider trenchless methods for utility crossings with these and other factors in mind. For this project, traditional open -cut was the most practical method of crossing the streams and tributaries. Also, given the size of the pipelines being installed, a trenchless jack and bore method would require a welded steel casing pipe, further reducing the cover between the top of the pipe and the bottom of the stream. In some cases along the gravity sewer project, this method might daylight the pipe in the bottom of the tributary streams and not meet minimum separation requirements. How will the large (see above) stream crossings be built? Will coffer dams and dewatering be implemented? Will coffer dams be constructed in stages? Coffer dams will be phased as shown in Detail E on Sheet D03 of the Muddy Creek WWTP Influent Transfer Force Main plan set. Construction will occur in two phases and the stream will be dewatered while allowing stream flow to continue uninterrupted in a portion of the channel. Ms. Karen Higgins October 14, 2014 Page 2 of 4 Permanent stream crossings on South Fork interceptor lines: Is the riprap outlet protection needed? If so can it be limited to the banks rather than bed ,of the channel similar to what NCI OT does with pipe crossings? If not, the riprap in the bed will be counted as a permanent impact. NCDENR Land Quality requires bottom and some bank stabilization downstream of culverts to prevent erosion For this project, it is most likely that the main creek channel will be approaching bank full conditions when the culverts in the tributary streams experience high volume of flow from upstream, creating a backwater condition NCDENR LQ typically requires the consultant.to design for a 10 year storm, flow through a culvert with free discharge, regardless of backwater conditions Therefore, we provide a detail for stabilization of the bottom and side slopes of the channel to prevent erosion. Under a free discharge condition, the water coming through the pipe will create a pool at the culvert's outlet which will eventually erode back under the outlet of the pipe, undermining the culvert Providing a permanent measure to prevent erosion an the bottom of the channel is important to prevent this. Our calculations have determined that reticulated concrete block matting (armorflex for example) will absorb the higher discharge shear stress in these locations Reticulating block matting is also easier and less invasive to install in streams with active or standing water Whale it is more beneficial to water quality to allow the stream to return to its normal conditions downstream of the culverts, our past experience with obtaining a LQ permit has required permanent measures downstream of culverts in order to obtain the LQ permit The block matting will be installed at the bed elevation of the stream in order to not block aquatic passage We are revisiting each crossing to determine if there is any more room to minimize this impact — this will be updated in the revised plans Can the permanent stream crossings be limited to 15 feet? If not, please provide additional justification for the wider,access requirement. Crossings are designed for 20 feet as the tributary streams being crossed are relatively incased (often 5 or more feet deep) Therefore, in order to place the pipe in the bed of the stream and provide adequate cover with stable slopes, additional maintenance area width is required to allow for a 1 S ft permanent access path over the pipe Are the permanent stream crossings only in areas where maintenance access is impractical due to lack of alternative access points? As can be seen on the attached map showing the permanent stream crossing locations and permanent access locations for maintenance, the stream crossings requiring permanent culverts are in locations that do not have easy access for maintenance The one exception is the eastern most crossing, which is located near Old Salisbury Road This location has a very short run to be maintained, and without a crossing would require excessive mobilization and demobilization to maintain the upper section of the corridor as a separate unit Ms. Karen Higgins October 14, 2014 Page 3 of 4 Provide a list of the stream crossings that are not perpendicular (75 to 105 degrees) and justification for them. Stream crossings were made perpendicular (between 75 and 105 degrees) to the maximum extent practical As can be seen on the attached table, only 9 of the 24 crossings are outside the recommended range Of these, only 3 are more than 10 degrees out (below 65 or above 115 degrees) Shifting the lanes to create perpendicular crossings was not practical as this project parallels or replaces existing lines in primarily already disturbed corridors Shifting the proposed line to accommodate this requirement would result in increased impacts and wider construction corridors Identify all locations where the construction corridor is within 10 feet of the bank of the main stem streams. The construction corridor is within 10 feet of the stream bank in two locations SF Sheet C6 Station 59 +50 — the proposed line has been shifted away from the existing line in this location to maximize distance from the stream Shifting further away is impractical as there is a confluence point of a small side channeljust'upstream of the current construction corridor. This would increase impacts and potentially cause bank instability in the area between the two channels. The existing pipe will be abandoned in place in this area leaving a concrete pipe buried between the stream and the new pipe. This will actually provide added protection to the new installation as the stream meanders over, time. SF Sheet C36 & 37 — a small tributary stream is within the existing sewer corridor in this location. As stated in the permit application, construction will not impact the stream. Notes will be added to the drawings directing the Contractor to not impact the stream or its banks in this area. -See below for additional protection measures at this location. At Site 21 (Sheets C36 and 37), consider dewatering the stream when construction is directly adjacent to the channel in order to prevent water - quality violations during construction. An example permit condition is provided. The contractor will be required to avoid the stream channel when installing the pipe parallel to it during construction We will incorporate the proposed dewatering language onto the drawings as a note for additional' measures of protection in this area The example dewatering language will be used as a basis for this note If you have any questions or need additional information please contact me at your earliest convenience at (919) 606 -1065 or phil.may @carolinaeco.com. Sincerely, Carolina Ecosystems, Inc. Philip May Senior Environmental Scientist Ms. Karen Higgins October 14, 2014 Cc. John Thomas — USACE Raleigh Regulatory Office Ron Hargrove, Utilities Director, City of Winston -Salem Terry Cornett, P.E., Black & Veatch Mary Sadler, P.E., Hazen & Sawyer, Inc. Attachments: Table 1 - Stream Impact Summary (Revised) Figure: Permanent Stream Crossings Figure 3: Impact Locations (Revised) Figure 4: Impact Sites (Revised) Engineering Plans — South Fork Interceptor (Revised) Page 4 of 4 Table 1: Stream Impact Summary Table Impact Site # PCN Impact Original Plan Sheet (Station Number) Plan Sheet (Station Number) Stream Crossing Angle Type of Impact Stream ID Stream Name Perennial or Intermittent Type of Jurisdiction Stream Width (ft) Original Total Impact (ft) Original Permanent Impact (ft) Original Temproary Impact (ft) Revised Total Impact (ft) Revised Permanent Impact (ft) Revised Temproary Impact (ft) Riprap Impact (ft) 2 S1 SF -05 (48 +95) SF -05 (48 +95) 75 Culvert Installation SAJ UT 1 to South Fork Muddy Creek Intermittent Corps 3 53 20 33 53 20 25 8 3 S2 SF -C6 (58 +17) SF -C6 (58 +17) 105 Excavation and Backfill SAG UT 2 to South Fork Muddy Creek Perennial Corps 4 44 0 44 44 0 44 6 S3 SF -C10 (90 +41) SF -C10 (90 +41) 115 Culvert Installation SAF UT 3 to South Fork Muddy Creek Intermittent Corps 7 56 20 36 56 20 26 10 7 S4 SF -C12 (111 +35) SF -C12 (111 +35) 110 Culvert Installation SAE UT 4 to South Fork Muddy Creek Intermittent Corps 4 55 20 35 55 0 55 8 S5 SF -C13 (120 +72) SF -C13 (120 +72) 80 Culvert Installation SAD UT 5 to South Fork Muddy Creek Perennial Corps 6 61 20 41 61 0 61 10 S6 SF -C16 (155 +81) SF -C16 (155 +81) 115 Culvert Installation SAC UT 6 to South Fork Muddy Creek Perennial Corps 7 56 20 36 56 20 26 10 11a S7 SF -C18 (178 +18) SF -C18 (178 +18) 145 Culvert Installation SAB UT 7 to South Fork Muddy Creek Intermittent Corps 3 60 20 40 48 0 48 12 S8 SF -C19 (186 +41) SF -C19 (186 +41) 105 Culvert Installation SAA UT 8 to South Fork Muddy Creek Intermittent Corps 2 60 24 36 60 20 32 8 17 S9 SF -C30 (3 +28) SF -C28 (3 +28) 125 Excavation and Backfill Sv UT 9 to South Fork Muddy Creek Perennial Corps 5 52 0 52 52 0 52 18 S10 SF -C31 (16 +6S) SF -C29 (16 +65) 8S Excavation and Backfill SY UT 10 to South Fork Muddy Creek Intermittent Corps 8 40 0 40 40 0 40 19 S11 SF -C33 (37 +90) SF -C31 (37 +90) 80 Excavation and Backfill SX UT 11 to South Fork Muddy Creek Intermittent Corps 3 33 0 33 33 0 33 20 S12 SF -C36 (60 +75) SF -C34 (60 +75) 105 Excavation and Backfill SU UT 12 to South Fork Muddy Creek Perennial Corps 5 69 0 69 69 20 41 8 21 S13 SF -C38 (19 +51) SF -C36 (19 +51) 100 Excavation and Backfill SW UT 13 to South Fork Muddy Creek Intermittent Corps 3 36 0 36 36 0 36 22 S14 MC -0O2 (13 +75) MC -0O2 (13 +75) 75 Excavation and Backfill SA Muddy Creek Perennial Corps 4S 48 0 48 48 0 48 23 S15 MC -0O2 (15 +88) MC -0O2 (15 +88) 115 Excavation and Backfill SAS UT to Muddy Creek Intermittent Corps 3 1 49 0 49 49 0 49 24 S16 MC -005 (48 +75) MC -005 (48 +75) 90 Excavation and Backfill SA Muddy Creek Perennial Corps 50 40 0 40 40 0 40 25 S17 MC -005 (49 +80) MC -CO5 (49 +80) 80 Excavation and Backfill SAO UT 1 to Salem Creek Intermittent Corps 1 58 0 58 58 0 58 26 S18 MC -008 (79 +27) MC -008 (79 +27) 110 Excavation and Backfill SAO UT 2 to Salem Creek Intermittent Corps 1 42 0 42 42 0 42 27 S19 MC -009 (82 +13) MC -009 (82 +13) 130 Excavation and Backfill SAP UT 3 to Salem Creek Intermittent Corps 2 56 0 56 56 0 56 29 S20 MC -C12 (114 +50) MC -C12 (114 +50) 7S Excavation and Backfill SAT UT 4 to Salem Creek Intermittent Corps 3 31 0 31 31 0 31 30 S21 MC -C13 (121 +63) MC -C13 (121 +63) 105 Excavation and Backfill SAU UT 5 to Salem Creek Perennial Corps 3 40 0 40 40 0 40 33 S22 MC -C17 (165) MC -C17 (16S) 8S Excavation and Backfill SAR UT 6 to Salem Creek Intermittent Corps 3 40 0 40 40 0 40 34 S23 MC -C18 (176 +50) MC -C18 (176 +50) 90 Excavation and Backfill SA Salem Creek Perennial Corps 45 40 0 40 40 0 40 36 S24 MC -C22 (208 +75) MC -C22 (208 +75) 8S Excavation and Backfill SA Salem Creek Perennial Corps 45 40 0 40 401 0 40 Totals I 1 1,159 144 1,015 1,147 1 100 1,003 44