HomeMy WebLinkAbout20181033 Ver 1_Owen Farms Repairs_20220916
Hamilton, Ryan
From:Davis, Erin B
Sent:Friday, September 16, 2022 11:43 AM
To:Hamilton, Ryan
Subject:FW: \[External\] Owen Farms Repairs (SAW-2018-01165)
Attachments:Owen Farms 2022 Repair Photo Log.pdf; Owen Farms 2022 Repair Figure.pdf
Follow Up Flag:Follow up
Flag Status:Flagged
Laserfiche Upload: Email & Attachments
DWR#: 20181033 v.1
Doc Date: 9/16/22
Doc Type: Mitigation Remediation Plans
Doc Name: General topic of email title
From: Furr, Benjamin <Ben.Furr@davey.com>
Sent: Friday, September 16, 2022 8:53 AM
To: Kim Browning <Kimberly.D.Browning@usace.army.mil>
Cc: Alex Digeronimo <Alex.Digeronimo@davey.com>; Kevin Williams <KWilliams@davey.com>; Tisdale, Jessica
<jessica.tisdale@hdrinc.com>; Leslie, Andrea J <andrea.leslie@ncwildlife.org>; Davis, Erin B <erin.davis@ncdenr.gov>;
Wiesner, Paul <paul.wiesner@ncdenr.gov>
Subject: \[External\] Owen Farms Repairs (SAW-2018-01165)
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Kim
Per our conversation last week, I wanted to provide you with a summary of our plan to complete additional bank repairs
at the Owen Farms Mitigation Site this fall/winter. Erosion is primarily occurring on streambanks that have poor
vegetative coverage. We plan to repair/stabilize approximately 355 LF of stream bank through the use of sod mats and
boulder toe. Standard construction equipment will be used to complete the repairs (i.e. excavator and off-road hauler).
The attached figure depicts the strategy that will be used at each bank repair location. A photo log is also attached that
shows current conditions at each repair location. Sod mats will be collected from on-site within the existing easement.
Areas where sod mats are collected and other areas disturbed during construction will be seeded and replanted. We
estimate needing a total of ~100 sq. yds. of sod mat.
This work will be completed under the existing Nationwide Permit 27 and Erosion Control Permit for the Site. We are
currently coordinating with a construction contractor to determine the repair schedule. Once finalized, we will submit a
written request for a waiver of the trout moratorium from WRC for purposes of completing repair work and minimizing
erosion on-site.
Thank you and please let me know if you have any questions or comments.
Benjamin Furr | Senior Consultant
Davey Resource Group, Inc.
1
3101 Poplarwood Court, Suite 120, Raleigh, NC 27604
P: 919.645.4350 ext. 4354 | M: 919.588.9663
Visit our local office page
2
Owen Farms Mitigation Site Photographic Documentation
Repair Areas 9-15-2022
1
P1: Bank erosion between Station 10+00 and 10+50
P2: Looking upstream at eroded right bank near Station 11+00
Owen Farms Mitigation Site Photographic Documentation
Repair Areas 9-15-2022
2
P3: Bank erosion slightly upstream from P2
P4: Looking downstream at eroded right bank by Station 14+00
Owen Farms Mitigation Site Photographic Documentation
Repair Areas 9-15-2022
3
P5: Looking downstream at eroded right bank shown in P4
P6: Toe erosion on right bank near Station 15+50
Owen Farms Mitigation Site Photographic Documentation
Repair Areas 9-15-2022
4
P7: Looking downstream at scour/bank erosion on left bank near Station 16+50
P8: Looking upstream at scour/bank erosion shown in P7
Owen Farms Mitigation Site Photographic Documentation
Repair Areas 9-15-2022
5
P9: Bank looking upstream at bank erosion on right bank near Station 22+50
P10: Bank erosion on right bank shown in P9
Owen Farms Mitigation Site Photographic Documentation
Repair Areas 9-15-2022
6
P11: Looking downstream at toe erosion on right bank near Station 25+50
60 FEET OF BANK REPAIRUSING SOD MATSAND BOULDER TOESEE PHOTO P4 & P5
55 FEET OF BANK REPAIRUSING SOD MATSSEE PHOTO P2 & P3
40 FEET OF BANK REPAIRUSING SOD MATSSEE PHOTO P1
60 FEET OF BANK REPAIRUSING BOULDER TOESEE PHOTOS P9 & P10
75 FEET OF BANK REPAIRUSING SOD MATSSEE PHOTOS P7 & P8
35 FEET OF TOE EROSIONTO BE FIXED USING BOULDER TOESEE PHOTO P11
30 FEET OF TOE EROSIONTO BE FIXED USING BOULDER TOESEE PHOTO P6
0 630Feet
O REPAIR PLAN MAP
FIGURE 1
OWEN FARMS MITIGATION SITE
MAP DATE: 09-15-2022
Legend
Erosion Area
Bank
Toe