September 7, 2022
Mr. David Hall
BGE, Inc.
1111 Metropolitan Avenue
Charlotte, NC 28204
SUBJECT: WATER AND SEWER FLOW ACCEPTANCE
GALLOWAY ROAD TOWNHOMES
1124 GALLOWAY ROAD, CHARLOTTE, NC 28262
CLTWATER TRACKING# 20223377
After an analysis of the sanitary sewer associated with the proposed design of project, 20223377,
GALLOWAY ROAD TOWNHOMES, it was determined that there is sufficient capacity to
accommodate the proposed sewer flow of 15,970 gallons per day (63 units x 190 gpd/unit; 400
people x 10 gpd/person) at the connection point(s) indicated on the submitted utility plan for
transmission to the Mallard Creek Wastewater Treatment Plant; NPDES permit number
NC0030210, for treatment. This acceptance of flow is based upon the existing capacity of the
designated publicly owned treatments works.
Please see attached NCDEQ-FTSE form.
Charlotte Water (CLTWater) agrees to furnish water to the subject project. The water quality to the
subject project is regulated by the State Drinking Water Act Amendments of 1986 and The Water
Supply Management Plan, PWS ID # 0160010 on file with the Public Water Supply Section of
NCDEQ. However, CLTWater cannot guarantee a constant pressure or quality of flow.
The applicant should understand that due to the involvement of other agencies and continuing
growth of the water system, the ability to provide service for future projects cannot be guaranteed
nor reserved. Connection to the CLTWater system is accepted on a first come, first served basis.
The applicant should understand that this letter is not authorization to construct or extend private
water or sewer systems, as the appropriate local or State permits are required prior to construction.
If the appropriate authorization to construct permits are not obtained, and construction has not
started within two (2) years of issuance of this flow acceptance, and payment for any service
connections have not been received within two (2) years of issuance of this flow acceptance letter,
this flow acceptance approval shall be rescinded, and a new flow acceptance request must be
made.
The CAP analysis performed determines available capacity within the existing public gravity sewer
system. The developer is responsible for any additional private or public sewer infrastructure
required to convey flow from the proposed development to the existing public gravity sewer.
If you have any questions, please do not hesitate to contact me at (704) 432-5801.
Sincerely,
wi.U,Q rpno-- Aaizo-1 a.
Guillermo Anzola / Engineering Assistant
CHARLOTTE WATER