HomeMy WebLinkAbout20131200 Ver 2_Emails_20141002Strickland, Bev
From: Lucas, Annette
Sent: Thursday, October 02, 2014 4:16 PM
To: Kelly Hefner; David Odom
Cc: Clemment Riddle; Chris Waters; Devane, Boyd; Cranford, Chuck; Pickle, Ken; William
Hunt (bill_hunt@ncsu.edu); Andrew Anderson (arander5@ncsu.edu); Strickland, Bev
Subject: RE: 13-1200v2 Tryon Horse Complex
Kelly,
Is this a firm commitment? You are a key person in this conversation.
Annette
From: Kelly Hefner [Kelly.Hefner@ads-pipe.com]
Sent: Thursday, October 02, 2014 3:18 PM
To: David Odom
Cc: Lucas, Annette; Clemment Riddle; Chris Waters; Devane, Boyd; Cranford, Chuck; Pickle, Ken; William Hunt
(bill hunt@ncsu.edu); Andrew Anderson (arander5@ncsu.edu); Strickland, Bev
Subject: Re: 13-1200v2 Tryon Horse Complex
I'm ok for 1:00 right now.
Thank you,
Kelly Hefner
Mobile 704-215-0743
kellv.hefner(a,ads-bibe.com
Sent from my iPhone
On Oct 1, 2014, at 1:03 PM, "David Odom" <davidodomgodomen ing eerieg com> wrote:
1 pm works for me as well.
Kelly?
On Wed, Oct 1, 2014 at 1:02 PM, Lucas, Annette <annette.lucasgncdenr.gov> wrote:
From: David Odom[maiIto: davidodom(a)odomenaineering. com]
Sent: Wednesday, October 01, 2014 1:01 PM
To: Lucas, Annette
Cc: Clemment Riddle; Kelly Hefner; Chris Waters; Devane, Boyd; Cranford, Chuck; Pickle, Ken; William
Hunt (bill huntCa)ncsu.edu); Andrew Anderson (arander5Cd)ncsu.edu); Strickland, Bev
Subject: Re: 13-1200v2 Tryon Horse Complex
How about 2 pm?
Kelly
Can you provide a conference number?
Dave
On Wed, Oct 1, 2014 at 12:59 PM, Lucas, Annette <annette.lucasgncdenr.gov> wrote:
•1111111111111F.Eff F. mo
From: David Odom[maiIto: davidodom(a)odomenaineering. com]
Sent: Wednesday, October 01, 2014 12:58 PM
To: Lucas, Annette; Clemment Riddle
Cc: Kelly Hefner; Chris Waters; Devane, Boyd; Cranford, Chuck; Pickle, Ken; William Hunt
(bill huntCa)ncsu.edu); Andrew Anderson (arander5(cncsu.edu); Strickland, Bev
Subject: Re: 13-1200v2 Tryon Horse Complex
Annette
I would like to see if we could do the call Tuesday at 9 am rather than 10 am if that works for
you. See below for some additional information regrading your comments.
GENERAL OVERVIEW:
. A reminder to everyone that this stormwater plan is to fulfill the requirements of a 401
Certification issued for this project on February 17, 2014. This certification can be viewed
at: http://its.enr.state.nc.us/WebLink8/DocView.aspx?id=217849. My understanding is that
there is currently a Notice of Violation for this project due to use of the facility before the
implementation of a stormwater management plan as well as deposition of sediment into the
receiving stream. Perhaps Chuck Cranford from the Asheville Regional Office can elaborate
on this when he returns next week.
. You are also requesting that this project be considered as a submittal to the PEP program.
. This submittal must be sufficient to address the programmatic issues associated with the
401 Certification program, resolution of the Notice of Violation and the requirements of the
PEP.
The site currently is under a Notice of Violation. A response was filed with Chuck August 25th. The
sedimentation cleanup is approximately 75% completely and will be completed later this week or
early next week. The site is still very much a construction site with limited asphalt and grading still
active. They did have some shows earlier in July as an introduction to the project and to meet
licensing requirements. It is our expectation that the treatment systems will be installed
immediately upon approval. We are requesting that the project be considered as a submittal to the
PEP program.
PEP REQUIREMENTS:
. Please provide a design narrative that states the design objective, summarizes in words the
design approach, and concludes with the assertion that the design is compliant with the
relevant rules?
• Please provide a QAPP for our review and a commitment to stay the course over 12 months
of testing.
. Pleae provide an agreement to replace or tweak the Isolator Rows if they don't work to
achieve 85% TSS or an effluent concentration of 20 mg/L or less.
We will provide the additional information requested above in conjunction with ADS.
PLEASE EXPLAIN:
Which portions of the site are already built and which areas are paved versus
gravel.
How the Notice of Violation will be resolved and the stream will be restored. It
sounds like the site has caused a significant amount of sediment to be deposited in
the stream.
Please also explain how the Isolator Row devices will be protected from sediment
after their installation, particularly the devices that will be located downslope of
permanently unvegetated areas like horse rings and trails.
Which portions of the stormwater plan you are requesting approval for now and
which areas will be designed/built in the future (if any).
I will provide you with a drawing that indicates what is built and where construction is
continuing. The NOV is in the process of being resolved now. The drawing will indicate what we
are requesting approval for now and what is for the future. Additional information will be provided
to address your other questions.
CALCULATIONS:
Flow calculations were provided for every catch basin and pipe in the storm
drainage network. However, for every drainage area, C was estimated to be 0.5 and
for many inlets, the storm intensity was given to be 0 inch/hour. Please double-
check.
Please provide calculations for the sizing of the Isolator Row systems.
We will review this immediately.
PLANS — PLEASE SHOW:
Drainage easements or deed restrictions for the stormwater control measures.
How the Isolator Row systems will be accessed.
Clear details of the Isolator Row systems, including inlet and outlet details and
elevations.
Dimensions, elevations and pipe sizes for every stormwater diversion device that
will be used with supporting calculations.
• A construction sequence.
We will provide this shortly along with the items below.
MAINTENANCE & MONITORING
Please provide a signed and notarized Operation & Maintenance Agreement for
the stormwater control measures.
4
Please provide a monitoring plan for one of the Isolator Row systems, including
the equipment, procedures and frequencies for cleaning the devices.
Please provide a signed and notarized agreement stating that the Isolator Row
systems will be replaced with another stormwater control measure if monitoring data
show that they are not working effectively.
On Wed, Oct 1, 2014 at 8:15 AM, Lucas, Annette <annette.lucasgncdenr.gov> wrote:
David, Chris and Kelly,
Ken Pickle and I have reviewed the submittal received in the Division of Water Resources Central Office
on September 9, 2014 for the above named project. In our review, we noted the following issues.
GENERAL OVERVIEW:
A reminder to everyone that this stormwater plan is to fulfill the requirements of a 401
Certification issued for this project on February 17, 2014. This certification can be viewed
at: http://its.enr.state.nc.us/WebLink8/DocView.aspx?id=217849. My understanding is that
there is currently a Notice of Violation for this project due to use of the facility before the
implementation of a stormwater management plan as well as deposition of sediment into the
receiving stream. Perhaps Chuck Cranford from the Asheville Regional Office can elaborate on
this when he returns next week.
You are also requesting that this project be considered as a submittal to the PEP program.
• This submittal must be sufficient to address the programmatic issues associated with the 401
Certification program, resolution of the Notice of Violation and the requirements of the PEP.
PEP REQUIREMENTS:
• Please provide a design narrative that states the design objective, summarizes in words the
design approach, and concludes with the assertion that the design is compliant with the relevant
rules?
• Please provide a QAPP for our review and a commitment to stay the course over 12 months of
testing.
Pleae provide an agreement to replace or tweak the Isolator Rows if they don't work to achieve
85% TSS or an effluent concentration of 20 mg/L or less.
PLEASE EXPLAIN:
Which portions of the site are already built and which areas are paved versus gravel.
• How the Notice of Violation will be resolved and the stream will be restored. It sounds
like the site has caused a significant amount of sediment to be deposited in the stream.
• Please also explain how the Isolator Row devices will be protected from sediment after
their installation, particularly the devices that will be located downslope of permanently
unvegetated areas like horse rings and trails.
• Which portions of the stormwater plan you are requesting approval for now and which
areas will be designed/built in the future (if any).
CALCULATIONS:
• Flow calculations were provided for every catch basin and pipe in the storm drainage
network. However, for every drainage area, C was estimated to be 0.5 and for many
inlets, the storm intensity was given to be 0 inch/hour. Please double-check.
Please provide calculations for the sizing of the Isolator Row systems.
PLANS — PLEASE SHOW:
Drainage easements or deed restrictions for the stormwater control measures.
How the Isolator Row systems will be accessed.
• Clear details of the Isolator Row systems, including inlet and outlet details and
elevations.
• Dimensions, elevations and pipe sizes for every stormwater diversion device that will be
used with supporting calculations.
• A construction sequence.
6
MAINTENANCE &MONITORING
°
Please provide a signed and notarized Operation & Maintenance Agreement for the
^
Please provide a monitoring plan for one of the Isolator Row systems, including the
equipment, procedures and frequencies for cleaning the devices.
°
Please provide a signed and notarized agreement stating that the Isolator Row systems
will be replaced with another stormwater control measure if monitoring data show that
they are not working effectively.
| suggest vxeschedule aconference call todiscuss these items in more detail. |fyou are interested in
that, please let me know some dates/times in the next week or so that you will be available.
Annette
Environmental Engineer
Phone: 1 Fax: 1 Email:
Weboite�
bA, Before printing this email, please consider your budget and. the environment.
E-mail correspondence to and from this address may be subject to the North Carolina Public Records Law and may
be disclosed to third parties.
7
Strickland, Bev
From:
David Odom < davidodom @odomengineering.com>
Sent:
Wednesday, October 01, 2014 1:03 PM
To:
Lucas, Annette
Cc:
Clemment Riddle; Kelly Hefner; Chris Waters; Devane, Boyd; Cranford, Chuck; Pickle,
Ken; William Hunt (bill_hunt @ncsu.edu); Andrew Anderson (arander5 @ncsu.edu);
Strickland, Bev
Subject:
Re: 13- 1200v2 Tryon Horse Complex
1 pm works for me as well.
Kelly?
On Wed, Oct 1, 2014 at 1:02 PM, Lucas, Annette <annette.lucasgncdenr.gov> wrote:
From: David Odom [mai Ito: davidodom (a)odomenaineerina.com]
Sent: Wednesday, October 01, 2014 1:01 PM
To: Lucas, Annette
Cc: Clemment Riddle; Kelly Hefner; Chris Waters; Devane, Boyd; Cranford, Chuck; Pickle, Ken; William Hunt
(bill huntCa)ncsu.edu); Andrew Anderson (arander5(cncsu.edu); Strickland, Bev
Subject: Re: 13- 1200v2 Tryon Horse Complex
How about 2 pm?
Kelly
Can you provide a conference number?
Dave
On Wed, Oct 1, 2014 at 12:59 PM, Lucas, Annette <annette.lucasgncdenr.gov> wrote:
1
From: David Odom [ mai Ito: davidodom (a)odomenaineerina.com]
Sent: Wednesday, October 01, 2014 12:58 PM
To: Lucas, Annette; Clemment Riddle
Cc: Kelly Hefner; Chris Waters; Devane, Boyd; Cranford, Chuck; Pickle, Ken; William Hunt (bill huntCa)ncsu.edu); Andrew
Anderson (arander5Cd)ncsu.edu); Strickland, Bev
Subject: Re: 13- 1200v2 Tryon Horse Complex
Annette
I would like to see if we could do the call Tuesday at 9 am rather than 10 am if that works for you. See below
for some additional information regrading your comments.
GENERAL OVERVIEW:
. A reminder to everyone that this stormwater plan is to fulfill the requirements of a 401 Certification issued
for this project on February 17, 2014. This certification can be viewed
at: http: / /its.enr. state. nc.us /WebLink8 /DocView.aspx ?id= 217849. My understanding is that there is
currently a Notice of Violation for this project due to use of the facility before the implementation of a
stormwater management plan as well as deposition of sediment into the receiving stream. Perhaps Chuck
Cranford from the Asheville Regional Office can elaborate on this when he returns next week.
. You are also requesting that this project be considered as a submittal to the PEP program.
. This submittal must be sufficient to address the programmatic issues associated with the 401 Certification
program, resolution of the Notice of Violation and the requirements of the PEP.
PEP REQUIREMENTS:
. Please provide a design narrative that states the design objective, summarizes in words the design
approach, and concludes with the assertion that the design is compliant with the relevant rules?
. Please provide a QAPP for our review and a commitment to stay the course over 12 months of testing.
. Pleae provide an agreement to replace or tweak the Isolator Rows if they don't work to achieve 85% TSS or
an effluent concentration of 20 mg /L or less.
We will provide the additional information requested above in conjunction with ADS.
PLEASE EXPLAIN:
Which portions of the site are already built and which areas are paved versus gravel.
How the Notice of Violation will be resolved and the stream will be restored. It sounds like the
site has caused a significant amount of sediment to be deposited in the stream.
Please also explain how the Isolator Row devices will be protected from sediment after their
installation, particularly the devices that will be located downslope of permanently unvegetated areas
like horse rings and trails.
Which portions of the stormwater plan you are requesting approval for now and which areas will
be designed /built in the future (if any).
I will provide you with a drawing that indicates what is built and where construction is continuing. The NOV is in
the process of being resolved now. The drawing will indicate what we are requesting approval for now and what is
for the future. Additional information will be provided to address your other questions.
CALCULATIONS:
Flow calculations were provided for every catch basin and pipe in the storm drainage network.
However, for every drainage area, C was estimated to be 0.5 and for many inlets, the storm intensity
was given to be 0 inch /hour. Please double- check.
Please provide calculations for the sizing of the Isolator Row systems.
We will review this immediately.
PLANS — PLEASE SHOW:
Drainage easements or deed restrictions for the stormwater control measures.
How the Isolator Row systems will be accessed.
Clear details of the Isolator Row systems, including inlet and outlet details and elevations.
Dimensions, elevations and pipe sizes for every stormwater diversion device that will be used
with supporting calculations.
• A construction sequence.
We wall provide this shortly along with the items below,
MAINTENANCE & MONITORING
Please provide a signed and notarized Operation & Maintenance Agreement for the stormwater
control measures.
Please provide a monitoring plan for one of the Isolator Row systems, including the equipment,
procedures and frequencies for cleaning the devices.
Please provide a signed and notarized agreement stating that the Isolator Row systems will be
replaced with another stormwater control measure if monitoring data show that they are not working
effectively.
On Wed, Oct 1, 2014 at 8:15 AM, Lucas, Annette <annette.lucasgncdenr.gov> wrote:
David, Chris and Kelly,
Ken Pickle and I have reviewed the submittal received in the Division of Water Resources Central Office on September 9,
2014 for the above named project. In our review, we noted the following issues.
GENERAL OVERVIEW:
A reminder to everyone that this stormwater plan is to fulfill the requirements of a 401 Certification issued for
this project on February 17, 2014. This certification can be viewed
at: http: / /its.enr. state. nc.us /WebLink8 /DocView.aspx ?id= 217849. My understanding is that there is currently a
Notice of Violation for this project due to use of the facility before the implementation of a stormwater
management plan as well as deposition of sediment into the receiving stream. Perhaps Chuck Cranford from the
Asheville Regional Office can elaborate on this when he returns next week.
You are also requesting that this project be considered as a submittal to the PEP program.
• This submittal must be sufficient to address the programmatic issues associated with the 401 Certification
program, resolution of the Notice of Violation and the requirements of the PEP.
PEP REQUIREMENTS:
• Please provide a design narrative that states the design objective, summarizes in words the design approach,
and concludes with the assertion that the design is compliant with the relevant rules?
Please provide a QAPP for our review and a commitment to stay the course over 12 months of testing.
• Pleae provide an agreement to replace or tweak the Isolator Rows if they don't work to achieve 85% TSS or an
effluent concentration of 20 mg /L or less.
PLEASE EXPLAIN:
Which portions of the site are already built and which areas are paved versus gravel.
How the Notice of Violation will be resolved and the stream will be restored. It sounds like the site has
caused a significant amount of sediment to be deposited in the stream.
• Please also explain how the Isolator Row devices will be protected from sediment after their installation,
particularly the devices that will be located downslope of permanently unvegetated areas like horse
rings and trails.
• Which portions of the stormwater plan you are requesting approval for now and which areas will be
designed /built in the future (if any).
CALCULATIONS:
Flow calculations were provided for every catch basin and pipe in the storm drainage network. However,
for every drainage area, C was estimated to be 0.5 and for many inlets, the storm intensity was given to
be 0 inch /hour. Please double- check.
Please provide calculations for the sizing of the Isolator Row systems.
PLANS — PLEASE SHOW:
Drainage easements or deed restrictions for the stormwater control measures.
How the Isolator Row systems will be accessed.
Clear details of the Isolator Row systems, including inlet and outlet details and elevations.
• Dimensions, elevations and pipe sizes for every stormwater diversion device that will be used with
supporting calculations.
• A construction sequence.
MAINTENANCE & MONITORING
• Please provide a signed and notarized Operation & Maintenance Agreement for the stormwater control
measures.
• Please provide a monitoring plan for one of the Isolator Row systems, including the equipment,
procedures and frequencies for cleaning the devices.
• Please provide a signed and notarized agreement stating that the Isolator Row systems will be replaced
with another stormwater control measure if monitoring data show that they are not working effectively.
I suggest we schedule a conference call to discuss these items in more detail. If you are interested in that, please let me
know some dates /times in the next week or so that you will be available.
Thanks,
Annette
Environmental Engineer
I
6
Phone: (919) 807-6381 1 Fax: (919) 807-6494 1 Email: annette.lucasgncdenngov
Website http://portal.ncdenr.org/web/Ir/stormwater
bA, Before printing this email, please consider your budget and. the environment.
E-mail correspondence to and from this address may be subject to the North Carolina Public Records Law and may be disclosed to
third parties.