From: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil>
Sent: Thursday, September 8, 2022 3:27 PM
To: Phil May
Cc: bryan.wuester@gflenv.com; Homewood, Sue; Mike Brinchek
Subject: [External] RE: Permit Modification letter: Waste Industries High Point C&D Landfill
expansion, Guilford County; SAW-2014-01568
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Hi Phil, and thank you for your email/request. After review and discussion with my Field Office Chief, we find your
request appropriate and acceptable. As such, please reference this email in your files to document the following change
in Corps Permit Special Conditions:
Special Condition XX), as written on page 2 of the Corps Permit Modification letter for the above referenced project
dated September 6, 2022, is hereby amended to state:
xx) The authorized work, with the exception of live stake planting, shall be completed within 120 days of the date
of this email. Submittal of an as -built survey shall be submitted to the Corps and NCDWR within 60 days of completion of
this authorized work.
All other conditions of the permit and subsequent modification, including the permit expiration date of December 31,
2036, remain in effect as written. If you have any questions, please contact me via phone or email.
Sincerely,
Dave Bailey
David E. Bailey, PWS
Regulatory Project Manager
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Mobile: (919) 817-2436
Email: David.E.Bailey2@usace.army.mil
We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is
located at: https://regulatory.ops.usace.army.mil/customer-service-survey/
Thank you for taking the time to visit this site and complete the survey.
From: Phil May <phil.may@carolinaeco.com>
Sent: Thursday, September 8, 2022 12:41 PM
To: Bailey, David E CIV USARMY CESAW (USA)<David.E.Bailey2@usace.army.mil>
Cc: bryan.wuester@gflenv.com; Homewood, Sue (sue.homewood@ncdenr.gov) <sue.homewood@ncdenr.gov>; Mike
Brinchek <mike@smithgardnerinc.com>
i
Subject: [URL Verdict: Neutral][Non-DoD Source] Re: Permit Modification letter: Waste Industries High Point C&D
Landfill expansion, Guilford County; SAW-2014-01568
David
On behalf of GFL, I would like to request that the time frame for this work be extended to 120 days rather
than the 60-day schedule referenced in Item XX of the permit modification. While the work on -site can be
accomplished in a 60-day time frame, supply chain issues associated with getting the materials for the
construction will likely require a longer lead time prior to the work commencing. GFL and Smith Gardner,
their engineer, feel that 120 days from the date of the modification is adequate given the current supply chain
issues. Let me know if you need any additional information to consider this extension.
Thanks
Phil
Phil May
CAROLINA ECOSYSTEMS INC.
(919) 606-1065
From: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil>
Sent: Wednesday, September 7, 2022 10:34 AM
To: bryan.wuester@gflenv.com <bryan.wuester@gflenv.com>; Phil May <phil.may@carolinaeco.com>; Mike Brinchek
<mike@smithgardnerinc.com>; David.Pepper@gflenv.com <David.Pepper@gflenv.com>
Cc: pete benjamin@fws.gov <pete benjamin@fws.gov>; Bowers, Todd <bowers.todd@epa.gov>; Homewood, Sue
<sue.homewood@ncdenr.gov>; Williams, Kelly <kelly.williams@ncdenr.gov>; Browning, Kimberly D CIV USARMY CESAW
(USA) <Kimberly.D.Browning@usace.army.mil>; ken.riley@noaa.gov <ken.riley@noaa.gov>
Subject: Permit Modification letter: Waste Industries High Point C&D Landfill expansion, Guilford County; SAW-2014-
01568
All,
Please see the attached permit modification letter for the above referenced project, pertaining to the stream
stabilization plan through a former wetland in the vicinity of Sediment Basin 8, and let me know if you have any
questions.
-Dave Bailey
David E. Bailey, PWS
Regulatory Project Manager
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Mobile: (919) 817-2436
Email: David.E.Bailey2@usace.army.mil
2
We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is
located at: https://regulatory.ops.usace.army.mil/customer-service-survey/
Thank you for taking the time to visit this site and complete the survey.