HomeMy WebLinkAbout08.29.2022 - DB00539 PreCon Mtg MinsSTATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
Roy COOPER
GOVERNOR
August 31, 2022
J. ERIC BOYETTE
SECRETARY
Contract No.: DB00539
WBS No.: 17BP.2.R.90
County: Lenoir
Route: SR1515
Description: Replacement of Bridge 68 over Groundnut Creek on SR1515 (Aldridge Store Rd)
Ronnie Melker
Dellinger, Inc.
P.O. Box 929
Monroe, NC 28111-0929
SUBJECT: Pre -Construction Conference Minutes
A pre -construction conference was held Monday, August 29, 2022 for the above referenced project. The
following individuals were in attendance.
Name
Company/Agency
Aaron Bullard
NCDOT —
Resident Engineer
Stanley Harrell
NCDOT —
Asst. Resident Engineer
Brett Smith
NCDOT —
Inspector
Andy Blankenship
NCDOT —
REU Field Ops Engineer
Justin Davis
NCDOT —
REU Field Ops Staff Engineer
Jay Sutton
NCDOT —
Lenoir Co. Maintenance Engineer
John Fields
NCDOT —
Lenoir Co. Bridge Maintenance Supervisor
Michael Aman
NCDOT —
Division Bridge Program Manager
Garcy Ward
NCDEQ/DWR — Environmental Specialist
Ronnie Melker
Dellinger
— Vice President
General Items
Mr. Bullard opened meeting with introductions by all attendees.
Mr. Bullard has received all the initial submittal documents from Contractor with exception of progress
schedule and SAFs. Mr. Melker said those documents will be submitted soon.
The estimate end date of the 15t' was agreed upon by Mr. Melker and Mr. Bullard.
The Resident Engineer for this project is Aaron Bullard. All correspondence should be directed to the
office as follows:
Mailing Address: Telephone: 252-775-6530 Location:
NC DEPARTMENT OF TRANSPORTATION Fax: 252-527-7920 1629 US 258 S
RESIDENT ENGINEER'S OFFICE Customer Service: 877-3684968 KINSTON, NC 28504
1629 US 258 S
KINSTON, NC 28504 Website: ncdot.gov
Pre -Construction Mins (DB00539)
August 29, 2022
Page 2 of 4
NC Department of Transportation
Mr. Aaron Bullard, PE
Resident Engineer
1629 US 258 S
Kinston, NC 28504
Mr. Stanley Harrell will be the Assistant Resident Engineer and Brett Smith will be the Lead Project
Inspector.
Contract Review
Floating Availability Date: August 8 to August 31, 2022
Overall Completion Date 90 days after completion of ICT #1
Liquidated Damages: $200.00 per calendar day
ICT #1 (All work except permanent vegetation establishment)
Floating Availability Date: Same as above
Completion Date: 150 days after Date of Availability
Liquidated Damages: $700.00 per calendar day
Contractor plans to start on Tuesday, September 6, 2022. Mr. Melker has contacted Traffic Services for
the detour installation on that date. Contractor will email a schedule to Mr. Bullard with a target date for
completion.
Project has the Permanent Vegetation Establishment provision.
Contract DBE goal was 5% and was met at 15.8% with Everett's Lot Clearing & Grading. Contractor
will have other DBEs — Garris Paving and a 4 D Construction. Mr. Bullard instructed contractor to be
sure to enter all payments into the Payment Tracking System each month, for both committed and non -
committed DBEs.
Contractor will not be using any Unmanned Aircraft Systems on this project.
Mr. Bullard reminded the Contractor to be aware of Equipment Idling Guidelines.
Subsurface Information is available for the structure portions, but there is no information for the roadway
portions.
NCDOT forces will do the offsite detour and final pavement markings after everything is done.
Contractor has contacted Mr. Jim Evans with Traffic Services. Mr. Harrell has contacted EMS and
schools and should be good to proceed on September 6.
Contract has a twelve-month guarantee on major items/components and workmanship.
Pavement along the transverse centerline of all caps shall be saw cut to a depth of 3/4"f, cleaned, and filled
with an approved asphalt sealant. Apply an approved epoxy protective coating to the tops of all caps and
to the exterior faces of all exterior cored slab units with a Type 4A epoxy coating.
Clearing and Grubbing will be Method II.
Pre -Construction Mins (DB00539)
August 29, 2022
Page 3 of 4
Mr. Bullard stated there was an addendum that added the provision for bridge approach fills. It will be
the standard modified approach fill for these smaller cored slab bridge projects. It's the last line item in
the contract.
Automated Machine Guidance will not be used on this project.
Type III guardrail end units shall come off the APL. Mr. Bullard requested Acceptance Letter and
Working Drawings prior to installation. Bullington will be doing the guardrail
CenturyLink, Suddenlink, and North Lenoir Water Corporation have completed their work so there
should be no utility conflicts remaining.
A Supplemental Agreement was added for Response for Erosion Control. This was omitted from original
contract.
Borrow source has not been decided yet. Contractor will advise.
Mr. Ward reviewed the DEQ Water Quality Certification. Mr. Ward questioned if Surveys for Neuse
River Water Dog and Carolina Madtom had been done. Mr. Aman confirmed these surveys were done on
January 28, 2022. Contractor will send copies to Mr. Garcy Ward and to Mr. Tom Steffens. Mr. Ward
stated Neuse buffer rules are in effect. Because of small buffer impact, Buffer Authorization was not
required. Mr. Bullard noted that the Buffer Permit Drawings were not included in the contract. Mr.
Aman will send these drawings to Mr. Bullard.
Mr. Bullard reviewed the Title VI contract requirements, specifically the posting of NCDOT's Notice of
Non-discrimination and the Contractor's EEO Policy on your job board. Include all Title IV clauses in all
contracts and subcontracts. Mr. Bullard will need one DBE and one non -DBE of subcontract documents
for verification.
Plan Review
Mr. Aman noted that on plan sheet 4, there is a note regarding minimizing disturbance of trees at the
Northeast quadrant. Mr. Blankenship asked Contractor to be mindful of the trees in the easement and
leave as many trees undisturbed as possible. It was noted that the allowable buffer impacts only extend to
the toe of fill and do not encompass the construction easements, rendering the easements in the buffer
zones unusable.
Mr. Harrell reached out to the schools about TMP Plan note to create a place for school bus turn around.
He has not had a response from the schools yet but will advise once he hears back.
Mr. Harrell mentioned that there is a Roadway item for Class II Rip Rap (220 tons) in addition to the
Structure item of Class II Rip Rap (125 tons). The Structure item is clearly for the End Bent slope
protection, but the plans do not specify the location of the Roadway item. Mr. Bullard will review the
Calculation of Quantities to try and find an answer.
Mr. Bullard noted that the Bridge Approach Slab plan sheet does not show the layer of geotextile to be
installed 1 foot below the top of the approach fill. Ensure that gets installed.
Additional Comments
Project survey control has been verified per Mr. Harrell.
Pre -Construction Mins (DB00539)
August 29, 2022
Page 4 of 4
East Group will be doing the surveying for contractor.
Contractor Project Superintendent will be Chris Evans and General Superintendent will be Chris McCray.
A copy of the attendance roster will be attached to these minutes for information.
Meeting was adjourned by Mr. Bullard.
These minutes are prepared as documented. Any discrepancies with the content of these minutes should
be submitted in writing to this office. Failure to do so will be an indication of agreement.
Sincerely,
DocuSigned by:
Ate. Ad"
39D7E831 C4434A4...
Aaron Bullard, PE
Resident Engineer