Loading...
HomeMy WebLinkAboutNC0025453_Annual Performance_20220831Annual Wastewater System Performance Report Fiscal Year 2021-2022 Town of Clayton Town of Clayton, North Carolina Annual Wastewater System Performance Report August 2022 Wastewater System Performance Annual Report Fiscal Year 2021-2022 Town of Clayton I. General Information Responsible Entity: Town of Clayton Wastewater Treatment Facility Name: Sam's Branch Water Reclamation Facility (SBWRF) ORC: William Simpson--SBWRF James Blalock --Collection System NPDES Permit: NC0025453 (SBWRF) Laboratory Certification: 348 Collection System: WQCS00110 Description of Treatment Process and Collection System: The SBWRF is comprised of an automated barscreen, grit chamber, sampling station, flow monitoring, dual oxidation ditches with biological nutrient removal, tertiary filter, ultraviolet disinfection, standby chlorination & dechlorination, sludge thickening, aerated sludge storage and reclaim water. The wastewater collection system is comprised of 28 lift stations, approximately 138 miles of gravity sewer and approximately 36 miles of force main. II. Performance The collection and treatment system recorded a good performance record for the twelve-month period from July 1, 2021, to June 30, 2022. The facility met the permit conditions with the following exception: The facility reported no overflows between 7-1-21 and 6-30-22 The treatment facility treated 590,356,692 gallons during the period and met NPDES permit limits. Clayton sent 134,390,410 gallons to Raleigh, and 374,610,200 gallons to Johnston County for treatment. The treatment facility delivered 11,090,560 gallons of reclaimed water to Pine Hollow Golf Course. The total system flow for the year: 1,110,447,682 gallons Sanitary sewer overflows that release 1,000 gallons or more and/or enter surface waters must be reported to the State of North Carolina. The collection system had 3 overflows during the period that did not meet the reporting criteria. The collection system had 7 overflows during the period that did require reporting which are listed below: Reportable Collection System Sanitary Sewer Overflows Date Location Gallons Cause 08/25/21 8368 US Hwy 70 Bus W 500 Faulty Air Release Valve 02/11/22 1000 Durham St. 7,200 Contractors bypass pump failed 03/15/22 317 S. Robertson St. 210 Roots and leaking joints in VCP pipe 03/17/22 1000 Durham St. 44,800 Contractors bypass pump fail/heavy rain 03/24/22 1000 Durham St. 18,000 Contractor bypass couldn't keep up with heavy rain inflow 03/31/22 11306 US Hwy 70 Bus W 135 Grease from restaurant 04/28/22 8368 US Hwy 70 Bus W 13,500 Contractor hit line Corrective measures for the overflows included line repairs, cleaning the line(s) involved and the immediate area(s) in accordance with State guidelines, I & I Investigation. Chemical Root Control was used throughout the year on lines with roots to avoid an SSO. The system also distributed Grease Public Education materials to all residents in accordance with requirements. The Town held the contractors to more stringent requirements on projects. No environmental impacts or adverse health effects were detected. The following improvements were made to the collection system during the twelve-month period: 1 Clear CAT FM easement 2 New Pumps & impeller kits 6 lift stations 3 Chemical Root Control 4 Clearing/Vegetation Control at L/S and on easements 5 CIPP lining of outfall and Main St. & Manholes 6 Blanch & O'Neil St. sewer replacement design 7 Liberty/West Main abandonment design 8 City Rd. L/S abandonment design 9 Starmount L/S abandonment design 10 Hamby St. sewer replacement design 11 ECIA new FM design to new WRF 12 Little Creek gravity construction & engineering 13 New Ven-trac mower for easement cutting 14 New software (NAASCO) for CCTV equipment 15 Little Creek L/S design, transmission line construction/design 16 Replace one truck & add two to fleet $34,440 $60,196 $5,820 $6,540 $302,381 $20,000 $4,165 $15,043 $40,617 $21,400 $614,532 $640,115 $30,745 $19,900 $1,138,588 $146,080 The cost of these improvements was approximately $ 3,100,562 In addition to the above projects the Town added two positions, a FOG Compliance Technician and a lift station Pump Technician to assist with the operating of the collections system. The Town is currently under a Town wide job classification/pay study review. The following improvements were made at the treatment facility during the twelve-month period. • Generator Control upgrade: $34,980 • Bar Screen Basket replacement: $15,005 • Grit Classifier Screw replacement: $12,580 The cost of these improvements was approximately $ 62,565 Construction & clearing for the new Sam's Branch Water Reclamation Facility started with the site and access road being graded and materials purchased. The cost of this work and design was approximately $14,614,594 III. Notification A notice of availability is published in the Johnstonian News and at www.townofclaytonnc.org. A report may be picked up from the customer service counter at Town Hall or the Operations Center at 653 NC 42 West. Customers may also call 919-553-1530 to request a copy by mail. It may also be viewed on-line at the Town's Web Site (www.townofclaytonnc.org). IV. Certification I certify under penalty of law that this report is complete and accurate to the best of my knowledge. I further certify that this report has been made available to the users or customers of the named system and that those users have been notified of its availability. ch Cappola, Interinflown Manager 7fZ9j2 �. Date This report is drafted to meet the reporting requirements established in House Bill 1160 and the Clean Water Act of 1999. TOWN OF CLAYTON Public Works, Water/Sewer, & Electric 653 NC Hwy 42 W., P.O. Box 879 Clayton, NC 27528 Phone: 919-553-1530 Fax: 919-553-1541 August 1, 2022 System Performance Annual Report North Carolina Division of Water Quality 1617 Mail Service Center Raleigh, NC 27699-1617 In accordance with House Bill 1160 and the Clean Water Act of 1999, three copies of the Wastewater System Performance Annual Report for FY 2021-2022 are being sent to you for NPDES Permit # NC0025453, Laboratory Certification # 348 and Collection System Permit # WQCS 00110. If there are any questions concerning the report or any further information is required, please contact the Operation Center at (919)553-1530. Sincerely, es E. Blalock Water Resources Maintenance Superintendent Think CLAYTO PO Box 879 • Clayton, NC 27528 • 919-553-1530 Fax 919-553-1541 • TownofClaytonNC.org TOWN OF CLAYTON Public Works, Water/Sewer, & Electric 653 NC Hwy 42 W., P.O. Box 879 Clayton, NC 27528 Phone: 919-553-1530 Fax: 919-553-1541 August 1, 2022 The Johnstonian News 614 E. Market St. Smithfield, NC 27577 ATTN: LEGAL DEPARTMENT In accordance with NC House Bill 1160 and the Clean Water Act of 1999, the Town of Clayton makes available an annual Wastewater System Performance Report. One of the means provided to accomplish this is for a newspaper that has circulation in the service area to publish the following information: The Town of Clayton's FY 2021-2022 Wastewater System Performance Report is now available. A copy of the report may be obtained from the Operations Center on NC 42 West. To obtain a copy by mail, please call 919-553-1530. It may also be viewed on-line at the Town's Web Site (www. to wn o fcl aytonnc. org). Thank you for the help with this. Sincerely, es E. Blalock ater Resources Maintenance Superintendent Cc: Nathanael Shelton, Public Information Officer Fax 919-553-1541 • TownofClaytonNC.org PO Box 879 • Clayton, NC 27528 • 919-553-1530