HomeMy WebLinkAboutSite Inspection 8.29.22 Chinquapin BridgeWetland Inspection Report
Inspection Type:
Reason for Inspection:
Inspection Date:
Site Owner Name:
Latitude:
County:
Project Name:
Project Num:
Location:
SW Plan Location:
20211560
TPB NCDOT - Replace Bridge 3 on SR 1887
Haywood
TPB NCDOT - Replace Bridge 3 on SR 1887
NC DOT Division 14 - Sylva
8/29/2022
Routine
Site Inspection (DOT)
Version: 1 Status:Issued
Project Type:Replace bridge with bridge
Region:Asheville
Longitude:-82° 48' 41''+35° 25' 04''
Inspection Contact Person:Title:Phone:
On-Site Representative(s):
Secondary Inspector(s):
Primary Inspector:Phone:Robert K Mitchell
Facility Compliance Status:Compliant Not Compliant
Program Areas: 401 (includes isolated/non-404)
Question Areas:
Permit (401 WQC)
Inspection Summary:
Site inspection was conducted on August 29, 2022 by Kevin Mitchell with the Asheville Regional Office. Chris Barker
was present during the inspection. The following are items that need attention:
Contractor is excavating the area on the right bank descending. Measures are needed at the end of the day. This was
discussed with Chris. Silt fence is to be added and spoils that have been discarded down the bank will be stabilized at
the end of the day.
NPDES records were up to date.
page:1
Inspection Date:
Site Number:
Inspection Type:
Owner:
Reason for Visit:
20211560
8/29/2022
Blazer, Keith
Site Inspection (DOT)Routine
Permit (401 WQC)Yes No NA NE
Does the impact(s) match what was approved in the 401 WQC or non 404 permit?
Are the culverts and/or filled areas installed properly?
Is the site compliant with additional conditions of the 401 WQC or non 404 permit?
H piles have been driven on the left bank descending. Area is being excavated on the right bank.Comment: