From: Phillips, George L CIV USARMY CESAW (USA) <George.L.Phillips@usace.army.mil>
Sent: Thursday, December 2, 2021 8:46 AM
To: Kevin Martin
Subject: Berry Tracts / Raleigh / Wake County / SAW-2021-02120 / Jurisdictional
Determination Request
Attachments: Figure 3 - Sketch Map.pdf
Morning Kevin,
Based on my site visit on 10/26/2021 the Corps concurs with the delineation within the red outlined "Parcel Boundary"
depicted on the attached "Figure 3 — Sketch Map" exhibit. It may take 90-120 days for the issuance of a written
jurisdictional determination. The delineation may be used for planning and permitting purposes, should a permit be
required the JD can be issued and the time of permit verification. AID for the project is SAW-2021-02120. I have
attached the "Figure 3 — Sketch Map" exhibit for reference.
Please let me know if you have any questions or concerns.
Lyle Phillips
Regulatory Specialist
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Phone: (919) 554-4884, Ext. 25.
Fax: (919) 562-0421
Email: George.L.Phillips@usace.armv.mil
We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is
located at https://regulatory.ops.usace.army.mil/customer-service-survey/ . Thank you for taking the time to visit this
site and complete the survey.