HomeMy WebLinkAboutNCC202100_NOT Closeout Documents_20220824North Carolina Department of Environmental Quality
Land Resources: 1628 Mail Service Center, Raleigh, NC 27699 (919) 791-4200
County: Halifax Project: Dawson's Crossroads Substation River basin: Tar -Pamlico
Person financially responsible: Halifax Electric Membership Corporation - Charles Project #: HALIF-2020-012
H Guery
Address: PO Box 667, Enfield, NC 27823-0667
1. Project Location: 13 Bridges Road, Scotland Neck
Pictures: No
2. Weather and soil conditions: hot dryworkable Initial inspection: No
3. Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A. and rules? Yes If no, check violations below:
5. Violations:
6. Is the site in compliance with NPDES Permit NCGO10000 Construction Stormwater requirements? Yes
Describe:
7. Has sedimentation damage occurred since last inspection? No If Yes, where? (check all that apply)
Degree of damage:
8. Contact made with (name): Brianna Eddy
Inspection report: Sent Report
9. Corrective action needed:
Title: General Manager
Date given/sent: June 10, 2022
10. Comments: This site is stable and can be closed in our office
Permanent ground cover sufficient to restrain erosion has been established. No additional
self -monitoring or self -inspections are required. Project is in compliance and released under
the SPCA. Termination of coverage under the NPDES General Stormwater Permit for
Construction Activities (NCGO1) must be requested by the permittee via a Notice of
Termination (NOT). The NOT is available at:
https://edocs.deq.nc.gov/Fonns/NCGOI-Termination. Please note that this correspondence
must be uploaded as part of completing the NOT process.
Reported by: Thaddeus Valentine Others present: no one
Date of inspection: June 08, 2022 Time arriving on site: 1:20 PM Time leaving site: 2:00 PM