I was looking over the additional information you provided on 4/26/2022. Everything looks good except for a few small
issues:
Please correct the following:
- Vallowable for the swales (Prior Comment 1,b,ii) – The provided swales matting (and associated maximum
allowable velocity) is temporary (since NAG-SC150 is a temporary matting) but the swales must remain
stable/nonerosive in perpetuity. Please revise the Vallowable values in the table (and calculations if needed) to
reflect the permanent conditions of the vegetated conveyances and ensure that they will be stable in
permanent conditions.
- Deed Restriction document BUA reallocation (per our phone conversation today). You are allowed to allocate a
maximum allowable BUA per lot to each individual lot (or group of lots). If you are changing the amount of BUA
for this project by changing the per lot BUA allocations, you will need to provided revised (original) deed
restriction documents (showing the new BUA allocations), recalculate the BUA for the site, BUA breakdown by
type, and %BUA for the site (Section IV, 8 & 10 of the Application and Lines 8, 9, 10, 12, & 18 of the Drainage
Areas Page of the Supplement-EZ Form).
- Please revise the table in Section IV, 10 of the Application to match the information shown in the Supplement-EZ
Form. The BUA allocated to the individual lots should be listed on the “On-site Buildings/Lots” line and not
broken down by type.
Impervious Surface Area (Section IV, 10 of the Equivalent Line of the Drainage Area Page of the
Application) Supplement-EZ Form
On-site Buildings/Lots Line 9 (For subdivisions only, otherwise, Line 12, Roof)
On-site Streets Line 12, Roadways
On-site Parking Line 12, Parking
On-site Sidewalks Line 12, Sidewalks
On-site Other Line 12, Other
Future Line 12, Future
Off-site Line 11
Existing BUA Line 15
Total Line 8
Please provide the following:
- 1x hard copy & 1x electronic copy of the revised swale calculations (if applicable)
- 1x hard copy & 1x electronic copy of an original, revised deed restriction document.
- 1x hard copy & 1x electronic copy of the revised pages of the Application Form.
- 1x hard copy & 1x electronic copy of the revised pages of the Supplement-EZ Form.
- 1x hard copy (2x hard copies for plans) & 1x electronic copy of anything else needed to address these
comments.
1
Hard copies should be mailed to me at the following address:
For FedEx/UPS:
Jim Farkas
512 N. Salisbury Street, Office 640E
Raleigh, NC 27604
For USPS:
Jim Farkas
1612 Mail Service Center
Raleigh, NC 27699-1612
Hand Delivery:
Please reach out to me prior to hand delivering a submission to make sure that I (or someone else in my group)
will be able to receive the submission. Do not leave the package in the foyer with the security guard.
NOTE: Hard copies should not be sent to a Regional Office. Doing so will delay the review process and the
submission package may be lost while being sent from the Regional Office to me in the Central Office.
Electronic copies should be uploaded at the following location:
https://edocs.deq.nc.gov/Forms/SW-Supplemental-Upload
Since these are really minor things, once I get the hard copies, anything else that may have changed from addressing
these issues, and the documents are uploaded to Laserfiche (Provided everything is still in order), we can issue the
permit without doing another formal review.
Let me know if you have any questions.
Jim Farkas
Environmental Engineer
North Carolina Department of Environmental Quality
Division of Energy, Mineral, & Land Resources – Stormwater Program
512 N. Salisbury Street
1612 Mail Service Center
Raleigh, NC 27699-1612
(919) 707-3646
Jim.Farkas@ncdenr.gov
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
Based on the current guidance to minimize the spread of COVID-19, the Department of Environmental Quality has
adjusted operations to protect the health and safety of the staff and public. Many employees are working remotely or
are on staggered shifts. To accommodate these staffing changes, all DEQ office locations are limiting public access to
appointments only. Please check with the appropriate staff before visiting our offices, as we may be able to handle your
2
requests by phone or email. We appreciate your patience as we continue to serve the public during this challenging
time.
From: Farkas, Jim J
Sent: Thursday, January 13, 2022 1:31 PM
To: Chad Abbott <chad@c3designeng.com>; craig.morrison@cimarronhomes.com
Cc: Eplin, Tamera <tamera.eplin@ncdenr.gov>
Subject: SW4210801; Holt Farm
Good Afternoon,
The Division of Energy, Mineral and Land Resources (DEMLR), received a Stormwater Management Permit Application
nd
for the subject project on November 22, 2021. A review of that information has determined that the application is not
complete. Attached is a letter describing the items that need to be submitted. If you have any questions, please feel free
to contact me. My contact information is listed below.
Thank you,
Jim Farkas
Environmental Engineer
North Carolina Department of Environmental Quality
Division of Energy, Mineral, & Land Resources – Stormwater Program
512 N. Salisbury Street
1612 Mail Service Center
Raleigh, NC 27699-1612
(919) 707-3646
Jim.Farkas@ncdenr.gov
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
Based on the current guidance to minimize the spread of COVID-19, the Department of Environmental Quality has
adjusted operations to protect the health and safety of the staff and public. Many employees are working remotely or
are on staggered shifts. To accommodate these staffing changes, all DEQ office locations are limiting public access to
appointments only. Please check with the appropriate staff before visiting our offices, as we may be able to handle your
requests by phone or email. We appreciate your patience as we continue to serve the public during this challenging
time.
3