Loading...
HomeMy WebLinkAbout20201285 Ver 1_More Info Received_20220610Strickland, Bev From: Anna Reusche <AReusche@sepiinc.com> Sent: Friday, June 10, 2022 1:54 PM To: Phillips, George L CIV USARMY CESAW (USA) Cc: Cohn, Colleen M; Mike Taylor Subject: [External] RE: Arbor Creek - Middle Creek Greenway / Holly Springs / Wake County / SAW-2020-00572 / Request for Additional Information Attachments: Arbor Creek USACE Comment Response Letter.pdf CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to Report Spam. Good afternoon, Responses to the comments below are addressed in the attached. Please don't hesitate to let me know if you have any additional questions regarding this project. Thank you, ANNA REUSCHE, PWS Senior Environmental Project Manager SEPI, Inc. One Glenwood, Suite 600, Raleigh, NC 27603 919.747.5865 D 919.816.7745 M Celebrating Twenty Years From: Phillips, George L CIV USARMY CESAW (USA) <George.L.Phillips@usace.army.mil> Sent: Thursday, May 12, 2022 3:01 PM To: Anna Reusche <AReusche@sepiinc.com> Cc: Cohn, Colleen M <colleen.cohn@ncdenr.gov> Subject: Arbor Creek - Middle Creek Greenway / Holly Springs / Wake County / SAW-2020-00572 / Request for Additional Information CAUTION: External email. **NEVER CLICK or OPEN** unexpected links or attachments. **NEVER** provide your user ID or Password. Send all suspicious email as an attachment to Report Spam. Ms. Reusche, I have reviewed the above referenced project and have the following questions/comments that need to be addressed to evaluate the project. 1) Cumulative permanent wetland impacts for this project exceeds the 0.1 acre threshold and per general condition 23, the district engineer will consider the following factors when determining appropriate and practicable mitigation necessary to ensure that the individual and cumulative adverse environmental effects are no more than minimal. The mitigation plan included with the application only accounts for crossings that exceed i 0.1 acre. While single and complete crossings can be viewed as separate for NWP authorization, mitigation is viewed as cumulative and wetland loss for the entire project would require mitigation. Please provide a compensatory mitigation plan that accounts for the cumulative impacts for the entire project. 2) Cumulative permanent stream impacts for this project exceeds the 0.02 acre threshold and per general condition 6 any NWP that results in a loss of more than 0.02 acres of stream bed, the permittee shall provide a mitigation proposal to compensate for more than minimal individual and cumulative adverse impacts to the aquatic environment. The mitigation plan included with the application does not address stream loss. While single and complete crossings can be viewed as separate for NWP authorization, mitigation is viewed as cumulative and stream loss for the entire project would require mitigation. Please provide a compensatory mitigation plan that accounts for the cumulative impacts for the entire project. 3) The proposed activities include permanent wetland loss for grading and paving for construction of the greenway trail. The need for a greenway is not disputed; however, it is unclear if the project has demonstrated avoidance and minimization to the maximum extent practicable as required by NWP General Conditions 23(a) and (b). Based on previous experience and past projects, raised piling boardwalks can been used within wetland areas to minimize impacts to wetlands. Please redesign or provide information to support grading and paving the greenway within wetland areas. 4) The proposed activities include the permanent discharge of fill material (loss of waters and no loss of waters) within stream channels for culvert installation (loss) and rip rap installation (no loss). The need for a greenway is not disputed; however, it is unclear if the project has demonstrated avoidance and minimization to the maximum extent practicable as required by NWP General Conditions 23(a) and (b). For example, based on previous experience, past projects and some crossings on this project raised bridges can be used to cross stream channels to avoid impacts to streams. Please redesign or provide information to support installation of culverts and riprap within stream channels. I have attached NWP 14 and conditions to help assist you in addressing the above comments/questions. Please submit the above information within 30 days of receipt of this Notification or we may consider your application withdrawn and close the file. Please call or email (George.L.Phillips@usace.army.mil) me if you have any questions. Lyle Phillips Regulatory Specialist US Army Corps of Engineers CE-SAW-RG-R 3331 Heritage Trade Drive, Suite 105 Wake Forest, North Carolina 27587 Phone: (919) 554-4884, Ext. 25. Fax: (919) 562-0421 Email: George.L.Phillips@usace.army.mil We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is located at https://regulatory.ops.usace.army.mil/customer-service-survey/ . Thank you for taking the time to visit this site and complete the survey. 2 SI RALEIGH: 1 Glenwood Avenue, Suite 600, Raleigh, NC 27603 E P OFFICE: 919.789.9977 / FAX: 919.789.9591 / WWW.SEPIINC.COM June 10, 2022 Mr. Lyle Philips USACE - Regulatory Division 3331 Heritage Trade Drive, Suite 105 Wake Forest, North Carolina 27587 Re: Response to Request for Additional Information Arbor Creek - Middle Creek Greenway (SAW-2020-00572) Holly Springs, Wake County Dear Mr. Philips, The following includes responses to the additional information request received May 12, 2022, from the U.S. Army Corps of Engineers: 1) Cumulative permanent wetland impacts for this project exceeds the 0.1 acre threshold and per general condition 23, the district engineer will consider the following factors when determining appropriate and practicable mitigation necessary to ensure that the individual and cumulative adverse environmental effects are no more than minimal. The mitigation plan included with the application only accounts for crossings that exceed 0.1 acre. While single and complete crossings can be viewed as separate for NWP authorization, mitigation is viewed as cumulative and wetland loss for the entire project would require mitigation. Please provide a compensatory mitigation plan that accounts for the cumulative impacts for the entire project. Permanent wetland impacts have been further reduced for the project. Revised impact maps are attached. In addition, compensatory wetland mitigation has been identified for the entirety of the project. A 2:1 mitigation ratio was assumed for all impacts except the boardwalk removal. A 1:1 mitigation ratio has been assumed for impacts associated with the boardwalk removal. Copies of the Statement of Availability Letters are provided in the attached. 2) Cumulative permanent stream impacts for this project exceeds the 0.02 acre threshold and per general condition 6 any NWP that results in a loss of more than 0.02 acres of stream bed, the permittee shall provide a mitigation proposal to compensate for more than minimal individual and cumulative adverse impacts to the aquatic environment. The mitigation plan included with the application does not address stream loss. While single and complete crossings can be viewed as separate for NWP authorization, mitigation is viewed as cumulative and stream loss for the entire project would require mitigation. Please provide a compensatory mitigation plan that accounts for the cumulative impacts for the entire project. 000000000000000 000000000000000 SEPI Permanent stream impacts have been further reduced for the project. Revised impact maps are attached. In addition, compensatory stream mitigation has been identified for the entirety of the project. A 2:1 mitigation ratio was assumed for all permanent stream impacts. 3) The proposed activities include permanent wetland loss for grading and paving for construction of the greenway trail. The need for a greenway is not disputed; however, it is unclear if the project has demonstrated avoidance and minimization to the maximum extent practicable as required by NWP General Conditions 23(a) and (b). Based on previous experience and past projects, raised piling boardwalks can been used within wetland areas to minimize impacts to wetlands. Please redesign or provide information to support grading and paving the greenway within wetland areas. The Town of Holly Springs Parks, Recreation and Greenway Master Plan's identified project corridor for this project follows Middle Creek between Sunset Lake Road and Holly Springs Road. Wetlands were mapped for the project and are almost continuous along the corridor. SEPI approached this project as an iterative design, studying multiple alignments to minimize the impacts to the maximum amount practicable. Boardwalk crossings were generally not a viable solution through much of the project due to the trail's location within the floodplain and Floodway. The structures create a blockage within the FEMA flood model, and result in an increase depth of upstream flood waters. The extensive wetlands also create limited access points and boardwalks can create large sections of asphalt trail that would become isolated (located between two boardwalks). Trail bridges and boardwalks are not designed to support loading associated with future grading and paving activities. Future maintenance operations would have to construct temporary access roads around the boardwalks, through the wetlands to access the isolated paved portions of trail. Specific examples are as follows: • At the Sunset Lake Road connection (northern most part of the trail), the original trail alignment would have removed the existing failing boardwalk and replaced it with an asphalt trail on fill. To avoid this wetland impact, easements were acquired on private property to move the trail out of the wetland. This trail relocation resulted in reducing permanent wetland impacts by approximately 0.62 acres. Near the middle of the trail between Bridge 1 and the largest wetland crossing (WI), the original trail alignment more closely followed the sewer easement closer to Middle Creek, with a spur trail to connect to the trail head. This alignment resulted in large parallel impacts along the wetland. To avoid these impacts, the trail was moved upland, outside of the wetland boundary, and crossed the wetland perpendicular at two locations. This trail relocation resulted in reducing permanent wetland impacts by approximately 0.78 acres. = 000000000000000 000000000000000 SEPI • Removed trail spur connecting to Aldenwood Place. This spur would have been constructed entirely in the wetland. Removal of this spur section resulted in reducing permanent wetland impacts by approximately 0.20 acres. • Boardwalk 'A' is used to cross the southeast end of Wetland WJ. The use of boardwalk in this location resulted in reducing permanent wetland impacts by approximately 0.07 acres. • Boardwalk 'B' is used to cross stream SJ. The use of boardwalk in this location resulted in reducing permanent stream impacts by approximately 20 linear feet. • Boardwalk 'C' is used to cross stream SI. The use of boardwalk in this location resulted in reducing permanent stream impacts by approximately 20 linear feet. 4) The proposed activities include the permanent discharge of fill material (loss of waters and no loss of waters) within stream channels for culvert installation (loss) and rip rap installation (no loss). The need for a greenway is not disputed; however, it is unclear if the project has demonstrated avoidance and minimization to the maximum extent practicable as required by NWP General Conditions 23(a) and (b). For example, based on previous experience, past projects and some crossings on this project raised bridges can be used to cross stream channels to avoid impacts to streams. Please redesign or provide information to support installation of culverts and riprap within stream channels. We relocated the trail outside of wetlands where possible, and designed stream and wetland crossings to be as perpendicular as possible. When pipes were needed, concrete endwalls were used to further minimize the pipe length and the impacts to streams and wetlands. In addition, as stated above: • Boardwalk 'B' is used to cross stream SJ. The use of boardwalk in this location resulted in reducing permanent stream impacts by approximately 20 linear feet. • Boardwalk 'C' is used to cross stream SI. The use of boardwalk in this location resulted in reducing permanent stream impacts by approximately 20 linear feet. 000000000000000 000000000000000 SEPI If you have any questions, please don't hesitate to contact me at areusche@sepiinc.com. Sincerely, Anna Reusche, PWS Environmental Project Manager SEPI, Inc. 000000000000000 000000000000000 SEPI Revised Impact Maps 000000000000000 000000000000000 ARBOR CREEK BRIDGEV WETLAND IMPACTS IMPACT LOCATION PERMANENT IMPACT AREA (AC) SHEET 1 0.02 WA-1 2 0.0002 WA-1 3 0.006 WA-1 4A 0.09 WA-2 413 0.001 WA-2 5 0.02 WA-3 6 0.35 WA-4 7 0.001 WA-5 8 0.0005 WA-5 9 0.0007 WA-5 10 0.04 WA-6 TOTAL 0.53 OARDWALK INSTALLATION IS BEING CONSIDERED A CONVERSION AND IS MITIGATED AS 1x1 800' 400' 0 SCALE: 1" = 800' S=;)1 SEPI ENGINEERING & CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE BEAUFORT, SC I CHARLESTON. SC 1 GLENWOOD AVE. I SUITE 600 RALEIGH, NC 27603 PHONE 1 919.789.9977 Sepiinc.com BEFORE YOU DIG Know wh&S below. FOR Call before you dig. CO STRUCTION SITE SAFETY IS THE SOLE NSIBILITY THECONTRA TOR NEITHER THE OWNER NOR THE ENGINEER LTYFOR SAALL BE apFEETYOFTHNEARBWORRK OCTEDTOAF PSUMEANYRESPO ESSONONGAGEONY HIBN THE WORKOF ANY I I sF0 12' ItkO,21 ? op90R4l�1��': SEAL is= C-2197 c N. C COPYRIGHT. -I Arbor Creek - Middle Creek Greenway Town of Holly Springs Parks and Recreation PREPARED FOR: Town of Holly Springs 128 S. Main Street Holly Springs, NC 27540 PRELIMINARY NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenwav [il Rev. Trail Grading A Rev. Now Trail ® Rev. Per Town Comments "GI: M. TAYLOR 'N BY: S. TEYMOURI KED BY: M. TAYLOR W ETLAN D IMPACT COVER WA-0 I WETLAND IMPACTS IMPACT LOCATION PERMANENT IMPACT AREA (AC) TEMPORARY IMPACT AREA (AC) 1 0.02 0.01 2 0.0002 0 3 0.01 0 BOARDWALK REMOVAL - 0.26 SUBTOTAL 0.02 0.27 SEPI — SEPI ENGINEERING & CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE BEAUFORT, SC I CHARLESTON, SC 1 GLENWOOD AVE. I SUITE 600 RALEI( NC 27603 PHONE 1 919.789.9977 /L— sepiinacom RK NO AYS s • Ro_ D E: / E YOU DIG Know what's below FoORBEFOR —n y Call before you dig. AlY All ALL 1— LTILD11 Nonce CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER SHALL BE EXPECTED TO ASSUME ANY RESPONSIBILITY FOR SAFETY OF THE WORK, OF PERSONS ENGAGED IN THE WORK, } OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. } Z14 0530321 �21 '�NEy'�`�.��� ` 12FOi3.�f` AL T - -2197 001FIGILT. -I Arbor Creek - Middle Creek Greenway Town of Holly Springs I Parks and Recreation 50' 25' 0 SCALE: 1" = 50' PREPARED FOR: Town of Holly Springs 128 S. Main Street Holly Springs, NC 27540 PRELIMINARY NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway & Rev. Trail Grading ® Rev. Now Trail ® Rev. Per Town Comments ,GR: ..TAYLOR BY: iEY S. EN TY: M. TAYLOR WETLAND IMPACT AREA 1 WA-1 WETLAND IMPACT AREA 413- + © " N + PERMANENT: 0.001 AC + TEMPORARY: 0.005 AC 1 1 + + N+ + + 1 + + + + t 31 11 + + + + C + + + + + + m 1 11 +; `\+ + + + + + �; t t I+p ; + - �� + + i{• ``\ + f+ i + ANCHOR CREER ;+ + !I + + p 1 „,hry + + + + + + + t + n + + + + + + + wi \ + + + + + -F + I + `"i-`�\ + + + 1 + + + + + `� + I + + + + + 1 PI + + + i + `. + + + EX. SANITARY SEWER EASMENT (TYP.) EX. COLONIAL PIPELINE EASMENT (TYP.) WETLAND IMPACT AREA 4A - PERMANENT: 0.09 AC TEMPORARY: 0.06 AC PROPOSED GREENWAY TRAIL 10' WIDE, PAVED (TYP.) 9\ G 1 + + + `f + f- + + I+ + \ ; iG + \ ` tz © 1 1 + + � + + + + + + RIPARIAN BUFFER- ZONE 2 (TYP.) RIPARIAN BUFFER- ZONE 1 (TYP.) IN, \9 sn Ey� v °PIN F oas9^�_ �h WETLAND IMPACTS IMPACT LOCATION PERMANENT IMPACT AREA (AC) TEMPORARY IMPACT AREA (AC) 4A 0.09 0.06 4B 0.001 0.005 SUBTOTAL 0.09 0.07 V- + + + (� + + + + + + + �O C 11 11 + + + ; � � ems' 1 - F - - + + + + + 7 + + ;+ + + 0+ + + + + + + + 6 I 1 +11� + ; + ; + + + ' + + +' + + + + + + + + %+ + + + + + + + + + + + I 0 l + + + + + + , + + + + + + + , + + + + r �1 I 1 + ;+ + + + �o t +a + 4) + a+ + 40 +\ + + + + + I + + `, +© + + + + + O+ + t + + + + ; + �+ + + + + + + + + + ; + + 1 + + + + + +; + �I + + �+ + EXISTING \+ + + + 1+ + + + + ZONE1 1' + `\+ I+ + I + + WETLAND (TYP) F; + + + I� + + + + + + .... + + + + ... + + + \+ + I + + I + + + .t + +IN + + I �+ + + + + + + ; + + + + + + + + + + \ -`N411 + + + + + . + + + + + + + + + + 0_;1+ -k + + + + `.+ + + + + + + + + + 0 \ 1++ +I + + + + ``+ + + + + + + + + + + + + + + + + + + + + + + + + + 0; + +� + + + ,+' + + + + + + + + + + \ -- + + +I + + + + + + t t t t t t t + + 100, 50' 0 SCALE: 1" = 100' S=�1 SEPI ENGINEERING & CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE BEAUFORT, SC I CHARLESTON, SC 1 GLENWOOD AVE. I SUITE 600 RALEI( NC 27603 PHONE 1 919.789.9977 SepiinC.Com AIS • No o°EINo DcsUEs BEFORE YOU DIG Know what's below. FOR TMr Call before you dig. NOTICE CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER SHALL BE EXPECTED TO ASSUME ANY RESPONSIBILITY FOR SAFETY OF THE WORK, OF PERSONS ENGAGED IN THE WORK, OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. SEAL 053032 'A1- 2 „2 AL i== -2197 Q N;c; SEPI ENGINEERRIING Ig COH CONSTRUCTION, INC Arbor Creek - Middle Creek Greenway Town of Holly Springs Parks and Recreation PREPARED FOR: Town of Holly Springs 128 S. Main Street Holly Springs, NC 27540 PRELIMINARY NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway & Rev. Trail Grading ® Rev. Now Trail ® Rev. Per Town Comments NGR: M.TAYLOR J BY: S. TEYMOURI ED BY: M. TAYLOR WETLAND IMPACT AREA 2 WA-2 ;+ +; ;+ + + + + + + + + + + + + + + + + + + + + + + + + + + + + + + + + + i + + + + + + + + + + + + + — — — — - ; + + ; + + + + + + + + + + + + + N + iT + + + + + + + + + ;_'+' + 1 "--------------i J + + + + + + p I+ + + + 4F + + + + + + + + + + + I I + ; + + + + + + -+ + + + j r + + + + + + + + + + \�+ +\ + + `* + + + + + + + + + + + ;+ '� + ;+ + + + + + 'T + I J,, ; ; ' + + + f + + + + ; + + + + + + +, 1 I 1+ + +; + + + + + .... + + + + + + + + + zl I + + + + + . .... + + + + + + + + '`,+ ,+ + + + + ' + �+ + + + + + + + + r + + i + + + + +' + + + + + + + + + + + + ' + + '` + + + + + + + + + .� + .... + + + + + \ s° II I ' + + + + + EXISTING + + + "+ + + + + WETLAND (TYP) + + -V I I `+ + + + + +� + + + + + + / T +``\ +`, + + + + + . + + + N S T_ + / \ �\+ + + + + + + + + ; + - -+ + + + 00 + + + + + + + + + + + +`, + ..... _+ + + + + + + + + + + + + + '+FUTURE LOCKLEY + + + + + +`, + ROAD R.O.W. + + + } + +„ k. + + + + + + + a +'-+ + EX. SANITARY SEWER + + + EASMENT (TYP.) + + 7f + +++ ++RIPARIAN ++` 41- + -H + - BUFFER- ZONE 2 + +,'` + + + I+ + + (TYP.) + + N +I + + + RIPARIAN + + +;+�,+ + + I+ +; + BUFFER -ZONE 1 + + i+`, + I I I + + ``, + + + + + WETLAND IMPACTS IMPACT LOCATION PERMANENT IMPACT AREA (AC) TEMPORARY IMPACT AREA (AC) 5 0.02 0.03 SUBTOTAL 0.02 0.03 SEPI SEPI ENGINEERING & CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE BEAUFORT, SC I CHARLESTON, SC 1 GLENWOOD AVE. I SUITE 600 RALEI( NC 27603 PHONE 1 919.789.9977 SepiinC.Com PROPOSED , / — , � , 4 lWORKl NG DAYS BEFORE YOU DIG oa me GREENWAY TRAIL - ! ° °'"L FAIE T �`""° KDDwWbGr:below�No�IaoUNOFA��L"� 10' WIDE, PAVED (TYP.) ' \ call before you dig. 1 \ 1 \ T ` \ WETLAND IMPACT AREA 5 - I ' ll P ERsE°NY LE1�o�—a; LIL1r=.o°a Eo< �µo PERMANENT: 0.02 AC \ NONCE THEI , I , , , THE CONTRACTOR O TRACTSRESAFER THE OWNER SOLE NOR THE ENGINEER SUME ANY RESPONSIBILITY FOR TEMPORARY: 0.03 AC \ `''` ; I \ \ SRESPONSIBILITY OF AFEIYALL BOFTTHE WORK OXPECTED TO AF PERSONS ENGAGED IN THE WORK, X�%/ _ — , •` �, `, `, ,``, Y` ; ; ,` `Y` —` — —_- \ OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. CURRENT END OF T T _- -- " STREET - LOCKLEY RD. --- ' ----------- -- ;°'4°uy'°-� T I `, `1 SEAL -053032 -- AL -2197 11 t j "` `` �` '` ``� `` `` ``� •` - _ _ ``` `` ``` ``` ``` ' - LCOPJc a CONSTRUCTION, Arbor Creek - - `-- -------- Middle Creek Greenway Town of Holly Springs Parks and Recreation o\_N1, o� 100, 50' 0 SCALE: 1" = 100' PREPARED FOR: Town of Holly Springs 128 S. Main Street Holly Springs, NC 27540 PRELIMINARY NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway & Rev. Trail Grading ® Rev. New Trail ® Rev. Per Town Comments NGR: M.TAYLOR J BY: S. iEVMOURI ED BY: I M. TAYLOR WETLAND IMPACT AREA 3 WA-3 ` + + + +' + + + + + + + + 1 PIN 1 0151311501 + r + \ +\ '+ + + + + + + -`+ + + 1 + + + ,%+ i `+ i11 + ` + + + +J(II+1 +\1 +\I + 1 + + + + + + + + -T +`___-'+ f' +1 T +`\ +`\ 1♦ + + + `- T./--'+ \T '` + + + + + + + + `I + + + +I + + +`♦ +`S`` T + + + + + +\\ +\ +; + RIPARIAN + + + + - + +`, + -f + + + + + +\ +\ ;+ + BUFFER- ZONE 2 +; + + + + )`'' '+ $. + + + + + + `,+ + (TYP.) '4. + + + + ; + + `,+ + \+ f/ `. + I+ RIPARIAN +`\ + .. + + + `I+ + .� + + - + + I + BUFFER- ZONE 1 ;E + + + + +`",+ + '+ , + + + r� ;r + .+ + + + ``+ + o (TYP) +; + �- > ©Y0 + 1�+ + + + 1+ + + `i, + 1 + m + T `S + + + + + + T'+ + " + +`. + + + ` + + +`♦ +---T i ' I m �O + I + I +'T + + + + 4- 4 4- '4- + + ♦+ + + , + +`. + +`. + ; , + + + + 4- + + EXISTING °65`°"s` e I WETLAND (TYP) _ =a♦�\` —\ate\ ♦♦`` � -''/ -' ' Lo_Lo 1 0 , - \ S P I SEPI ENGINEERING & CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE BEAUFORT, SC I CHARLESTON, SC 1 GLENWOOD AVE. I SUITE 600 RALEIGH, NC 27603 PHONE 1 919.789.9977 SepiinC.Com / OO�. p' + + + + '+ + + + + + + + + + + +\ + + «oas9<,I' + I+ + + f -- f + + / + _ +__-+ + + ` \+ + + + + ` + t + \ + + + r +, + +'T + + +v + + �,+ + +. + + + aQa w9 U + + + I +: + + - 4 + + + + + + + + + f + + k + + + + + \ `\ + + . I+ : + + + + +' + +'; + + + + + + + ,+ + 4, + + + -+ +♦ T / , + + + I f ++ Y+ +�' + + + _P + + + + + +" + + + + + + + ... + + + cF + + + +`, + + +` + + -- k- + + - ___ 4y; + +' + + + +' + + + + + + + + + ``, + + + + + * -- + - ` +" + #�, + + + + + +. + + + + ;- + +; + + +---+ + + `k_ + + + + + ♦ �+ + + + + + + `.. + + + +.-_T + I\+ + +-'' + ♦`♦'� + + _ _ + +``. T + /t + + + ' + + + + + + ... + + .... \+ +` + + + + + ♦-_-+'-_+ + + --+--- --------- + r + + + + `,+ WETLAND IMPACT AREA 6 - - + + ; + +`I + + + + + + + +" -+K, + + + + + + + + -- f PERMANENT: 0.35 AC + + -0 + + + \`+' + + - ---+ .-- -- + t__-+ + _+_ -� ---+ + + + + + + + + + + ,\-� t + `ir TEMPORARY: 0.12 AC + + `•,+ .. + + + + + + + -- + + `,+ + + + + + + + + + y + T ' + + + + ♦ +.' + + + + + + + + + + `, + + + + ♦ ♦ ♦+ + + + + I + + + +---t + + + + + ++ + + + + \ -� +, + + + + + + + - + + + + + + + + + + + + + + •.+ + -♦+ + + + + + + + + + + + + ♦\I+ +__ +' -__ _- + 4 - -- "; ,; -+ o I + + + ; '+ + EX. SANITARY SEWER + + + + +` `+; F + - ``+ + + + + + + --+, + + + + + + + + + m I / + + +-''+ _+, + EASMENT TYP. ( ) + + + + + + + + +_-, + + + + + + + + + + + + + + + 0 I/ + + a + + +--+..+-__+ i +,-' 4 + + + + + -f� + +`, EXISTING + + + + + + + + + + + + + + + + + + + + + + + + + + + + + + m f PROPOSED WETLAND TYP o i + + + + GREENWAY TRAIL + + + + `,+, `, + + + + + + + + + ..... ;- + + + + + + $ 11 +; -----__- +,. + + + * -_ 10' WIDE, PAVED (TYP.) + + + + + + + + +'`\ "P. + + + + + + + + + + + + + + + + + + + + `, + + + + + + + + --♦♦ + + + +___�-' + + - ;+ ,-'+ ;+_: }-.;�-, + + + -. + + + + + + .... + + ; t + + + + + + + + + .... + + + + `- F + + `-� +\,♦ + �♦ ♦ '� -+ + + + + + + + + + + + + + I + + + + + + + + + + + '\ + 4- + + + + + + + + ;'k,--+ + + + + + + + + + + + `+ + +' + + ' + + + + + + + + + + + + + + + ``+ - :+� + F + + + + +;"\+ + + + `+ + +.'I + + + + + + + + + +' + + .f + + + + +' `' + + + + + + +-' +--+--_+ '*-- + +"\+ + + + + + + + + + + + + + + ..... + + + + + + + +-' + + + +_♦ + ; �; ;+ + + + + + ..... + + + + + ..... + + + '+ _-` + + + + + +'-` t + + + + + + + `-+,- F + ♦.+ ♦-+-__T + + + + -+--♦+ ;+ \ + + + + + + + + +, +� + + ... + + + + + + + + + + + + + + 'L + + + + + 1+ ;\. + + + + +' •' + + + + + + + +\ + - + +\ + + , + + + + WETLAND IMPACTS IMPACT LOCATION PERMANENT IMPACT AREA (AC) TEMPORARY IMPACT AREA (AC) 6 0.35 0.12 SUBTOTAL 0.35 0.12 100, 50' 0 SCALE: 1" = 100' AYS • o a _ D<<°E, BEaFORE YOU DIG Know what's below. Call before you dig. NOTICE CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER SHALL BE EXPECTED TO ASSUME ANY RESPONSIBILITY FOR SAFETY OF THE WORK, OF PERSONS ENGAGED IN THE WORK, OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. `��HtnHC,dRpu� SEAL 053032 q� R 12 -I AL ik -2197 t sEPI ENG—RING Ia CONsmUICTION, INC Arbor Creek - Middle Creek Greenway Town of Holly Springs Parks and Recreation PREPARED FOR: Town of Holly Springs 128 S. Main Street Holly Springs, NC 27540 PRELIMINARY NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway & Rev. Trail Grading ® Rev. Now Trail ® Rev. Per Town Comments PROJ.MGR: M.TAYLOR DRAW N BY: 5. iEYMOURI CHECKED BY: 1 M. TAYLOR WETLAND IMPACT AREA 4 + + + + + + + + + +KT1+ .-+�— + + + + + + + +; +--+ + + + + + + 11 + + + +'1 _+ _+ + + L+ �+ + + + + + + + + + + + + + + + + `l``+ `+ + + 1I + + + + + + + + 4-1'+ + + + + + + 4--- + l- + + —'+ + +��'+---+ + l + + + + + + + EXISTING + + + + + + + + + + + + t + + + + + + + + _f "- --`+ -_+ + 1, + `,+ + + + + + + + + + + '-+--.+ + WETLAND (TYP) + + + + +; + + + + + + + + + + + + + + 4-' + + + `+-- + 4. + + + + + + + + + `i + + + + + +--+--.+ + + + + + + + + �+ + + + + + + + + + + + '+r 4 + + + +_ �' + �"--�-, + + +- + + +T + + + + + + + + + + *_--+' + 1' + + + ``, + -/F. + + + + + + + + + ' + + -� i -�'' �^+ / + + 4 + + + + ;+ + + WETLAND IMPACT AREA 7 - + + + +' + +`, 4- + + + 4 + + + + + EXISTING + + +,% +.% + + �-, + + + + + + + + + + + WETLAND (TYP) + + ~ + +-', j + +-,, +---� PERMANENT: 0.001 AC + + + + WETLAND IMPACT AREA 8 - + +''--I-_, + + + + + + + + + ;'+ + + + + + +-- +; --_+ + + TEMPORARY: 0.003 AC + + PERMANENT: 0.0005 AC + + r +'`, + + .... + + + + + + + + + _ + + + + '+ `,+ +"I. + + + + + + + + + + + - - -+ TEMPORARY: 0.004AC + + -'�; +`, + + +; + + + + -+ + +� + +''-+--+-":L+ + + + + + + + + + + `+ + + + + + + -- PROPOSED + + + + EX. SANITARY SEWER F + +, 4 + PROPOSED + + +_ + + + + + + + + + ;+ v+ + + , + + + EASMENT (TYP.) + + + + + + + % * + + + + • + + + + + GREENWAY TRAIL + + `+ GREENWAY TRAIL 10' WIDE, PAVED TYP. _+ *---+ + I. + + + + 10' WIDE, PAVED (TYP.) + + +1 + 4" + + + + + +" + -+ +. + + + + + + + + + _++ + + + + + i + + + ` + 4;+ + ``+ - + -- \(+ -F + (( + + + + '♦- `�` .---------T `� L f 1+ + '- EXISTING } 1. + \ ___- - - -� WETLAND (TYP) >a S=�1 SEPI ENGINEERING & CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE BEAUFORT, SC I CHARLESTON, SC 1 GLENWOOD AVE. I SUITE 600 RALEI( NC 27603 PHONE 1 919.789.9977 + + /+ /+ + +i' sepiinc.com + + � + +--' 4 / + +/+// + + + + yy \+ \+ T + + , + + DAYS BEFORE FORE YOU DIG �4\\ + \( + + + + + Know what's belOwU��`a�aooNOFA�i�inE: Call before you dig. +\ +\ + + + +\ + All ALL uuoFxcaouuo ununFs . ANY NOTICE CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER FOR '---NC GRID z 4 nil SHALL BE EXPECTED TO ASSUME ANY RESPONSIBILITY THEY SAFPERSONS ENGAGED IN THE W RKTURES, +\11 SSTTRU OF ANY RBF OR OF ANY OTHER PERSONS. + + i \ + + 4 053032 + + +.- + + + \+ '' + �qA( iNE ` ' +. +`+ + +4 12 � _� \ Y/. ,. \ '--- + + + + + - ---- 0 V VI P`+ +` + `` `o A�l� RIPARIAN BUFFER- ZONE 2 (TYP.) ?ONE 1 WETLAND IMPACT AREA 9 - PERMANENT: 0.0007 AC sRSSOIN %011�WO / W LTLAND IMPACTS IMPACT LOCATION PERMANENT IMPACT AREA (AC) TEMPORARY IMPACT AREA (AC) 7 0.001 0.003 8 0.0005 0.004 9 0.0007 0 SUBTOTAL 0.002 0.007 + \} + + + + + + + + ` -+ +'T + + + + + - + 4 SEPI ENCI= ac H=010N, INC \ - + + ,.+ + + + -- s waoas 100, 50' 0 SCALE: P = 100' Arbor Creek - Middle Creek Greenway Town of Holly Springs Parks and Recreation PREPARED FOR: Town of Holly Springs 128 S. Main Street Holly Springs, NC 27540 PRELIMINARY NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway [� Rev. Trail Grading ® Rev. Now Trail ® Rev. Per Town Comments PROJ.MGR: M.TAYLOR DRAWN BY: S. iEYMOURI CHECKED BY: 1 M. TAYLOR WETLAND IMPACT AREA 5 PlN xocsv 11093 I / , i 1 / 1 1 I,' a S ' 1 I tY J I l I I 1 ` nl _ , , I 1 I , / 1 1 + ,-+— +___+ + +---------- --= ---- PROPOSED — + + + —+� _+ + +'`, + GREENWAY TRAIL \ + + + ` + + + + + + + + + + 10' WIDE, PAVED (TYP.) + + + + + + + +, + + '`+ + + + _+"-'+ f-__- + + + + + + + + + + + + + + + `+ + + ,—+ + + + i WETLAND IMPACT AREA 10 — ` + + + + +` , + `` + + + + + + + + PERMANENT: 0.038 AC + + + + + + + + +:, + '--+ + +___+ + '+'—_- __+_ TEMPORARY: 0.068 AC + + + ,_+ I + + + + + + + + + + + + + + + + + + 't + + + ' + + + + + + + EXISTING + + + PROPOSED BOARDWALK + + + + ; + +;' WETLAND (TYP) + + +; + ± 1,647 SF + + + .I+__Fr- ''+ ;+ + + + i` + + + + + ;+ ,+-1�. •t + + + + -I- + + + + +/ TI + + + + +I + "+ f +` +__ + I + + + ; + + ; + + + + + + + EX. SANITARY SEWER _.�. + _t + 4- + ;-; .+;' + + + + + + + + +; + EASMENT (TYP.) - - — r _ + + + + ;+ t T T T - , ti + + + + + + \+ \ + :. + _+ + + + + / + + + + + +! + + t t i 02 o , a n Toiri"�'�, eN>oas"°�Ho� LID o NI5 t Wi- - / V \ l EXISTING WETLAND (TYP) / WETLAND IMPACTS IMPACT LOCATION PERMANENT IMPACT AREA (AC) TEMPORARY IMPACT AREA (AC) 10 0.038 0.068 SUBTOTAL 0.04 0.07 *BOARDWALK INSTALLATION IS BEING CONSIDERED A CONVERSION AND IS MITIGATED AS 1x1 SEPI \, \\ `` __—_ ---- ��_—_— --�' SEPI ENGINEERING & CONSTRUCTION, INC. __ \ jti ♦ RALEIGH I WILMINGTON I CHARLOTTE r \ 11 , \ , ` \ \ — `�-- _/-' `` ` BEAUFORT, SC I CHARLESTON, SC ��\\„ \ ` ` , ' / i - `, `, `♦`\ `� ♦ ` t 1 GLENWOODAVE. SUITE 600 ---------"''' RALEIGH, NC 27603 " i �/ --r'_- ♦` ` PHONE 1 919.789.9977 'i � ` ` \♦� ♦`♦ ` sepiinc.com _ — _` 3WORKING DAYS ____ " ♦�`♦, `♦` BEFOREYOU DIG `��` `�;♦` ``,\ \ ', - u oEre�reouNo,Ac,n\s , Know what's belOW. r + _+ _ _ k---+ call before you dig. RIPARIAN %% .1�%+i;'+ + + + +' + + + .; )NE - BUFFER— ZONE 2 '�' ,+ �-' +', + + + t ' + ` `` xAnLY1OCAiEµ� LT 20(TYP.) --:— - �'; :+ +' + ' + + + % + ; + +`, \`�`,�`N ; NO➢CE.N.ANOAILINoE=rea��oLlILr,\. / I ` ` , CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF + / + + / + /+ + ( + rt + `• THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER RIPARIAN +''-1+ + + + �+ + T + \ + + ,``\`` SAFEIYSHALL BOFTTHE WORK, OF PERSONS ENGAGED IN THEXPECTED TO ASSU.E ANY RESPONSIBILITY FWORK, /' / + , / + i + + I\, + +, + + ,, OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. BUFFER— ZONE 1 T T (TYP.) + EXISTING + +'`, }, isv°�'tii° 11 + WETLAND (TYP) + ` 1�\+ Q0 + Tip + I + I + , / +-' + T T T T T .'+ + I + `\ + `T `` _ ' / 05'4 3032 + + + '~F''-+ + +I + + + + I', + + + + + + + I i T AL `1� _ — ` ♦` --- _ __ \ -- __ G ` - - seal ENGINEERING & CONSTRUCILONINC Arbor Creek - I , I - ---- - -- Middle Creek Greenway ^ °♦ _ Town of Holly Springs Parks and Recreation PREPARED FOR: Town of Holly Springs S. Main Street Holly Springs, NC 27540 PRELIMINARY NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway E K/IC%l. P P E D USING DATE PROJECT: SE20.W7A0 100' 50' 0 SCALE: 1" = 100' Trail ® Rev. New Trail ® Rev. Per Town Comments NGR: M. TAYLOR J BY: S. TEYMOURI ED BY: M.TAYLOR WETLAND IMPACT AREA 6 WA-6 ARBOR CREEK BA-1 SA-1 SUNSET RIDGE NORTH RIPARIAN BUFFER & STREAM IMPACTS I PROJECTTOTAL AREA (SF) N OTES ZONE 1 ZONE 2 ALLOWABLE UPON AUTHORIZATION 54,965 39,818 LIMITS OF DISTURBANCE (CLEARING PLUS BUILT UPON AREA) BUILT UPON AREA I PERMANENT 19,602 131592 10' WIDE PAVED GREEN WAY TRAIL UL 1 111111111111111111111111111111 -= -,/_� PROPOSED GREENWAY TRAIL 10' WIDE, PAVED (TYP.) rr' ON) pr � ` ♦ IWIII � �, se—,ebi NO ��r sei SA-4 -5 i � • 800' 400' C SCALE: 1" = 800' SEPI SEPI ENGINEERING & CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE BEAUFORT, SC I CHARLESTON, SC 1 GLENWOOD AVE. I SUITE 600 RALEI( NC 27603 PHONE 1 919.789.9977 Sepiinc.com BEFRORE YOU DIG Knowwhat'S below. FO before III L11AT E, _.Alo l—, TAVI-11N you dig. N TICE CO STRUCTION SITE SAFETY IS THE SOLE NSIBILITY THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER BILITY FOR SA AETYSHALL BOF iH NY NEARBY OE EXPECTED TO AF PES 50 OR SUME ANY RANY OTOHSRO I I PERSONS. II S1011 SEAL 053032 pNC. �. 'Al2- „ AL i== -2197 Q N;c; TO SEPIENGINEERING CONSTRUCTION, INC Arbor Creek - Middle Creek Greenway Town of Holly Springs Parks and Recreation PREPARED FOR: Town of Holly Springs 128 S. Main Street Holly Springs, NC 27540 PRELIMINARY NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway & Rev. Trail Grading ® Rev. Now Trail ® Rev. Per Town Comments MGR: ..TAYLOR NEI S. TEY OURI "E 'Y: M. TAYLOR BUFFER/STREAM IMPACT COVER BA-0 �ZI ZONE 1 -Allowable Upon Authorization 4,432 SF �Z2— �—Z2 Z2 �Zl —Z1—Z1_ - ZONE 1 Allowable --= Upon Authorization ------_-___ - _==-- 1,213SF --_- -- -- _ _-_--- ZONE 2-Allowable �-z - _--_-_-_- - - - - Upon Authorization _ --- ' 615 SF - z2 EX. SANITARY SEWER - \ EASMENT (TYP.) / /^ rllvFruiDu- lu-aiva / C �O �O C" RIPARIAN BUFFER IMPACTS AREA (SF) NOTES ZONE 1 ZONE 2 ALLOWABLE UPON AUTHORIZATION 5,047 2,278 LIMITS OF DISTURBANCE (CLEARING PLUS BUILT UPON AREA) BUILT UPON AREA I PERMANENT 1,900 420 10' WIDE PAVED GREENWAY TRAIL T T T - T �T I + + + + + it N + + + + + + +/ + + + + + 4- 4- 4- 4- 4- I SEPI SEPI ENGINEERING & CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE BEAUFORT, SC I CHARLESTON, SC 1 GLENWOOD AVE. I SUITE 600 RALEI( NC 27603 PHONE 1 919.789.9977 SepiinC.Com RK NO AYS • oHo Ro _ D���E: BEFORE YOU DIG Know w1&S belOW FOR Call before you dig. ti Nonce CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER SHALL BE EXPECTED TO ASSUME ANY RESPONSIBILITY FOR SAFETY OF THE WORK, OF PERSONS ENGAGED IN THE WORK, OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. `��HuFHC�A,,R,ou IS904.'%9'� SEAL 053032 pNC. �. - 12 'A 12 AL i== -2197 Q N;c; CRING&C Nam' Arbor Creek - Middle Creek Greenway Town of Holly Springs Parks and Recreation 11 PREPARED FOR: �111 Town of Holly Springs 128 S. Main Street Holly Springs, NC 27540 PRELIMINARY NOT FOR CONSTRUCTION 1 90% CONSTRUCTION DRAWINGS I I REF 09-012: Arbor Creek Greenway DATE PROJECT: SE20.027A0 �D NORTH 50' 25' 0 SCALE: 1" = 50' [� Rev. Trail Grading ® Rev. Now Trail ® Rev. Per Town Comments MGR: ..TAYLOR HEY: S.TEYMOURI UED BY: M. TAYLOR BUFFER IMPACT AREA 1 BA-1 �Z2 �\ \ — — — — — — —/ — — _ �• / / // \ 1• I I I SEPI ENG iI HEII W LMN. INGTON I CRHARLOTTE INC. RALEA BEAUFORT, SC I CHARLESiON, $C \\\` �p_p--_—� /•///////[_) 1 I L1 \ // / 1 GLENWOOD AVE. SUITE 600 1 1 + + �' / /' / / RALEI( NC 27603 —_-----_\ \ l� — 1 _—_ ����jj / / I / PHONE 1919.789.9977 SepiinC.Com PROPOSED 1 \ 3WORK INO DAYS BEFORE YOU DIG GREENWAY TRAILF's I 10' WIDE, PAVED (TYP.) / KnoCClllbefore0you dig. oNOF"cnE nroA.E o E�oa°ooRa"Po;a`oa'Araa'VAENI '`l ::wxCIT1 ANY All ALI 1­ LIL1111 N TICE CONTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF / _ 2 THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER / Z'1 ° + / + / / / / \ / \ SHALL BE EXPECTEDTOASSUMEANYRESPONSIBILITYFOR SAFETY OF THE WORK U PERSONS ENGAGED IN THE WORK, N/F I \ � Y / 1 OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. IF ARBOR CRR[ HOMEOWNI I ASSOC INS — \ PIN # 0750-10f923 \ 053032 SEAL —Z2— _Z2 Z2_�Z2 / O ~ \ `•,�gq�'' / 2 / 12,�� —Zl _— —_— / I J_ PERMANENT STREAM IMPACT _ _ 22 LF RIP RAP 469 SF ClPERMANENT STREAM IMPACT i ' ` -z97 _ / + NOT MITIGABLE 6 18 LF I � Co RI�T®-, ` ----_—_ --- + 426 SF + — _ _ RIPARIAN NGIN RNDaeDNSRU ON, INC _— —_---- ;;------ + + ? - BUFFER- ZONE 2 + -� ArborCreek- ----------- — \ \ I° �ti -� -------------- z,-- --�_ �::\\� '! \ + z ti° (TYP.) + + Middle Creek _-_ -_�_ RIPARIAN Greenway BUFFER- ZONE 1 + + + HollyTown of Z2 " \ \��O\� `\\ \+ + + - (TYP.) + + Parks and Recreation EX. SANITARY SEWER EASMENT (TYP.) \\ \ EXISTING rlly + a ulDu- Iu-aiva / I Iz� \ +I / — — WETLAND (TYP) I I l + + + - + \ 1 h PREPARED FOR: \ // / I 1111 Town of Holly Springs \ \ 1 1 I + 128 S. Main Street Holly Springs, NC 27540 + / + + + rt + �? PRELIMINARY NOT FOR CONSTRUCTION C, II / 90% CONSTRUCTION o u �� I I //// +� +/ + + + + + + + I DRAWINGS 1+ + + + + II\ + REF 09-012: Arbor Creek Greeo EE � 4- \ I I PROJECT: SE20.027.00 ISSUE: . STREAM IMPACTS LENGTH (LF) AREA (SF) STREAM IMPACT PERMANENT 22 469 EXISTING STREAM IMPACT (SEWER) STREAM IMPACT PERMANENT I NOT MITIGABLE 18 426 RIP RAP OUTLET REVISIONS: ® Rev. Trail Grading 4.20.2021 ® Rev. New Tmil W-06.202 Per Town Comments 09.03.202 NORTH 50 25' 0 PROJ.MGR. ..TAYLOR LJ DRAWN BY: S. TEYMOURI CHECKED BY: M. TAYLOR SCALE: I ' = 50' STREAM IMPACT AREA 1 SA-1 $P G$ \ 1 I I SEPI ENGINEERING & CONSTRUCTION, INC. ;55 N \VA\ I I RABEGH UFOTSC I C�RLEsoNLOTTE 3\� \\\ \\ k \ \ 1GLENWOOD AVE. SUITE 600 — — \ _ \ • \ \ \�\ I I RALEIGH, NC 27603 �' \ \ \ I I I I PHONE 1 919.789.9977 + + + sepiinc.com PROPOSED \\ \\f — i ZONE 2 - Allowable GREENWAY TRAIL \I \ Upon Authorization +313 S + I 1WORNHGDAYS10'WIDE, PAVED (TYP.) r 6NEoRoN?IJDIG I Knowwhat'B + + + + below.FORTMrL \\ \ \ \\\\\\ \\ \ \\ 1 \\\ I 1\ Call before you dig oc + + + + + + I ND >R� Es.�o.,EN_ Ra°o r rESTOE + + + + + NG➢CF. e,wLL,: P � �a�, a.N..No., AMA � M �, \\\\ m CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF \\ I 11 H THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER \ \ \\\` K 1 I I+ + + + + + + SHALL BE EXPECTED TO ASSUME ANY RESPONSIBILITY FOR O O \ 1 \ \ \ I \\\ I I SAFETY OF THE WORK, OF PERSONS ENGAGED IN THE WORK, ZONE 2 - Allowable 0 OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. Upon Authorization �� /� 1 �� i I I �11 1 \\ liiI I + EX SANIT SANITARY SEWER + NNETH J& TAYLD I I I I QpTcsva,W ,9'3� 858 SF NETTEC ,%� ` i I i \ III + + ,'IN # U659-29-2534 EASMENT (TYP.) „?QiSEAL — + + Jill I PROPOSED ZONE 1 -Allowable iI E ' ' + - BRIDGE + + + Upon Authorization 12'08-2021.' I IIIIIII111111 ' \ / ill IIII ti + RIPARIAN + + + + 1,020SF Il /L _ I + BUFFER- ZONE 2 + +/f + + RP RP"'��t'-. /1 fit (TYP.) / _ c EAL 2197 s + RIPARIAN + ' / + + + N.0 l it 9-2/��R$A v vv + BUFFER -ZONE 1 + +� I + (TYP.) + + + COPYRIGHT.i ENGINEERING &CONSTRCONSTRUCTION, INC N/F VOLNMAII THOMAS SCOTT /TR & VOLKMAN, 11111 / 01 I 1 i \ \ wo 2m +,\ry + + + + + + +1 + + + Arbor Creek - GINNY PAULETTE /TR I I I I I I I 1 I \ \ PIN # 0659-29-2387 illlll \ \ I I V \ l + + I + + + + I ' + \ + + \ , �a I I EXISTING Middle Creek I I 1 I ' vz \ I1 I I . \\ No 2a t + + + WETLAND (TYP) + \, + + Greenway ZONE 1 -Allowable 1 I I NI \ \\ I \\ \ t — Town of Holly Springs Upon Authorization + + + + + + + + + + \\+ I Parks and Recreation III I I 1 1 \ \ \ 4,296 SF A/F 111 I I I\ \ \ \ \ I + I + + + + + + + _ROWN, WILLIAM M BROWN, HOPE M PIN # 0659-29-238\\ I+ I 1 4_ .._� + + + + + I + + ' \\`\ \ I � \ �. •' I \ I I I o l \ \ 1 I \1 \\vvvvvvv v v \ ++ + II +\ +�I I + ++1\ \ I1 PREPARED FOR: 2- Allowable v v v v + Town of HollySprings s Upon Authorization 1 + + +1I + + + � 128 S. Main Street 2,742 SF 0I \ Holly Springs, INC 27540 o v v v \ \ vv+ + + `+ I + 7 I+ + I+ + 1 \ \ 1—„v v v• \ I \ I�,r \ \ \ / 1 I _ „\ ° ° ° ° ° \\ — PRELIMINARY UFF, CHRISTOPHER JAME: o \. \ \ �y ° ° ° HUFF, EMILY ELISABETH �.- v v v • • \ NOT FOR CONSTRUCTION + + + + + + + + PIN tf ')65e 9e 2286 v v v CNSTRUCT + + + + I + + I + + 901 DORAWINGS ION + ` + + + + + II REF 09-012: Arbor Creek Greenway DATE PROJECT: SE20.027,W ISSUE: . RIPARIAN BUFFER & STREAM IMPACTS AREA (SF) NOTES ZONE 1 ZONE 2 ALLOWABLE UPON AUTHORIZATION S,316 3,913 LIMITS OF DISTURBANCE (CLEARING PLUS BUILT UPON AREA) BUILT UPON AREA I PERMANENT 1,620 1,120 10' WIDE PAVED GREENWAY TRAIL REVISIONS: m Rev. Trail Grading 4.20.2021 ® Rev. New Trail 07.06.202 ® Rev. Per Town Comments 09.03.202 NORTH 50 G LJ 0 PROJ. MGR: M. TAYLOR DRAWN BY: S. TEYMOURI CHECKED BY: M.TAYLOR SCALE: I°=50' BUFFER IMPACT AREA 2 BA-2 I \ CO \ r °j + \�1 CD`°7 u + LD \ LD 07 °j \ LD O - LD + + + + PROPOSED GREENWAY TRAIL + + + + 10' WIDE, PAVED (TYP.) + + + + + ZONE 2 -Allowable \ \ + + + + + Upon Authorization o + + + + + + 592 SF o + + + + + + ZONE 1 - Allowable I o 0 + + + + + + + Upon Authorization 1 Zz 1,701 SF + + + + + + Zl � + + + + + + + + 3v v vvv v l— + + + + + + + ++ + + v v v v v v v v v ---------- + + + + + + + + + + + N vvvv wo% + + EXISTINGi i + + + + + v v v v t + + WETLAND (TYP) F + + + + + + v v v I I vvvv No + + + + + + + + T T Zl 1 ZONE 1 - Allowable + + + + + + Upon Authorization + —� \ - 1,157 SF /tz _ Z2 ZONE 2 - Allowable o + + + + + + Upon Authorization I o + + + + + + + 547 SF + + + + + + + ro o + + + + 1�\t + I J + + + + 7� \\ + i + + + + + I+ \\ o I 1 1 J RIPARIAN BUFFER IMPACTS AREA (SF) N OTES ZONE1 ZONE2 ALLOWABLE UPON AUTHORIZATION 2,858 1,139 LIMITS OF DISTURBANCE (CLEARING PLUS BUILT UPON AREA) BUILT UPON AREA I PERMANENT 600 400 10' WIDE PAVED GREENWAY TRAIL S=;)1 SEPI ENGINEERING & CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE BEAUFORT, SC I CHARLESTON. SC 1 GLENWOOD AVE. I SUITE 600 RALEIGH, NC 27603 PHONE 1 919.789.9977 SepiinC.Com • lG DAYS BEFRORE YOU DIG FO wO oulHo unEs Know what's below uHo Call before you dig. ANY All ALL 1111010— �TL— NOTICE CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER SHALL BE EXPECTED TO ASSUME ANY RESPONSIBILITY FOR SAFETY OF THE WORK, OF PERSONS ENGAGED IN THE WORK, OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. `��HuFHC�ou IssIak s3u053032 � f— %��qR( R 12- ItkO,21 ? op900?41�1��', SEAL is= fC-2197 = Q� N'c1 �DR.RI�CONSTRUCTION, T®z� Arbor Creek - RIPARIAN Middle Creek BUFFER- ZONE 2 Greenway (TYP.) Town of Holly Springs RIPARIAN Parks and Recreation BUFFER- ZONE 1 (TYP.) PREPARED FOR: Town of Holly Springs 128 S. Main Street Holly Springs, INC 27540 PRELIMINARY NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway MC REVISIONS: m Rev. Trail Grading 4.20.2021 ® Rev. New Trail 07.06.202 ® Rev. Per Town Comments 09.03.202 NORTH 50 25' 0 PROJ.MGR. ..TAYLOR LJ DRAWN BY: S. TEYMOURI CHECKED BY: M. TAYLOR SCALE: 1" = 50' BUFFER IMPACT AREA 3 BA-3 + _ Q� IJ SEPI EN OENGINEERING &COONSCR CHARLOTTE INC. Ir \ \ a7 \ BEAUFORT, SC I CHARLESTON. SC \ u 1 GLENWOOD AVE. I SUITE 600 CD 7 \ PHONE RALE H919.789 CD 9977 � CD F 0j � � CD • p� sepiinc.com + + + `CD CD + + + u"o wO"" CIDAIS BEFORo"I"o E YOU DIG + + + + PROPOSED l Know wnaYs below. I CC11before you dig. GREENWAY TRAIL + + + + 10' WIDE, PAVED (TYP.) EN + + + + + b O] (I NoncEANYAlo:"L"111111N_I I0L=10L.1LILIL11 °:a1`1oc`Ha:o" \ \ CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER + + + + + SHALL BEEXPECTEDTO ASSUMEANYENGAGED THE FOR RIP RAP SAFETY FTHENEARBY STRUCTURE, ONO ENGAOTHER THE WORK, 0 OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. + + + + + + PERMANENT STREAM IMPACT o + + + + + + + NOT MITIGABLE 33 LF z2 I 0SE 32 ! , + + + + + + + 333 SF Z2 + + + + + + + + + + qR „ \� Z Zl 12- 021 0^ \ opPOR4l�l��': + + + + + + PERMANENT STREAM IMPACT + g Rz%7 + + 'EXISTING �D I + + _ 250 SF + a ' T / t + + WETLAND (TYP) F + + + + + + I( SEPI �o"GIeC "�I MON, INC O p N NOS + + + + + + + + + + + z1 ' N Arbor Creek - + �,, + _+ + + + + + + + i2 RIPARIAN Middle Creek -� BUFFER- ZONE 2 I—S+ + + + /lt2 J Z2 (TYP.) Greenway I I � Town of Holly Springs + + + + + + + + + RIPARIAN Parks and Recreation 6 g o BUFFER- ZONE 1 + + + + + + + + + I I o (TYP.) + + + + + + + + + + o II PREPARED FOR: + + I ' Town of Holly Springs + + + + + + + 128 S. Main Street 0 0 Holly Springs, INC 27540 + + + + /I t + I I PRELIMINARY + + + + 7� \� + r Q NOT FOR CONSTRUCTION 90% CONSTRUCTION + + —� — — i— r I I DRAWINGS + + + + I + REF 09-012: Arbor Creek Greenway O Q DATE i 1 mc PROJECT: SE20.027.00 ISSUE, . STREAM IMPACTS LENGTH (LF) AREA (SF) STREAM IMPACT PERMANENT 22 250 CULVERT STREAM IMPACT PERMANENT I NOT MITIGABLE 33 333 RIP RAP OUTLET REVISIONS: m Rev. Trail Grading 4.20.2021 ® Rev. New Tmil 07.06.202 ® Rev. Per Town Comments 09.03.202 NORTH 50 25' 0 PROJ.MGR. ..TAYLOR LJ DRAWN BY: S. TEYMOURI CHECKEDBY: M. TAYLOR SCALE: 1" = 50' STREAM IMPACT AREA 3 SA-3 \ // PIN # 0659-28-7388 p + ` \ / \ + +\ + +// + + +\\ / + \\ I\ + + \ _ +/ + + + I I ILIPK ILIP KI, BE \\ + + + + + + + + O PIN ; + + + + + + PROPOSED I I \ \ + + + + + GREENWAY TRAIL + \\ + + + + + + 10' WIDE, PAVED (TYP.) nII + `\\+ + + + + ZONE 2 - Allowable Upon Authorization u + + + + + + + 826 SF u + + + + + + ZONE 1 -Allowable �- + + + + + + Upon Authorization + + + + + 1,902 SF + � EXISTING + + + + ° Y \ + WETLAND (TYP) + + + + T + + + + + + ZONE 1 -Allowable ° + + + + + - Upon Authorization - - - - + N ° ° vv ° + + + + + + + 1,259 SF + ti + + ° + + + + + + _ ZONE 2 - Allowable + +I Upon Authorization I + + + + + + + 626 SF + + + + + + + + + + + //+ +� + + J�� + + + + + + + ESANITARY SEWER + EASMENT (TYP.) 11 + + + + + + or + + + j+ + + + + + + + + + + + RIP + 4 BUFFER- ZONE 2 +/ + (TYP.) - ii + N + I - I + + + + + + + + + o + + RIPARIAN ZONE + ZONE �, + + + + + + + BUFFER- ZONE 1 + + + (TYP.) + + + + + + + + + L I + + + + + + „ 1 RIPARIAN BUFFER IMPACTS AREA (SF) NOTES ZONE1 ZONE2 ALLOWABLE UPON AUTHORIZATION 3,161 1,452 LIMITS OF DISTURBANCE (CLEARING PLUS BUILT UPON AREA) BUILT UPON AREA I PERMANENT 760 540 10' WIDE PAVED GREENWAY TRAIL S=;)1 / SEPI ENGINEERING & CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE y I BEAUFORT, SC I CHARLESTON. SC ' 1 GLENWOOD AVE. SUITE 600 RALEIGH, NC 27603 PHONE 1 919.789.9977 SepiinC.COm / /// \ \ 7 • 1WORK ING DAYS BEFORE YOU DIG AT oie.1 IHorAasmes Know wh&S below. Call before you dig. \ ou.=o ­a.T E�MR..o"FAL'aETOE nY�W.CH. N TICE CONTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF \ \ \ \ \ O\ \ \ THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER SHALL BE EXPECTED TO ASSUME ANV RESPONSIBILITY FOR % \ \ \ \ SAFETY OF THE WORK, OF PERSONS ENGAGED IN THE WORK, OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. 1\ \ \\ \\ I 2 ! _ r Ir I\ \ \ 12 kO21 0 `\ \� ? l opPOR4SEAL s ` �k \ ot 2197 Arbor Creek - �\`, Middle Creek Greenway Town of Holly Springs Parks and Recreation 1 1 1 I I I PREPARED FOR: I I I I Town of Holly Springs \ a IIIII I�I2III 128 S. Main Street Holly Springs, NC 27540 PRELIMINARY \ NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway LD // PROJECT: SE20.027.W REVISIONS: m Rev. Trail Grading 4.20.2021 ® Rev. New Trail 07.06.202 ® Rev. Per Town Comments 09.03.202 NORTH 50 LJ 0 PROJ.MGR. ..TAYLOREVMDRAWN BY: S. TOURI CHECKED By. M.TAYLOR SCALE: 1 ° = 50' BUFFER IMPACT AREA 4 BA-4 I\ / / LAPIN # 0659-28-, 7p IIIIIIII + \ + +\ + +/ _ I � \+ + + +\ +/ + + + + ILIPFILISK SKIPBE \\ + + + + + + + + + PIN ; +\ + + + + + + PROPOSED \\+ + + + + + GREENWAY TRAIL + \ + + + + + + 10' WIDE, PAVED (TYP.) ` n O J + ��\+ + + + + + I IJ + + + + + \/� �_ + + o> % + + + + + + \\\ + / �- + + + + + + + ' II + �EXISTING + + + PERMANENT STREAM IMPACT j g WETLAND (TYP) 30 LF + + + - 242 SF r + + + + + + + + + o� % + + ,� RIP RAP PERMANENT STREAM IMPACT + + + + + + + NOT MITIGABLE + + + + + + + + + 21 F + +I I + + + + + + + 193 3r /T T + + + J� �, 114 + + + + + + + �+ \ + + + + + + + + + + + ESANITARY SEWER + + EASMENT (TYP.) 1:2� + + + + + + or + RIPARIAN + + + + + + + 4 BUFFER- ZONE 2 + N + I + + + + + + ++ (TYP.) + + ZONE ZONE + + + + + + �+ + RIPARIAN �, + + + + + / + + BUFFER- ZONE 1 + + + (TYP.) + + + + + + + + + °+ + �'II� + + i +I L + + + +// + + + + + II NI -\I I + I + STREAM IMPACTS LENGTH (LF) AREA (SF) STREAM IMPACT PERMANENT 28 255 CULVERT STREAM IMPACT PERMANENT I NOT MITIGABLE 21 193 RIP RAP OUTLET S=;)1 / SEPI ENGINEERING & CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE y I SEAUFORT, SC I CHARLESTON. SC ' 1 GLENWOOD AVE. I SUITE 600 RALEIGH, NC 27603 PHONE 1 919.789.9977 sepiinc.com /// \ \ • IWORK INO DAYS YOU DIG oiacao1NOF All Know wh&S belOWu Call before you dig. \ ou.=oN�a.T E� R..oRSFAL'aETOE nr�W.ICH. N TICE CONTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF \ \ \ \ \ O\ \ \ THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER SHALL BE EXPECTED TO ASSUME ANY RESPONSIBILITY FOR \ \ \ SAFEIVOF THE WORK, OF PERSONS ENGAGED IN THE WORK, OFANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. SEAL 053032 \ F• f gNF. �� I \ \ \ 12 kO21 \ \ \ \ � ��"-, ,X\�'R" \ � l� ; � `ppPORgSEAL ` \ ot 2197 C Nam' SEPIENGIN -N INC \ \ \ Arbor Creek - ��`, Middle Creek Greenway Town of Holly Springs \\\\ \\ ' Parks and Recreation \ I I I I I PREPARED FOR: I I I I Town of Holly Springs \ a IIIII \ I�I2III 128 S. Main Street Holly Springs, INC 27540 PRELIMINARY \ NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway Lb PROJECT: SE20.027M REVISIONS: m Rev. Trail Grading 4.20.2021 ® Rev. New Trail 07.06.202 ® Rev. Per Town Comments 09.03.202 NORTH 50 LJ 0 PROJ.MGR. ..TAYLOR DRAWN BY: S. TEVMOURI CHECKED BY: M. TAYLOR SCALE: V = 50' STREAM IMPACT AREA 4 SA-4 +/ / tt� / /+ I + + 1 + + + ` / -+ + + + `\ + + + + + + SEPI ENGINEERING &CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE \ BEAUFORT, SC I CHARLESTON. SC +\ � + �; ,--IT—I + + + —\� + + + + - + I _ 1 GLENWOOD AVE. I SUITE 600 RALEIGH, NC 27603 PHONE 1919.789.9977 \\ `\ \ `• • • f \ — _ \ (1 3 WORKING DAYS BEFORrE YOU Know what's belOW. DIG a S. Aa LixcxouNovsmes \ \\\ \ • .��.• \ `\ + `\ +\ \ \ \ + \ +\ \\ + + + + �' /� \ \ + + + + \\ + -� + Call before you dig. ZONE 2 - Allowable \\\\ \ v I \ // — � \ \ \ / 1 P ERsE°IN, No _...o '1 =:o°an Eo<<°µps, \ \"` \ \ \ \ I I + \+ I + + + /— + + + +� 1 + \ I I + Nonce \ • CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF Upon Authorization q �� \ \ v \, / N/F / / I THE CONTRACTOR NEITHER THE OWNER NO THEENGINEER I v c SHALL BE EXPECTED TO ASSUME ANY RESPONSIBILITY FOR 4,767 SF \\ ` \ i'. ';S TOWN �F / \\\ I} }/ I SAFETY OF THE WORK, OF PERSONS ENGAGED IN THE WORK, \\\\ \ \ \ \ • •\• I + - + 7-4�+ + + + + + \ / I \ \ — — _ OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. ZONE 1 -Allowable -PROPOSED \ `—`----- \ \. \ \\\ \\\\ v •'\ — Upon Authorization ��`\��\��\ `�\:\\\\�� S v'•' GREENWAY TRAIL 1,638 SF \��`\\�`\ \\\\ + + + = SEAL \ \ \\\ \\ \\\\ (�\ v 053032 "` ��\ 10' WIDE, PAVED (TYP.) RIPARIAN ``�`�\� ��\ \\`�\` \`v v 1 T T T T EXISTING 'F fqE EX. SANITARY SEWER WETLAND (TYP) BUFFER -ZONE 1 - z°'o"a"zozl (TYP.) `�\� \�\• \\\ \\ v + + EASMENT (TYP.) RIPARIAN Ii \\ \\ \ pPORgl� \� \\� �\ '• BUFFER- ZONE 2 �\\ \\� `��\� �/ L SEAL -r + + + + + + + _ = `p C-2197 (TYP.)\\�A\\\ _ �• Imo\ \\14, - \ + + + + + ZONE 2 - Allowable T — + + + + N.C. 4 \\+ \+ + + Upon Authorization +\\ + + + - OPYFIGHT®lbt1 ERING & CONSTRUCTION, INC \,II + Arbor Creek - r,\\\ Middle Creek Greenway t\ - Town of Holly Springs v I / \ \ Parks and Recreation + + + \I \I PREPARED FOR: Town of Holly Springs I7 \`. \�\\\ ��\♦ v vvv••• �\ �— 128 S. Main Street "\\ \X\ v v v ••••••••• �OT -�/� Holly Springs, NC 27540 Z2 Z, \\� v v o ' '•, •••••••• • \moo PRELIMINARY \\� \\\\ v ° ••1 ` pI Q'1 NOT FOR CONSTRUCTION ZONE 1 - Allowable \���\�\ v ° 90% CONSTRUCTION Upon Authorization.•/ • \ DRAWINGS 3,278 SF \ \\ \ \ REF 09-012: Arbor Creek Greenway 1� \ PROJECT: SE20.027.00 \ ISSUE: . RIPARIAN BUFFER IMPACTS AREA (SF) NOTES ZONE1 ZONE2 ALLOWABLE UPON AUTHORIZATION 4,916 8,191 LIMITS OF DISTURBANCE (CLEARING PLUS BUILT UPON AREA) BUILT UPON AREA I PERMANENT 3,334 3,225 10' WIDE PAVED GREENWAYTRAIL �D NORTH 50' 25' 0 SCALE: 1" = 50' [L\ Rev. Trail Grading ® Rev. New Trail ® Rev. Per Town Comments . MGR: M. TAYLOR VN BY: S. TEYN I :KED BY: M. TAYLOR BUFFER IMPACT AREA 5 BA-5 1} S =� 1 1} + + + + + + + + + + + + + + '\ + + I \ \ + + + `� I N + + + SEPI ENGINEERING NSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE 1 1 1 + 1 1 / + 1 1 1 1 1 \ 1 1 1 1 \\ 1 SEAUFORT, SC I CHARLESTON. SC I+ I+ I+ I+ ZONE 2 - Allowable I+ I+ I+ I+ I+ I+ I+ 1y\ \ I+ I+ I+ I+ I I+ I+ I+ I+ I+ I+ I+ 1 GLENWOOD AVE. I SUITE 600 RALEC 27603 + + + Upon Authorization + + + + + + + �- + + , \\ + + + + + + — PHONE H9119.789.9977 + + + 972 SF + + + + + + + i + i r/ sepiinc.com + + + ZONE 1 -Allowable + EXISTING +� + �z - Upon Authorization WETLAND (TYP) I \ 1WORKINCIAYS + + + + 4,284 SF + + + \\ + + + 1 +\ + + Imo\ + + ow 2 BE EOREYOUocDnG Knwh&Y belOWueo + + + +_ + + + -� + + + I\ + \ 1\ + + + +\ \ \ \ \ �r Call before you dig.N TICE A • ° ° ° ° \ \— + + I _ + 1 1 \ \\ \\ \\ + + 1\ ? CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF •• v ° v v ° ° v ° v I \ \ THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER 1 \ \ \ _ SHALL BEF THE TED WORK, ASSUMEOF ANYENGAGED NG GEDI THITYE FOR SAFZONE 2 - Allowable �,I`y I\ \\ \\— I/ \ �/ \ OF ANYONE NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. Upon Authorization 4,919 SF���Qo1csvo�°�'yv. \"/ %/�� \\ v v • o� + + EX. SANITARY SEWER `\\ `\ _ ¢oa3L 032 + EASMENT (TYP.) �- \� \ \\ ZONE 2 - Allowable \\\\I \\\ems\ - ` Upon Authorization PROPOSED 1 ` \\ 2209 SF z 'oa-'soil , GREENWAY TRAIL / \ �` \• 10' WIDE, PAVED (TYP.) + �� \\'--- ZONE 1-Allowable P'In :. Upon Authorization SEAL NORTH \ _ _ - 9,541 SF c-zlg7 1 ' /\\\\\ \ \ .. • • • • \ • - \ / COPYRIGHT® aov sR C. v v y.�. v v• v I�� � � --\ \ \ v v•v •�'�'. PIENGINEERING & CONSTRUCTION, INC v v v - N ° f Arbor Creek - v - --- Middle Creek v v MIDDLE CREEK ��� ° ° ° °� ° !`� ° ° °. _ v Greenway - v v v v v vvvo CREEK \ \ \`� = tppLE �\ v • • Town of Holly Springs \ Parks and Recreation If) Z1— Z PREPARED FOR: Zi assra INc jl. Town of Holly Springs �� Z2 PI n co_ni_An IIIII 128 S. Main Street RIPARIAN 111\ Holly Springs, NC 27540 BUFFER- ZONE 1 z2 I 1� Z2 �� PRELIMINARY (TYP.) \ NOT FOR CONSTRUCTION RIPARIAN tie 90% CONSTRUCTION BUFFER- ZONE 2 �2 N DRAWINGS \ REF 09-012: Arbor Creek Greenway (TYP.) DATE PROJECT: SE20.027,00 ISSUE: . RIPARIAN BUFFER IMPACTS AREA (SF) NOTES ZONE 1 ZONE 2 ALLOWABLE UPON AUTHORIZATION 13,825 8,100 LIMITS OF DISTURBANCE (CLEARING PLUS BUILT UPON AREA) BUILT UPON AREA I PERMANENT 5,171 2,153 10' WIDE PAVED GREENWAYTRAIL NORTH 50' 25' 0 SCALE: 1'I = 50' & T Rev. rail Grading ® Rev. New Trail ® Rev. Per Town Comments MGR: M. TAYLOR IN BY: S. TEYMOURI KED BY: M.TAYLOR BUFFER IMPACT AREA 6 BA-6 RALEIGH I WILMINGTON I CHARLOTTE SEPI ENGINEERING & CONSTRUCTION, INC. BEAUFORT, SC I CHARLESTON. SC \\ J 1GLENWOODA C- SUITE 600 1 \27603 RALEIGH, NC 89.99 J � �/ PHONE 919.789.9977 Zl I \` J�J 1 1 X /\ �.I sepiinc.com EXISTING X 22 11 D X WETLAND (TYP) T2/ \ X/ X 1y, I`/y,��1 \ �C Y. \ D D - /x • 3 WORKING DAYS \ \ �r X — \ 1 I 1 \ �/ 7 / X BEFORE L.YOU DIG PROPOSED i X X /\ yC / X KDowwhat's belOwUOEaRo2HofACIIE: :> ,'x \ \ '\ ~ 12 �[ X Cdl before you dig. D ZC GREENWAY TRAIL X V(/ X x EXISTING X X D D D J \ 10' WIDE, PAVED (TYP.) X X X WETLAND (TYP) i nLY o pTEµp �\ D D I ZONE 2 -Allowable I '' / X zl /I X X P ,_ANY � E_.K_E c"r='oo:M: / X X X. X NO°C� Upon Authorization \\ I ZONE 1 - Allowable r CONSTRUCTION SITE SAFETY ISTHE SOLE RESPONSIBILITY OF \ e THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER 6,238 SF '� X Upon Authorization X �C SHALLBEFTHECTEDTO ASSUMEANYENGAGED IN 1 � � �/ SAFETY OF THE WORK, OF PERSONS ENGAGED IN THE WORK, \ D "17,260 SF D� " * \ //\ OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. \ `' � �C X ZONE 1 -Allowable X �\ EX. SANITARY SEWER - - �� \� ,, X X X �N""c \ D " f Upon Authorization X N I EASMENT (TYP.) , _ _ - �\ X ZONE 2 - AllowableQQo�E�a,, y9''- Z\\ D,\. 4,052 SF i I?` - X I x X Upon Authorization x 053 32- e" \� D. \ 1 \ iX ��'� �\ X 1,722SF 1\\\ \\ \ D" al 12-08 -2021 ZONE 1 -Allowable Upon Authorization P0)1?4 �4�51',N7,260 SF SE197 Ep��D D D\ D D D -A` N. T D D P�DD—D D DDD\D -es,- — _ � \ — JIIIOODS \ \ \ \ � — — , �� D� \ �D \ COPYRIGHTO2EQI MIDDLE CRE , \ - - l?: \ X EK =RPIRNGIHRRRNDBCDN=TRUCTIDN INC qsSF �\' `� D D - ` Arbor Creek - l ' ' �Y X Middle Creek Greenway D h Il `\ 4 (; cry �O \�\ D D D p\ Town of Holly Springs - Parks and Recreation Z2 (i St D I .QtiSFr zf Z/ ZONE 2 - Allowable `- _ a ^SFrR F RIPARIAN Awe R7 , Upon Authorization \ o6-, 6� BUFFER- ZONE 1 4 (TYP.) RIPARIAN BUFFER- ZONE 2 (TYP.) 948 SF \r7 7 79 ti` I? 12 Z2 \ I _- 1 x �2'� 81, \ �17Iv- RIPARIAN BUFFER IMPACTS AREA (SF) N CITES ZONE1 ZONE2 ALLOWABLE UPON AUTHORIZATION 12,810 8,908 LIMITS OF DISTURBANCE (CLEARING PLUS BUILT UPON AREA) BUILT UPON AREA I PERMANENT 41332 3,619 10' WIDE PAVED GREENWAY TRAIL NORTH 50' 25' 0 SCALE: 1" = 50' PREPARED FOR: Town of Holly Springs 128 S. Main Street Holly Springs, NC 27540 PRELIMINARY NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway & Rev. Trail Grading ® Rev. Now Trail ® IRov. Per Town Comments NGR: M. TAYLOR J BY: S. TEYMOURI ED BY: M. TAYLOR BUFFER IMPACT AREA 7 BA-7 \ I �� I X \ SEPI ENGINEERING &CONSTRUCTION, INC. RAOBEAUFORISC I CARLESTOILIC T,HCHARLOTTE 1 GLENWOOD AVE. I SUITE 600 PHONE H9N9.78969977 1 0 X X X Z 1 \X I I X I / `I �/ X I X sepiinc.com `` \ EXISTING � X z WETLAND ? ND (TYP) 7C 3 WORKING DAYS BN EOREo NOUcDnG X X / \ X I X I \ X oR r X X X Kno elo Call bwh&Sefore you dig. EXISTING�. oAMA E w M.T SSECEPROPOSED X zt I 2 X WETLAND (TYP) X i nLY o Eµp \ \ \ I\ X X \ X\ I GREENWAY TRAIL X.' X X Non�E=oyo.rE o Ra°o c" =°�aMMEN woR..> ,\ CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF 1O' WIDE, PAVED (TYP.) \\ �i/ _/ X SHALLBEEACTORNDTHERTHE OWNER PNOR THE ITYFORENGINEER /` \' X /� n SHALLBEFTHECTEDTO ASSUMEANYENGAGED NG GEDI THE FOR SAFETY NEARBY STRU OF TURPERSONS, ENGA OTHER THE WORK, _ OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. EX. SANITARY SEWER \ \ X RIP RAP X / L\X \ \ �C X% ' PERMANENT STREAM IMPACT X °'oA�oEsv^R�Zy9,, N I EASMENT (TYP.) _ XQQ �` 1 ' X NOT MITAGABLE SEAL 22 LF X 053032 —I I X %�/- 111 Ql _ dl Cll \ / �1 / \ X /\ X X� f 12-08-�2021 _ S 63°24'1 -°j al a� aVN ,gw&�Isiari; \`oSEALl� �s- ��"� , WK L \ \ \ X C-2197 9c BUFFER- ZONE 2 (TYP.) B— L-0+�� —rya �Lp�� —_� \ X X X N.C. 1 A °NG'R'JOODS SEPENGINEERINGCONSTRUCTION, Arbor Creek - \ °°Z \ -X Middle Creek I X Greenway Town of Holly Springs Parks and Recreation _ S�tiSFT tiF PERMANENT STREAM IMPACT 065, Ty / \ _ _ I J ° x 17 LF _ v 22_ 145 SF z2 1, J \\ `°� PREPARED FOR: Town of Holly Springs I 128 S. Main Street RIP RAP �II v Holly springs, NC 27540 �� PERMANENT STREAM IMPACT NI I�i i PRELIMINARY NOT MITIGABLE /'/ 6 LF 0/ 50 SF 01/ STREAM IMPACTS LENGTH (LF) AREA (SF) STREAM IMPACT PERMANENT 18 14S CULVERT STREAM IMPACT PERMANENT I NOT MITIGABLE 6 50 RIP RAP OUTLET ro / NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway DATE PROJECT: SE20.027.W J�AREVISIONS: NORTH 50' 25' 0 LJ SCALE: 1" = 50' m ® ® Rev. Trail Grading 4.20.2 Rev. NOw Trail 07.06. Rev. Per Town Comments 09.03. PI MGR: M. TAYLOR DRAWN BY: S. TEYMOURI CHECKED BY: M. TAYLOR STREAM IMPACT AREA 7 SA-7 IDS \ ������� �������� ��� ���� ��� PROPOSED BRIDGE r 4- �17 � a /\ 4 6, / / Q (�\ / PROPOSED GREENWAY TRAIL 10' WIDE, PAVED (TYP.) �� �oOPP y / / (31 ZONE 2 - Allowable Upon Authorization — \ 737 SF ZONE 2 - Temporary Buffer Impact i\ Fig 6 i ti2� 677 SF ZONE 1 -Allowable • •�' • P �� Z' Upon Authorization �� •r •• 1,049 SF f `" " ` •�•• D D ��� ZONE 1 -Temporary �s �• �� �: I' D D p Buffer Impact V r. IF 779 SF b: gDpD TEMPORARY BRIDGE FOR CONSTRUCTION ACCESS -D PROPOSED 1 C> BRIDGE 292.39 D D ZONE 1 -Allowable p D Upon Authorization WOODS p 1,062 SF ------- - ZONE 1 - Temporary Fqs • p ZONE 2 - Allowable Buffer Impact �M�tir o Upon Authorization 999 SF 1,031 ZONE 2 - Temporary 4 Buffer Impact �r 402SF RIPARIAN BUFFER IMPACTS AREA (SF) N OTES ZONE 1 ZONE 2 LIMITS OF DISTURBANCE ALLOWABLE UPON AUTHORIZATION 2,774 2,844 (CLEARING PLUS BUILT UPON AREA) TEMPORARY BUFFER IMPACT 1 1,7781 1,0791 FOR CONSTRUCTION ACCESS BUILT UPON AREA I PERMANENT 1 596 1 1,092 1 10' WIDE PAVED GREENWAY TRAIL WIf tit `\ S_N "01 SEPI ENGINEERING & CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE ` SEAUFORT, SC I CHARLESTON, SC � \ 1 GLENWOOD AVE. SUITE 600 - -0^�- a RALEIGH, NC 27603 PHONE 1 919.789.9977 — Lp— _ _ D_ \' \ LD �,� T _ _ D 'f sepiinc.com ZONE 2 - Allowable lti2/ Upon Authorization 1,076 SF ZONE 1 - Allowable Upon Authorization ti 663 SF 0/1( N �2 RIPARIAN �01 BUFFER- ZONE 1 (TYP.) \�3 RIPARIAN 2 BUFFER- ZONE 2 (TYP.) F/p 12 ti • 3 WORKING DAYS BEFFORE YOU DIG C�( Know, wh&t below�NOEa�Ro�NOFA���E: - Call before you dig. P a a,oNo,.L u,N U, ,E=aE,oRE aMMEN I• woR..No 50' 25' 0 SCALE: 1" = 50' NoEDE CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER SHALL BE EXPECTED TO ASSUME ANY RESPONSIBILITY FOR SAFETY OF THE WORK, OF PERSONS ENGAGED IN THE WORK, OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. 3"L32 12-08 -�2021 �{ `pp90R4tF, SEAL AZ C-2197 = N.C. SEPI ENGINEERING 'aCON1.1 UCTION,INC Arbor Creek - Middle Creek Greenway Town of Holly Springs Parks and Recreation PREPARED FOR: Town of Holly Springs 128 S. Main Street Holly Springs, INC 27540 PRELIMINARY NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway DATE PROJECT: SE20.027,w ISSUE'. z1A Rev. Trail Grading ® Rev. New Trail ® Rev. Per Town Comments MGR: M. TAYLOR 'N BY: S. TEVN I RED BY: M. TAYLOR BUFFER IMPACT AREA 8 BA-8 r; \ \ SEPI ENGINEERING &CONSTRUCTION, INC. \ ~ Ha RABE UFORT,'SC I CHOARLESTON, SC \ 1 GLENWOOD AVE. I SUITE 600 RALEI( NC 27603 \ \ PHONE 1 919.789.9977 \ \ sepiinc.com 12 \ l \ ?2 \ \ \ • 3 WORKING DAYS \ BN EORE� NOUcDnG \ \ Know what's below.FOR TMr \ Call before you dig. N No o All \ \ \ 0�✓ Y` \ \aY�WUCHa ANY All ALL 111-10— �ILEG (R� \ NORCE: CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER SHALL BE EXPECTED TO ASSUME ANV RESPONSIBILITY FOR SAFETY OF THE WORK, OF PERSONS ENGAGED IN THE WORK, N N ti H �.'\ OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PER SONS. eaI' 053032 ZONE 2 - Allowable Upon Authorization 641 SF \ lz'oa-'soil PROPOSED RPT;'' A BOARDWALK PROPOSED o�= US�EA NGREENWAY TRAIL 10' WIDE, PAVED (TYP.) `>> \ '......... SEP E°N�'aCO SRU RIPARIAN BUFFER- ZONE 2 - - Arbor Creek - � o ••�' T ,T � � \ 1 �1 �' TYP. \� _ - ZONE 2 - Allowable (TYP.) \ \ '�-_� Middle Creek Upon Authorization I\ RIPARIAN \\ Greenway 562 SF o- o \ \ \ \\\ \ \ BUFFER- ZONE 1 \ JI \\ \\\ \ \\ I 1 \ \\ Town of Holly Springs I \ \ \ \\ \ 1 \ \ (TYP.) \ Parks and Recreation -AllowableZONE 1 Upon Authorization PIN # 0659-67-019 __F ICY FLINTOM, MARGARET WHIT ZONE 1 ZONE 2 \ \\ 11 11 \ \ \\\\ \ \\ 11 \\ \\ \\ \\ \ \ \ 1 I 1 I I I\ 1 III II 30' 20' LI I\ I I I I I I I I I I \\\\ RIPARIAN BUFFER IMPACTS AREA (SF) N OTES ZONE 1 ZONE 2 ALLOWABLE UPON AUTHORIZATION 1,797 1,203 LIMITS OF DISTURBANCE (CLEARING PLUS BUILT UPON AREA) BUILT UPON AREA I PERMANENT 598 401 10' WIDE PAVED GREENWAYTRAIL NORTH 50' 25' 0 SCALE: I" = 50' PREPARED FOR: Town of Holly Springs 128 S. Main Street Holly Springs, INC 27540 PRELIMINARY NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway (2, Rev. Trail Grading ® Rev. New Trail ® Rev. Per Town Comments MGR: M. TAYLOR 'N BY: S. TEYMOURI KED BY: M. TAYLOR BUFFER IMPACT AREA 9 BA-9 ED �\ �'.`--------------- AP,_ILIALEXTENSION COMPANY `A7EASE1RiE1NT III ZONE 2-Allowable Upon Authorization , II1 1 1 I I I PIN # 0659-77-4232 / 1 / 1 11 1/ l l IIII \ \ I I I 1 111 \ I I I I I IIII/ O N/r HASKINS, CATh__." HASKINS, GEORGE D JR PIN # 0659-77-4181 NN /1 \ \ ZONE 1 -Allowable 1 Upon Authorization1,088 SF \ \ \ \ ZONE 2 - Allowable 995 SF —� ' � Upon Authorization ,\ ,. v � _, ZONE 1 -Allowable — — , � 746 SF Upon Authorization — v v v 1,228 SF \ C \. \ `\ '`�• \�� \� \\ \���� ��\\\ �\_ —_ 1 \\ \\\\ \ \\ \\ / // ,' // // \, + PROPOSED GREENWAY TRAIL �' / \ \ I `• `\_ \`�, �ar� \. 10' WIDE, PAVED (TYP.)cv RIPARIAN E + BUFFER- ZONE 2 (TYP.) __ _+ _— � EXISTING + + + WETLAND (TYID) + EXISTING UTILITY 3p, EASEMENT + RIPARIAN + + + + + + + -� + Z0, BUFFER- ZONE 1 \ (TYP.) + + + + + + + + + \ + fi fi + + + + + + + + + + + + vv+ + + RIPARIAN BUFFER IMPACTS AREA (SF) N CITES ZONE1 ZONE2 ALLOWABLE UPON AUTHORIZATION 2,461 1,790 LIMITS OF DISTURBANCE (CLEARING PLUS BUILT UPON AREA) BUILT UPON AREA I PERMANENT 691 622 10' WIDE PAVED GREENWAY TRAIL NORTH 50' 25' 0 SCALE: 1" = 50' SEN SEPI ENGINEERING & CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE BEAUFORT,SC I CHARLESTON,SC 1 GLENWOOD AVE. I SUITE 600 RALEIGH, NC 27603 PHONE 1 919.789.9977 SepiiITC.COm BEFORE YOU DIG Know what's below. re dig. —NE olnIIIIII 1ANIE Nonce CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER SHALL BE EXPECTED TO ASSUME ANY RESPONSIBILITY FOR SAFETY OF THE WORK, OF PERSONS ENGAGED IN THE WORK, OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. CO,""" s¢ L 053032 12-08-2021 �g�rG&col�'rq�;-, USEAA Arbor Creek - Middle Creek Greenway Town of Holly Springs Parks and Recreation PREPARED FOR: Town of Holly Springs 128 S. Main Street Holly Springs, NC 27540 PRELIMINARY NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway & Rev. Trail Grading ® Rev. Now Trail ® Rev. Per Town Comments M. TAYLOR S. TEYMOURI M.TAYLOR IMPACT AREA 10 BA-10 PIN # 0659-77-4232 - \ �'\___________ T,"-APTILIAL EXTENSION COMPANY A7EASE?Ki T I I I I 1 I 1 1 I\ \ \ I I I 11 I I 1 — — — — / d / / / I I I I I11 lo \ \>� -- ---' — N/F HASKINS CATHERINE A & \\ \ HASKINS, GEORGE D JR \�---------- _ / / / / i / , / / / , I 1 I \ / I 1 I I PIN # 0659-77-4181 (7)r � \ \ \\ ♦\ \\ \�\ �>� / // // __ ` \\� // // ��/ /// , / / II / I III \ 1 1 I 1 \ 1 \ \ \`\—I�/ //' � `\ \ \ I I 1 I \ RIP RAP PERMANENT STREAM IMPACT / - / \ `\ ` `. \ `\ ``\ /`�,-40 NOT MITIGABLE 117 SF ^PERMANENT Az _ '---- \ STREAM IMPACT I\ _► i - — \ _fi- \ 135 SF I \ I I + PROPOSED GREENWAY TRAIL / \ \ I \•\ `\ \ �yo �\ `\ 10' WIDE, PAVED (TYP.) +\\I\+ RIPARIAN E + I B UFFER-ZONE 2 + �/+ 4- (TYP.) — — EXISTING WETLAND (TYP) +\ 2proF \ RIPARIAN + + BUFFER- ZONE 1 + + + + + + (TYP.) + + + i + + + I \ I _ STREAM IMPACTS LENGTH (LF) AREA (SF) STREAM IMPACT PERMANENT 20 152 CULVERT STREAM IMPACT PERMANENT I NOT MITIGABLE 12 117 RIP RAP OUTLET 50' 25' 0 SCALE: 1" = 50' SEPI SEPI ENGINEERING & CONSTRUCTION, INC. RALEIGH I WILMINGTON I CHARLOTTE BEAUFORT, SC I CHARLESTON, SC 1 GLENWOOD AVE. I SUITE 600 RALEI( NC 27603 PHONE 1 919.789.9977 SepiinC.Com BEFORE YOU DIG Know wh&S below. Call before you dig. NOTICE CONSTRUCTION SITE SAFETY IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR NEITHER THE OWNER NOR THE ENGINEER SHALL BE EXPECTED TO ASSUME ANY RESPONSIBILITY FOR SAFETY OF THE WORK, OF PERSONS ENGAGED IN THE WORK, OF ANY NEARBY STRUCTURES, OR OF ANY OTHER PERSONS. �H TNT ou *' Q,%asva yr` SEAL 053032 12 'A- „1z AL i== -2197 SEPIENGINEERING 'aCONSTRUCTION, INC Arbor Creek - Middle Creek Greenway Town of Holly Springs Parks and Recreation PREPARED FOR: Town of Holly Springs 128 S. Main Street Holly Springs, NC 27540 PRELIMINARY NOT FOR CONSTRUCTION 90% CONSTRUCTION DRAWINGS REF 09-012: Arbor Creek Greenway & Rev. Trail Grading ® Rev. Now Trail ® Rev. Per Town Comments M. TAYLOR S. TEYMOURI M.TAYLOR IMPACT AREA 10 SA-10 SEPI Stream and Wetland Impact Totals 000000000000000 000000000000000 WETLAND IMPACTS Site No. (Sheet) Reason Impact Type Type of W* W* Nme Forested Type of Jurisdiction Impact Area Bottomland 1 (WA-1) Fill P Hardwood Forest WA Yes 401/404 0.02 Bottomland 1 (WA-1) Temp Cons. Easement T Hardwood Forest WA Yes 401/404 0.01 Bottomland 2 (WA-1) Fill P Hardwood Forest WA Yes 401/404 0.0002 Bottomland 3 (WA-1) Fill P Hardwood Forest WB Yes 401/404 0.01 Bottomland Hardwood Forest BR(WA-1) Boardwalk Removal T (Disturbed) WA No 401/404 0.11 Bottomland Hardwood Forest BR(WA-1) Boardwalk Removal T (Disturbed) WB No 401/404 0.15 Bottomland 4a(WA-2) Fill P Hardwood Forest WJ Yes 401/404 0.09 Bottomland 4a(WA-2) Temp Cons. Easement T Hardwood Forest WJ Yes 401/404 0.06 Bottomland 4b(WA-2) Fill P Hardwood Forest WJ Yes 401/404 0.001 Bottomland 4b(WA-2) Temp Cons. Easement T Hardwood Forest WJ Yes 401/404 0.005 Bottomland 5(WA-3) Fill P Hardwood Forest WJ Yes 401/404 0.02 Bottomland 5(WA-3) Temp Cons. Easement T Hardwood Forest WJ Yes 401/404 0.03 Bottomland 6(WA-4) Fill P Hardwood Forest WJ Yes 401/404 0.35 Bottomland 6(WA-4) Temp Cons. Easement T Hardwood Forest WJ Yes 401/404 0.12 Bottomland 7(WA-5) Fill P Hardwood Forest WJ Yes 401/404 0.001 Bottomland 7(WA-5) Temp Cons. Easement T Hardwood Forest WJ Yes 401/404 0.003 Bottomland 8(WA-5) Fill P Hardwood Forest WJ Yes 401/404 0.0005 Bottomland 8(WA-5) Temp Cons. Easement T Hardwood Forest WJ Yes 401/404 0.004 Bottomland 9(WA-5) Fill P Hardwood Forest WJ Yes 401/404 0.0007 Bottomland 10(WA-6) Fill P Hardwood Forest WJ Yes 401/404 0.038 Bottomland 10(WA-6) Temp Cons. Easement T Hardwood Forest WJ Yes 401/404 0.068 Total Permanent Impacts 0.53 Total Temporary Impacts 0.565 STREAM IMPACTS Reason for Impact Impact Type Type of Impact Name Stream Type Type of Jurisdiction S.Width Impact Length S1 Greenway crossing P Culvert SB PER 401/404 4-6 22 S1 Rip Rap Outlet P Rip rap SB PER 401/404 4-6 18 S3 Greenway crossing P Culvert SAA INT 401/404 3-5 22 S3 Rip Rap Outlet P Rip rap SAA INT 401/404 3-5 33 S4 Greenway crossing P Culvert SG PER 401/404 3-6 28 S4 Rip Rap Outlet P Rip rap SG PER 401/404 3-6 21 S7 Greenway crossing P Culvert SP PER 401/404 2-5 18 S7 Rip Rap Outlet P Culvert SP PER 401/404 2-5 6 S10 Greenway crossing P Culvert SK PER 401/404 3-6 20 S10 Rip Rap Outlet P Culvert SK PER 401/404 3-6 12 OTAL 200 SEPI Mitigation Letters of Availability 000000000000000 000000000000000 fires EBX-Neuse I, LLC Stream and Wetland Banks Statement of Availability June 9, 2022 U.S. Army Corps of Engineers Lyle Phillips Raleigh Regulatory Field Office 3331 Heritage Trade Center, Suite 105 Wake Forest, NC 27587 Re Project: Arbor Creek Greenway This document confirms that Town of Holly Springs (Applicant) for the Arbor Creek Greenway (Project) has expressed an interest to utilize 220 Stream Mitigation Credits from the EBX-Neuse sponsored Neu -Con Wetland & Stream Umbrella Mitigation Bank, specifically 220 stream credits from the Meadow Spring Site, in the Neuse HUC 03020201. As the official Bank Sponsor, EBX-Neuse I, LLC, attests to the fact that mitigation is available for reservation at this time. These mitigation credits are not considered secured, and consequently are eligible to be used for alternate purposes by the Bank Sponsor, until payment in full is received from the Applicant resulting in the issuance of a Mitigation Credit Transfer Certificate by the bank acknowledging that the Applicant has fully secured credits from the bank and the Banker has accepted full responsibility for the mitigation obligation requiring the credits/units. The Banker will issue the Mitigation Credit Transfer Certificate within three (3) days of receipt of the purchase price. Banker shall provide to Applicant a copy of the Mitigation Credit Transfer Certificate and a documented copy of the debit of credits from the Bank Official Credit Ledger(s), indicating the permit number and the resource type secured by the applicant. A copy of the Mitigation Credit Transfer Certificate, with an updated Official Credit Ledger will also be sent to regulatory agencies showing the proper documentation. If any questions need to be answered, please contact me at 919-209-1055 or astaley@res.us. Best Regards, -A Y�— �' Amy Staley Credit Sales Manager RES fires EBX-Neuse I, LLC Stream and Wetland Banks Statement of Availability June 9, 2022 U.S. Army Corps of Engineers Lyle Phillips Raleigh Regulatory Field Office 3331 Heritage Trade Center, Suite 105 Wake Forest, NC 27587 Re Project: Arbor Creek Greenway This document confirms that Town of Holly Springs (Applicant) for the Arbor Creek Greenway (Project) has expressed an interest to utilize 1.02 Riparian Wetland Mitigation Credits from the EBX- Neuse sponsored Neu -Con Wetland & Stream Umbrella Mitigation Bank, specifically 1.02 wetland credits from the Arrington Bridge III Site, in the Neuse HUC 03020201. As the official Bank Sponsor, EBX-Neuse I, LLC, attests to the fact that mitigation is available for reservation at this time. These mitigation credits are not considered secured, and consequently are eligible to be used for alternate purposes by the Bank Sponsor, until payment in full is received from the Applicant resulting in the issuance of a Mitigation Credit Transfer Certificate by the bank acknowledging that the Applicant has fully secured credits from the bank and the Banker has accepted full responsibility for the mitigation obligation requiring the credits/units. The Banker will issue the Mitigation Credit Transfer Certificate within three (3) days of receipt of the purchase price. Banker shall provide to Applicant a copy of the Mitigation Credit Transfer Certificate and a documented copy of the debit of credits from the Bank Official Credit Ledger(s), indicating the permit number and the resource type secured by the applicant. A copy of the Mitigation Credit Transfer Certificate, with an updated Official Credit Ledger will also be sent to regulatory agencies showing the proper documentation. If any questions need to be answered, please contact me at 919-209-1055 or astaley@res.us. Best Regards, _Ay�- �' Amy Staley Credit Sales Manager RES