HomeMy WebLinkAboutSW6211002_Supplement-EZ Form_20220810SUPPLEMENT-EZ COVER PAGE
FORMS LOADED
PROJECT INFORMATION
1 Project Name
2 Project Area ac
3 Coastal Wetland Area ac
B&B Loop Subdivsion
14.33
0
0.56
4
Surface Water Area ac
5
Is this Droiect High or Low Density?
Low
6
Does this protect use an off -site SCM?
No
COMPLIANCE WITH 02H .1003(4)
7
Width of ve etated setbacks provided feet
30
8
Will the vegetated setback remain vegetated?
Yes
9
If BUA is proposed in the setback, does it meet NCAC 02H.1003 4 c-d ?
N/A
10
1 Is streambank stabilization proposed on this project?
No
NUMBER AND TYPE OF SCMs:
11
Infiltration System
12
Bioretention Cell
13
Wet Pond
14
Stormwater Wetland
15
Permeable Pavement
16
Sand Filter
17
Rainwater Harvesting RWH
18
Green Roof
19
Level Spreader -Filter Strip LS-FS
20
Disconnected Impervious Surface DIS
21
Treatment Swale
22
Dry Pond
23
StormFilter
24
Silva Cell
25
Ba filter
IFilterra
26
FORMS LOADED
NER CERTIFICATION
Name and Title:
Organization:
Street address:
City, State, Zip:
Phone number(s):
Email:
C. Scott Brown, PE
4D Site Solutions Inc.
409 Chicago Drive, Ste. 112
Fayetteville, NC 28306
910-426-6777
3brown(&4dsitesolutions.com
Certification Statement:
I certify, under penalty of law that this Supplement-EZ form and all supporting information were prepared under my direction or supervision; that
the information provided in the form is, to the best of my knowledge and belief, true, accurate, and complete; and that the engineering plans,
specifications, operation and maintenance agreements and other supporting information are consistent with the information provided here.
Seal
Signature of Designer
Date
DRAINAGE AREAS
1
Is this a high density project?
No
2
If so, number of drainage areas/SCMs
0
3
Does this oroiect have low densit areas?
Yes
4
If so number of low 4-ify drainage areas
1
5
Is all/part of this project subject to previous rule
versions?
No
FORMS LOADED
DRAINAGE AREA INFORMATION
Entire Site
LID 1
4
Type of SCM
n/a
n/a
5
Total drainage area (sq ft
624214
624214
6
Onsite drainage area (sq ft
624214
624214
7
Offsite drainage area (sq ft
0
0
8
Total BUA in project (sq ft
149736 sf
149736
9permitting)
New BUA on subdivided lots (subject to
s ft
102587 sf
102587
10
New BUA not on subdivided lots (subject to
permitting) (sf)
47149 sf
47149 sf
11
Offsite BUA (sq ft
sf
sf
12
Breakdown of new BUA not on subdivided lots:
- Parking (sq ft
- Sidewalk (sq ft
6215 sf
6215 sf
- Roof (sq ft
- Roadway s ft
40934 sf
40934 sf
- Future (sq ft
- Other, please specify in the comment box
below (sq ft
13
New infiltrating permeable pavement on
subdivided lots (sq ft
sf
sf
14
New infiltrating permeable pavement not on
subdivided lots (sq ft
sf
sf
15permitting)
Existing BUA that will remain (not subject to
s ft
sf
sf
16
lExistina BUA that is already permitted (sq ft
sf
sf
17
Existing BUA that will be removed (sq ft
sf
sf
18
Percent BUA
24 0
0.24
19
IDesign storm inches
1.0 in
1.0 in
20
IDesign volume of SCM cu ft
n/a
n/a
21 lCalculation method for design volume n/a
ADDITIONAL INFORMATION
Please use this space to provide any additional information about the
22 drainage area(s):
n/a
LOW DENSITY
DESIGN
REQUIREMENTS FOR LOW DENSITY PROJECTS FROM 021-1.1003
1
Is project below density thresholds set forth in the applicable stormwater rule?
Yes
2
Does project maximize dispersed flow and minimize channelization of flow?
Yes
3
Has the use of piping been minimized per .1003(2)(c)?
Yes
4
Side slopes of the vegetated conveyances (H:V)
3 sf
5
Maximum velocity in the vegetated conveyances during the 10-year storm?
2
6
Are curb outlet swales proposed?
Yes
7
Maximum longitudinal slope of curb outlet swale(s) (%)
2
8
Bottom width of curb outlet swale(s) (feet)
2 It
9
Maximum side slope of curb outlet swale(s) (H:V)
3:1
10
Minimum length of curb outlet swale(s) (feet)
100 It
11
Are treatment swales used instead of curb outlet swales?
No
12
Is stormwater released at the edge of the setback as dispersed flow?
Yes
13
Have stormwater outlets been designed to prevent downslope erosion?
Yes
14
Are variations to rule .1003 proposed?
No
ADDITIONAL INFORMATION
15 JPlease use this space to provide any additional information about this low density project: