July 27, 2022
LETTER OF APPROVAL WITH MODIFICATIONS
Duke Energy Carolinas, LLC
Attention: Jeffrey Goto, Lead Permitting Manager
EC09Q 526 South Church Street
Charlotte, NC 28202
RE: Project Name: Duke Energy Toyota Tap 100kV Transmission Line
Acres Approved: 106.36 (fees paid for contingency reviews up to 117 acres)
Project ID: RANDO-2022-041
County: Guilford and Randolph
City: Climax
Address: Hunt Road
River Basin: Cape Fear
Stream Classification: WS-III
Submitted By: HDR Engineering Inc.
Date Received by LQS: June 27, 2022
Plan Type: New
-b- a ►A_61aI
This office has reviewed the subject erosion and sedimentation control plan. We find the plan to be
acceptable with modifications and hereby issue this letter of Approval with Modifications. The
modifications required for approval are listed on the attached page. This plan approval shall expire three
(3) years following the date of approval, if no land -disturbing activity has been undertaken, as is
required by Title 15A NCAC 4B .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an electronic
Notice of Intent (eNOI) form requesting a Certificate of Coverage (COC) under the NCG010000
Construction General Permit. After the form is reviewed and found to be complete, you will receive a
link with payment instructions for the $100 annual permit fee. After the fee is processed, you will
receive the COC via email. As the Financially Responsible Party shown on the FRO form submitted for
this project, you MUST obtain the COC prior to commencement of any land disturbing
activity. The eNOI form may be accessed at deq.nc.gov/NCGO 1. Please direct questions about
the eNOI form to the Stormwater Program staff in the Raleigh central office. If the owner/operator of
this project changes in the future, the new responsible party must obtain a new COC.
North Carolina Department of Environmental Quality Division of Energy, Mineral and Land Resources
Winston-Salem Regional Office =tSO Hanes Mill Road, Suite 300 Winston-Salem, North Carolina 27105
'�"' 336-776-9800
Letter of Approval with Modifications
Duke Energy Carolinas, LLC
July 27, 2022
Page 2 of 3
Title 15A NCAC 4B .0118(a) and the NCGO1 permit require that the following documentation be kept
on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic inspection to
insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring protection of
existing natural resources and adjoining properties. If, following the commencement of this project, it is
determined that the erosion and sedimentation control plan is inadequate to meet the requirements of the
Sedimentation Pollution Control Act of 1973 (North Carolina General Statute 113A-51 through 66), this
office may require revisions to the plan and implementation of the revisions to ensure compliance with
the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal and State water
quality laws, regulations, and rules. In addition, local city or county ordinances or rules may also apply
to this land -disturbing activity. This approval does not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided in the
Financial Responsibility Form, which you provided. You are requested to file an amended form if there
is any change in the information included on the form. In addition, it would be helpful if you notify this
office of the proposed starting date for this project.
Your cooperation is appreciated.
Sincerely,
l
!�
Tamera
Regional Engineer
Land Quality Section
Enclosures: Certificate of Approval
Modifications Required for Approval
NCGO1 Fact Sheet
ec: Brooke Ahrens, HDR (email)
David Baker, HDR (email)
Letter of Approval with Modifications
Duke Energy Carolinas, LLC
July 27, 2022
Page 3 of 3
MODIFICATIONS REQUIRED FOR APPROVAL
Project Name: Duke Energy Toyota Tap 100kV Transmission Line
Project ID: RANDO-2022-041
County: Guilford and Randolph
Modifications pursuant to applicable North Carolina General Statutes and/or Regulations:
1. As clarified in the project narrative on the plans, this plan review is for 106.36 acres, and fees
have been paid for a total of 117 acres of plan reviews on a contingency basis.
2. Additional measures may be required - The applicant is responsible for the control of
sediment on -site. If the approved erosion and sedimentation control measures prove
insufficient, the applicant must take those additional steps necessary to stop sediment from
leaving this site. [15A NCAC 4B .0115]
3. This ESC plan was approved based on information submitted via E-mail to Tamera Eplin, PE
on July 25, 2022. For inspection purposes, two copies of revised plans reflecting the E-
mailed information must be delivered to this office by August 12, 2022 or prior to the
beginning of construction, whichever date is earlier. Please reference "Project Number
RANDO-2022-041 INSPECTION COPIES" in your cover memo. [15A NCAC 4B .0107(c)]
Ref: G.S. 113A-54.1 through G.S. 113A-57
Sections 15A NCAC 04A.0101 through 15A NCAC 04E.0504
General Permit NCG 010000 NPDES for Construction Activities