HomeMy WebLinkAbout20090136 Ver 9_05_SAW-2022-00621 (Dunn Creek Greenway) PJD Concurrence_20220808 From: Norton,April R CIV USARMY CESAW(USA)
To: Sullivan.William
Cc: Wyatt,Brandon
Subject: SAW-2022-00621(Dunn Creek Greenway)PJD Concurrence
Date: Tuesday,April 26,2022 3:19:08 PM
Attachments: SAW-2022-00621 PJD Features Marm)df
Dear William Sullivan,
Reference is made to Corps Action ID: SAW-2022-00621. Please reference this number on any
correspondence regarding this action.
We have reviewed the information provided by you concerning the aquatic resources, and by copy
of this e-mail, are confirming that the aquatic resources delineation has been verified by the Corps
to be a sufficiently accurate and reliable representation of the location and extent of aquatic
resources within the identified review area. The location and extent of these aquatic resources are
shown on the delineation map entitled "Potentially Jurisdictional Features Map" and dated March
2022.
Regulatory Guidance Letter(RGL) 16-01
https://usace.contentdm.ocic.org/utils/getfile/collection/pl602lco119/id/1256 provides guidance for
Jurisdictional Determinations (JD) and states, "The Corps generally does not issue a JD of any type
where no JD has been requested." Currently, we are only verifying the delineation. This delineation
may be relied upon for use in the permit evaluation process, including determining compensatory
mitigation. This verification does not address nor include any consideration for geographic
jurisdiction on aquatic resources and shall not be interpreted as such.
This delineation verification is not an Approved Jurisdictional Determination (AJD) and is not an
appealable action under the Regulatory Program Administrative Appeal Process (33 CFR Part 331).
However, you may request an AJD, which is an appealable action.
If you wish to receive a Preliminary Jurisdictional Determination (PJD), or an Approved Jurisdictional
Determination (AJD) please respond accordingly, otherwise nothing further is required and we will
not provide any additional documentation.
**Due to workload volume, it may take 90- 120 days or more for the issuance of a standalone JD;
however, you may use the delineation for planning and permitting purposes.
Thank you,
April Norton
April R. Norton
Regulatory Division
US Army Corps of Engineers
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Phone: (919) 441-3637
Fax: (919) 562-0421
Email: April.R.Norton(@usace.army.mil