July 6, 2022
LETTER OF APPROVAL
RE: Project Name: 1963 & 1970 Basin Excavation Erosion & Sediment Control Plan
Acres Approved: 59
Project ID: CHATH-2022-008
County: Chatham
City: Moncure
Address: 500 CP&L Road
River Basin: Cape Fear
Stream Classification: Other
Submitted By: Wood Engineering, ATTN: Claudia Prado
Date Received by LQS: May 23, 2022
Plan Type: Utility
Dear Mr. Zarzar:
The subject erosion and sedimentation control plan has been approved by default. The
Sedimentation Pollution Control Act (hereinafter "Act") states that this plan must be filed
a minimum of 30 days (15 days for revised plans) prior to the activity and the approving
authority must approve or disapprove the submitted plan within 30 days (15 days for
revised plans) of receipt of G.S. 113A-54.1. The Act further states that if the approving
authority fails to approve or disapprove the submitted plan within the 30-day (15 days for
revised plans) period, the plan will be deemed approved. The enclosed Certificate of
Approval must be posted at the job site. This plan approval shall expire three (3) years
following the date of approval, if no land -disturbing activity has been undertaken, as is
required by Title 15A NCAC 413 .0129.
As of April 1, 2019, all new construction activities are required to complete and submit an
electronic Notice of Intent (eNOI) form requesting a Certificate of Coverage (COC) under
the NCG010000 Construction General Permit. After the form is reviewed and found to be
complete, you will receive a link with payment instructions for the $100 annual permit
fee. After the fee is processed, you will receive the COC via email. As the Financially
R11 :AA01 D_E Q�
1 Ervirpnnrndl pYllll�
North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources
Raleigh Regional Office 11628 Mail Service Center 13800 Barrett Drive I Raleigh, North Carolina 27609
919.791.4200
Letter of Approval
Duke Energy Progress, LLC
July 6, 2022
Page 2of3
Responsible Party shown on the FRO form submitted for this project, you MUST obtain
the COC prior to commencement of any land disturbing activity. The eNOI form may be
accessed at deq.nc.gov/NCGOL Please direct questions about the eNOI form
to the Stormwater Program staff in the Raleigh central office. If the owner/operator of this
project changes in the future, the new responsible party must obtain a new COC.
Title 15A NCAC 413 .0118(a) and the NCGO1 permit require that the following
documentation be kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCGO1 permit and the COC, once it is received.
3. Records of inspections made during the previous 12 months.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic
inspection to ensure compliance with the approved plan.
Title 15A NCAC 413 .0118(a) requires that a copy of the approved erosion control plan be
on file at the job site. Also, this letter gives the notice required by G.S. 113A-61.l(a) of
our right of periodic inspection to ensure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If, following the
commencement of this project, it is determined that the erosion and sedimentation control
plan is inadequate to meet the requirements of the Sedimentation Pollution Control Act of
1973 (North Carolina General Statute 113A-51 through 66), this office may require
revisions to the plan and implementation of the revisions to ensure compliance with the
Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal
and State water quality laws, regulations, and rules. In addition, local city or county
ordinances or rules may also apply to this land -disturbing activity. This approval does not
supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the information provided
in the Financial Responsibility Form, which you provided. You are requested to file an
amended form if there is any change in the information included on the form. This permit
allows for a land -disturbance, as called for on the application plan, not to exceed the
approved acres. Exceeding the acreage will be a violation of this permit and would require
a revised plan and additional application fee. In addition, it would be helpful if you notify
this office of the proposed starting date for this project.
Your cooperation is appreciated.
North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources
Raleigh Regional Office 11628 Mail Service Center 13800 Barrett Drive I Raleigh, North Carolina 27609
NORTH CAADUNA
Dq-h enW F' .lw.1 919.791.4200
Letter of Approval
Duke Energy Progress, LLC
July 6, 2022
Page 3 of 3
Sin erely,
1) L L-�5—
Dylan Reinhardt
Assistant Regional Engineer
Land Quality Section
Enclosures: Certificate of Approval
NPDES NCGO1 Fact Sheet
cc: Regional Office file
Wood Engineering, ATTN: Claudia Prado (claudia.pradogwoodplc.com)
North Carolina Department of Environmental Quality I Division of Energy, Mineral and Land Resources
Raleigh Regional Office 11628 Mail Service Center 13800 Barrett Drive I Raleigh, North Carolina 27609
+NORTH CAROLINP.
Dq.tId ti 0,.1 919.791.4200