HomeMy WebLinkAboutNC0024244_SOC quarterly report 3Q - 2022_20220718Strickland, Bev
From: Rob McIntyre <rob@lkcengineering.com>
Sent: Monday, July 18, 2022 3:14 PM
To: Basinger, Corey; Scheller, Roberto
Cc: Hinson, Bryan L; Voyles, Jay; Brandon Plyler (bplyler@ci.albemarle.nc.us); Whitley,
Derek S; Adam Kiker
Subject: [External] Albemarle SOC quarterly report 3Q - 2022
Attachments: 2022 - Q3 Report - SOC WQ S19-007.pdf
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Good afternoon Corey and Roberto —
Attached is the quarterly report for 3Q 2022 for the Albemarle SOC. I had this prepared on Friday but forgot to send it,
my apologies!
Please let us know if you have any questions or need additional information.
Thanks,
Rob
ROB MCINTYRE, P.E.
LEC
LKC Engineering, PLLC
140 Aqua Shed Court
Aberdeen, NC 28315
Ph: (910) 420-1437
Cell: (980) 622-0376
Follow us on Instagram! @Ikc_engineering
1
___________
LKC Engineering, PLLC, 140 Aqua Shed Court, Aberdeen, North Carolina 28315
PH: 910/420-1437 * FAX: 910/637-0096 * License No. P-1095
July15,2022
Mr.W.CoreyBasinger
RegionalSupervisor,Mooresville
NCDEQ–DivisionofWaterResources
610ECenterAvenue,Suite301
Mooresville,NC281115
Re:QuarterlyReport–ThirdQuarter2022
SOCWQS19Ͳ007
DearMr.Basinger:
OnbehalfofAlbemarle,pleaseacceptthisasaQuarterlyReportforthesubjectSpecialOrderbyConsent.
BelowisabriefupdateontheSOCandassociatedprojects:
1. AlbemarlereceivedfundingthroughtheDivisionofWaterInfrastructurefor$16,453,000in
fundingforamajorrenovationtotheLongCreekWastewaterTreatmentPlant.Theprimary
objectiveoftheprojectistotransitiontheaerationprocessfromthefloatingaeratorsoverto
diffusedaeration.Theprojectwouldalsoprovidefor8,000,000gallonsofflowequalization
volumetomanagepeakflowevents.
2. TheEngineeringReportwassubmittedtotheNCDEQWastewaterProjectsUnitonAugust25,
2021.
3. ARequestforAdditionalInformationwasreceivedonNovember9th,2021.
4. TherevisedEngineeringReportwassubmittedbacktotheDivisionofWaterInfrastructureon
December8th,2021.
5. Theprojectcosthasincreasedto$19,385,000.ThiswaspresentedtotheAlbemarleCityCouncil
inDecemberof2021andCouncilreͲaffirmedtheircommitmenttotheproject.
6. TheFinalEngineeringReportwassubmittedonApril18th,2022.Weexpecttoreceivewritten
approvalfromNCDEQDWIanydaynow.
7. OnJune22,2022,theCitysubmittedarevisedSOCapplicationwithnewproposedmilestone
completiondates.Thesedatesreflectthescopeandtimelineoftheproposedimprovementsat
theWWTP,projectCS370522Ͳ08.Pleaseseethetablebelowforthosemilestonesanddates:
Scheduled Activity Original Due Date Proposed Due Date
Submit Quarterly Progress Reports
(see details in paragraph 2(b) below.)
Beginning October 15,
2020 Ongoing
For NPDES Permit NC0024244:
Begin implementation or construction of
WWTP improvements items in Attachment B. March 31, 2022 July 31, 2024
Complete construction of all WWTP
improvements September 30, 2023 February 28, 2026
Attain Compliance with NPDES permit limits September 30, 2023 May 31, 2026
8. Albemarle’sCouncilvotedtoutilizeallfundsobligatedunderCS370522Ͳ07ongravitysewer
rehabilitation.ThePhase3projectincludesaninvestmentof$6,156,000ontherehabilitationof
24”,18”,12”,and8”gravityseweralongtwomajoroutfallsthatareknownsourcesofinflowand
infiltration.
9. TheprojectCS370522Ͳ07iscurrentlyinthedesignphaseandwillbesubmittedtoDWIforreview
February2022.TheprojectisexpectedtobeginconstructionintheSummerof2022andtake
approximatelyninemonthstocomplete.
10. TheprojectdesignpackageforprojectCS370522Ͳ07wassubmittedtoDWIinearlyFebruary.DWI
completeditsreviewandprovidedcommentsonApril1st,2022.Finaldesignpackagewas
submittedonJuly7th.WereceivedPlansandSpecificationsFundingApprovalfromNCDWIon
July12th.WeplantoadvertisethismonthandopenbidsinearlySeptember2022.
11. OnJune22,2022,theCitysubmittedarevisedSOCapplicationwithnewproposedmilestone
completiondates.Theproposedworkforthecollectionsystemisslatedtobecompletedby
November30,2023.Pleaseseethetablebelowforthemilestonesandproposedcompletion
dates:
Scheduled Activity Original Due Date in
Executed SOC
Proposed Due
Date
Submit Quarterly Progress Reports
(see details in paragraph 2(b) below.)
Beginning October 15,
2020 Ongoing
For Collection System Permit WQCS00016:
Complete Sanitary Sewer Rehab, Phase 1 December 31, 2019 Met
Begin construction on Sanitary Sewer Rehab,
Phase 2 July 31, 2019 Met
Apply for funding for Sanitary Sewer Rehab,
Phase 3 September 30, 2019 Met
Receive Letter of Intent to Fund for Phase 3 March 31, 2020 Met
Submit finished plans and specifications for
review for Phase 3 September 30, 2021 Met
Complete construction on Phase 2 November 30, 2020 Met
Begin Construction and execute construction
contract for Phase 3 March 31, 2022 August 31, 2022
Complete construction on Phase 3 March 31, 2023 June 30, 2023
Review infrastructure improvements for
maintaining compliance September 30, 2023 November 30,
2023
Attain Compliance with the Collection System
Permit September 30, 2023 November 30,
2023
Ifyouhaveanyquestions,orifwemaybeofassistance,pleasedonothesitatetocontactmebyphone
at(910)420Ͳ1437orbyemailatadam@LKCengineering.com.
VeryBest,
JohnR.McIntyre,P.E.
!"#$%&’()