Attached is a copy of the inspection report which was prepared following an on -site inspection of the
subject site. This report is intended to provide you with information concerning the status of the site as
it relates to compliance with the North Carolina Sedimentation Pollution Control Act of 1973.
Please review this report carefully as it may contain corrective actions needed or comments which will
assist you in meeting the required performance standards of the Act.
It is our desire that any and all possible problems be discussed and resolved at the earliest possible time.
To facilitate this effort, please contact the named inspector at the address shown on the inspection
report if you have any questions.
Sincerely,
Land Quality Section
Mooresville Regional Office
North Carolina Department of Environmental Quality I Division of Energy. Mineral and Land Resources
Mooresville Regional Office 610 East Cenler Avenue, Suite 301 Mooresville, North Carolina 281 I5
ig D704-663-1699
air
Sedii-neiitatioii/Coiistructioii Stormwater Inspection Report
North Carolina Department of Environmental Quality
Land Resources: 610 East Center Avenue, Suite 301, Mooresville, NC 28115 (704) 663-1699
County: iredell Project: 200260-Lakeshore Elem Bldg Additions River basin: Catawba
Person financially responsible: Iredell Statesville Schools -Scott Hager, Director Project #: IREDE-2021-011
of Construction
Address: 549 North Race Street, Statesville, NC 28677
1. Project Location: Lakeshore School Road, Mooresville
Pictures: No
2. Weather and soil conditions: Sunny, workable soil Initial inspection: No
3. Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A. and rules? Yes If no, check violations below:
5. Violations:
6. Is the site in compliance with NPDES Permit NCG010000 Construction Stormwater requirements? Yes
Describe:
7. Has sedimentation damage occurred since last inspection? No If Yes, where? (check all that apply)
Degree of damage:
8. Contact made with (name): No one on site Title:
Inspection report: Sent Report Date given/sent: June 24, 2022
9. Corrective action needed:
10. Comments: Overall the site has sufficient permanent ground cover to restrain erosion, however there are
some bare areas and rills that need to be repaired and stabilized. No additional self -monitoring
or self -inspections are required. Project is in compliance and released under the SPCA.
Termination of coverage under the NPDES General Stormwater Permit for Construction
Activities (NCG01) must be requested by the permittee via a Notice of Termination (NOT).
The NOT is available at: https://edoes.deq.nc.gov/Forms/NCGOI-Termination. Please note
that this correspondence must be uploaded as part of completing the NOT process.
All project that have been approved prior to April 01, 2019, under the old permit system, are
not required to take any additional actions. The stormwater permit is terminated at the same
time as the termination of this erosion control permit.
Reported by: Jesse McDonnell Others present:
Date of inspection: June 21, 2022 Time arriving on site: 12:15 pM Time leaving site: 12:25 PM