HomeMy WebLinkAboutSW5220101_Plansheet - SCM Detail_20220408STORMWATER CONTROL MEASURE 'A' CONSTRUCTION SPECIFICATIONS GENERAL NOTES CONSTRUCTION SEQUENCE 1. PRIOR TO CONSTRUCTION, ANY DISCREPANCIES IN THE PLANS AND NOTES SHALL BE BROUGHT TO THE DESIGN ENGINEER'S ATTENTION 1. PRIOR TO CONSTRUCTION, THE OWNER SHALL OBTAIN A LAND DISTURBING (GRADING) PERMIT AND AN "APPROVAL TO CONSTRUCT" IMMEDIATELY. FROM THE NORTH CAROLINA DEPARTMENT OF ENVIRONEMNTAL QUALITY AND ALL OTHER NECESSARY PERMITS FROM APPLICABLE AGENCIES (E.G. 404 / 401 PERMITS) 2. THE PROJECT WILL MEET ALL OF THE REQUIREMENTS RELATIVE TO BEST MANAGEMENT PRACTICES AND ENGINEERED STORMWATER CONTROL STRUCTURES AS OUTLINED IN NORTH CAROLINA STORMWATER CONTROL DESIGN MANUAL. 2. INSTALL ALL SEDIMENT AND EROSION CONTROL MEASURES PER THE APPROVED SEDIMENT AND EROSION CONTROL PLAN. THE CONTRACTOR SHALL MAINTAIN ALL APPROVED SEDIMENT AND EROSION CONTROL MEASURES THROUGHOUT THE ENTIRE PROJECT, AS 3. THE FINAL CERTIFICATION FOR THIS FACILITY WILL INCLUDE A CERTIFICATION BY THE ON -SITE GEOTECHNICAL ENGINEER THAT THE REQUIRED. THE CONTRACTOR SHALL RECEIVE APPROVAL FROM THE EROSION CONTROL INSPECTOR, AS REQUIRED BY GOVERNING PROJECT WAS CONSTRUCTED PER THE APPROVED PLANS. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO COORDINATE WITH THE AGENCIES, PRIOR TO ANY CLEARING. ON -SITE GEOTECHNICAL ENGINEER FOR OBSERVATION AND TESTING SUCH THAT THE ON -SITE GEOTECHNICAL ENGINEER CAN CERTIFY THE CONSTRUCTION OF THE DAM EMBANKMENT AND SPILLWAY. THIS CERTIFICATION MUST ADDRESS THE TESTING FOR MATERIALS AND 3. CLEAR AND GRUB AREA WITHIN THE LIMITS OF THE PROPOSED DAM CONSTRUCTION. ALL TREES AND THEIR ENTIRE ROOT SYSTEMS MUST COMPACTION OF THE DAM EMBANKMENT AND SPILLWAY. BE REMOVED FROM THE DAM FOOTPRINT AREA AND BACKFILLED WITH SUITABLE SOIL MATERIAL. THE BACKFILLED AREAS SHALL BE COMPACTED TO THE SAME STANDARDS AS THE DAM EMBANKMENT. THE REMAINING AREA OF THE EMBANKMENT SHALL BE STRIPPED TO 4. ALL CONSTRUCTION ACTIVITY RELATED TO THE PROPOSED STORMWATER CONTROL MEASURE SHALL BE PER THE DETAILS AND ASUITABLE DEPTH AS DIRECTED BY THE ON SITE GEOTECHNICAL ENGINEER. ANY RESIDUAL SOILS TO BE LEFT IN PLACE MUST BE WELL SPECIFICATIONS SHOWN IN THESE DRAWINGS. SOILS, COMPACTION, AND OTHER MISCELLANEOUS DETAILS AND SPECIFICATIONS MAY BE SCARIFIED TO PROMOTE BONDING OF THE NEW EMBANKMENT FILL. NO EMBANKMENT MATERIAL SHALL BE PLACED FOR THE DAM OR MODIFIED PER THE RECOMMENDATIONS OF THE ON -SITE GEOTECHNICAL ENGINEER. HOWEVER, PRIOR TO IMPLEMENTATION, THE DESIGN KEY TRENCH UNTIL APPROVAL OF THE DAM SUBGRADE IS OBTAINED FROM THE ON -SITE GEOTECHNICAL ENGINEER. ENGINEER SHALL BE NOTIFIED OF ANY DEVIATION FROM THESE DESIGN DRAWINGS, INCLUDING SHOP DRAWINGS FOR ANY PROPOSED MODIFICATION. 4. EXCAVATE FOR THE NEW KEY TRENCH ALONG THE CENTERLINE OF THE PROPOSED DAM EMBANKMENT. THE TRENCH SHALL EXTEND A MINIMUM OF 5 FT BELOW EXISTING GRADE OR 2 FT BELOW THE 18"0 RCP OUTLET BARREL AND SHALL HAVE A MINIMUM BOTTOM 5. DURING THE INITIAL STAGES OF CONSTRUCTION THE STORMWATER CONTROL MEASURE MAY BE USED AS A SEDIMENT BASIN FOR WIDTH OF 5 FEET. THE KEY TRENCH SIDESLOPES SHALL BE A MINIMUM OF 1:1 (H:V). WHEN EXCAVATING THE KEY TRENCH, IF ANY DEBRIS EROSION CONTROL PURPOSES. IF SO, THE CONTRACTOR SHALL FOLLOW THE GENERAL CONSTRUCTION SEQUENCE BELOW: IS ENCOUNTERED TO AN EXTENT THAT SUCH DEBRIS MAY EXIST IN OTHER INSITU PORTIONS OF THE DAM EMBANKMENT, IT SHOULD ALSO A. THE CONTRACTOR SHALL CONSTRUCT THE ENTIRE FACILITY (PERMANENT OUTLET STRUCTURE, DAM, ETC.) WITH THE EXCEPTION OF BE REMOVED. THE KEY TRENCH SHALL BE COMPACTED TO THE SAME SPECIFICATION LISTED IN ITEM 4 OF THE SECTION TITLED "BERM THE INTERIOR FINE GRADING FOR THE FACILITY. THE INTERIOR FINE GRADING WILL BE CONSTRUCTED ONCE THE EROSION CONTROL AND SOIL COMPACTION SPECIFICATIONS." DEPENDING UPON ON -SITE SOIL CONDITIONS ENCOUNTERED DURING EXCAVATION, THE PHASE IS COMPLETE. ON -SITE GEOTECHNICAL ENGINEER MAY VARY THE DEPTH AND DIMENSIONS OF THE KEY TRENCH AS DEEMED NECESSARY. THE ON -SITE B. THE TEMPORARY DRAW DOWN RISER (OR SKIMMER) SHALL BE CONNECTED TO THE PERMANENT 6"0 DIP DRAIN PIPE. GEOTECHNICAL ENGINEER SHALL RETAIN DOCUMENTATION OF ANY VARIATION FOR FUTURE AS -BUILT SUBMITTALS TO THE TOWN OF C. ONCE THE UPSTREAM DRAINAGE AREA IS STABILIZED AND THE EROSION CONTROL INSPECTOR APPROVES THE REMOVAL OF THE BUNN. SEDIMENT BASIN, THE CONTRACTOR SHALL REMOVE THE TEMPORARY DRAW DOWN RISER (OR SKIMMER) AND CLEAN OUT THE BASIN. ALL SEDIMENT, TRASH, ETC. SHALL BE DISPOSED OF PROPERLY (I.E. - PLACED IN A LANDFILL) AND NOT STOCKPILED IN AN AREA 5. BEGIN PLACEMENT OF BACKFILL WITHIN THE KEY TRENCH. THE KEY TRENCH SHALL BE COMPACTED TO THE SPECIFICATIONS LISTED ITEM 4 WHERE WATER QUALITY COULD BE ADVERSELY AFFECTED. OF THE SECTION TITLED "BERM AND SOIL COMPACTION SPECIFICATIONS." THE KEY TRENCH SHALL BE TESTED PER THE SPECIFICATIONS D. ONCE THE BASIN IS CLEANED OUT, AND ALL EROSION CONTROL DEVICES REMOVED, THE CONTRACTOR SHALL CONSTRUCT THE LISTED IN THAT SECTION. INTERIOR GRADING SHOWN ON THIS SHEET. - E. ONCE THE GRADING IS COMPLETE, THE CONTRACTOR SHALL REQUEST AN ON SITE INSPECTION AND AN AS BUILT SURVEY PRIOR TO 6. PRIOR TO INSTALLATION SUBGRADE CONDITIONS ALONG THE SPILLWAY PIPES SHOULD BE EVALUATED BY THE ON -SITE GEOTECHNICAL , INSTALLATION OF THE STORMWATER CONTROL MEASURE PLANTS. IF THE CONTRACTOR PLANTS THE PROPOSED VEGETATION PRIOR ENGINEER TO ASSESS WHETHER SUITABLE BEARING CONDITIONS EXIST AT THE SUBGRADE LEVEL. SHOULD SOFT OR OTHERWISE TO AN AS -BUILT SURVEY (AND SUBSEQUENT APPROVAL), ANY CHANGES TO THE GRADING / RE -PLANTING OF PLANTS WILL BE AT THE UNSUITABLE CONDITIONS BE ENCOUNTERED ALONG THE PIPE ALIGNMENTS, THESE MATERIALS SHOULD BE UNDERCUT AS DIRECTED BY CONTRACTOR'S EXPENSE. THE GEOTECHNICAL ENGINEER. THE UNDERCUT MATERIALS SHALL BE REPLACED WITH ADEQUATELY COMPACTED STRUCTURAL FILL, LEAN F. ONCE THE ENGINEER HAS APPROVED THE AS -BUILT GRADING, THE CONTRACTOR SHALL PLANT THE PROPOSED STORMWATER CONCRETE OR FLOWABLE FILL AS DIRECTED BY THE ON -SITE GEOTECHNICAL ENGINEER. CONTROL MEASURE PLANTS SHOWN ON THE LANDSCAPE PLAN FOR THE FACILITY. AFTER COMPLETION OF THE PLANTING, THE LANDSCAPE CONTRACTOR SHALL PROVIDE A LETTER TO THE ENGINEER CERTIFYING THAT THE PLANTS HAVE BEEN INSTALLED PER THE 7. IN ORDER TO HELP PROTECT THE SOIL SUBGRADE FROM DETERIORATION (DUE TO EXPOSURE, RAINFALL, SEEPAGE, AND RUNOFF) BEFORE APPROVED STORMWATER CONTROL MEASURE PLANTING PLAN. THE CRADLE CAN BE POURED, IT IS STRONGLY RECOMMENDED THAT A 3" TO 4" THICK CONCRETE MUD MAT BE POURED OVER THE 6. ALL OSHA REQUIREMENTS FOR EXCAVATIONS (SHORING, DEPTH, ETC.) ARE THE RESPONSIBILITY OF THE CONTRACTOR. IF REQUIRED, THE SUBGRADE ONCE IT IS APPROVED BY THE ON -SITE GEOTECHNICAL ENGINEER. THE MUD MAT WILL ALSO PROVIDE BEARING FOR THE CONTRACTOR SHALL PROVIDE AN EXCAVATION PLAN TO BE SEALED BY A NC P.E. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO BLOCKS THAT TEMPORARILY SUPPORT THE SPILLWAY PIPE UNTIL THE CRADLE CAN BE POURED. THE METHOD OF BLOCK SUPPORT FOR THE DETERMINE IF AN EXCAVATION PLAN IS REQUIRED. THE JOHN R. MCADAMS COMPANY ASSUMES NO RESPONSIBILITY FOR ANY PIPE PROPOSED BY THE CONTRACTOR SHOULD BE SUBMITTED TO THE JOHN R. MCADAMS COMPANY FOR REVIEW. EXCAVATION DESIGN RELATED TO SAFETY OR OSHA REQUIREMENTS. 8. BEGIN CONSTRUCTION OF THE NEW EMBANKMENT. FILL MATERIALS SHALL BE PLACED IN MAXIMUM 8" THICK LIFTS PRIOR TO 7. ON -SITE GEOTECHNICAL ENGINEER TO DETERMINE IF IN -SITU SOILS ENCOUNTERED WOULD MAINTAIN A STORMWATER CONTROL COMPACTION, UNLESS DIRECTED OTHERWISE BY THE ON -SITE GEOTECHNICAL ENGINEER. FILL LIFTS SHALL BE CONTINUOUS OVER THE MEASURE PERMANENT POOL AT DESIGN ELEVATION. IF HIGHLY PERMEABLE SOILS ARE ENCOUNTERED THAT WOULD NOT MAINTAIN ENTIRE LENGTH OF FILL. IF IT IS NECESSARY, THE EMBANKMENT FILL MATERIAL WILL BE OVERBUILT IN HORIZONTAL LIFTS AND CUT BACK THE PERMANENT POOL ELEVATION AS DESIGNED, A CLAY LINER MAY BE REQUIRED TO MAINTAIN A PERMANENT POOL OF WATER IN THE TO FINAL GRADE IN ORDER TO ACHIEVE PROPER COMPACTION. STORMWATER CONTROL MEASURE. FINAL DETERMINATION IF A CLAY LINER IS NEEDED SHALL BE THE RESPONSIBILITY OF THE ON -SITE GEOTECHNICAL ENGINEER. UPON DETERMINATION OF HIGHLY PERMEABLE SOIL CONDITIONS, ON -SITE GEOTECHNICAL ENGINEER WILL 9. AS CONSTRUCTION OF THE EMBANKMENT MOVES FORWARD, IT WILL BE NECESSARY TO INSTALL THE CONCRETE CRADLE. SEE NOTE ON INFORM THE DESIGN ENGINEER AND RECOMMEND LINER SPECIFICATIONS. CRADLE DETAIL (SHEET C9.03). THIS MAY BE CONSTRUCTED USING ONE OF THE FOLLOWING METHODS: 8. IT IS ANTICIPATED THAT DEWATERING WILL BE NECESSARY IN THE EXCAVATION AREAS (E.G. - EMBANKMENT SUB GRADE, INTERIOR A. IF THE PROPOSED STRUCTURAL FILL MATERIAL IS UTILIZED AS THE FORMWORK FOR THE CONCRETE CRADLE, THEN THE STRUCTURAL PORTIONS OF THE STORMWATER CONTROL MEASURE, KEY TRENCH, ETC.). THEREFORE, THE CONTRACTOR SHALL FURNISH, INSTALL, FILL SHOULD BE INSTALLED AND COMPACTED UP TO THE TOP OF CONCRETE CRADLE ELEVATION. ONCE THE STRUCTURAL FILL OPERATE, AND MAINTAIN ANY PUMPING EQUIPMENT, ETC. NEEDED FOR REMOVAL OF WATER FROM VARIOUS PARTS OF THE REACHES THE NEXT DOWNSTREAM JUNCTION BOX OR HEADWALL AND IS COMPACTED TO THE ELEVATION OF THE TOP OF THE STORMWATER CONTROL MEASURE SITE. DURING PLACEMENT OF FILL WITHIN THESE AREAS, THE CONTRACTOR SHALL KEEP THE WATER CONCRETE CRADLE, EXCAVATE THE CONCRETE CRADLE TRENCH PER THE PROVIDED DETAILS AND CONSTRUCT THE CONCRETE CRADLE LEVEL BELOW THE BOTTOM OF THE EXCAVATION / CONSTRUCTION AREAS. THE MANNER IN WHICH THE WATER IS REMOVED SHALL BE AS PER THE PROVIDED CONCRETE CRADLE DETAIL. SUCH THAT THE EXCAVATION BOTTOM AND SIDE SLOPES ARE STABLE, WITH NO SEDIMENT DISCHARGED FROM THE SITE (I.E. PUMPED WATER MAY NEED TO BE DIRECTED TO AN APPROVED EROSION CONTROL DEVICE SUCH AS A DIRT BAG (ACF ENVIRONMENTAL), OR B. IF THE PROPOSED STRUCTURAL FILL IS NOT UTILIZED AS THE FORMWORK FOR THE CONCRETE CRADLE, THEN PRIOR TO ENGINEER APPROVED EQUIVALENT, PRIOR TO DISCHARGE). CONSTRUCTING THE STRUCTURAL FILL EMBANKMENT, THE FORMWORK FOR THE CONCRETE CRADLE SHOULD BE INSTALLED ON EXISTING GROUND AND/OR THE MUD MAT. THE CONCRETE CRADLE SHALL BE CONSTRUCTED PER THE PROVIDED DETAILS 9. THE GRADES SHOWN ON THIS PLAN ARE FINISHED GRADES. IF THE EXISTING SOIL LAYER AFTER CONSTRUCTION / COMPACTION IS NOT DETERMINED SUITABLE BY A LANDSCAPE PROFESSIONAL FOR THE WETLAND PLANTINGS, THEN THE CONTRACTOR SHALL AMEND THE 10. AS AN ALTERNATE TO A CONCRETE CRADLE UNDER THE BARREL PIPE (SEE SHEET C9.03), THE CONTRACTOR MAY CHOOSE TO ELIMINATE PLANTING AREA OF THE WETLAND AS DIRECTED BY A LANDSCAPE PROFESSIONAL. THE CONCRETE CRADLE AND USE COMPACTED BACKFILL IF THE ON -SITE GEOTECHNICAL ENGINEER WILL PROVIDE A NC PE SEALED LETTER CERTIFYING THAT THE COMPACTION UNDER, AROUND, AND ABOVE THE BARREL MEETS THE SPECIFICATIONS OF THE EMBANKMENT 10. PRIOR TO TOPSOIL INSTALLATION, THE CONTRACTOR SHALL SCARIFY THE TOP 2"-3" OF THE BERM SECTION TO PROMOTE BONDING OF COMPACTION REQUIREMENTS AND MOISTURE CONTENT. THIS CERTIFICATION LETTER MUST BE SUBMITTED TO THE DESIGN ENGINEER THE TOPSOIL WITH THE COMPACTED FILL. THE TOPSOIL DEPTH SHALL RANGE FROM 3C-4" ON THE DAM EMBANKMENT AND THE PRIOR TO BACKFILL. THIS SEPARATE CERTIFICATION MUST BE SPECIFIC TO THE BARREL PIPE FOR THE FACILITY AND MUST CLEARLY STATE WETLAND. PLEASE NOTE THE TOPSOIL SHALL BE AMENDED, AS DIRECTED BY A LANDSCAPE PROFESSIONAL, PRIOR TO INSTALLATION ON THAT ALL SOIL MATERIAL UNDER, AROUND, AND ABOVE THE BARREL PIPE MEETS THE BERM AND SOIL COMPACTION SPECIFICATIONS ON THE EMBANKMENT AND WETLAND. THIS SHEET. THIS CERTIFICATION IS TO INCLUDE REFERENCE TO BOTH MATERIAL AND COMPACTION, AND MUST STATE THAT ALL 0 AND ABOVE THE BARREL HAVE BEEN COMPACTED PER THE BERM MATERIAL SPECIFICATIONS AT LEAST 95/0 MATERIALS UNDER AROUND ( 11. THE CONTRACTOR SHALL REFER TO THE LANDSCAPE PLAN FOR THE PERMANENT PLANTING PLAN/SCHEDULE FOR THIS FACILITY. OF MAXIMUM DRY DENSITY USING ASTM D698 STANDARD PROCTOR) WITH NO VOID SPACES PRESENT. THE CONTRACTORS INTENT TO CONTRACTOR SHALL COORDINATE WITH A LANDSCAPE PROFESSIONAL REGARDING SCHEDULING FOR PLANT INSTALLATION. PLEASE NOTE UTILIZE THIS ALTERNATIVE MUST BE STATED PRIOR TO CONSTRUCTION TAKING PLACE. THIS CONTRACTORS CERTIFICATION MUST BE THAT NO TREES/SHRUBS OF ANY TYPE MAY BE PLANTED ON THE PROPOSED DAM EMBANKMENT (FILL AREAS). PRESENTED TO THE DESIGN ENGINEER BEFORE AN AS -BUILT CERTIFICATION CAN BE ISSUED FOR THIS FACILITY. 11. INSTALL RISER / BARREL ASSEMBLY, ALONG WITH THE EMERGENCY DRAIN SYSTEM. INSTALL 18" RCP OUTLET BARREL SPILLWAY FILTER OUTLET STRUCTURE MATERIAL SPECIFICATIONS FROM THE DETAILS SHOWN ON SHEET C9.03. 1. THE 18" 0 RCP OUTLET BARREL SHALL BE CLASS III RCP, MODIFIED BELL AND SPIGOT, MEETING THE REQUIREMENTS OF ASTM C76-LATEST. 12. CONSTRUCT EMBANKMENT PER SPECIFICATIONS LISTED IN THE SECTION TITLED "BERM AND SOIL COMPACTION SPECIFICATIONS" AND THE PIPES SHALL HAVE CONFINED O-RING RUBBER GASKET JOINTS MEETING ASTM C-443-LATEST. THE PIPE JOINTS SHALL BE TYPE R-4. REQUIREMENTS OF THE ON -SITE GEOTECHNICAL ENGINEER. ALL CHARACTERISTICS OF THE EMBANKMENT FILL MATERIAL SHALL MEET THE STANDARDS SET FORTH IN "BERM AND SOIL COMPACTION SPECIFICATIONS", INCLUDING COMPACTION AND MOISTURE REQUIREMENTS. IF 2. THE STRUCTURAL DESIGN FOR THE 4' X 4' INTERNAL DIMENSIONS RISER BOX WITH EXTENDED BASE SHALL BE BY OTHERS. PRIOR TO ( ) NECESSARY TO ACHIEVE PROPER COMPACTION, THE EMBANKMENT FILL MATERIAL WILL BE OVERBUILT IN HORIZONTAL LIFTS AND CUT ORDERING THE STRUCTURES THE CONTRACTOR SHALL PROVIDE TO THE DESIGN ENGINEER FOR REVIEW SHOP DRAWINGS AND BACK TO PROPER FINAL GRADE. ANY HAND COMPACTION ACTIVITIES AROUND SPILLWAY OR DRAIN STRUCTURES SHALL BE CONDUCTED IN SUPPORTING STRUCTURAL CALCULATIONS SEALED BY A P.E. REGISTERED IN NORTH CAROLINA DEMONSTRATING THE PERTINENT VERTICAL 4-INCH LOOSE LIFTS AND BE TO THE SAME COMPACTION AND MOISTURE REQUIREMENTS AS THE ENTIRE EMBANKMENT. ALL LOADS ARE SUPPORTED BY THE CONCRETE RISER STRUCTURE. COMPACTION AND MOISTURE TESTING SHALL BE CARRIED OUT AS DIRECTED BY THE ON -SITE GEOTECHNICAL ENGINEER AND AS LISTED IN THE SECTION TITLED "BERM AND SOIL COMPACTION SPECIFICATIONS". 3. THE RISER BOX OUTLET STRUCTURE SHALL BE PROVIDED WITH STEPS 16" ON CENTER. STEPS SHALL BE PROVIDED ON THE INNER WALL OF THE RISER BOX. STEPS SHALL BE IN ACCORDANCE WITH NCDOT STD. 840.66. PLEASE REFER TO SHEET C9.02 FOR LOCATION OF THE RISER 13. UPON COMPLETION OF DAM EMBANKMENT, PROMPTLY STABILIZE AND SEED DAM EMBANKMENT PER SEEDING SCHEDULE. PERMANENT STEPS. NOTE THE STEPS SHALL LINE UP WITH THE ACCESS HATCH OF THE TRASH RACK. GROUND COVER SHALL BE ESTABLISHED PER THE PERMANENT SEEDING SCHEDULE FOUND ON SHEET C9.04. 4. THE CONCRETE ANTI -FLOTATION BLOCK SHALL BE CAST -IN -PLACE. STEEL REINFORCEMENT AND CONNECTION TO THE RISER SHALL BE 14. SCHEDULE A FINAL AS -BUILT INSPECTION AND AS -BUILT SURVEY WITH THE ENGINEER AND SURVEYOR. AN AS -BUILT INSPECTION AND PROVIDED IN ACCORDANCE WITH THE DETAIL ON SHEET C9.03. THE CONTRACTOR SHALL ENSURE THE WEIGHT OF THE ENTIRE RISER SURVEY SHALL BE SCHEDULED BEFORE IMPOUNDING WATER IN THE FACILITY AND A MINIMUM OF 60 DAYS PRIOR TO THE ANTICIPATED STRUCTURE IS GREATER THAN OR EQUAL TO 13,193 LBS. IN LIEU OF CAST -IN -PLACE, THE CONTRACTOR MAY OPT FOR A PRECAST DATE OF CERTIFICATION APPROVAL. ANY COMMENTS OR DEFICIENCIES IN THE SCM CONSTRUCTION MUST BE CORRECTED TO THE ANTI -FLOTATION BLOCK. SHOP DRAWINGS FOR THE PRECAST BLOCK SHALL BE SUBMITTED TO THE ENGINEER FOR REVIEW. THE PRECAST SATISFACTION OF THE ENGINEER AND OWNER BEFORE CERTIFICATION SHALL BE GRANTED. ANTI -FLOTATION BLOCK SHALL HAVE A SHIPPING WEIGHT OF 9,088 LBS. BERM AND SOIL COMPACTION SPECIFICATIONS 5. THE RISER BOX JOINTS SHALL BE SEALED USING BUTYL RUBBER SEALANT CONFORMING TO ASTM -C990- LATEST. IF NECESSARY, THE CONTRACTOR SHALL INCORPORATE A WATERSTOP INTO THE RISER BOX JOINTTO ENSURE A WATERTIGHT CONNECTION. THE 1. PRIOR TO CONSTRUCTION, THE ON -SITE GEOTECHNICAL ENGINEER SHALL IDENTIFY BORROW / FILL AREAS AND VERIFY THEIR SUITABILITY CONTRACTOR SHALL PARGE JOINTS ON BOTH THE INSIDE AND OUTSIDE WITH NON -SHRINK GROUT AND INSTALL GALVANIZED STEEL FOR USE WITHIN THE DAM EMBANKMENT. ALSO, THE ON -SITE GEOTECHNICAL ENGINEER SHALL PERFORM STANDARD PROCTORS ON THE STRAPS PER DETAIL ON SHEET C9.02. PROPOSED BORROW MATERIAL TO ENSURE THAT OPTIMUM MOISTURE CONTENT AND COMPACTION CAN BE ACHIEVED / CONTROLLED DURING CONSTRUCTION. 6. PRIOR TO ORDERING, THE CONTRACTOR SHALL SUBMIT TRASH RACK SHOP DRAWINGS TO THE ENGINEER FOR REVIEW. CONTRACTOR SHALL ENSURE THAT AN ACCESS HATCH IS PROVIDED WITHIN THE TRASH RACK (SEE DETAIL FOR LOCATION) THAT WILL ALLOW FOR 2. ALL FILL MATERIALS TO BE USED FOR THE DAM EMBANKMENT SHALL BE TAKEN FROM BORROW AREAS APPROVED BY THE ON -SITE FUTURE MAINTENANCE ACCESS. CONTRACTOR SHALL ALSO PROVIDE A CHAIN AND LOCK FOR SECURING THE ACCESS HATCH. NOTE THE GEOTECHNICAL ENGINEER. THE FILL MATERIAL SHALL BE FREE FROM ROOTS STUMPS WOOD STONES GREATER THAN 6" AND FROZEN ACCESS HATCH SHALL LINE UP WITH THE ACCESS STEPS AFTER INSTALLATION. OR OTHER OBJECTIONABLE MATERIAL. THE FOLLOWING SOIL TYPES ARE SUITABLE FOR USE AS FILL WITHIN THE DAM EMBANKMENT AND KEY TRENCH: ML AND CL. ALL FILL MATERIALS SHALL BE APPROVED BY THE ONSITE GEOTECHNICAL ENGINEER FOR THE INTENDED USE. 7. ALL POURED CONCRETE SHALL MEET THE FOLLOWING SPECIFICATIONS UNLESS OTHERWISE NOTED: 3. FILL PLACEMENT FOR THE EMBANKMENT SHALL NOT EXCEED A MAXIMUM 8" LIFT (UNCOMPACTED). EACH LIFT SHALL BE CONTINUOUS -MINIMUM 3000 PSI (28 DAY) FOR THE ENTIRE LENGTH OF EMBANKMENT. BEFORE PLACEMENT OF FILL FOR THE BERM SECTION, ALL UNSUITABLE MATERIAL SHALL BE -SLUMP = 3" - 5" REMOVED AND THE SURFACE PROPERLY PREPARED FOR FILL PLACEMENT. FILL MATERIAL ADJACENT TO ALL SPILLWAY AND DRAINAGE STRUCTURES SHALL BE PLACED IN 4-INCH (UNCOMPACTED) LIFTS AND HAND -COMPACTED TO THE SAME COMPACTION AND MOISTURE -ENTRAINED AIR = 5%- 7% REQUIREMENTS AS THE ENTIRE EMBANKMENT. PLEASE NOTE NO CONCRETE SHALL BE POURED WHEN THE AMBIENT AIR TEMPERATURES ARE EXPECTED TO BE ABOVE 85°F OR BELOW 4. ALL FILL SOILS USED IN THE EMBANKMENT CONSTRUCTION SHALL BE COMPACTED TO AT LEAST 95% OF THE STANDARD PROCTOR 40'F. CAST -IN -PLACE CONCRETE SHALL BE "WET CURED" AFTER FINISHING FOR A MINIMUM OF 48 HOURS. MAXIMUM DRY DENSITY (ASTM D-698). THE FILL SOILS SHALL BE COMPACTED AT A MOISTURE CONTENT WITHIN -1 TO +3 PERCENT OF ITS OPTIMUM MOISTURE CONTENT. COMPACTION TESTS SHALL BE PERFORMED BY THE ON -SITE GEOTECHNICAL ENGINEER DURING CONSTRUCTION TO VERIFY THAT THE PROPER COMPACTION LEVEL HAS BEEN REACHED. THE FILL SHOULD BE COMPACTED USING A ON -SITE GEOTECHNICAL ENGINEER TO ENSURE AND CERTIFY ALL POURED CONCRETE MEETS THE ABOVE SPECIFICATIONS. SHEEPSFOOT TYPE COMPACTOR. IN ORDER TO PREVENT DAMAGE TO THE PIPE, NO COMPACTION EQUIPMENT SHALL CROSS ANY PIPE UNTIL MINIMUM COVER IS ESTABLISHED ALONG THE PIPE. 8. GEOTEXTILE FABRIC FOR THE 18" 0 RCP OUTLET BARREL JOINTS SHALL BE MIRAFI 180N OR ENGINEER APPROVED EQUAL (NON -WOVEN FABRIC). 5. THE DESIGN ENGINEER SHALL BE PROVIDED WITH REPORTS AND CERTIFICATION, BY THE ON -SITE GEOTECHNICAL ENGINEER, THAT THE GEOTECHNICAL ASPECTS OF THE FACILITY HAVE BEEN CONSTRUCTED PER PLAN. THIS CERTIFICATION MUST ADDRESS THE TESTING FOR 9. STORMWATER CONTROL MEASURE EMERGENCY DRAW DOWN IS VIA AN 6"0 PLUG VALVE. THE VALVE SHALL BE A M&H STYLE 1820 MATERIALS AND COMPACTION OF THE DAM EMBANKMENT AND SPILLWAY. THESE REPORTS AND CERTIFICATION WILL BE NEEDED DURING ECCENTRIC VALVE OR APPROVED EQUAL. THIS VALVE IS IN ACCORDANCE WITH AWWA C-517, AND SHALL BE OPERABLE FROM TOP OF THE AS -BUILT CERTIFICATION PROCESS FOR THIS STORMWATER CONTROL MEASURE. THEREFORE, IT SHALL BE THE CONTRACTOR'S OUTLET STRUCTURE VIA A HAND WHEEL (SEE DETAIL SHEET C9.03). THE CONTRACTOR SHALL PROVIDE A REMOVABLE VALVE WRENCH RESPONSIBILITY TO COORDINATE TESTING AND OBSERVATION WITH THE ON -SITE GEOTECHNICAL ENGINEER. WITH A HAND WHEEL ON TOP FOR OPERATION OF THE 6" 0I PLUG VALVE. 6. TESTING OF THE NEW FILL MATERIALS SHALL BE PERFORMED TO VERIFY THAT THE RECOMMENDED LEVEL OF COMPACTION IS ACHIEVED DURING CONSTRUCTION. THEREFORE, ONE DENSITY TEST SHALL BE PERFORMED FOR EVERY 2,500 SQUARE FEET OF AREA FOR EVERY LIFT OF FILL OR AS RECOMMENDED BY THE ON -SITE GEOTECHNICAL ENGINEER. 7. TESTING WILL BE REQUIRED ALONG THE 18" 0 RCP OUTLET BARREL AT A FREQUENCY OF ONE TEST PER 25 LF OF PIPE PER VERTICAL FOOT OF FILL OR AS DIRECTED BY THE ON -SITE GEOTECHNICAL ENGINEER. STATEMENT OF RESPONSIBILITY 1. ALL REQUIRED MAINTENANCE AND INSPECTIONS OF THE STORMWATER CONTROL MEASURE SHALL BE THE RESPONSIBILITY OF THE OWNER, PER THE EXECUTED OPERATION AND MAINTENANCE AGREEMENT FOR THIS FACILITY. ou ou ou �- ou ou -emu ou you ou ouo��- ou rU= - °U ou - T_ WARREN AVE 60 PUBLIC sa- ;s \ - ss ss I ss ss ss ss ss �- ss ss ss s ss ss - ss ss ss ss I� I - - C - �= � �- LD 7 / LD - �'- - -�- - w � wow w- -_J_ \oS os \ -� _=01 jW w- w- - w w --- -- ---' -273 -- µ 28 LF 18"0 CLASS III N _ - < 0-RING RCP @ 1.79% / - - \ - T_ (JOINTS WRAPPED VLZ G / IN GEOTEXTILE FABRIC) q LZ - CLASS 'B' RIP RAP - - - - 9L - - - - - - - / \ VELOCITY DISSIPATOR PAD - - - - - - - - - - - - - - - - - I \ \ 9.OLX4.5WX22T - - \ (SEE DETIAL, SHEET C9.03) I I \ \ I \ \\ N II \ \ \\ I ENDWALL PER r I \ / \ \ NCDOT STD. 838.80 N / INV. OUT (18" RCP) = EL. 271.00 / PRECAST RISER OUTLET STRUCTUREN + 274.5 SHAPE = SQUARE I I INTERNAL DIMENSIONS = 4 FT. x 4 FT. TOP OF RISER = 273.25 A I 11 WEIR INVERT EL. = 237.25' I 4.0" PVC PIPE INVERT EL. = 272.00 I I I - _ INVERT OUT 18"� 0 RING RCP 271.50 3 :1 SLOPE .. o I (SEE DETAIL ON SHEET C9.02) (TYP.) O O I 274.5 I I o I I II N I SHALLOW I I WATER III ■ ■ ■ STORMWATER MANAGEMENT FACILITY \� ACCESS EASEMENT \\ MICROPOOL \\ M II I I I \> I I + 3:1 SLOPE 271.5 (TYP. M II I 13 -M ry I 00 - 6 I Q J I I +272.5 I \I I r I N I N Ln I I w is 272.5 I I \ 271.5 I I I - I \ I I \I I TOP OF DAM I I I I I I I I 3:1 SLOPE I I I (TYP.) I I I I I 272.5 I I I I I I I I I II I N I I IZ I I 1 PROPERTY LINE I (TYP) I SHALLOW II I I ELEV. = 268.9 I WATER I I SHALLOW �? I (FOREBAY ENTRANCE) I \ 1 II I I ELEV. = 269.0 1272.5+ / - i i LAND I I I (FOREBAY EXIT) I I I I I II I I I I I I ZON I I+ 1 o O 0 I I 1274.5 i 1 Q J 3:1 I SLOPE I -_ I I \ I 1 N N I I I■ + NI PE I PARALLEL PIPE END SECTION- m \\ \ I \ NI 2.100) TYP.) I 272 5 -CLASS 'B' RIP RAP \ \ I I I C0 I I VELOCITY DISSIPATOR PAD \ \ \ I I I I I + I I \\ \ I N I I I 271.5 I I I■ MICROPOOL CLASS 'B' RIP RAP VELOCITY DISSIPATOR PAD \ I ■ \ \ \ I \ 274.5 Di \ \ \\ r•r•ri■ri■ri■■r.■■ri■■■ ■r•■r.r•ririririririr•■ r■ _ - i STORMWATER MANAGEMENT FACILITY \\ \\\ ss _ ACCESS EASEMENT SS - SS �SS - SS n� y \ I I II I II \ \ I I I I i I I \ I \I \ II I $ I I � \ STORMWATER CONTROL MEASURE'A' PLAN VIEW 1" = 20' T- m cn 01 LIMITS OF DISTUBANCE (TYP) EXISTING TREE (TYP) �J ai a-1 GRAPHIC SCALE 0 10 20 40 1 inch = 20 ft. 'J McADAMS The John R. McAdams Company, Inc. 2905 Meridian Parkway Durham, INC 27713 phone 919. 361. 5000 fax 919. 361. 2269 license number: C-0293 C-187 www.mcadamsco.com CLIENT BODDIE-NOELL ENTERPRISES, INC. P.O. BOX 1908 ROCKY MOUNT, INC 27802 Contact PHONE: 252. 937. 2800 W W W W z Q~ W a te Z � Z 0 Z lil O M W Lu Cz O N `,,,�I111111IIq',, N CA R 0 i SEAL r i 11682 .F^ �.I '1111/11111��,, Ray Watson Apr 8 2022 12:09 PM REVISIONS NO. DATE 1 12. 17. 2021 OWNER COMMENTS 2 1. 20. 2022 NCDEQ RESUBMISSION #1 3 1. 28. 2022 BID SET 4 4. 11.2022 NCDEQ RESUBMISSION #2 5 6 PLAN INFORMATION PROJECT NO FILENAME CHECKED BY DRAWN BY SCALE DATE SHEET 2021110321 2021110321-SW RW KEG 1"=20' 04.11.2022 STORMWATER CONTROL MEASURE 'A' C9601 PRELIMINARY DRAWING - NOT RELEASED FOR CONSTRUCTION NOTES: TRASH RACK (SEE DETAIL, SHEET C9.02) 1. REMOVED TOPSOIL SHALL BE STOCKPILED FOR USE IN PLANTING (SEEDING) THE DAM COMPACTED BERM SECTION EMBANKMENT ONCE FINAL GRADES (AS SHOWN ON THE GRADING PLAN) HAVE BEEN TOP OF HANDWHEEL CONCRETE COLLAR (SEE BERM AND SOIL ESTABLISHED WITH COMPACTED FILL. PRIOR TO TOPSOIL INSTALLATION, THE CONTRACTOR APPROXIMATE LOCATION OF TO EXTEND 1-FOOT (TO BE CONSTRUCTED IN THE FIELD BY THE COMPACTION SPECIFICATIONS, SHALL SCARIFY THE TOP 2- TO 3-INCHES OF THE BERM SECTION TO PROMOTE BONDING EXISTING GROUND ABOVE TRASH RACK CONTRACTOR, SEE DETAIL, SHEET C9.03 ) SHEET C9.01) OF THE TOPSOIL WITH THE COMPACTED FILL. THE TOPSOIL DEPTH SHALL RANGE FROM 3- TO 4-INCHES ON THE DAM EMBANKMENT. 1'L WEIR INVERT TOP OF EMBANKMENT = 274.50 EL. = 237.25' PROPOSED GRADE SPILLWAY FILTER APPROXIMATE LOCATION OF 100-YR STORM W.S.E = 273.97 (SEE DETAIL, EXISTING GROUND 25-YR STORM W.S.E = 273.88 6"0 EMERGENCY DIP DRAIN TOP OF DAM WIDTH = 10' MIN. SHEET C9.03) 10-YR STORM W.S.E = 273.69 WITH TRASH RACK 12" COVER TOP OF EMBANKMENT = 274.50 PROPOSED GRADE 1-YR STORM W.S.E = 273.57 EIA (SEE DETAIL, SHEET C9.03) (MIN.) 3 H MIN :1 V TOP OF RISER = 273.50 -1 - - - - - ------------------------------� Ny _ WEIR INVERT = 273.25 _ 0 0 0 MAN - - - - - _ .1" WATER QUALTY STORM W.S.E. = 272.87 __ ____ _ _____________________ v--------------------- - _ _ _ FLOW 28.00 LF CLASS III 18"0 0-RING RCP (ASTM C76-LATEST) Q 1.79% MICROPOOLI NORMA OOL W. = 2 2.00 ��y MICROPOOL _�p� L a ---- --r-_ _ _ 2NMjN (FOREBAY) (NON-FOREBAY) J��L ° .• °-�- ° o o • o -18 "0 O-RI G RCP INVERT 0 T EL. = 71.50 J - - PROPOSED GRADEEJE1111 EJE1111 �111EEJI �JJEEj �111EEJI 269.00 -1 " THICK JOINT 2.0' MIN FILLER MATERIAL -I -CONCRETE CRADLE - T IN INVERTED TAKE 18' CLASS III 0-RING RCP (SEE DETAIL SHEET C9 03) _ 'J McADAMS The John R. McAdams Company, Inc. 2905 Meridian Parkway Durham, NC 27713 phone 919. 361. 5000 fax 919. 361. 2269 license number: C-0293, C-187 www.mcadamsco.com (SEE DETAIL, SHEET C9.03) I - INV. IN = 271.50 - _ 5.0' MIN BODDIE-NOELL ENTERPRISES, INC. I I I CONTRACTOR SHALL FORM INVERT OF I - -I I I I P.O. BOX 1908 I I I I I 16" PLUG VALVE. THE VALVE (SHALL BE A -RISER STRUCTURE TO DRAIN ROCKY MOUNT, NC 27802 POSITIVELY TO INVERT OF OUTLET ILI _ II III I- III I I I I M&H STYLE 1820 ECCENTRIC VALVE OR_ -BARREL USING NON -SHRINK GROUT Contact APPROVED EQUAL. THIS VALVE SHALL BE - IN ACCORDANCE WITH AWWA C517, AND PHONE: 252. 937. 2800 SHALL BE OPERABLE FROM TOP OF KEY TRENCH (SEE BERM AND SOIL ENDWALL PER OUTLET STRUCTURE VIA A HANDWHEEL. COMPACTION SPECIFICATIONS, NCDOT STD. 838.80 CONCRETE DETAIL ON SHEET C9.01) INV. OUT (18" RCP) = 271.00 ANTI -FLOTATION BLOCK (SEE DETAIL SHEET C9.03) PERMANENT DAM AND SCM CROSS SECTION (SEE DETAIL) A DOUBLE LAYER OF NON -WOVEN CLASS 'B' RIP RAP GEOTEXTILE FABRIC SHALL BE PLACED VELOCITY DISSIPATOR N.T.S. AROUND EACH JOINT OF THE 18"0 0-RING RCP PAD 9.01 X 4.5'W X 22"T BARREL IN 2' WIDE STRIPS CENTERED ON JOINT. (SEE DETAIL, SHEET C9.03) NOTES: 1. ALL REBAR TO BE #4 REBAR. 2. ALL REBAR AND ANGLES TO BE HOT -DIPPED GALVANIZED AND BE PROVIDED WITH AN EPDXY COATING. 8' 3. THE HOT -DIPPED, GALVANIZED 2"x2"x1/4" ANGLE SHALL BE WELDED TO THE REBAR TRASH RACK. ONCE 3j"L x 4"0 GRADE 8 WELDED, THE ENTIRE ASSEMBLY SHALL BE PLACED ONTO THE RISER WITH ANGLES SITTING DIRECTLY ON a STAINLESS STEEL TOP OF RISER. CONCRETE LAG 4. TRASH RACK IS TO BE SECURELY FASTENED TO THE SPILLWAY RISER WITH A MINIMUM OF FOUR ° SCREW 1.5' S' 1.5' CORROSION -RESISTANT ANCHORS. 5. ACCESS HATCH SHALL ALIGN WITH STEPS IN RISER. 0 18" X 4" X 4 GALVANIZED STEEL 1 5' d 1 " THICK CONCRETE CRADLE CORROSION RESISTANT ANCHOR 5.5' o STRAP (4 PER d d JOINT FILLER (SEE DETAIL (TYP., SEE NOTE #4) 5.5' RISER JOINT) (1) 1'L WEIR 4 d d MATERIAL SHEET C9.03) 1(TYP.) INVERT EL. = 273.25 4 1.0' O.C. (TYP.) 4 CORROSION RESISTANT ANCHOR 6"0 DIP DRAIN d (TYP., SEE NOTE #4) a W/ TRASH RACK a d d 4 d a 2.0' (SEE DETAIL 4 ° °I IF SHEET C9.03) ❑ - - - - - ° o d 1.0' RISER JOINT CONNECTION DETAIL $, 5, 18"0 0-RIN `RCP 8" N.T.S. 4 FLOW ACCESS HATCH ACCESS HATCH SHALL (TYP.) ° (TYP.) �] 1.0' O.C. a BE POSITIONED OVER STEPS. ° INVERTED INTAKE O - - - - 7.0' 4.0' (TYP.) D (SEE DETAIL, < E;m° NOTES: SHEET C9.03) • a ❑ ° a° a d I d 1. CONCRETE ANTI -FLOTATION BLOCK TO BE PROVIDED WITH MINIMUM TEMPERATURE AND 44 d d d 6 ° SHRINKAGE STEEL REINFORCEMENT. FT Q 2. TRASH RACKS NOT SHOWN FOR CLARITY. 4 4 ° ° a ° 3. THE NUMBER OF GUIDES FOR THE VALVE STEM SHALL BE DETERMINED IN THE FIELD BY THE d d 4 4 CONTRACTOR. THE VALVE STEM MUST BE OPERABLE FROM THE TOP OF THE RISER VIA THE d d JOINT( FILLER HANDWHEEL WITH AN INSIGNIFICANT AMOUNT OF PLAY IN THE VALVE STEM. 4 4 d d MATERIAL 4. CONTRACTOR SHALL PROVIDE A JOINT IN THE OUTLET BARREL NO MORE THAN 5-FT FROM THE 4 TRASH RACK (ABOVE) RISER. 7.0 LF ANCHOR TRASH RACK TO RISER WALL WITH FOUR PRECASTER SHALL PROVIDE 2"x2'xa 4 ANGLE EQUALLY SPACED STAINLESS STEEL CONCRETE CONTRACTOR SHALL PROVIDE A BLOCK OUT FOR THE 18"0 THE BOLD /DASHED LINETYPE DENOTES THE WEDGE ANCHORS. EACH CLAMP ATTACHED TO RISER BY 2-4"x1/4" CONCRETE ANCHOR BOLTS STEPS IN ACCORDNACE WITH 0-RING RCP ACCESS HATCH TO BE PROVIDED BY THE TRASH NCDOT STD. 840.66. STEPS RACK FABRICATOR PER OUTLET STRUCTURE EACH CLAMP TO BE COATED W/ AN EPDXY SHALL BE PLACED AT 16" O.C. CONCRETE COLLAR MATERIAL SPECIFICATIONS (SHEET C9.F1) COATING. AND SHALL LINE UP WITH TRASH (TO BE CONSTRUCTED IN RACK ACCESS HATCH THE FIELD BY THE CONTRACTOR - SEE DETAIL) 4'X4' RISER 3-SIDED TRASH RACK DETAIL N.T.S. SAW OFF 4"0 PVC (SCH 40) TO ADJUSTED NORMAL POOL FOLLOWING AS -BUILT SURVEY EVALUATION BY DESIGN ENGINEER. DESIGN NORMAL POOL = 272.00 NOTES: (SEE DETAIL ON SHEET C9.03) CONTRACTOR SHALL PROVIDE 1. ALL REBAR TO BE #4 REBAR. 2. WRAP OUTSIDE OF PIPE WITH VOLCLAY WATERSTOP-RX® STEPS IN ACCORDNACE WITH 101 (OR PRE -APPROVED EQUIVALENT) AT THE FACE OF NCDOT STD. 840.66. STEPS THE PRECAST STRUCTURE WALL. PROVIDE 6" OVER LAP W W Z Q 1 W W a W 0 F_ W W cc F_ z Q U Z Z .z � m O M 41* oz O N 1 TOP OF 1-FOOT ABOVE TRAOSEXTEND H RACK ANDLL BE SHALL LINE PLACED AT UP WITH O.C. ON THE BOTTOM OF THE PIPE. ay Watson (1) 11 WEIR TRASH RACK ACCESS HATCH INVERT EL. = 273.25 #4 REBAR ANCHORS. pr 8 2022 12:11 PM TOP OF RISER REAR WALL EL. = 275.50 CONCRETE COLLAR 5' TO BE CONSTRUCTED IN THE 3" ANCHOR DEPTH CONTRACTOR SHALL DRILL INTO ( 3" CLEARANCE TO PRECAST STRUCTURE WALL AND VALVE STEM GUIDE FIELD Y H CONTRACTOR SET ANCHORS USING EPDXY - OUTSIDE OF #4 CONCRETE CONTRACTOR SHALL PROVIDE d SEE DETAIL) REBAR) GROUT ANTI -FLOTATION d 4 (SEE NOTE #3) 4 3" CLEARANCE TO BLOCK d STEPS IN ACCORDNACE WITH OUTSIDE OF #4 REVISIONS 4 NCDOT STD. 840.66. STEPS 2.0' PRECASTER SHALL PROVIDE REBAR - 4 (1) 1'L WEIR ) 4" 5' SHALL BE PLACED AT 16" O.C. 3" CLEARANCE WRAP OUTSIDE OF AND SHALL LINE UP WITH INVERT EL. = 273.25 A BLOCK OUT FOR THE 18"0 a 0-RING RCP TO OUTSIDE OF PIPE WITH FLEXIBLE PRECAST 1' DEPTH (CENTER TO a 1' DEPTH NO. 4' TRASH RACK ACCESS HATCH #4 REBAR) WATERSTOP SEAL (SEE STRUCTURE 3000 PSI CONCRETE CENTER) TOP OF RISER EL. = 273.50 d NOTE 2) WALL COLLAR 1 WEIR INVERT EL. = 273.25 a a 11 #4 REBAR ANCHORS MIN.28 DAY STRENGTH 2 d a / / /18"0 0-RIN� RCP (1 2' 4' 0.5' INVERTED INTAKE (SEE DETAIL C9.03) RISER INVERT EL. = 271.50 4' PVC INVERTED INTAKE INVERT = 1 4 • � 4 4 d 18"0 0-RING RCP FLOW - d �- - -� - - 2.7' ° a ° / \ I 18" 0-RING RCP �_ a __ _ __aa _4 a • • • 3'S INVERT TO ANTIFLOAT CONTRACTOR SHALL DRILL INTO PRECAST STRUCTURE WALL AND SET ANCHORS USING EPDXY GROUT WRAP OUTSIDE OF PIPE WITH FLEXIBLE WATERSTOP SEAL SEE ( NOTE 2) I ° 3" CLEARANCE TO OUTSIDE A 4 # 18" O-RING REBAR) RCP 5' 5.5" CENTER TO CENTER --*_6"INVERT TO ANTIFLOAT 3.7' 4 4 d d ^ d d ^ o^ v ? w U C> v 3" CLEARANCE TO OUTSIDE OF 3 #4 REBAR) 4 5 18" 0-RING 6 RCP DATE 12. 17. 2021 OWNER COMMENTS 1. 20. 2022 NCDEQ RESUBMISSION #1 1. 28. 2022 BID SET 4. 11.2022 NCDEQ RESUBMISSION #2 PLAN INFORMATION 3000 PSI CONCRETE PROJECT NO 12" 4 d I 4 1I0 v 4 a d ANCHOR ° ° ° ° 12" ANCHOR DEPTH o COLLAR (MIN.28 DAY FILENAME 4 Qa 4 Q 4 ♦L 4 � d < 4 DEPTH ° ° ° a Q ° ° 4.6" � (CENTER TO o STRENGTH) CHECKED BY � ° BOTTOM EL. = 270.00 d 1" THICK ° d a d CENTER) a o DRAWN BY CONTRACTOR SHALL FORM INVERT 6" PLUG VALVE. THE VALVE SHALL BE JOINT FILLER CONCRETE nF RICER CTRII(TIIRF Tn r)PAIKI 6"0 DIP DRAIN PIPE CONTRACTOR _ _ _ _ _ A M&H STYLE 1820 ECCENTRIC VALVE AAATFRIAI ° ° ° #4 REBAR ANCHORS. PRECAST nnniToenmo cues i cToi inTi for uiei � SCALE --.._.._._ SHALL CORE -DRILL THE HOLE _ _ anw ivnL vvl D ULLARANI.L ANTI -FLOTATION POSITIVELY TO INVERT OF OUTLET OR ENGINEER -APPROVED EQUAL. THIS 4.6" 3.7' 4.6" DRILL INTO PRECAST TO OUTSIDE M n(1v oeoori I IC' kln ninni C'"O K1v none iT FOR THE 6"0 DIP PIPE IN THE VAI VF �HAI I RF IN ACCC1RhAN(:F WITH 3" CLEARANCE RACP AMn CPT WRAP OUTSIDE OF PIPE .,,. DATE 2021110321 2021110321-SW RW KEG NTS _ __ 04.11.2022 FIELD. PRECASTER SHALL OMIT J (CENTER TO I I �ULNILN 1U I CENTER TO TO OUTSIDE OF 1 WITH FLEXIBLE OF ff4 REBAR) AWWA C-517, AND SHALL BE CONCRETE CRADLE ANCHORS USING EPDXY INVERTED INTAKE REINFORCEMENT IN THIS AREA OPERABLE FROM TOP OF OUTLET (SEE DETAIL CENTER) CENTER) CENTER) #4 REBAR) SIDE VIEW GROUT WATERSTOP SEAL (SEE TOP VIEW SHEET (SEE DETAIL, STRUCTURE VIA A HANDWHEEL. SHEET C9.03) CONCRETE FRONT VIEW CONCRETE NOTE 2) SHEET C9.03 6"0 DIP DRAIN W/ ANTI -FLOTATION BLOCK ANTI -FLOTATION 6"0 DIP DRAIN W/ TRASH RACK ) TRASH RACK CONTRACTOR SHALL SEAL THE PIPE BLOCK 18" 0 CLASS INV. = 271.70 PENETRATION USING A RUBBER BOOT STORMWATER CONTROL LASS III 0-RING RCP INV. = 271.70 INVERT 271III (SEE DETAIL SHEET C9.03) AND STAINLESS STEEL HARDWARE (SEE DETAIL SHEET C9.03) MEASURE DETAIL 18"0 CONCRETE COLLAR DETAIL PERMANENT OUTLET STRUCTURE DETAILS N.T.S. N.T.S. C960 PRELIMINARY DRAWING - NOT RELEASED FOR CONSTRUCTION NOTES: 1. ALL REINFORCING STEEL IN RISER ANTI -FLOTATION BLOCK TO BE GRADE 60 #4 BARS FOR HORIZONTAL CROSSING AND GRADE 60 #4 BARS FOR VERTICAL CONNECTIONS. 2. INSIDE OF RISER BOTTOM TO BE FORMED WITH NON -SHRINK GROUT TO INVERT ELEVATION OF BARREL. 3. ALL PIPE PENETRATIONS THROUGH THE CONCRETE RISER STRUCTURE INSIDE OF RISER TO BE SHALL BE MADE WATERTIGHT. FORMED WITH NON -SHRINK PRECAST GROUT TO INVERT RISER STRUCTURE ELEVATION OF BARREL I 18'0 I 0-RING 4 STEEL \ RCP / EBAR �6� 14 AI__ A' d ^ #4 REBAR VERTICAL d A' ' ° X CONNECTION (TYP.) r B' ° °d < ° e< d < 3000 PSI CONCRETE 1g' 8 0' ANTI FLOTATION BLOCK #4 STEEL REBAR 0 ro BAR CROSS SECTION A' -A' N. T. S. ILA DE -DAD %/CDT1r'AI VKVJJ JtV IIVIV t5 -C N.T.S. RISER/ANTI-FLOTATION BLOCK CONNECTION N.T.S. NOTES: z INSTALL ALL STEPS PROTRUDING 4" FROM INSIDE FACE OF STRUCTURE WALL. STEPS DIFFERING IN DIMENSIONS, CONFIGURATION, OR MATERIALS FROM THOSE SHOWN MAY ALSO BE USED PROVIDED THE CONTRACTOR HAS FURNISHED Q THE ENGINEER WITH DETAILS OF THE PROPOSED STEPS AND HAS RECEIVED WRITTEN APPROVAL FROM THE ENGINEER FOR THE USE OF SUCH STEPS. <Q =OC�U 00�2Z LLJQZLL= 1 QU¢0H Cn HLL O J oU)Q W z r Er rr PLAN SIDE ELEVATION PLAN SIDE ELEVATION _ �\ N oa W , 14/pLL r o" CAST IRON CAST IRON z N ELEVATION ELEVATION 3 W 0 13Cr 16„ H :..± #6 BAR OR Cr 1„ 8g/ 11/4" #8 BAR \ m GALV'D. Z m 1/ „ Q CA 5/8' � U) W \ 0 T Qa POLYPROPYLENE Z 0 PLAN SIDE PLASTIC SIDE Q Q ELEVATION PLAN ELEVATION- Cr CC COMPOSITE Q R77_7_� REINFORCING STEEL 12' F« ELEVATION NOTE: #3 DEFORMED 12" DO NOT USE IN STEEL ROD SANITARY SEWER MANHOLES. SECTION A -A ELEVATION SHEET 1 of 1 840.66 (2) 4" PERFORATED, CORRUGATED HDPE PIPE (DOUBLE -WALL SMOOTH BORE HDPE TYPE "S" OR ENGINE[ APPROVED EQUIVALEN NOTE: 1. HAVILAND DRAINAGE PRODUCTS 4" ALUMINUM ANIMAL GUARD ITEM NUMBER AGSSO4 (OR ENGINEER APPROVED EQUIVALENT) TO BE INSTALLED AT OUTLET OF 4" HDPE PIPES PROPOSED GRADE 6" MIN. 18"0 RCP FLOW- e e < < a < e a e° ° e o 0 4 a °° o c 1' MIN. NO. 67 WASHED STONE ENCASED IN NON -WOVEN FILTER FABRIC (MIRAFI 18ON OR EQUIVALENT) (2) 4" PERFORATED, CORRUGATED HDPE PIPE (DOUBLE -WALL SMOOTH BORE HDPE TYPE "S" OR ENGINEER APPROVED EQUIVALENT) WITH ANIMAL GUARD ENDWALL PER NCDOT STD. 838.80 4" WEEPHOLES TO BI PROVIDED WITH ANIME GUARD ON DOWNSTR[ SIDE AND GALVANIZE[ HARDWARE CLOTH ON UPSTREAM SIDE (Y4" MAXIMUM OPENINGS) ENDWALL PER o r NCDOT STD. 838.80 0 0 o o \ 0 0 0 0 0 0 0 c NO. 67 WASHED (2) 4" PERFORATED, STONE ENCASED CORRUGATED HDPE PIPE IN NON -WOVEN (DOUBLE -WALL SMOOTH BORE FILTER FABRIC HDPE TYPE "S" OR ENGINEER (MIRAFI 180N OR APPROVED EQUIVALENT) WITH EQUIVALENT) ANIMAL GUARD 18" SPILLWAY FILTER DETAIL N.T.S. J R ON #4 REBAR (TYP.) W1 (FT.) 8" O.C.(TYP.) REFER TO CHART FOR BAR SIZE ELEVATION PLAN PERMANENT OUTLET STRUCTURE a d• a d SAW OFF 4"0 PVC (SCH 40) 4"0 PVC (SCH 40) TO ADJUSTED NORMAL POOL FOLLOWING AS -BUILT ° a SURVEY EVALUATION BY DESIGN ENGINEER. DESIGN e NORMAL POOL = 272.00 d ` 3" 44" PVC CAP (MIN.) " ° d WITH SCREW TYPE PLUG 4" PVC CAP `rry v s TOP EL. = 272.33 WITH SCREW CONTROL EL. = 272.00 TYPE PLUG v d d 4" 0 PVC INVERT EL. = 271.50 d ° ° - d a < e �° U) 4" PVC CAP WITH • ° < d °% • d 1 "0 DRILLED CONTRACTOR TO PROVIDE d e ° ORIFICE WATERTIGHT CONNECTION a 1- :1 INVERTED INTAKE e d • g AND RISER ° < . e <d ° e d • , d d < ° ^ ° ed• CONCRETE ANTI -FLOATATION - - BLOCK INVERTED INTAKE DETAIL (RISER N.T.S. z O O Q NOTES: Q D 6" * THIS PRECAST ENDWALL MAY BE USED FOR THE FOLLOWING STANDARDS: 838.01, 838.11, 838.21, 838.27, 838.33, H U LL J 6"H Z O = 838.39, 838.51, 838.57, 838.63 AND 838.69. F MCA * INSTALL PRECAST ENDWALLS WITH WINGS AND PAY LU Q Q LL = FOR IN ACCORDANCE WITH SPECIFICATION SECTION 838. U = O CD1 -0 * USE 4000 PSI CONCRETE. H = ~ Z L * PROVIDE ALL REINFORCING STEEL WHICH MEETS ASTM A615 U LL O J - FOR GRADE 60 AND WELDED WIRE FABRIC CONFORMING =O 0cf) Q Cc O I TO ASTM A185 WITH 2" MIN. CLEARANCE. H2 PLACE LIFT HOLES OR PINS IN ACCORDANCE WITH IL H OSHA STANDARD 1926.704. LU 0 H1 I * PIPE TO BE GROUTED INTO HEADWALL AT JOB SITE BY 0 'JAI- CONTRACTOR ALL ELEMENTS PRECAST TO MEET ASTM C913. 1' 0" WELDED WIRE FABRIC MAY BE SUBSTITUTED FOR REBAR AS LONG AS THE SAME AREA OF STEEL IS PROVIDED. * CHAMFER ALL CORNERS 1" OR HAVE A RADIUS OF 1". 6 8" O.C.(TYP.) REFER TO CHART FOR BAR SIZE w NOTE: THE MINIMUM BAR SIZE SHALL BE #5 BARS J y AT 8" CTS.THE CONTRACTOR WILL HAVE THE OPTION SIDE = 0 J TO INCREASE THIS BAR SIZE AS NEEDED. a o ENDWALL DIMENSIONS FT. MINIMUM MIN./MAX. MIN./MAX. MIN./MAX. MIN./MAX. MIN./MAX. PIPE DIA. BAR SIZE H1(FT.) H2(FT.) D (FT.) W1 W2 1.0 #5 @ 8" 1.25/2.00 2.00/3.75 1.25/1.75 3.00/3.75 5.50/6.00 1.25 #5 @ 8" 1.25/2.00 3.00/3.75 1.25/2.00 3.50/3.75 6.50/6.75 1.50 #5 @ 8" 1.25/2.00 3.00/4.25 1.50/2.50 3.50/3.75 6.50/6.75 2.0 #5 @ 8" 1.50/2.50 4.00/4.75 1.75/2.50 4.00/4.25 7.50/8.25 2.5 #5 @ 8" 2.50/3.50 4.00/6.00 2.00/3.00 4.50/5.50 10.00/11.50 3.0 #5 @ 8" 3.00/3.50 5.00/6.00 2.75/3.50 5.25/5.75 11.50/11.75 3.5 #5 @ 8" 3.25/4.50 6.00/6.75 3.25/3.50 6.00/6.75 12.00/13.25 4.0 #5 @ 8" 3.50/4.50 6.50/7.00 3.25/3.50 6.50/6.75 13.00/13.25 4.5 #5 @ 8" 4.00/5.00 6.50/8.50 3.25/4.00 1 7.00/9.25 13.50/15.75 5.0 #5 @ 8" 4.50/5.00 7.00/8.50 3.25/4.00 1 7.25/9.25 1 13.75/15.75 5.5 #5 @ B" 4.50/5.00 7.50/8.50 3.25/4.00 1 7.25/9.25 1 14.00/15.75 6.0 #5 @ 8" 4.50/5.00 1 7.50/8.50 3.25/4.00 1 7.75/9.25 1 14.75/16.75 NOTES: 1. A FILTER BLANKET IS TO BE INSTALLED BETWEEN THE RIPRAP AND SOIL FOUNDATION. THE FILTER BLANKET WILL CONSIST OF A MINIMUM 4" THICK LAYER OF STONE (NCDOT #57) UNDERLAIN WITH MIRAFI FILTER WEAVE 700 OR ENGINEER -APPROVED EQUIVALENT. 2. RIPRAP TO EXTEND TO TOP OF CHANNEL WITH 2:1 SIDE SLOPES THROUGHOUT THE EXTENT OF CHANNEL. PER ;TD. N 8 18" RCI MINIMUM DIMENSIONS NCDOT CLASS B RIPRAP 9'L X 4.5'W X 22" THICK TO BE LINED WITH GEOTEXTILE FABRIC OR ENGINEER -APPROVED EQUIVALENT 4.5' - - � 3 m H Z 3: W w Q a 0 W a 0 I-- N _ I` 0C-0Cr zz Z O CIO C3 Q ~ w Cn Q Q z o W cr o IL NOTE: 1. CONTRACTOR SHALL PROVIDE A JOINT IN THE OUTLET BARREL NO MORE THAN 5-FT FROM THE RISER. ANTI -FLOTATION BLOCK TOP VIEW #6 REBAR PERIMETER FRAME 4"x4" 8 WELDED WIRE FABRIC 6" MIN. (EACH SIDE & WALL TOP OF CAGE) THICKN 18" TYP. 2.03' 9" TLllrl/ InIAIT CONCRETE ANTI-rL.V I/i IIUIN BLOCK SIDE VIEW RISER BARREL/CRADLE CONNECTION DETAIL N.T.S. 4"x4" WELDED WIRE FABRIC (EACH SIDE & TOP OF CAGE) 0.86' (CENTER TO CENTER) E S CONTRACTOR SHALL SEAL THE PIPE PENETRATION d ° 6" MIN. WALL ° USING A RUBBER BOOT ° d ° THICKNESS AND STAINLESS STEEL HARDWARE 2LF Oo ° 6" 0 DIP d 2.00' ° d 6" PLUG VALVE. THE VALVE SHALL BE A M&H STYLE 18' (TYP.) d ° 1820 ECCENTRIC VALVE OR ° d d ° ° ENGINEER -APPROVED ° 2LF 9 d EQUIVALENT. THIS VALVE d d 6"0 DIP 4" ANCHOR DEPTH ° SHALL BE IN ACCORDANCE CONTRACTOR SHALL d° d a ° WITH AWWA C-517, AND 6 REBAR ° DRILL INTO SHALL BE OPERABLE FROM PERIMETER ° ^ PRECAST EXTENDED 0 86' TOP OF OUTLET STRUCTURE FRAME ( ) SHALL BASE AND SET CENTER TO CENTER VIA A HANDWHEEL. 6" PLUG VALVE. THE VALVE ANCHORS USING LL BEAM &H STYLE 1820 EPDXY GROUT CONTRACTOR SHALL SEAL THE ECCENTRIC VALVE OR PIPE PENETRATION USING A ENGINEER -APPROVED RUBBER BOOT AND STAINLESS EQUIVALENT. THIS VALVE SHALL STEEL HARDWARE BE IN ACCORDANCE WITH AWWA C-517, AND SHALL BE OPERABLE FROM TOP OF OUTLET STRUCTURE VIA A HANDWHEEL. 6"0 EMERGENCY DIP DRAIN TRASH RACK DETAILS NOTE: 1. AS AN ALTERNATE TO A CONCRETE CRADLE UNDER THE BARREL PIPE (THIS DETAIL), THE CONTRACTOR MAY CHOOSE TO ELIMINATE THE CONCRETE CRADLE AND USE COMPACTED BACKFILL IF THE ON -SITE GEOTECHNICAL ENGINEER WILL PROVIDE A NC PE SEALED LETTER CERTIFYING THAT THE COMPACTION UNDER, AROUND, AND ABOVE THE BARREL MEETS THE SPECIFICATIONS OF THE EMBANKMENT COMPACTION REQUIREMENTS AND MOISTURE CONTENT. THIS CERTIFICATION LETTER MUST BE SUBMITTED TO THE DESIGN ENGINEER BEFORE AS -BUILT CERTIFICATION OF THE FACILITY. THIS SEPARATE CERTIFICATION MUST BE SPECIFIC TO THE BARREL PIPE FOR THE FACILITY, AND MUST CLEARLY STATE THAT ALL SOIL MATERIAL UNDER, AROUND, AND ABOVE THE BARREL PIPE MEETS THE BERM MATERIAL SPECIFICATIONS. THIS CERTIFICATION IS TO INCLUDE REFERENCE TO BOTH MATERIAL AND COMPACTION, AND MUST STATE THAT ALL MATERIALS UNDER, AROUND, AND ABOVE THE BARREL HAVE BEEN COMPACTED PER THE BERM MATERIAL SPECIFICATIONS (AT LEAST 95% OF MAXIMUM DRY DENSITY USING ASTM D698 STANDARD PROCTOR) WITH NO VOID SPACES PRESENT. THE CONTRACTORS INTENT TO UTILIZE THIS ALTERNATIVE MUST BE STATED PRIOR TO CONSTRUCTION TAKING PLACE. THIS CONTRACTORS CERTIFICATION MUST BE PRESENTED TO THE DESIGN ENGINEER BEFORE AN AS -BUILT CERTIFICATION CAN BE ISSUED FOR THIS FACILITY. 2. CONTRACTOR SHALL PROVIDE A JOINT IN THE OUTLET BARREL NO MORE THAN 5-FT FROM THE RISER. BARREL PIPE CONCRETE CRADLE CONSTRUCTION SEQUENCE 1. IF OPTION A IS CHOSEN FROM NOTE 9 OF THE OUTLET STRUCTURE MATERIAL SPECIFICATIONS, THEN BRING GRADE OF DAM EMBANKMENT TO SPRINGLINE OF PIPE ELEVATION. IF OPTION B IS CHOSEN FROM NOTE 9 OF THE OUTLET STRUCTURE MATERIAL SPECIFICATIONS, THEN CONSTRUCT FORMWORK FOR CONCRETE CRADLE ON EXISTING GRADE. 2. IF OPTION A IS CHOSEN FROM NOTE 9 OF THE OUTLET STRUCTURE MATERIAL SPECIFICATIONS, THEN EXCAVATE TRENCH FOR CRADLE AND BARREL PER DIMENSIONS ON DRAWINGS. IF OPTION B IS 18"0 0-RING RCP CHOSEN FROM NOTE 9 OF THE OUTLET STRUCTURE MATERIAL SPECIFICATIONS, PROCEED TO STEP 3 BELOW. ENDWALL PER NCDOT STD. 838.80 3 PLACE BARREL PIPE ON CONCRETE BLOCKS TO GRADE AT THIS STEP CONTRACTOR SHALL WRAP A - o I_I ,III1 I I TIN � FILTER BLANKET (SEE NOTE) 91 �- PLAN PROFILE VIEW OUTLET BARREL VELOCITY DISSIPATER N.T.S. N.T.S. DOUBLE LAYER OF NON -WOVEN GEOTEXTILE FABRIC AROUND EACH JOINT OF THE 18"0 0-RING RCP BARREL IN 2' WIDE STRIPS CENTERED ON JOINT. 4. PLACE CONCRETE FOR CRADLE FOR EACH SECTION FROM ONE SIDE OF THE TRENCH. ALLOW CONCRETE TO FILL ENTIRE AREA UNDER PIPE AND PIPE HAUNCHES AS TO LEAVE NO VOIDS UNDER THE PIPE BEFORE PLACING CONCRETE ON THE OPPOSITE SIDE OF THE TRENCH. PLACE ENTIRE CRADLE AS ONE LIFT (VERTICALLY) PER DRAWINGS. 5. CONCRETE CRADLE MAY BE ELIMINATED PER RECOMMENDATION FROM THE ON -SITE GEOTECHNICAL ENGINEER. ANY DEVIATION FROM THIS DETAIL SHALL BE SUBMITTED TO AND REVIEWED BY THE DESIGN ENGINEER PRIOR TO IMPLEMENTATION. IF THE CRADLE IS ELIMINATED, THEN A LETTER FROM AN NC PE CERTIFYING THAT ALL SOIL MATERIAL UNDER, AROUND, AND ABOVE THE BARREL PIPE MEETS THE 22" LAYER BERM MATERIAL SPECIFICATIONS IS REQUIRED. CLASS �OF B RIPRAP 6. ALLOW CRADLE TO CURE FOR A MINIMUM OF 7 DAYS BEFORE ANY VIBRATING COMPACTION 4" FILTER BLANKET EQUIPMENT IS USED IN THE VICINITY OF THE BARREL PIPE. 7. TRENCH TO BE BACKFILLED IN 5" LIFTS WHEN COMPACTION IS BY HAND. BACKFILL IS IN 8" LIFTS WHEN CONDUCTED BY MACHINE. MINIMUM OF 2 FEET COVER MUST BE PRESENT ON 18"0 RCP BEFORE DRIVING OVER WITH HEAVY EQUIPMENT. \ (MIN.) I 18"0 0-RING RCP ' 1 1.5" • '. •. d, 12" MIN . a ; •'e. ; t e 777 3000 PSI CONCRETE, OR PER RECOMMENDATION FROM ON -SITE GEOTECHNICAL ENGINEER 18" CONCRETE CRADLE DETAIL N.T.S. 'J McADAMS The John R. McAdams Company, Inc. 2905 Meridian Parkway Durham, INC 27713 phone 919. 361. 5000 fax 919. 361. 2269 license number: C-0293, C-187 www.mcadamsco.com BODDIE-NOELL ENTERPRISES, INC. P.O. BOX 1908 ROCKY MOUNT, INC 27802 Contact PHONE: 252. 937. 2800 W W W W z Q~ate W Z � Q • 7Z M W O m M W Uj Cz O N 0,0111111111,41 '•1z SEAL I SON'.' Ray Watson Apr 8 2022 12:11 PM REVISIONS NO. DATE 1 12. 17. 2021 OWNER COMMENTS 2 1. 20. 2022 NCDEQ RESUBMISSION #1 3 1. 28. 2022 BID SET 4 4. 11.2022 NCDEQ RESUBMISSION #2 5 6 PLAN INFORMATION PROJECT NO. 2021110321 FILENAME 2021110321-SW CHECKED BY RW DRAWN BY KEG SCALE NITS DATE 04.11.2022 SHEET STORMWATER CONTROL MEASURE DETAILS C9603 PRELIMINARY DRAWING - NOT RELEASED FOR CONSTRUCTION STORMWATER CONTROL MEASURE 'A' PIANIING PLAN SPECIFICATIONS LEGEND QTY. SYM. SCIENTIFIC NAME COMMON NAME HATCH TYPE SPACING % OF TOTAL AREA PROVIDED AREA I LOW MARSH (SHALLOW WATER, TOTAL AREA = 2,507 SF) 183 JE JUNCUS EFFUSUS COMMON RUSH 4—INCH CONTAINER 24" O.C. PROVIDED PERCENTAGE = 29% 731 SF 152 PP PONTEDERIA PECTINATUS PICKEREL WEED 4—INCH CONTAINER 24" O.C. PROVIDED PERCENTAGE = 24% 608 SF 292 ZM ZIZANIOPSIS MILIACEA GIANT CUTGRASS 4—INCH CONTAINER 24" O.C. PROVIDED PERCENTAGE = 47% 1,168 SF HIGH MARSH (SHALLOW LAND, TOTAL AREA = 2,311 SF) 177 VH VERBENA HASTATA SWAMP VERBENA 4—INCH CONTAINER 24" O.C. PROVIDED PERCENTAGE = 30% 705 SF 213 HA HELENIUM AUTUMNALE SNEEZEWEED ° ° ° 4—INCH CONTAINER 24" O.C. PROVIDED PERCENTAGE = 37% 850 SF 189 CG CHELONE GLABRA WHITE TURTLEHEAD 4—INCH CONTAINER 24" O.C. PROVIDED PERCENTAGE = 33% 756 SF SEEDBED PREPARATION 1. CHISEL COMPACTED AREAS AND SPREAD TOPSOIL 3 INCHES DEEP OVER ADVERSE SOIL CONDITIONS, IF AVAILABLE. 2. RIP THE ENTIRE AREA TO 6 INCHES DEPTH. 3. REMOVE ALL LOOSE ROCK, ROOTS, AND OTHER OBSTRUCTIONS LEAVING SURFACE REASONABLY SMOOTH AND UNIFORM. 4. PER ONE TIME ONLY, APPLY AGRICULTURAL LIME, FERTILIZER, AND SUPERPHOSPHATE UNIFORMLY AND MIX WITH SOIL. 5. CONTINUE TILLAGE UNTIL A WELL —PULVERIZED, FIRM REASONABLY UNIFORM SEEDBED IS PREPARED 4 TO 6 INCHES DEEP. 6. SEED ON A FRESHLY PREPARED SEEDBED AND COVER. 7. MULCH IMMEDIATELY AFTER SEEDING AND ANCHOR MULCH. 8. INSPECT ALL SEEDED AREAS AND MAKE NECESSARY REPAIRS OR RESEEDINGS WITHIN THE PLANTING SEASON, IF POSSIBLE. AFTER PERMANENT COVER IS ESTABLISHED. 9. CONSULT CONSERVATION INSPECTOR ON MAINTENANCE TREATMENT TEMPORARY SEEDING SCHEDULE SEEDING DATE JAN 1 — MAY 1 MAY 1 — AUG 15 AUG 15 — DEC 30 SEEDING MIXTURE RYE (GRAIN) KOBE LESPEDEZA GERMAN MILLET RYE (GRAIN) APPLICATION RATE 120 LBS/AC 50 LBS/AC 40 LBS/AC 120 LBS/AC SOIL AMENDMENTS FOLLOW RECOMMENDATIONS OF SOIL TESTS OR APPLY 2,000 LB/AC GROUND AGRICULTURE LIMESTONE AND 750 LB/AC 10-10-10 FERTILIZER (FROM AUG 15 — DEC 30, INCREASE 10-10-10 FERTILIZER TO 1000 LB/AC) MULCH APPLY 4000 LB/AC STRAW. ANCHOR STRAW BY TACKING WITH ASPHALT, NETTING, OR A MULCH ANCHORING TOOL. A DISK WITH BLADES SET NEARLY STRAIGHT CAN BE USED AS A MULCH ANCHORING TOOL. MAINTENANCE JAN 1 — AUG 15: REFERTILIZE IF GROWTH IS NOT FULLY ADEQUATE. RESEED, REFERTILIZE, AND MULCH IMMEDIATELY FOLLOWING EROSION OR OTHER DAMAGE. AUG 15 — DEC 30: REPAIR AND REFERTILIZE DAMAGED AREAS IMMEDIATELY. TOP DRESS WITH 50 LB/AC OF NITROGEN IN MARCH. IF IT IS NECESSARY TO EXTEND TEMPORARY COVER BEYOND JUNE 15, OVERSEED WITH 50 LB/AC KOBE LESPEDEZA IN LATE FEBRUARY OR EARLY MARCH. NOTE: USE THE TEMPORARY SEEDING SCHEDULE ONLY WHEN DATE IS NOT CORRECT TO USE THE PERMANENT SEEDING SCHEDULE. PERMANENT SEEDING SCHEDULE (DAM EMBANKMENTS) SEEDING DATE SEEDING MIXTURE APPLICATION RATE AUG 25 — OCT (BEST) TALL FESCUE 200 LBS/AC FEB — APR 15 (POSSIBLE) SOIL AMENDMENTS FOLLOW RECOMMENDATIONS OF SOIL TESTS OR APPLY 4,000 LB/AC GROUND AGRICULTURE LIMESTONE AND 1000 LB/AC 10-10-10 FERTILIZER. MULCH APPLY 4000 LB/AC STRAW. ANCHOR STRAW BY TACKING WITH ASPHALT, NETTING, OR A MULCH ANCHORING TOOL. A DISK WITH BLADES SET NEARLY STRAIGHT CAN BE USED AS A MULCH ANCHORING TOOL. MAINTENANCE INSPECT AND REPAIR MULCH FREQUENTLY. REFERTILIZE IN LATE WINTER OF THE FOLLOWING YEAR; USE SOIL TESTS OR APPLY 150 LB/AC 10-10-10 FERTILIZER. MOW REGULARLY TO A HEIGHT OF 2-4 INCHES. NOTE: PERMANENT SEEDING SCHEDULE IS FOR SLOPES OF THE BASIN, TOP OF BERM, AND BASIN FLOOR. PLANTING INSTRUCTIONS PLANTING TECHNIQUES A. INSURE THAT ROOTS, ONCE REMOVED FROM POT, ARE STRAIGHTENED AND FACE DOWNWARD. B. CREATE PLANTING AREA FOR EACH PLANT AND EXCAVATE PIT. C. PLACE PLANTS IN PIT INSURING ROOTS ARE FACING COMPLETELY DOWNWARD. D. HEEL IN SOIL AROUND PLANT AND PROCEED TO NEXT PLANTING LOCATION. E. NEWLY PLANTED PLANTS NEED TO BE FASTENED TO THE SUBSTRATE FOR THE ESTABLISHMENT OF NEW ROOTS. F. ROOTS SHALL BE SPREAD IN THEIR NORMAL POSITION. ALL BROKEN OR FRAYED ROOTS HALL BE CUT OFF CLEANLY. G. THE DIAMETER OF THE PITS FOR ALL VEGETATIVE STOCK SHALL BE AT LEAST THREE TIMES THE DIAMETER OF THE ROOT MASS. PLANT PIT WALL SHALL BE SCARIFIED PRIOR TO PLANT INSTALLATION. H. SET THE PLANTS UPRIGHT, IN THE CENTER OF THE PIT. THE BOTTOM OF THE ROOT MASS SHOULD BE RESTING ON UNDISTURBED SOIL. I. PLACE THE BACKFILL AROUND THE BASE AND SIDES OF THE ROOT MASS, AND WORK EACH LAYER TO SETTLE BACKFILL AND TO ELIMINATE VOIDS AND AIR POCKETS. WHEN PIT IS APPROXIMATELY 2/3 FULL, WATER THOROUGHLY BEFORE PLACING REMAINDER OF THE BACKFILL. WATER AGAIN AFTER PLACING FINAL LAYER OF BACKFILL. J. BROKEN OR DAMAGED PARTS WILL BE CUT BACK TO UNDAMAGED TISSUE, LEAVING AS MUCH GREEN BASAL TISSUE AS POSSIBLE ABOVE THE ROOTS. IF MORE THAN FIFTY PERCENT (50%) OF THE PLANT IS DAMAGED THEN CONTRACTOR SHALL REPLACE THE PLANT. CONTAINER STOCK / BARE ROOT A. STOCK SHALL HAVE BEEN GROWN IN A CONTAINER LONG ENOUGH FOR THE ROOT SYSTEM TO HAVE DEVELOPED SUFFICIENTLY TO HOLD ITS SOIL TOGETHER ONCE REMOVED FROM THE CONTAINER. B. CONTAINER PLANTS WILL NEED TO BE WATERED REGULARLY AND PLACED IN SHADY CONDITIONS UNTIL PLANTING OCCURS. C. BARE ROOT PLANTS ARE FOR IMMEDIATE PLANTING, OTHERWISE SEE D) BELOW. D. IF BARE ROOTS SPECIMENS ARE NOT TO BE PLANTED WITHIN FOUR (4) DAYS, TEMPORARY HOLDING OF BARE ROOT SPECIMENS ARE TO BE COVERED ENTIRELY BY A SUITABLE MEDIUM (ETC. SOIL, SAWDUST, MULCH OR THE LIKE) AND WATERED REGULARLY SO AS TO NOT DRY OUT. PLANT LOCATIONS A. NEW PLANTINGS SHALL BE LOCATED WHERE SHOWN ON PLAN EXCEPT WHERE CHANGES HAVE BEEN MADE IN PROPOSED CONSTRUCTION. B. NECESSARY ADJUSTMENTS SHALL BE MADE ONLY AFTER APPROVAL BY THE OWNER OR THE OWNER'S REPRESENTATIVE. WATER WATER SHALL BE POTABLE AND SHALL NOT CONTAIN ELEMENTS TOXIC TO PLANT LIFE. ou ou3=� ou ou ou ou °U I �%o—emu ou you ou ou— ou W— --- I I�------- —_-- — --_ --- ---- -/�--- WARREN AVE - 60 PUBLIC \ — ss ss 'I ss ss ss sQ- SS SS �— SS Ss Ss S SS Ss — SS SS ss � ss SS I LD LD LD LD / LD - -- — W W — w— W W — °S °s w ( —Q�W L-- —W 1 W W —274 -- 0% \ I9L_---- -- \ � I o - I I \ \ \ \ 274.5 \ / — — — . II .Mons... ■MMMMI / II \\ I I I '274.5 I I MICROPOOL T I I I Yy I SHALLOW 14 I I WATER _ \ f 00 oI IIIIII u I \ I I Jz I I \ J II i -n N J'D E D EI ` I I N D °°° ❑ ❑ I I rLA 90 I M° `HEl El I I I tit I ° ❑ ❑ ❑ I I I I v Cn ° ° I I ❑❑❑ I I I I I ° I I ° ❑ ❑❑ ° II \ I 1 IFF II ° ° ° I I 11 El El I I it \ I ° 1 I in I ❑❑❑ 11 °° II 2j9 PROPERTY LINE 1 ° ❑ ❑ ❑ ° I I (TYP) / I II 1 I I oo JJ II I \ 1 I \ I + 274.5 I J Q I \ I \ I I =J I. I■ \ \ \ II I I a I \ � \ I I N I I I• \ I I \ + Oi 274.5 SHALLOW LAND 0� tm 0-1 cn MICROPOOL I I ACCESS EASEMENT (TYP) \ \ ss ssSS— _S I � / I I II \ I I \ I N I \ I \I E0 \ N s EXISTING TREE (TYP) \ ss ss ss — r— \ I � \ 1 I \ I \ I \ I \ I I I I I II I J STORMWATER CONTROL MEASURE 'A' PLANTING PLAN 1" = 20' 'J McADAMS The John R. McAdams Company, Inc. 2905 Meridian Parkway Durham, INC 27713 phone 919. 361. 5000 fax 919. 361. 2269 license number: C-0293, C-187 www.mcadamsco.com BODDIE-NOELL ENTERPRISES, INC. P.O. BOX 1908 ROCKY MOUNT, NC 27802 Contact PHONE: 252. 937. 2800 W W W W cc isEn � z Q~< W U �Z Z p . � z M CalO m � M W Lu Ito 0 O N 0-1 0-1 CARO m m m 01 �`� p SS LIMITS OF _ SEAL 1 BF32 DISTUBANCE (TYP) Ae:Fi ay Watson pr 8 2022 12:12 PM � J REVISIONS NO. DATE 1 12. 17. 2021 OWNER COMMENTS \ \ 2 1. 20. 2022 NCDEQ RESUBMISSION #1 3 1. 28. 2022 BID SET \ I 4 4. 11.2022 NCDEQ RESUBMISSION #2 \ i 5 6 \ I PLAN INFORMATION \i I PROJECT NO. 2021110321 FILENAME 2021110321-SW CHECKED BY RW DRAWN BY KEG SCALE 1"=20' DATE 04.11.2022 SHEET GRAPHIC SCALE STORMWATER CONTROL 10 20 40 MEASURE 'A' PLANTING PLAN 1 inch = 20 ft. C960 PRELIMINARY DRAWING - NOT RELEASED FOR CONSTRUCTION