HomeMy WebLinkAbout20190206 Ver 2_Permit Transfer_20220308Strickland, Bev
From: Perry, John M
Sent: Tuesday, March 8, 2022 8:04 AM
To: Ginger Turner; Charles, Thomas P CIV USARMY CESAW (USA)
Cc: THall@windsorhomes.us; Doug Brady
Subject: RE: [External] RE: Permit transfer SAW-2002-01322
Attachments: 20190206v2_Calico Subdivision_IC_CartCo_Mar.22.docx.pdf
Good Morning Ginger,
I have attached the Individual 401 Water Quality Certification for the new owner. This will replace the Written Approval
with Additional Conditions that was issued to the previous owner in 2019. The conditions will be the same, however our
format changed slightly with the rollout of our new rules. Please do not hesitate to reach out with any questions.
Thanks,
John Perry
Environmental Specialist II
Divison of Water Resources
Department of Environmental Quality
127 Cardinal Drive Extension
Wilmington, NC 28405
Office: (910) 796-7341
Cell: (910) 617-9577
From: Ginger Turner [mailto:ginger@tcgpa.com]
Sent: Monday, February 28, 2022 12:10 PM
To: Charles, Thomas P CIV USARMY CESAW (USA) <thomas.p.charles@usace.army.mil>
Cc: Perry, John M <John.Perry@ncdenr.gov>; THall@windsorhomes.us; Doug Brady <dbradydev@gmail.com>
Subject: [External] RE: Permit transfer SAW-2002-01322
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Tom,
Thank you. For clarification, your email below extends the project one additional year from date of signature. Does this
imply the permit will expire 2/25/2023?
1
Li
From: Charles, Thomas P CIV USARMY CESAW (USA) <thomas.p.charles@usace.army.mil>
Sent: Monday, February 28, 2022 10:17 AM
To: THall@windsorhomes.us; Doug Brady <dbradydev@gmail.com>
Cc: Ginger Turner <ginger@tcgpa.com>; Perry, John M <John.Perry@ncdenr.gov>
Subject: Permit transfer SAW-2002-01322
Good morning,
The Corps has completed your permit transfer for action ID# SAW-2002-01322. Your year extension is from the date the
permit was signed and you must stay in compliance with the permit.
Regards, Tom
Thomas Charles (Tom)
thomas.p.charles@usace.army.mil
Regulatory Specialist
910-251-4101 cell 910-465-7602
https://www.saw.usace.army.mil/Missions/Regulatory-Permit-Program/Permits/2017-Nationwide-Permits/
E-PCN-Submittal
https://edocs.deq.nc.gov/Forms/Pre-Construction Notification Form
PJDs' &JD's. http://saw-reg.usace.army.mil/JD/FINALSAW-JD-REQUEST-FORM-20170508.pdf
Submittal You may submit requests via e-mail in PDF format to
WilmingtonNCREG@usace.army.mil
The Wilmington District is committed to providing the highest level of support to the public.
2
To help us ensure we continue to do so, please complete the Customer Satisfaction Survey located at:
https://regulatory.ops.usace.army.mil/customer-service-survey/
DocuSign Envelope ID: BE1D409B-9035-496C-88D5-C4F33CE5583A
ROY COOPER
Governor
ELIZABETH S. BISER
Secretary
S. DANIEL SMITH
Director
NORTH CAROLINA
Environmental Quality
March 07, 2022
DWR # 20190206v2
Carteret County
Calico Area Developers, LLC
Attn: Thomas C. Hall
5603 New Garden Village Drive
Greensboro, NC 27410
Subject: Approval of Individual 401 Water Quality Certification
Calico Subdivision
USACE Action ID. No. SAW-2002-01322
Dear Mr. Hall:
Attached hereto is a copy of Certification No. WQC004681 issued to Thomas C. Hall and Calico Area
Developers, LLC, dated March 07, 2022. This Certification replaces the Certification issued on April 11,
2019. This approval is for the purpose and design described in your application. The plans and
specifications for this project are incorporated by reference as part of this Water Quality Certification. If
you change your project, you must notify the Division and you may be required to submit a new
application package with the appropriate fee. If the property is sold, the new owner must be given a copy
of this Certification and is responsible for complying with all conditions. [15A NCAC 02H .0507(d)(2)].
This Water Quality Certification does not relieve the permittee of the responsibility to obtain all other
required Federal, State, or Local approvals before proceeding with the project, including those required
by, but not limited to, Sediment and Erosion Control, Non -Discharge, Water Supply Watershed, and
Trout Buffer regulations.
This Water Quality Certification neither grants nor affirms any property right, license, or privilege in any
lands or waters, or any right of use in any waters. This Water Quality Certification does not authorize
any person to interfere with the riparian rights, littoral rights, or water use rights of any other person
and does not create any prescriptive right or any right of priority regarding any usage of water. This
Water Quality Certification shall not be interposed as a defense in any action respecting the
determination of riparian or littoral rights or other rights to water use. No consumptive user is deemed
by virtue of this Water Quality Certification to possess any prescriptive or other right of priority with
respect to any other consumptive user.
Upon the presentation of proper credentials, the Division may inspect the property.
North Carolina Department of Environmental Quality I Division of Water Resources
Wilmington Regional Office ! 127 Cardinal Drive Extension I Wilmington, North Carolina 28405
YORTH CFRCILINA �
o,y„9n,ne os �.����m auand 910.796.7215
DocuSign Envelope ID: BE1D409B-9035-496C-88D5-C4F33CE5583A
Calico Area Developers, LLC
DWR project #20190206v2
WQC004681
Page 2 of 10
This Water Quality Certification shall expire on the same day as the expiration date of the corresponding
Section 404 Permit. The conditions shall remain in effect for the life of the project, regardless of the
expiration date of this Water Quality Certification.
Non-compliance with or violation of the conditions herein set forth may result in revocation of this
Water Quality Certification for the project and may also result in criminal and/or civil penalties.
If you are unable to comply with any of the conditions of this Water Quality Certification you must notify
the Wilmington Regional Office within 24 hours (or the next business day if a weekend or holiday) from
the time the permittee becomes aware of the circumstances.
The permittee shall report to the Wilmington Regional Office any noncompliance with, and/or any
violation of, stream or wetland standards [15A NCAC 02B .0200] including but not limited to sediment
impacts to streams or wetlands. Information shall be provided orally within 24 hours (or the next
business day if a weekend or holiday) from the time the permittee became aware of the non-compliance
circumstances.
This approval and its conditions are final and binding unless contested [G.S. 143-215.5].
This Certification can be contested as provided in Chapter 150B of the North Carolina General Statutes by
filing a Petition for a Contested Case Hearing (Petition) with the North Carolina Office of Administrative
Hearings (OAH) within sixty (60) calendar days. Requirements for filing a Petition are set forth in Chapter
150B of the North Carolina General Statutes and Title 26 of the North Carolina Administrative Code.
Additional information regarding requirements for filing a Petition and Petition forms may be accessed at
http://www.ncoah.com/ or by calling the OAH Clerk's Office at (919) 431-3000.
A party filing a Petition must serve a copy of the Petition on:
William F. Lane, General Counsel
Department of Environmental Quality
1601 Mail Service Center
Raleigh, NC 27699-1601
If the party filing the Petition is not the permittee, then the party must also serve the recipient of the
Certification in accordance with N.C.G.S 15013-23(a).
This letter completes the Division's review under section 401 of the Clean Water Act and 15A NCAC 02H
.0500. Please contact John Perry at (910) 796-7341 or lohn.perry@ncdenr.ov if you have any questions
or concerns.
Sincerely,
DocuS, ned by:
10.K �natrl�On,
o ri�'1Fr'ai ro n
Assistant Regional Supervisor
Water Quality Regional Operations Section
DocuSign Envelope ID: BE1D409B-9035-496C-88D5-C4F33CE5583A
Calico Area Developers, LLC
DWR project #20190206v2
WQC004681
Page 3 of 10
Electronic cc: Ginger Turner, Consultant
USACE Wilmington Regulatory Field Office
Todd Bowers, EPA
DWR 401 & Buffer Permitting Branch Electronic file
Calico Area Developers, LLC
DocuSign Envelope ID: BE1D409B-9035-496C-88D5-C4F33CE5583A DWR project #20190206v2
WQC004681
Page 4 of 10
NORTH CAROLINA 401 WATER QUALITY CERTIFICATION
CERTIFICATION #WQC004681 is issued in conformity with the requirements of Section 401, Public Laws
92-500 and 95-217 of the United States and subject to North Carolina's Regulations in 15 NCAC 02H .0500
and 15A NCAC 0213.0200, to Thomas C. Hall and Calico Area Developers, LLC, who have authorization for
the impacts listed below, as described within your permit transfer request received by the N.C. Division of
Water Resources (Division) on February 25, 2022.
The State of North Carolina certifies that this activity will comply with water quality requirements and
the applicable portions of Sections 301, 302, 303, 306, 307 of the Public Laws 92-500 and PL 95-217 if
conducted in accordance with the application, the supporting documentation, and conditions
hereinafter set forth.
The following impacts are hereby approved. No other impacts are approved, including incidental
impacts. [15A NCAC 02H .0506(b)]
Type of Impact
Amount Approved (units)
Permanent
Amount Approved (units)
Temporary
404/401 Wetlands
Site 6 and 8
0.081 acres
N/A
Open Waters
Site 1-7
0.22 acres
N/A
This approval requires you to follow the conditions listed in the certification below.
CONDITIONS OF CERTIFICATION [15A NCAC 02H .0507(c)]:
1. If this Water Quality Certification is used to access residential, commercial or industrial
building sites, then all parcels owned by the permittee that are part of the single and
complete project authorized by this Certification must be buildable without additional
impacts to streams or wetlands.
Citation: 15A NCAC 02H .0502(a);15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
2. Turbidity Standard
The turbidity standard of 25 NTUs (Nephelometric Turbidity Units) shall not be exceeded
as described in 15 A NCAC 2B .0220. Appropriate sediment and erosion control practices
must be used to meet this standard. Turbidity curtains shall be used as appropriate.
Please notify this Office if any turbidity issues arise at 910.796.7215
Citation: 15A NCAC 02B .0211 (21)
All wetlands, streams, surface waters, and riparian buffers located within 50 feet of the
construction area on the project site shall be clearly marked (example- orange fabric
fencing) prior to any land disturbing activities and must be maintained on the property
until the project phase is completed.
Calico Area Developers, LLC
DocuSign Envelope ID: BE1D409B-9035-496C-88D5-C4F33CE5583A DWR project #20190206v2
WQC004681
Page 5 of 10
Citation: 15A NCAC 02H .0506 (b)(2) and (c)(2) and 15A NCAC 02H .0507 (c)
4. For road construction purposes, this Certification shall only be utilized from natural high
ground to natural high ground.
Citation: 15A NCAC 02H .0502(a);15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
5. Deed notifications or similar mechanisms shall be placed on all lots/parcels with retained
jurisdictional wetlands, waters, and state regulated riparian buffers within the project
boundaries in order to assure compliance with NC Water Quality Certification Rules (15A NCAC
02H .0500), NC Isolated Wetland Rules (15A NCAC 02H .1300), and/or State Regulated Riparian
Buffer Rules (15A NCAC 02B .0200). These mechanisms shall be put in place at the time of
recording of the property or individual parcels, whichever is appropriate.
Citation: 15A NCAC 02H .0502(a);15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
6. If this Water Quality Certification is used for utility related impacts, then the following Activity
Specific Conditions shall apply to those impacts.
a. All sewer lines shall be designed, constructed and maintained in accordance with Title 15A
NCAC Chapter 02T, applicable Minimum Design Criteria (MDC), and/or Alternative Design
Criteria.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
b. Any utility construction corridor that is parallel to a stream or open water shall not be
closer than 10 feet to the top of bank or ordinary high-water mark.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
c. Where there are temporary or permanent impacts from stream crossings, utility lines shall
cross the stream channel at a near -perpendicular direction (i.e., between 75 degrees and 105
degrees to the stream bank).
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
d. Construction corridors in wetlands and/or across stream channels shall be minimized tothe
maximum extent practicable and shall not exceed 40 feet wide for utility lines.
For construction corridors in wetlands and across stream channels, stumps shall be
grubbed only as needed to install the utility and remaining stumps shall be cut off at
grade level. The general stripping of topsoil within wetlands along the construction
corridor is prohibited.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
e. Permanent maintained access corridors in wetlands and across stream channels shall be
restricted to the minimum width practicable and shall not exceed 30 feet wide except at
manhole locations.
Calico Area Developers, LLC
DocuSign Envelope ID: BE1D409B-9035-496C-88D5-C4F33CE5583A DWR project #20190206v2
WQC004681
Page 6 of 10
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
f. For all utility lines constructed within wetlands, an anti -seep collar shall be placed at the
downstream (utility line gradient) wetland boundary and every 150 feet up the gradient
until the utility exits the wetland. Anti -seep collars may be constructed with class B
concrete, compacted clay, PVC pipe, or metal collars. Wetland crossings that are
directionally drilled, and perpendicular wetland crossings that are open cut and less than
150 feet long do not require anti -seep collars. The compacted clay shall have a specific
infiltration of 1 X 10-5 cm/sec or less. A section and plan view diagram is attached for the
anti -seep collars.
The following specifications shall apply to class B concrete:
i. Minimum cement content, sacks per cubic yard with rounded coarse aggregate 5.0
ii. Minimum cement content, sacks per cubic yard with angular coarse aggregate 5.5
iii. Maximum water -cement ratio gallons per sack 6.8
iv. Slump range 2" to 4"
v. Minimum strength - 28-day psi 2,500
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
g. The permittee shall have a specific plan for restoring wetland contours to pre -construction
conditions. Any excess material will be removed to a high ground disposal area.
The mixing of topsoil and subsoils within the wetlands along utility corridors shall be
minimized to the greatest extent practical. During excavation, the soils shall be placed on
fabric to minimize impacts whenever possible. Topsoil excavated from utility trenches will
be piled separately from subsoils and will be backfilled into the trench onlyafter the
subsoils have been placed and compacted.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
The permittee shall report to the DWR Wilmington Regional Office any noncompliance with, and/or any
violation of, stream or wetland standards [15A NCAC 02B .0200], including but not limited to sediment
impacts to streams or wetlands. Information shall be provided orally within 24 hours (or the next
business day if a weekend or holiday) from the time the permittee became aware of the non-
compliance circumstances.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
8. No waste, spoil, solids, or fill of any kind shall occur in wetlands or waters beyond the footprint of the
approved impacts (including temporary impacts).
Citation: 15A NCAC 02H .0506; 15A NCAC 02H .0507(c)
9. All activities shall be in compliance with any applicable State Regulated Riparian Buffer Rules in
Chapter 2B of Title 15A in the North Carolina Administrative Code.
Citation: 15A NCAC 02H .0506(b), 15A NCAC 02H .0507(c)
DocuSign Envelope ID: BE1D409B-9035-496C-88D5-C4F33CE5583A
Calico Area Developers, LLC
DWR project #20190206v2
WQC004681
Page 7 of 10
10. When applicable, all construction activities shall be performed and maintained in full compliance
with G.S. Chapter 113A Article 4 (Sediment and Pollution Control Act of 1973). Regardless of
applicability of the Sediment and Pollution Control Act, all projects shall incorporate appropriate Best
Management Practices for the control of sediment and erosion so that no violations of state water
quality standards, statutes, or rules occur.
Design, installation, operation, and maintenance of all sediment and erosion control measures shall
be equal to or exceed the requirements specified in the most recent version of the North Carolina
Sediment and Erosion Control Manual, or for linear transportation projects, the North Caroline
Department of Transportation Sediment and Erosion Control Manual.
All devices shall be maintained on all construction sites, borrow sites, and waste pile (spoil) sites,
including contractor -owned or leased borrow pits associated with the project. Sufficient materials
required for stabilization and/or repair of erosion control measures and stormwater routing and
treatment shall be on site at all times.
For borrow pit sites, the erosion and sediment control measures shall be designed, installed,
operated, and maintained in accordance with the most recent version of the North Carolina Surface
Mining Manual. Reclamation measures and implementation shall comply with the reclamation in
accordance with the requirements of the Sedimentation Pollution Control Act and the Mining Act of
1971.
If the project occurs in waters or watersheds classified as Primary Nursery Areas (PNAs), SA, WS-I,
WS-II, High Quality Waters (HQW), or Outstanding Resource Waters (ORW), then the sedimentation
and erosion control designs shall comply with the requirements set forth in 15A NCAC 04B .0124,
Design Standards in Sensitive Watersheds.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c); 15A NCACO28.0200; 15A NCAC 028 .0231
11. Sediment and erosion control measures shall not be installed in wetland or waters except within the
footprint of temporary or permanent impacts otherwise authorized by this Certification. If placed
within authorized impact areas, then placement of such measures shall not be conducted in a
manner that results in dis-equilibrium of any wetlands, streambeds, or streambanks. Any silt fence
installed within wetlands shall be removed from wetlands and the natural grade restored within two
(2) months of the date that DEMLR or locally delegated program has released the specific area within
the project to ensure wetland standards are maintained upon completion of the project.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c); 15A NCAC 028.0200; 15A NCAC 028.0231
12. Erosion control matting that incorporates plastic mesh and/or plastic twine shall not be used along
streambanks or within wetlands.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
13. If the project is covered by NPDES Construction Stormwater Permit Number NCG010000 or NPDES
Construction Stormwater Permit Number NCG250000, full compliance with permit conditions
including the erosion & sedimentation control plan, inspections and maintenance, self -monitoring,
record keeping and reporting requirements is required.
DocuSign Envelope ID: BE1D409B-9035-496C-88D5-C4F33CE5583A
Calico Area Developers, LLC
DWR project #20190206v2
WQC004681
Page 8 of 10
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c); 15A NCAC 02B .0200; 15A NCAC 02B .0231
14. All work in or adjacent to streams shall be conducted so that the flowing stream does not come in
contact with the disturbed area. Approved best management practices from the most current
version of the NC Sediment and Erosion Control Manual, or the NC Department of Transportation
Construction and Maintenance Activities Manual, such as sandbags, rock berms, cofferdams, and
other diversion structures shall be used to minimize excavation in flowing water.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c); 15A NCAC 02B .0200
15. Culverts shall be designed and installed in such a manner that the original stream profiles are not
altered and allow for aquatic life movement during low flows. The dimension, pattern, and profile of
the stream above and below a pipe or culvert shall not be modified by widening the stream channel
or by reducing the depth of the stream in connection with the construction activity. The width,
height, and gradient of a proposed culvert shall be such as to pass the average historical low flow and
spring flow without adversely altering flow velocity. If the width of the culvert is wider than the
stream channel, the culvert shall include multiple boxes/pipes, baffles, benches and/or sills to
maintain the natural width of the stream channel. If multiple culverts/pipes/barrels are used, low
flows shall be accommodated in one culvert/pipe and additional culverts/pipes shall be installed such
that they receive only flows above bankfull.
Placement of culverts and other structures in streams shall be below the elevation of the streambed
by one foot for all culverts with a diameter greater than 48 inches, and 20% of the culvert diameter
for culverts having a diameter less than or equal to 48 inches, to allow low flow passage of water and
aquatic life. If the culvert outlet is submerged within a pool or scour hole and designed to provide for
aquatic passage, then culvert burial into the streambed is not required.
For structures less than 72" in diameter/width, and topographic constraints indicate culvert slopes of
greater than 2.5% culvert burial is not required, provided that all alternative options for flattening the
slope have been investigated and aquatic life movement/connectivity has been provided when
possible (e.g. rock ladders, cross -vanes, sills, baffles etc.). Notification, including supporting
documentation to include a location map of the culvert, culvert profile drawings, and slope
calculations, shall be provided to DWR 30 calendar days prior to the installation of the culvert.
When bedrock is present in culvert locations, culvert burial is not required, provided that there is
sufficient documentation of the presence of bedrock. Notification, including supporting
documentation such as a location map of the culvert, geotechnical reports, photographs, etc. shall be
provided to DWR a minimum of 30 calendar days prior to the installation of the culvert. If bedrock is
discovered during construction, then DWR shall be notified by phone or email within 24 hours of
discovery.
Installation of culverts in wetlands shall ensure continuity of water movement and be designed to
adequately accommodate high water or flood conditions. When roadways, causeways, or other fill
projects are constructed across FEMA-designated floodways or wetlands, openings such as culverts
or bridges shall be provided to maintain the natural hydrology of the system as well as prevent
constriction of the floodway that may result in destabilization of streams or wetlands.
DocuSign Envelope ID: BE1D409B-9035-496C-88D5-C4F33CE5583A
Calico Area Developers, LLC
DWR project #20190206v2
WQC004681
Page 9 of 10
The establishment of native woody vegetation and other soft stream bank stabilization techniques
shall be used where practicable instead of rip -rap or other bank hardening methods.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
16. Application of fertilizer to establish planted/seeded vegetation within disturbed riparian areas and/or
wetlands shall be conducted at agronomic rates and shall comply with all other Federal, State and
Local regulations. Fertilizer application shall be accomplished in a manner that minimizes the risk of
contact between the fertilizer and surface waters.
Citation: 15A 02H .0506(b); 15A NCAC 02H .0507(c), 15A NCAC 02B .0200; 15A NCAC 02B .0231
17. If concrete is used during construction, then all necessary measures shall be taken to prevent direct
contact between uncured or curing concrete and waters of the state. Water that inadvertently
contacts uncured concrete shall not be discharged to waters of the state.
Citation: 15A 02H .0506(b); 15A NCAC 02H .0507(c), 15A NCAC 02B .0200, 15A NCAC 02B .0231
18. All proposed and approved temporary fill and culverts shall be removed and the impacted area shall
be returned to natural conditions within 60 calendar days after the temporary impact is no longer
necessary. The impacted areas shall be restored to original grade, including each stream's original
cross -sectional dimensions, planform pattern, and longitudinal bed profile. All temporarily impacted
sites shall be restored and stabilized with native vegetation.
Citation: 15A NCAC 02H.0506(b), 15A NCAC 02H .0507(c)
19. All proposed and approved temporary pipes/culverts/rip-rap pads etc. in streams or wetlands shall
be installed as outlined in the most recent edition of the North Carolina Sediment and Erosion Control
Planning and Design Manual or the North Carolina Surface Mining Manual or the North Carolina
Department of Transportation Best Management Practices for Construction and Maintenance
Activities so as not to restrict stream flow or cause dis-equilibrium during use of this Certification.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
20. Any rip -rap required for proper culvert placement, stream stabilization, or restoration of temporarily
disturbed areas shall be restricted to the area directly impacted by the approved construction
activity. All rip -rap shall be placed such that the original streambed elevation and streambank
contours are restored and maintained and shall consist of clean rock or masonry material free of
debris or toxic pollutants. Placement of rip -rap or other approved materials shall not result in de-
stabilization of the stream bed or banks upstream or downstream of the area or be installed in a
manner that precludes aquatic life passage.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
DocuSign Envelope ID: BE1D409B-9035-496C-88D5-C4F33CE5583A
Calico Area Developers, LLC
DWR project #20190206v2
WQC004681
Page 10 of 10
21. All mechanized equipment operated near surface waters shall be inspected and maintained regularly
to prevent contamination of surface waters from fuels, lubricants, hydraulic fluids, or other toxic
materials. Construction shall be staged in order to minimize the exposure of equipment to surface
waters to the maximum extent practicable. Fueling, lubrication, and general equipment maintenance
shall be performed in a manner to prevent, to the maximum extent practicable, contamination of
surface waters by fuels and oils.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c); 15A NCAC 02B .0200, 15A NCAC 02B .0231
22. Heavy equipment working in wetlands shall be placed on mats or other measures shall be taken to
minimize soil disturbance and compaction.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c); 15A NCAC 02B .0231
23. In accordance with 143-215.85(b), the permittee shall report any petroleum spill of 25 gallons or
more; any spill regardless of amount that causes a sheen on surface waters; any petroleum spill
regardless of amount occurring within 100 feet of surface waters; and any petroleum spill less than
25 gallons that cannot be cleaned up within 24 hours.
Citation: 15A NCAC 02H .0507(c); N.C.G.5143-215.85(b)
24. The permittee and their authorized agents shall conduct all activities in a manner consistent with
State water quality standards (including any requirements resulting from compliance with §303(d) of
the Clean Water Act), and any other appropriate requirements of State and Federal Law.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
25. The permittee shall require its contractors and/or agents to comply with the terms and conditions of
this certification in the construction and maintenance of this project, and shall provide each of its
contractors and/or agents associated with the construction or maintenance of this project with a
copy of this Water Quality Certification. A copy of this Water Quality Certification shall be available
at the project site during the construction and maintenance of this project.
Citation: 15A NCAC 02H .0506(b); 15A NCAC 02H .0507(c)
This approval to proceed with your proposed impacts or to conduct impacts to waters as depicted in
your application shall expire upon expiration of the 404 Permit. The conditions in effect on the date of
issuance shall remain in effect for the life of the project, regardless of the expiration date of this
Certification. [15A NCAC 02H .0507(c)]
This, the 7t" day of March 2022
DocuS, ed by:
0
Y1�F I fld���l3s011
Assistant Regional Supervisor
Water Quality Regional Operations Section