Loading...
HomeMy WebLinkAbout20210816 Ver 1_More Info Received_20220627Strickland, Bev From: Brad Luckey <bluckey@pilotenviro.com> Sent: Monday, June 27, 2022 5:39 PM To: David.E.Bailey2@usace.army.mil; dhgriffinjr@dhgriffin.com; grogers@dhgriffin.com; jmbalderamos@dhgriffin.com; ms@pnk.group; gmuraview@pnk.group Cc: Homewood, Sue; Munzer, Olivia Subject: [External] RE: Request for Additional Information for Gallimore Dairy Road Extension- DWR#20220379 and Project Elixir (350 South)-DWR#20210816- Guilford Co Attachments: RES Cape Fear 03 SOA - Feed & Seed - 350 South-PNK High Point.pdf; 350 South Project Elixir DMS Acceptance.pdf; HP Industrial Park North DEM Overlay.png Follow Up Flag: Follow up Flag Status: Flagged CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to Report Spam. Good Afternoon David and Sue, Please find the below applicant response and attachments. Please let me know if you require additional information. Thanks. USACE RFI 1) Based on the information submitted the Corps will evaluate impacts to potential waters of the US proposed under both PCNs as cumulative for one single and complete project, pertaining to NWP and compensatory mitigation thresholds (per NWP General Condition 28). USACE RFI 2) Thank you for the information submitted in response to item 2) from our 4/7/2022 request for additional information. The data resolved our concerns with this item. Applicants Response: The applicants acknowledge. USACE RFI 3) Additional information was not provided to justify the Gallimore Dairy Road Extension as a transportation project with independent utility, as requested in items 1)b. or c. of our 4/7/2022 request for additional information. As such, if the primary purpose of Phase A of the Gallimore Dairy Road Extension is to provide access to Project PNK-High Point, could additional avoidance and minimization of impacts to potential waters of the US (per NWP General Conditions 23.(a)) be achieved by accessing the proposed PNK-High Point development site via Joe Drive instead of the proposed Phase A of the Gallimore Dairy Road Extension? If so, please re -design the project accordingly. If such design is not practicable (available and capable of being done after taking into consideration cost, existing technology, and logistics in light of overall project purposes), please provide specific justification. Applicant Response: The use of Joe Drive for accessibility to the Project PNK-High Point project is not feasible for multiple reasons. The Project PNK-High Point's access has been designed to utilize access from Gallimore Dairy Road extension to meet or exceed general safety requirements for separation of tractor and vehicular traffic in addition to satisfying the users internal requirements for operational efficiency. The Project PNK-High Point has been designed for approximately 180 tractor trailer trips and 550 vehicular trips daily for employees and visitors. The proposed facility is anticipated to operate three shifts that allow 24-hour per day operations. As part of the user's site development requirements, access to Sandy Ridge Road near the intersection of Interstate 40 from a signaled intersection is a necessity for tractor and vehicular travel. i The use of Joe Drive for access to the Project PNK-High Point project was evaluated and considered to not be feasible, absent of Phase A of the Gallimore Diary Road extension, for multiple reasons. Joe Drive is a state maintained road with an existing approximate 60-foot right of way. Generally, a proposed industrial right of way for a thoroughfare will be as much as twice this for general safety concerns. Five private landowners, four single family residences and one church, are located adjacent to Joe Drive. The church's primary building is currently located approximately 25' to 30' from the exiting right of way and approximately 65' or less from existing edge of pavement. For Joe Drive to be utilized as sole access for Project PNK-High Point, then additional right of ways would need to be obtained to support the necessary width of the road such that the road can safely accommodate the proposed tractor trailer and vehicular requirements of the site. Doing so has significant potential to result in demolition of the existing church structure and/or potential rebuilding of the church on the existing parcel or relocation of the church to another off -site location. Notwithstanding significant concerns associated with the church, the remaining single family residences only access to or from their residences is from Joe Drive, which would result in significant adverse effects to aesthetics, property value and safety of those residences due to substantial increases in vehicular and tractor trailer traffic. Therefore the use of Joe Drive was determined to not be feasible because it does not meet the users' internal requirements, general safety requirements and would be a significant adverse effect to nearby populace along Joe Drive. While the use of Gallimore Diary Road extension for access to the Project PNK-High Point facility does result in impact to streams, this impact is necessary The applicants have utilized several methods of avoidance and minimization including a smaller building footprint, redesign of cross-dock/trailer storage to reduce stream impact from the road drive around the building, utilization of a bottomless arch/span crossing for Gallimore Diary Road extension and several other methods to avoid and minimize impacts to the waters of the US. There are no other practical or reasonable design considerations that can be incorporated that meets the projects' purpose and need and general safety requirements that would avoids or minimizes more impacts to the waters of the US than proposed. USACE RFI 4) Thank you for the additional information provided pertaining to the proposed bottomless culvert structure. The information provided satisfies item 3)a. from our 4/7/2022 request for additional information. The information also indicates that the structure would be tied to bedrock within 5 vertical feet of the soil surface, although it remains uncertain that the City of High Point would accept the proposed design. Based on our review of the information provided, proposed permanent loss of stream for the single and complete project is 0.0198 acre (158 linear feet), whereas the amount of stream proposed under the bottomless culvert is approximately 0.01 acre (135 linear feet). As stated in our request for additional information, based on our District's considerable experience with these structures, the shading that will occur under the proposed bottomless culvert (^'4-7 foot height within the ^'145-foot long structure) will lead to the die -off of woody vegetation which provides the structure that keeps the stream banks intact. Erosion of stream banks then occurs leading to sediment loading in the stream, over -widening of the channel, and reductions in habitat heterogeneity. Such reductions in stream function are predictable, and therefore the District reviews these activities as indirect impacts per the NWP General Conditions District Engineer's Decision part 2. Given that such reduction in function to 0.01 acre (135 linear feet) of stream channel is anticipated as indirect impacts, and considering that the proposed permanent loss impacts to streams associated with the project (0.0198 acre [158 linear feet]) are only slightly below the compensatory mitigation threshold typified in NWP 39/14 Regional Condition C.7, compensatory mitigation for these cumulative impacts is warranted to ensure that the cumulative adverse environmental effects associated with this project are no more than minimal. You correctly note that the proposed bottomless culvert would not result in a complete loss of aquatic habitat/function, and does not eliminate all habitat/function or aquatic passage compared to a traditional culvert with bottom. However, as stated above, reductions in these functions are predictable and therefore justify a compensatory mitigation requirement, understandably at a reduced mitigation -to -impact ratio at least for the indirect impacts. Whereas a compensatory mitigation ratio of 2:1 is typically required for permanent loss impacts, a reduced ratio of 1:1 is typically required for reductions (though not a loss) of aquatic function. As an example, NCDOT, the entity primarily installing bottomless culverts in North Carolina does so rarely, and when they do typically provide compensatory mitigation at a 1:1 ratio. As stated in our request for additional information, an evaluation of stream function (i.e. NCSAM) could be provided in 2 an attempt to propose compensatory mitigation ratios different than those listed above for both permanent loss and indirect impacts. Applicant Response: The applicant proposes 1:1 compensatory mitigation for the cumulative and indirect impacts to 135 linear feet of stream channel affected by the bottomless arch culvert. The applicant will satisfy the mitigation proposal from the Feed & Seed private mitigation bank, which according to attached SOA dated 6.27.22, currently has credits available to satisfy the mitigation proposal. If mitigation credits are not available from the Feed & Seed private mitigation bank at the time of NWP verification, then the applicant will utilize available credits from NCDMS to satisfy the mitigation proposal. Please find also attached NCDMS letter dated 3.8.22. USACE RFI 5) Information provided in your response do not adequately address item 5 from our 4/7/2022 request for additional information. Information we previously provided pertaining to the High Point North Industrial Center clearly shows that there are future plans for development within this area. These concerns are more relevant given the absence of justification of the Gallimore Dairy Road Extension as a single and complete project. Unless the currently proposed project can be justified as having independent utility from the High Point North Industrial Center, information is needed to justify that the reasonably foreseeable impacts associated with full buildout of the High Point North Industrial Center would not exceed NWP thresholds. Applicant Response: The extension of Gallimore Diary Road from Sandy Ridge to Adkins Road is planned, per zoning requirements of the site, but only Phase A has been designed. Phase A of the Gallimore Dairy Road extension will provide access to the PNK-High Point project. Phase B of the Gallimore Diary Road extension would require 2 additional stream crossings. It is the applicant's intention to avoid exceedance of NWP impact thresholds associated with the construction of the remaining two stream crossings by utilizing remaining NWP impact amounts and/or the use of bottomless arch culverts or spans. Neither applicants nor the owner have proposed plans for future development or impacts to waters within the larger High Point Industrial Park at this time, with the exception of the disclosed two future crossings associated with the extension of Gallimore Diary Road. The informational brochure provided in USACE RFI dated 4.7.22 for the larger High Point Industrial Park is conceptual and was contracted, designed, and created by the City of High Point without consent, recommendations, or communications from the owner or either of the applicants. Significant portions of the areas shown in the larger High Point Industrial Park have not been delineated or contracted to be delineated by the owner or applicants, specifically those north or across Adkins Road as there are no proposed development plans for these areas at this time. The informational brochure was completed utilizing a previously expired delineation/USACE JD that has since been updated in 2021 for the Proposed PNK-High Point project and publicly available GIS stream/wetland information for marketing purposes by the City of High Point or local chamber of commerce. However, the informational brochure combined with the most recently completed stream/wetland delineation and overlaid on DEM (attached) does reasonably validate that large scale industrial buildings and development, specifically up to a 600,000SF and 175,000SF building could occur north of the Gallimore Diary Road extension/south of Adkins Road without future impact to waters. Therefore, additional impact to waters associated with future build out of the High Point Industrial Park located south and east of Adkins Road is not proposed or anticipated at this time. As documented within the informational brochure, the northern portion of the larger High Point Industrial Park, designated as Phase II, is located north and west of Adkins Road and south of West Market Street, both of which are existing NCDOT throughfares. Generally speaking, the depicted conceptual industrial buildings have been designed to avoid impacts to waters based on GIS locations of streams and anticipated jurisdictional features. Based on the conceptual layout, it is reasonable to foresee that independent utility and access from Adkins Road and/or West Market Street could be utilized to eliminate or avoid impact to waters from the shown internal access and interconnectivity for development located north and west of Adkins Road. Based on information at this time, the anticipated use of future bottomless arch culverts/bridge span for the future two crossing for Gallimore Diary Road extension and the conceptual layout of future speculative build out of the larger High Point Industrial Park North, it is reasonable to conclude that future development or build out of the larger High Point Industrial Park North will be done in a manner that would avoid impacts to waters. 3 Sincerely, Bradley S. Luckey, PWS 336.708.4997 (c) 336.310.4527 (o) PO Box 128 Kernersville, NC 27285 www.pilotenviro.com bluckey@ " .com From: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil> Sent: Wednesday, June 22, 2022 11:38 AM To: Brad Luckey <bluckey@pilotenviro.com>; dhgriffinjr@dhgriffin.com; grogers@dhgriffin.com; jmbalderamos@dhgriffin.com; ms@pnk.group; gmuraview@pnk.group Cc: Homewood, Sue <sue.homewood@ncdenr.gov>; Munzer, Olivia <olivia.munzer@ncwildlife.org> Subject: RE: Request for Additional Information for Gallimore Dairy Road Extension-DWR#20220379 and Project Elixir (350 South)-DWR#20210816- Guilford Co All, Thank you for your response to our request for additional email. Upon review of the submitted information the following items are unresolved and/or require clarification before proceeding with verifying the use of Nationwide Permits (NWPs) 14 (https://saw-reg.usace.army.mil/NWP2021/NWP-14.pdf) and 39 (https://saw- reg.usace.army.mil/NWP2021/NWP39.pdf). Please submit the requested information below (via e-mail is fine) within 30 days of receipt of this Notification, otherwise we may deny verification of the use of the NWPs or consider your applications withdrawn and close the files: 1) Based on the information submitted the Corps will evaluate impacts to potential waters of the US proposed under both PCNs as cumulative for one single and complete project, pertaining to NWP and compensatory mitigation thresholds (per NWP General Condition 28). 2) Thank you for the information submitted in response to item 2) from our 4/7/2022 request for additional information. The data resolved our concerns with this item. 3) Additional information was not provided to justify the Gallimore Dairy Road Extension as a transportation project with independent utility, as requested in items 1)b. or c. of our 4/7/2022 request for additional information. As such, if the primary purpose of Phase A of the Gallimore Dairy Road Extension is to provide access to Project PNK-High Point, could additional avoidance and minimization of impacts to potential waters of the US (per NWP General Conditions 23.(a)) be achieved by accessing the proposed PNK-High Point development site via Joe Drive instead of the proposed Phase A of the Gallimore Dairy Road Extension? If so, please re -design the project accordingly. If such design is not practicable (available and capable of being done after taking into consideration cost, existing technology, and logistics in light of overall project purposes), please provide specific justification. 4) Thank you for the additional information provided pertaining to the proposed bottomless culvert structure. The information provided satisfies item 3)a. from our 4/7/2022 request for additional information. The information also indicates that the structure would be tied to bedrock within 5 vertical feet of the soil surface, although it remains uncertain that the City of High Point would accept the proposed design. Based on our review of the information provided, proposed permanent loss of stream for the single and complete project is 0.0198 acre (158 linear feet), whereas the amount of stream proposed under the bottomless culvert is approximately 0.01 acre (135 linear feet). As stated in our request for additional information, based on our District's considerable experience with these structures, the shading that will occur under the proposed bottomless culvert (^'4-7 foot height within the ^'145-foot long structure) will lead to the die -off of woody vegetation which provides the structure that keeps the stream banks intact. Erosion of stream banks then occurs leading to sediment loading in the stream, over -widening of the channel, and reductions in habitat heterogeneity. Such reductions in stream function are predictable, and therefore the District reviews these activities as indirect impacts per the NWP 4 General Conditions District Engineer's Decision part 2. Given that such reduction in function to 0.01 acre (135 linear feet) of stream channel is anticipated as indirect impacts, and considering that the proposed permanent loss impacts to streams associated with the project (0.0198 acre [158 linear feet]) are only slightly below the compensatory mitigation threshold typified in NWP 39/14 Regional Condition C.7, compensatory mitigation for these cumulative impacts is warranted to ensure that the cumulative adverse environmental effects associated with this project are no more than minimal. You correctly note that the proposed bottomless culvert would not result in a complete loss of aquatic habitat/function, and does not eliminate all habitat/function or aquatic passage compared to a traditional culvert with bottom. However, as stated above, reductions in these functions are predictable and therefore justify a compensatory mitigation requirement, understandably at a reduced mitigation -to -impact ratio at least for the indirect impacts. Whereas a compensatory mitigation ratio of 2:1 is typically required for permanent loss impacts, a reduced ratio of 1:1 is typically required for reductions (though not a loss) of aquatic function. As an example, NCDOT, the entity primarily installing bottomless culverts in North Carolina does so rarely, and when they do typically provide compensatory mitigation at a 1:1 ratio. As stated in our request for additional information, an evaluation of stream function (i.e. NCSAM) could be provided in an attempt to propose compensatory mitigation ratios different than those listed above for both permanent loss and indirect impacts. 5) Information provided in your response do not adequately address item 5 from our 4/7/2022 request for additional information. Information we previously provided pertaining to the High Point North Industrial Center clearly shows that there are future plans for development within this area. These concerns are more relevant given the absence of justification of the Gallimore Dairy Road Extension as a single and complete project. Unless the currently proposed project can be justified as having independent utility from the High Point North Industrial Center, information is needed to justify that the reasonably foreseeable impacts associated with full buildout of the High Point North Industrial Center would not exceed NWP thresholds. Please note that responses to the questions above may prompt additional information requests to allow full evaluation of the proposed project(s), and let me know if you have any questions. Sincerely, Dave Bailey David E. Bailey, PWS Regulatory Project Manager US Army Corps of Engineers CE-SAW-RG-R 3331 Heritage Trade Drive, Suite 105 Wake Forest, North Carolina 27587 Mobile: (919) 817-2436 Office: (919) 554-4884, Ext. 30. Fax: (919) 562-0421 Email: David.E.Bailey2@usace.army.mil We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is located at: https://regulatory.ops.usace.army.mil/customer-service-survey/ Thank you for taking the time to visit this site and complete the survey. From: Brad Luckey <bluckey@pilotenviro.com> Sent: Tuesday, May 24, 2022 4:21 PM To: Homewood, Sue <sue.homewood@ncdenr.gov>; Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil>; Munzer, Olivia <olivia.munzer@ncwildlife.org> 5 Cc: dhgriffinjr@dhgriffin.com; gropers@dhgriffin.com; jmbalderamos@dhgriffin.com; ms@pnk.group; gmuraview@pnk.group Subject: [URL Verdict: Neutral][Non-DoD Source] RE: Request for Additional Information for Gallimore Dairy Road Extension-DWR#20220379 and Project Elixir (350 South)-DWR#20210816- Guilford Co Good Tuesday Afternoon David/Sue, I hope you both are well. Please find the attached updated PCNs for the Gallimore Diary Road extension and Project PNK-High Point and below applicant's response to request for information and comments. Additionally, please note that Project Elixir name has been changed to Project PNK-High Point. If you require additional information to process the requests, then please let me know. Thanks and have a great day. NCDWR RFI 1) Please provide a drawing/plan sheet that shows both Gallimore Dairy Road Extension (in it's entirety) and Project Elixir and all jurisdictional features to assist the Division with evaluating Avoidance and Minimization for both projects. Applicant Response: See Attached Overall Impacts Map, Exhibit 1.0, Gallimore Dairy Road PCN NCDWR RFI 2) Notwithstanding the responses to item 1 below regarding Gallimore Dairy Road extension: a. If this roadway is determined to be a public thoroughfare maintained by the City of High Point then we strongly recommend that the City be a co -applicant for the 401. b. Depending on the further evaluation of the roadway, the proposed Randleman Buffer impacts may require Division review and approval. c. Please clarify who/what entity is providing assurances that future crossings will be constructed as spanning structures. d. If the City of High Point is to assume responsibility of the proposed roadway, please provide documentation that they will allow the proposed spanning structure as it does not appear to comply with local NCDOT recommendations/requirements. e. Please clearly show the proposed limits of Phase 1 of Gallimore Dairy Rd extension on the plan sheets. f. Please provide a detailed stormwater management plan and/or diffuse flow plan for the entirety of Gallimore Dairy Rd Extension and ensure that the proposed plan is in compliance with the Randleman Buffer Rules. Applicant Response: As noted within attached PCNs, the purpose of Phase A of the extension of Gallimore Dairy Road is to provide access and water/sewer services to the PNK-High Point project. As proposed, the applicant of the Gallimore Diary Road extension would relinquish maintenance of Gallimore Diary Road extension to the City of High Point following construction of the Gallimore Dairy Road extension. The proposed Phase A of the extension of Gallimore Diary Road has been designed to be in compliance with the City of High Point, NCDOT and the Randleman Lake stormwater and riparian buffer regulations. Requests for review and approval of site plan engineering and stormwater management requirements has been submitted to the City of High Point for their review and approval. NCDWR RFI 3) Notwithstanding the responses to item 1 below regarding Project Elixir: A Please provide information regarding the location of utilities being provided to the site. Will any utility corridors require additional jurisdictional impacts? B While the Division recognizes the parking requirements of the applicant, and safe ingress/egress for large vehicles, it is unclear that the current roadway alignment and parking areas provide for the maximum Avoidance and Minimization within the site. For example, could employee parking be reconfigured in a more North/South alignment allowing for the western access road to be moved west and south and impact less of the stream and buffer at this location? C It is unclear from the application documentation that the project is in compliance with the City of High Point's Ordinance requirements regarding the Randleman Buffer Rules. As the Division is unable to issue a 401 Certification that may not be in compliance with the local ordinances related to the Randleman Buffer 6 Rules, please provide a Buffer Authorization (or other form of approval) from the City of High Point or provide further information/documentation of the City's review process. Applicant Response: See Attached Overall Impacts Map, Exhibit 1.0, Gallimore Dairy Road PCN and updated PCNs. The proposed project PNK-High Point is being accessed from Phase A of the Gallimore Diary Road extension (SAW-2014- 02098). The proposed PNK High Point project will connect to exiting sanitary sewer from the southwestern portion of the site and existing water services from Sandy Ridge Road. An aerial sewer crossing that does not impact waters is proposed on the western portion of the site. Other or future impacts to waters as a result of the proposed project are not anticipated. Please see attached page 16, Impact Exhibits, Project PNK-High Point PCN. The proposed riparian buffer impact and associated stream impact has been designed as a road crossing, whereas up and down -gradient grading impacts from the proposed access road at 2:1 slope result in the temporary and permanent impact to the proposed stream buffer as proposed within this application, regardless of overlap of grading or final conditions within the riparian buffer from parking and proposed building impervious surfaces. Therefore, the proposed crossing is an allowable use within the Randleman Buffer table of uses. The applicant is in the process of submitting a Randleman Lake Riparian Buffer No Practical Alternative Letter to the City of High Point for review and approval. NCWRC Comment 1) We recommend further minimizing impacts to streams. As Sue mentioned, it seems that the parking layout could be tweaked to reduce impacts. NCWRC Comment 2) The applicant should consider integrating some Low Impact Development techniques, such as swales instead of curb and gutter and bioretention cells in parking lot medians (https://www.uni-groupusa.org/PDF/NC LID Guidebook.pdf) could reduce the size of the stormwater BMP. NCWRC Comment 3) Sediment and erosion control measures should be installed prior to any land -disturbing activity. Incorporate the following elements into erosion and sediment control plans: minimize clearing and grading, protect waterways, phase construction for larger construction sites (>25 acres), stabilize soils as rapidly as possible (<2 weeks), protect steep slopes, establish appropriate perimeter controls, employ advanced settling devices, implement a certified contractors program, and regularly inspect erosion control measures. Excessive silt and sediment loads can have detrimental effects on aquatic resources including destruction of spawning habitat, suffocation of eggs, and clogging of gills. NCWRC Comment 4) Erosion control matting made of plastic mesh or twine should not be used within the project area, including upland areas, because it can entrap and kill wildlife. The use of biodegradable and wildlife -friendly sediment and erosion control devices is strongly recommended. Silt fencing, fiber rolls and/or other products should have loose -weave netting that is made of natural fiber materials with movable joints between the vertical and horizontal twines. Silt fencing that has been reinforced with plastic or metal mesh should be avoided as it impedes the movement of terrestrial wildlife species. NCWRC Comment 5) Also, non-native plants should not be used for seeding disturbed areas. Specifically, avoid using Bermudagrass, redtop, tall fescue, and lespedeza, which are invasive and/or non-native. A list of alternatives to non-native species has been attached. Alternatively, use a grain, such as oats, wheat, or rye for temporary cover and native seed mixes for permeant seeding. We recommend planting native, wildflower seed mixes that will create pollinator habitat and/or and plant native trees and shrubs for landscaping rather than using turf grass. Using native plants will also reduce costs and time for maintenance of landscaping. NCWRC Comment 6) Avoid tree clearing activities during the maternity roosting season for bats (May 15 — August 15) because of the decline in populations of several tree -roosting bat species. NCWRC Comment 7) We recommend not clearing the entire site, but rather maintaining the maximum amount of native vegetation as possible. We suggest having the site logged instead of burning the cleared trees. Applicants Response: The applicants acknowledge recommendations and comments from NCWRC and will incorporate these recommendations and comments into construction and maintenance of the proposed projects whereas practical and possible. USACE RFI 1) The information provided does not fully justify that the proposed Gallimore Diary Road Extension is a project with independent utility from Project Elixir (350 South). Please provide the following to enable our continued evaluation: a. What municipality/entity will assume responsibility and maintenance of this transportation facility into perpetuity? Please provide any supporting documentation; b. Provide documentation to justify that this road extension is part of a thoroughfare or other transportation plan to show purpose and need other than to facilitate access to Project Elixir (350 South) and future portions of the High Point North Industrial Center; c. Provide traffic data/analysis to justify the Gallimore Dairy Road Extension as a transportation project with independent utility, absent of future traffic needs for Project Elixir (350 South) and future portions of the High Point North Industrial Center; d. Design of the first crossing only, which does not allow evaluation of all potential direct and indirect impacts required to complete the proposed road extension to Adkins Road (i.e. not logical termini), is insufficient for the evaluation of the proposed road extension. Please provide plan and cross section drawings of the remaining crossings; e. In order to justify width of the proposed roadway and show avoidance and minimization to the maximum extent practicable per NWP General Condition 23a, please provide the roadway cross section showing the number and width of travel lanes and shoulder widths, and a description of how that compares to the existing portion of Gallimore Dairy Road just east of the existing intersection of Sandy Ridge Road and Gallimore Dairy Road; f. Absent Project Elixir (350 South), would an alignment of Gallimore Dairy Road be available/viable to avoid at least one stream crossing, such as aligning the route south of the origins of Streams MSB/BSA and thereby crossing Stream MSA downstream of its confluence with Stream MSC? Applicant Response: See attached updated PCNs. The proposed project PNK-High Point is being accessed from Phase A of the Gallimore Diary Road extension (SAW-2014-02098). The proposed PNK High Point will connect to exiting sanitary sewer service from the southwestern portion of the site and existing water services along Sandy Ridge Road. USACE RFI 2) The Gallimore Dairy Road Extension alignment intersects with Adkins Road just west of a topographic drainage that occurs outside of the PJD Review Area for Project Elixir (350 South) and does not appear to be covered by the additional evaluation area you provided in the PCN. Within the proposed alignment, has this drainage been evaluated for the presence of potential waters of the US, including wetlands? Please provide documentation accordingly. Applicant Response: Pilot personnel conducted a stream/wetland delineation for an approximate 5.10-acre tract, located along Adkins Road, which contains the above described drainage swale. Based on the stream/wetland delineation, jurisdictional waters are not present on the approximate 5.10-are tract or within the proposed disturbance limits of the Gallimore Diary Road extension. USACE RFI 3) Proposed bottomless culverts: A Please provide a cross section view of the proposed bottomless culvert structures (see item 1)d. above) clearly showing the outer walls of the culvert structures and footers, disturbance limits needed to construct the structure, and the stream profile. This information is needed to ensure that this structure would not result in direct impacts to the stream; B The Corps Wilmington District Raleigh Regulatory Field Office has had long experience with bottomless culverts. We generally agree with NCDOT that the long-term success of such structures is significantly enhanced when they are tied into shallow bedrock. NCDOT Division 7 does not typically pursue bottomless culverts unless there is non-scourable bedrock within 5 vertical feet of the soil surface. In cases where the structures are not tied into bedrock we have seen numerous instances of foundation undercutting, often leading to replacement with traditional culverts. Further, shading under the arch 8 culvert inevitably leads to die -off of any remaining woody vegetation. These factors predictably lead to loss of aquatic function through stream bank erosion and winnowing out from foundation to foundation. C Given that the project proposes impacts requiring 404 approval, we are evaluating both direct and reasonably foreseeable indirect impacts to 404 resources associated with the project to ensure that the individual and cumulative adverse environmental effects are no more than minimal (NWP General Condition 23 and District Engineer's Decision part 2). Based on the above, it is reasonable to conclude that the proposed bottomless culverts would result in indirect impacts to streams in the footprint of the structures. The proposed indirect impacts to streams appears to exceed 0.02 acre, the typified stream mitigation threshold per Regional Condition B.7, in this case. Compensatory mitigation for this predictable reduction in (though not a total loss of) stream function is typically required at 1:1, unless otherwise justified based on an evaluation of stream function (i.e. NCSAM). Applicant Response: See Impact Exhibit 2.0, Gallimore Diary Road Extension PCN. The proposed bottomless arch culvert does not result in a net loss fill impact to the stream and is being tied to shallow bedrock. It is our opinion that all factors as outlined in the District Engineers Decision Part 2 of NWP 39 should be evaluated to determine what is or is not minimal indirect loss or cumulative effect to the environment as a whole, and thus appropriate compensatory mitigation, if any, for effects that would be considered more than individual or minimal. As noted within District Engineers Decision Part 2 of NWP 39, "The district engineer will also consider site specific factors, such as the environmental setting in the vicinity of the NWP activity, the type of resource that will be affected by the NWP activity, the functions provided by the aquatic resources that will be affected by the NWP activity, the degree or magnitude to which the aquatic resources perform those functions, the extent that aquatic resource functions will be lost as a result of the NWP activity (e.g., partial or complete loss), the duration of the adverse effects (temporary or permanent), the importance of the aquatic resource functions to the region (e.g., watershed or ecoregion), and mitigation required by the district engineer". While there will be some decreases in aquatic function comparatively to conditions now, it is not a complete or net loss (i.e. a minimal loss) of aquatic habitat/function and does not prohibit habitat/function or aquatic passage comparatively to a traditional culvert with bottom. Furthermore, the size of the culvert (width and length) will minimize the effect of shading impacts and die -back of woody species. Additionally, existing channel stability and local geology (i.e. low channel slope, no presence of highly erosive soils, etc.) contribute to minimalizing the potential indirect effect of the bottomless arch culvert to overall watershed or ecoregion. Based on these factors, we have determined that the loss of aquatic function from the bottomless arch culvert to the stream would not be more than minimal indirect impact or require compensatory mitigation and would have negligible effect to the overall function of the watershed or ecoregion. USACE RFI 4) USACE RFI 5) The information provided does not fully justify that Project Elixir is a project with independent utility from the Gallimore Dairy Road Extension. Specifically, a portion of impacts proposed to Stream MSB are for an access road that does not connect to any infrastructure (i.e. has no purpose) absent the proposed Gallimore Dairy Road Extension. Information in item 1 above will be required to evaluate the independent utility of the Gallimore Dairy Road Extension. Otherwise, note that these projects currently appear to be part of the same single and complete project to provide required infrastructure to develop Project Elixir (350 South) and future portions of the High Point North Industrial Center. It has come to our attention that the area proposed for development of the Gallimore Dairy Road Extension and Project Elixir (350 South) appear to be phases of the High Point North Industrial Center (see attached). Generally, the Corps would consider the entire buildout of such an industrial park as a single and complete project with impacts considered cumulative with respect to NWP and compensatory mitigation thresholds. Please provide for our evaluation any information available to justify that Project Elixir (350 South) is a single and complete project with independent utility apart from the High Point North Industrial Center. Furthermore, even if Project Elixir (350 South) and the Gallimore Dairy Road Extension are considered part of an overall High Point North Industrial Center single and complete project, it may still be possible to permit in phases by stacking NWPs if it can be shown that the reasonably foreseeable impacts associated with full buildout of the High Point North Industrial 9 Center would not exceed the NWP threshold; any information you can provide to this effect would be useful. UACCE RFI 6) Thank you for addressing avoidance of indirect impacts to remaining portions of Stream MSB downstream of the proposed fill slope. Please show the location of the proposed French drain on the zoomed -in plansheet; Applicant Response: See updated PCNs. There are no future plans for development within the High Point Industrial Center. The extension of Gallimore Diary Road from Sandy Ridge to Adkins Road is planned but only Phase A has been designed. Phase A of the Gallimore Dairy Road extension will provide access to the PNK-High Point project. Phase B of the Gallimore Diary Road extension would require 2 additional stream crossings. It is the applicant's intention to avoid exceedance of NWP impact thresholds associated with the construction of the remaining two stream crossings by utilizing remaining NWP impact amounts and/or the use of bottomless arch culverts or spans. Therefore, at this time and based on the limited information from conceptual designs, it is not possible for the Applicant to speculate any future roadway impact or development within the larger High Point Industrial Centers project's purpose and need or if there would be an impact to waters as a result thereof. The Applicants acknowledges that should the future Phase B of Gallimore Diary Road extension or other development within the larger High Point North Industrial Center were to impact jurisdictional waters, then the USACE would need review the project's purpose and need to determine if the road improvement project or other development within the larger High Point Industrial Center was considered cumulative to impacts to jurisdictional waters as a result of the proposed project. Sincerely, Bradley S. Luckey, PWS 336.708.4997 (c) 336.310.4527 (o) PO Box 128 Kernersville, NC 27285 www.pilotenviro.com bluckey@pilotenviro.com From: Homewood, Sue <sue.homewood@ncdenr.gov> Sent: Monday, April 11, 2022 9:18 AM To: Brad Luckey <bluckey@pilotenviro.com> Cc: dhgriffinjr@dhgriffin.com; gropers@dhgriffin.com; jmbalderamos@dhgriffin.com; David.E.Bailey2@usace.army.mil; ms@pnk.group; gmuraview@pnk.group; Samuel Hinnant<samuel.hinnant@highpointnc.gov>; Munzer, Olivia <olivia.munzer@ncwildlife.org> Subject: Request for Additional Information for Gallimore Dairy Road Extension-DWR#20220379 and Project Elixir (350 South)-DWR#20210816- Guilford Co All, I have completed the DWR review of the subject projects. I have many of the same questions as the USACE, therefore please copy me on your response to the items listed below. In addition, please address the following additional items. Please response within 30 days of this request and note that both applications will be considered "on hold" until receipt of a complete response to all listed items. 1. Please provide a drawing/plan sheet that shows both Gallimore Dairy Road Extension (in it's entirety) and Project Elixir and all jurisdictional features to assist the Division with evaluating Avoidance and Minimization for both projects. 2. Notwithstanding the responses to item 1 below regarding Gallimore Dairy Road extension: a. If this roadway is determined to be a public thoroughfare maintained by the City of High Point then we strongly recommend that the City be a co -applicant for the 401. 10 b. Depending on the further evaluation of the roadway, the proposed Randleman Buffer impacts may require Division review and approval. c. Please clarify who/what entity is providing assurances that future crossings will be constructed as spanning structures. d. If the City of High Point is to assume responsibility of the proposed roadway, please provide documentation that they will allow the proposed spanning structure as it does not appear to comply with local NCDOT recommendations/requirements. e. Please clearly show the proposed limits of Phase 1 of Gallimore Dairy Rd extension on the plan sheets. f. Please provide a detailed stormwater management plan and/or diffuse flow plan for the entirety of Gallimore Dairy Rd Extension and ensure that the proposed plan is in compliance with the Randleman Buffer Rules. 3. Notwithstanding the responses to item 1 below regarding Project Elixir: a. Please provide information regarding the location of utilities being provided to the site. Will any utility corridors require additional jurisdictional impacts? b. While the Division recognizes the parking requirements of the applicant, and safe ingress/egress for large vehicles, it is unclear that the current roadway alignment and parking areas provide for the maximum Avoidance and Minimization within the site. For example, could employee parking be reconfigured in a more North/South alignment allowing for the western access road to be moved west and south and impact less of the stream and buffer at this location? c. It is unclear from the application documentation that the project is in compliance with the City of High Point's Ordinance requirements regarding the Randleman Buffer Rules. As the Division is unable to issue a 401 Certification that may not be in compliance with the local ordinances related to the Randleman Buffer Rules, please provide a Buffer Authorization (or other form of approval) from the City of High Point or provide further information/documentation of the City's review process. Please be aware that the upon review of the responses to the items requested, it may be necessary to request additional information. Sue Homewood Division of Water Resources, Winston Salem Regional Office Department of Environmental Quality 336 776 9693 office 336 813 1863 mobile Sue.Homewood@ncdenr.gov 450 W. Hanes Mill Rd, Suite 300 Winston Salem NC 27105 From: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil> Sent: Thursday, April 7, 2022 3:36 PM To: Brad Luckey <bluckey@pilotenviro.com> Cc: Homewood, Sue <sue.homewood@ncdenr.Rov>; dhgriffinjr@dhgriffin.com; grogers@dhgriffin.com; jmbalderamos@dhgriffin.com; ms@pnk.group; gmuraview@pnk.group Subject: [External] Request for Additional Information: SAW-2014-02098/SAW-2021-01390, Gallimore Dairy Road Extension and Project Elixir (350 South), Colfax, Guilford Co, NWP 14 and 39 Verifications 11 CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to Report Spam. All, Thank you for your PCNs for the above referenced Gallimore Dairy Road Extension and Project Elixir (350 South) projects, dated 3/8/2022 and 3/16/2022, respectively. I have reviewed the information and need clarification before proceeding with verifying the use of Nationwide Permits (NWPs) 14 (https://saw-reg.usace.army.mil/NWP2021/NWP- 14.pdf) and 39 (https://saw-reg.usace.army.mil/NWP2021/NWP39.pdf). Please submit the requested information below (via e-mail is fine) within 30 days of receipt of this Notification, otherwise we may deny verification of the use of the NWPs or consider your applications withdrawn and close the files: The following items are specific to the proposed Gallimore Diary Road Extension: 1) The information provided does not fully justify that the proposed Gallimore Diary Road Extension is a project with independent utility from Project Elixir (350 South). Please provide the following to enable our continued evaluation: a. What municipality/entity will assume responsibility and maintenance of this transportation facility into perpetuity? Please provide any supporting documentation; b. Provide documentation to justify that this road extension is part of a thoroughfare or other transportation plan to show purpose and need other than to facilitate access to Project Elixir (350 South) and future portions of the High Point North Industrial Center; c. Provide traffic data/analysis to justify the Gallimore Dairy Road Extension as a transportation project with independent utility, absent of future traffic needs for Project Elixir (350 South) and future portions of the High Point North Industrial Center; d. Design of the first crossing only, which does not allow evaluation of all potential direct and indirect impacts required to complete the proposed road extension to Adkins Road (i.e. not logical termini), is insufficient for the evaluation of the proposed road extension. Please provide plan and cross section drawings of the remaining crossings; e. In order to justify width of the proposed roadway and show avoidance and minimization to the maximum extent practicable per NWP General Condition 23a, please provide the roadway cross section showing the number and width of travel lanes and shoulder widths, and a description of how that compares to the existing portion of Gallimore Dairy Road just east of the existing intersection of Sandy Ridge Road and Gallimore Dairy Road; f. Absent Project Elixir (350 South), would an alignment of Gallimore Dairy Road be available/viable to avoid at least one stream crossing, such as aligning the route south of the origins of Streams MSB/BSA and thereby crossing Stream MSA downstream of its confluence with Stream MSC? 2) The Gallimore Dairy Road Extension alignment intersects with Adkins Road just west of a topographic drainage that occurs outside of the PJD Review Area for Project Elixir (350 South) and does not appear to be covered by the additional evaluation area you provided in the PCN. Within the proposed alignment, has this drainage been evaluated for the presence of potential waters of the US, including wetlands? Please provide documentation accordingly. 3) Proposed bottomless culverts: a. Please provide a cross section view of the proposed bottomless culvert structures (see item 1)d. above) clearly showing the outer walls of the culvert structures and footers, disturbance limits needed to construct the structure, and the stream profile. This information is needed to ensure that this structure would not result in direct impacts to the stream; b. The Corps Wilmington District Raleigh Regulatory Field Office has had long experience with bottomless culverts. We generally agree with NCDOT that the long-term success of such structures is significantly enhanced when they are tied into shallow bedrock. NCDOT Division 7 does not typically pursue bottomless culverts unless there is non-scourable bedrock within 5 vertical feet of the soil surface. In cases where the structures are not tied into bedrock we have seen numerous instances of foundation 12 undercutting, often leading to replacement with traditional culverts. Further, shading under the arch culvert inevitably leads to die -off of any remaining woody vegetation. These factors predictably lead to loss of aquatic function through stream bank erosion and winnowing out from foundation to foundation. c. Given that the project proposes impacts requiring 404 approval, we are evaluating both direct and reasonably foreseeable indirect impacts to 404 resources associated with the project to ensure that the individual and cumulative adverse environmental effects are no more than minimal (NWP General Condition 23 and District Engineer's Decision part 2). Based on the above, it is reasonable to conclude that the proposed bottomless culverts would result in indirect impacts to streams in the footprint of the structures. The proposed indirect impacts to streams appears to exceed 0.02 acre, the typified stream mitigation threshold per Regional Condition B.7, in this case. Compensatory mitigation for this predictable reduction in (though not a total loss of) stream function is typically required at 1:1, unless otherwise justified based on an evaluation of stream function (i.e. NCSAM). The following items are specific to Project Elixir (350 South): 4) The information provided does not fully justify that Project Elixir is a project with independent utility from the Gallimore Dairy Road Extension. Specifically, a portion of impacts proposed to Stream MSB are for an access road that does not connect to any infrastructure (i.e. has no purpose) absent the proposed Gallimore Dairy Road Extension. Information in item 1 above will be required to evaluate the independent utility of the Gallimore Dairy Road Extension. Otherwise, note that these projects currently appear to be part of the same single and complete project to provide required infrastructure to develop Project Elixir (350 South) and future portions of the High Point North Industrial Center. 5) It has come to our attention that the area proposed for development of the Gallimore Dairy Road Extension and Project Elixir (350 South) appear to be phases of the High Point North Industrial Center (see attached). Generally, the Corps would consider the entire buildout of such an industrial park as a single and complete project with impacts considered cumulative with respect to NWP and compensatory mitigation thresholds. Please provide for our evaluation any information available to justify that Project Elixir (350 South) is a single and complete project with independent utility apart from the High Point North Industrial Center. Furthermore, even if Project Elixir (350 South) and the Gallimore Dairy Road Extension are considered part of an overall High Point North Industrial Center single and complete project, it may still be possible to permit in phases by stacking NWPs if it can be shown that the reasonably foreseeable impacts associated with full buildout of the High Point North Industrial Center would not exceed the NWP threshold; any information you can provide to this effect would be useful. 6) Thank you for addressing avoidance of indirect impacts to remaining portions of Stream MSB downstream of the proposed fill slope. Please show the location of the proposed French drain on the zoomed -in plansheet; Please note that responses to the questions above may prompt additional information requests to allow full evaluation of the proposed project(s). Also note that it appears that an Individual 401 WQC would be required from NCDWR for the proposed project(s); the Corps cannot verify the use of any NWP without a valid 401 Water Quality Certification. Please let me know if you have any questions. Sincerely, Dave Bailey David E. Bailey, PWS Regulatory Project Manager US Army Corps of Engineers CE-SAW-RG-R 13 3331 Heritage Trade Drive, Suite 105 Wake Forest, North Carolina 27587 Mobile: (919) 817-2436 Office: (919) 554-4884, Ext. 30. Fax: (919) 562-0421 Email: David.E.Bailey2@usace.army.mil We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is located at: https://regulatory.ops.usace.army.mil/customer-service-survey/ Thank you for taking the time to visit this site and complete the survey. From: RaleighNCREG <RaleighNCREG@usace.army.mil> Sent: Thursday, March 17, 2022 11:34 AM To: Brad Luckey <bluckey@pilotenviro.com>; RaleighNCREG <RaleighNCREG@usace.army.mil> Cc: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil>; Homewood, Sue <sue.homewood@ncdenr.gov> Subject: RE: SAW-2021-01390, Project Elixir (350 South), Colfax, Guilford Co, NWP 39 Verification Good Morning, We have received your Pre -Construction Notification (PCN) NWP request for the above project. Dave-docs forwarded it to your folder. Sorry for the mistake, but the correct action ID for this project is SAW-2014-02098 (Project 350 South / Sandy Ridge Road / Adkins Road / Joe Drive / Greensboro / Guilford County). Thank you, Josephine Schaffer From: Brad Luckey <bluckey@pilotenviro.com> Sent: Wednesday, March 16, 2022 4:35 PM To: RaleighNCREG <RaleighNCREG@usace.army.mil> Cc: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil>; Homewood, Sue <sue.homewood@ncdenr.gov> Subject: [URL Verdict: Unknown][Non-DoD Source] SAW-2021-01390, Project Elixir (350 South), Colfax, Guilford Co, NWP 39 Verification Happy Mid Week Corps —please find attached PCN for NWP 39 Verification of above referenced site. Please let me know if you require additional information. Sue —we will upload to DWR today. Thanks. Sincerely, Bradley S. Luckey, PWS 336.708.4997 (c) 336.310.4527 (o) PO Box 128 14 Kernersville, NC 27285 www.pilotenviro.com bl uckey@ pilotenviro.com 15 Environmental Banc & Exchange, LLC Stream and Stream Banks Statement of Availability June 27, 2022 U.S. Army Corps of Engineers David Bailey Raleigh Regulatory Field Office 3331 Heritage Trade Center, Suite 105 Wake Forest, NC 27587 Re Project: 350 South/Project PNK High Point This document confirms that the PNK Holdings, LLC (Applicant) for the 350 South/Project PNK High Point (Project) has expressed an interest to utilize 243.38 Stream Mitigation Credits from the EBX sponsored RES Cape Fear 03 Umbrella Mitigation Bank, specifically 243.38 Stream credits from the Feed and Seed Site, in the Cape Fear HUC 03030003. As the official Bank Sponsor, Environmental Banc & Exchange, LLC, attests to the fact that mitigation is available for reservation at this time. These mitigation credits are not considered secured, and consequently are eligible to be used for alternate purposes by the Bank Sponsor, until payment in full is received from the Applicant resulting in the issuance of a Mitigation Credit Transfer Certificate by the bank acknowledging that the Applicant has fully secured credits from the bank and the Banker has accepted full responsibility for the mitigation obligation requiring the credits/units. The Banker will issue the Mitigation Credit Transfer Certificate within three (3) days of receipt of the purchase price. Banker shall provide to Applicant a copy of the Mitigation Credit Transfer Certificate and a documented copy of the debit of credits from the Bank Official Credit Ledger(s), indicating the permit number and the resource type secured by the applicant. A copy of the Mitigation Credit Transfer Certificate, with an updated Official Credit Ledger will also be sent to regulatory agencies showing the proper documentation. Please contact me at 919-209-1055 or astaley@res.us if you have any questions. Best Regards, Amy Staley Resource Environmental Solutions, LLC 3600 Glenwood Avenue, Suite 100 Raleigh, NC 27612 ROY COOPER. Governor ELIZABETH S. BISER Secretory MARC RECKTENWALD Director Bradley Luckey Pilot Environmental Inc. PO Box 128 Kernersville, NC 27285 NORTH CAROLINA Environmental Quality March 8, 2022 Expiration of Acceptance: 9/8/2022 Project: 350 South Project Elixir County: Guilford The purpose of this letter is to notify you that the NCDEQ Division of Mitigation Services (DMS) is willing to accept payment for compensatory mitigation for impacts associated with the above referenced project as indicated in the table below. Please note that this decision does not assure that participation in the DMS in - lieu fee mitigation program will be approved by the permit issuing agencies as mitigation for project impacts. It is the responsibility of the applicant to contact permitting agencies to determine if payment to the DMS will be approved. You must also comply with all other state, federal or local government permits, regulations or authorizations associated with the proposed activity including G.S. § 143-214.11. This acceptance is valid for six months from the date of this letter and is not transferable. If we have not received a copy of the issued 404 Permit/401 Certification within this time frame, this acceptance will expire. It is the applicant's responsibility to send copies of the permits to DMS. Once DMS receives a copy of the permit(s) an invoice will be issued based on the required mitigation in that permit and payment must be made prior to conducting the authorized work. The amount of the in -lieu fee to be paid by an applicant is calculated based upon the Fee Schedule and policies listed on the DMS website. Based on the information supplied by you in your request to use the DMS, the impacts for which you are requesting compensatory mitigation credit are summarized in the following table. The amount of mitigation required and assigned to DMS for this impact is determined by permitting agencies and may exceed the impact amounts shown below. River Basin Impact Location (8-digit HUC) Impact Type Impact Quantity Cape Fear 03030003 Randleman Riparian Buffer Z1 Up to 11,672 Riparian Buffer Z2 Up to 19,500 Cape Fear 03030003 Warm Stream Up to 385 Upon receipt of payment, DMS will take responsibility for providing the compensatory mitigation. The mitigation will be performed in accordance with the In -Lieu Fee Program instrument dated July 28, 2010 and 15A NCAC 02B .0295 as applicable. Thank you for your interest in the DMS in -lieu fee mitigation program. If you have any questions or need additional information, please contact Kelly.Williams@ncdenr.gov. cc: Bradley Luckey, agent Sincerely, 7Jh FOR James. B Stanfill Asset Management Supervisor North Carolina Department of Environmental Quality I Division of Mitigation Services 217 West Jones Street 11652 Mail Service Center I Raleigh, North Carolina 27699-1652 919.70711976 Table Of Contents p ❑ Wetland Pt p ❑ Culvert_pt ■ p ❑ Marginal Stream p ❑ Culvert p 0 Intermittent Stream p 0 Perennial Stream p 0 Phase 2 Boundary CI p ❑ Matchline p 0 Pilot Enviro Boundary ❑ p 0 Pond p 0 Wetland p 0 DEM2.img Value High:981.433 1 Low: 822.741 O 0 RGB Red: Band_1 Green: Band_2 Blue: Band_3 p ❑ DEM.tif Value High :981.244 Low: 834.704 Brcchure.png ❑+ ❑ NC1Map Parcels ❑+ ❑ NRCS Soil Data Mart Data Access Web 0. p ❑ Basemap p 0 World Imagery p ❑ Basemap ❑+ ❑� USA_Topo_Maps 7 O Table Of Contents l e Table f u o � ti u< High ,d, Oa; ni A v