Good Morning,
The Division of Energy, Mineral, and Land Resources (DEMLR), received a complete Stormwater Management Permit
Application for the subject project on June 21, 2022. Staff review of the plans and specifications has determined that the
project, as proposed, will comply with the Stormwater Regulations set forth in Title 15A NCAC 2H.1000 - 1062 rules. We
are forwarding Permit No. SW3220305, dated June 21, 2022, for the construction, operation and maintenance of the
subject project and the stormwater system. This permit shall be effective from the date of issuance and shall be subject
to the conditions and limitations as specified therein, and does not supersede any other agency permits that may be
required.
The original signed permit package and plans are being mailed to the permittee, Chad VonCannon, at the following
address (NOTE: An electronic version of this permit can be found in our online repository:
https://edocs.deq.nc.gov/WaterResources/Browse.aspx?id=494276&dbid=0&repo=WaterResources):
Water and Sewer Authority of Cabarrus County (WSACC)
Attn: Chad VonCannon, Engineering Director
232 Davidson Highway
Concord, NC 28027
I will hold onto our hard copies of these projects for 30 days (in case any issues/typos with the permit are noticed and
corrections need to be made) after which point, they will be kept on file at the Mooresville Regional Office. If you have
any questions, or need additional information concerning this matter, please contact me at jim.farkas@ncdenr.gov.
Thank you,
Jim Farkas
Environmental Engineer
North Carolina Department of Environmental Quality
Division of Energy, Mineral, & Land Resources – Stormwater Program
512 N. Salisbury Street
1612 Mail Service Center
Raleigh, NC 27699-1612
(919) 707-3646
Jim.Farkas@ncdenr.gov
1
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
Based on the current guidance to minimize the spread of COVID-19, the Department of Environmental Quality has
adjusted operations to protect the health and safety of the staff and public. Many employees are working remotely or
are on staggered shifts. To accommodate these staffing changes, all DEQ office locations are limiting public access to
appointments only. Please check with the appropriate staff before visiting our offices, as we may be able to handle your
requests by phone or email. We appreciate your patience as we continue to serve the public during this challenging
time.
From: Tran, Kieu M <kieu.tran@ncdenr.gov>
Sent: Friday, March 25, 2022 3:13 PM
To: cvoncannon@wsacc.org; kdevendorf@brwncald.com
Cc: Farkas, Jim J <Jim.Farkas@ncdenr.gov>; Khan, Zahid <zahid.khan@ncdenr.gov>
Subject: SW3220305 Rocky River Regional Wastewater Treatment Plant Phase 3 Expansion Design
Good afternoon,
We received your post-construction stormwater permit application for the above mentioned project on 3/24/2022.
Reviews under the standard permitting process generally take 45 calendar days, but can take up to 90 calendar days per
statute (our other reviewer, Corey Anen, no longer works for the State, so this review may exceed 45 days). Please
upload all documents that you mailed into our office through the link provided below. Be sure to choose the Central
Office as the Primary Contact office.
https://edocs.deq.nc.gov/Forms/SW-Supplemental-Upload
IMPORTANT NOTE: Please ensure that each file is uploaded under its appropriate file type. Additional file types can be
entered into the electronic form by clicking on the “Add Another Post-Construction File Upload” link directly below the
“State Stormwater Information Uploads” section of the form. Please do not upload entire plan sets through this form,
but rather upload the relevant individual sheets under the appropriate file type. Selecting the correct file type ensures
that the files are properly named in the electronic repository and it helps expedite the review process.
Please type in permit #: SW3220305
If you have any questions, please contact Jim Farkas Jim.Farkas@ncdenr.gov 919-707-3646.
Thank you,
Kieu Tran
Stormwater Program Administrative Assistant
Office: (919) 707- 3640
Kieu.Tran@ncdenr.gov
2
North Carolina Department of Environmental Quality
Division of Energy, Mineral, and Land Resources Stormwater Program
512 N. Salisbury Street, Raleigh, NC 27604 (location)
1612 Mail Service Center, Raleigh, NC 27699-1612 (mailing)
Website: http://deq.nc.gov/about/divisions/energy-mineral-land-resources/stormwater