HomeMy WebLinkAboutNCC200385_NOT Closeout Documents_20220615North Carolina Department of Environmental Quality
Land Resources: 943 Washington Square Mall, Washington, NC 27889 (252) 946-6481
County: Gates Project: Suffolk Swamp Winfall 230 kv Rebuild Sect. 2 River basin: Chowan
Person financially responsible: VEPCO dba Dominion Energy NC - Mark Allen, Project #: GATES-2020-003
Director ET Project Development
Address: 10900 Nuckols Road, 4th Floor, Glen Allen, VA 23060
1. Project Location: HWY 158, Adams Swamp Rd
Pictures: No
2. Weather and soil conditions: Sunny, warm, wet Initial inspection: No
3. Is site currently under notice of violation? No
4. Is the site in compliance with S.P.C.A. and rules? Yes If no, check violations below:
5. Violations:
6. Is the site in compliance with NPDES Permit NCGO10000 Construction Stormwater requirements? Yes
Describe:
7. Has sedimentation damage occurred since last inspection? No If Yes, where? (check all that apply)
Degree of damage:
8. Contact made with (name): No one Title:
Inspection report: Sent Report Date given/sent: May 26, 2022
9. Corrective action needed:
Permanent ground cover sufficient to restrain erosion has been established. No additional self -monitoring or self -
inspections are required. Project is in compliance and released under the SPCA. Termination of coverage under the NPDES
10. Comments: General Stormwater Permit for Construction Activities (NCG01) must be requested by the permittee via a Notice of
Termination (NOT). The NOT is available at:.https:Hedocs.deg.nc.gov/Forms/NCGOl-Termination. Please note that this
correspondence must be uploaded as part of completing the NOT process.
Reported by: Bradley West Others present:
Date of inspection: May 19, 2022 Time arriving on site: 12:30 PM Time leaving site: 1:30 PM