Loading...
HomeMy WebLinkAbout20020672 Ver 3_Monroe Bypass Comments_20140612Strickland, Bev From: Johnson, Alan Sent: Thursday, June 12, 2014 4:25 PM To: Michael Wood (mwood @thecate nag roup.com); Turchy, Michael A Subject: Monroe Bypass Comments I reviewed the minutes of the past meetings and just need confirmation for the most part. It looks like a lot, but should go quickly (if you can remember). So if you have copies that were handed out at the meeting yesterday, I just followed the same format and you should be able to read the comments that I am referencing. So here it goes: Reply just noting the items not done if that is the case. And just say everything else was done for the remainder. March 14, 2012; 4B for section "small portion of 3A and a 313, 10:30 am: Sheet 68 (W174): The change been done on the plan? Sheet 70/71 (S162, W176, W177): Was this site reviewed? As stated in the comment? Sheet 72 (S169a, S169c, W199, W201): Was the buffer extended to 100 ft? It states a "small portion" of 3A. Was the remainder covered? March 28, 2012; Field review, 10:30 am: Additional wetland (sheet 54 of 56): These changes reflected? Site 302 (sheet 18 of 56): Baffles added? Austin Chaney Rd: This covered at the 413? Again "part of 3A" is stated. Is this the remainder not cover on March 14tH. April 11, 2012; 4B for section 2C, 12:30 pm: Sheet 38 (S76): Polly "sign off' on the use of baffle criteria stated by Ms. Cook? Sheet 49 (S80c): This looked at in the field? (baffles). Decision made? Sheet 48: Is the pond to be drained? Stability of sediment deposition to be consider if it is to be drained. Sheet 48 (P44): Again ponds be drained. Concern with pond sediment being stabilized. Sheet 48 (W101, W102, S92b): Was this looked at in the field as stated in comments? Sheet 50 (PX75, S, 102b): Was this clarified at field visit? Sheet 52 (s103b, W107): Was the 18" RCP made a CAAP? (last sentence) April 11, 2012, 4C "part of " 3A and 313, 9:00 am: 1 NO COMMENT /QUESTION April 11, 2012, 4B for section 3A, 10:30 am: Sheet 57 (S114a, W138): Was the stream looked at in field? Was the length confirmed? Sheet 60 (S145 et al.....): Was this reviewed? The alignment adjusted? (last sentence) April 11, 2012, 4B for 2C and "western" 3A, 10:30 am: Site 257 (sheet 62): was this done? Site 254 (sheet 58 -59): was this done? Site 253 (sheet 57): was this done? Site 212 (sheet 49): Is the pond stable or will be stabilized? Site 210, 211 (sheet 48): was this done one (last sentence) Sheet 43: Was this done? (last sentence) IF ALL this was done, no need to go backward. Thanks Alan