From:Parker, Jerry A
Sent:Tuesday, June 7, 2022 11:02 AM
To:David.E.Bailey2@usace.army.mil
Cc:Conchilla, Ryan; Carpenter,Kristi; dmoore@rkk.com
Subject:RE: \[External\] Request for Additional Information: SAW-2019-00874 (NCDOT / Bridge
267 on Coble Church Road / SR 3336 over Climax Creek / Guilford County / Div 7)
Attachments:Coble Church Rd SWP Survey.pdf; RE: T&E Survey
Follow Up Flag:Follow up
Flag Status:Flagged
Dave,
I have provided answers to Item 1 and 3 in red. I have attached email documents to answer Item 2. Thanks and let me
know if you have any questions.
Jerry
From: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil>
Sent: Thursday, May 26, 2022 10:00 AM
To: Parker, Jerry A <japarker3@ncdot.gov>
Cc: Conchilla, Ryan <ryan.conchilla@ncdenr.gov>; Carpenter,Kristi <kristilynn.carpenter@ncdenr.gov>
Subject: \[External\] Request for Additional Information: SAW-2019-00874 (NCDOT / Bridge 267 on Coble Church Road /
SR 3336 over Climax Creek / Guilford County / Div 7)
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Jerry,
Thank you for your PCN, dated 4/27/2022, for the above referenced project. I have reviewed the information and need
clarification before proceeding with verifying the use of Regional General Permit (RGP) 50 (https://saw-
reg.usace.army.mil/RGP/RGP50.pdf). Please submit the requested information below (via e‐mail is fine) within 30 days
of receipt of this Notification, otherwise we may deny verification of the use of the Nationwide Permit or consider your
application withdrawn and close the file:
1) NCDOT currently proposes no compensatory mitigation for this project. To enable my evaluation, please confirm
whether or not any of the proposed hand clearing of forested wetlands at Sites 2, 4, and/or 5 would be
permanently maintained as herbaceous wetlands following construction (whether due to relocation of utilities
or some other reason). If such activities are proposed, please provide a compensatory mitigation plan to account
for the proposed permanent wetland fill and permanent conversion of forested to herbaceous wetlands. Note
that, unless otherwise justified based on a functional assessment (i.e. NCWAM), appropriate compensatory
mitigation ratios are 2:1 for permanent wetland fill and 1:1 for permanent conversion of forested to herbaceous
wetlands. Note also that a statement of availability letter would also be required for your proposed mitigation
provider. I spoke with the Project Bridge Engineer and was informed that hand clearing of any forested wetlands
1
at Site 2, 4 or 5 would not be permanently maintained as herbaceous wetlands and those areas would be
allowed to transition back to a forested wetland state.
2) Please provide the “T & E survey performed by consultants” referenced in your PCN; See attached documents.
3) At Site 6, the Corps is concerned that proposed toe protection extending through and downslope of the
proposed permanent impact to Stream A may redirect flow away from the continuation of Stream A and instead
into the toe-protected swale along the edge of the roadway. Please provide additional information to
ensure/justify that the flow within the downstream portion of Stream A would be maintained. I was informed by
the Project Bridge Engineer that at the intersection of where Stream A and the toe protection meets (reference
Station Number L-19+ 50 +/-), the stream elevation is lower than the toe protection and therefore water should
not redirect away from the stream. The toe protection detail is described in Detail #3 on the Permit Drawings.
Please let me know if you have any questions.
Sincerely,
Dave Bailey
---
David E. Bailey, PWS
Regulatory Project Manager
US Army Corps of Engineers
CE-SAW-RG-R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Mobile: (919) 817-2436
Office: (919) 554-4884, Ext. 30.
Fax: (919) 562-0421
Email: David.E.Bailey2@usace.army.mil
We would appreciate your feedback on how we are performing our duties. Our automated Customer Service Survey is
located at: https://regulatory.ops.usace.army.mil/customer-service-survey/
Thank you for taking the time to visit this site and complete the survey.
From: NCDOT_REG <NCDOT_REG@usace.army.mil>
Sent: Friday, April 29, 2022 3:54 PM
To: japarker3@ncdot.gov
Cc: Bailey, David E CIV USARMY CESAW (USA) <David.E.Bailey2@usace.army.mil>; Matthews, Monte K CIV USARMY
CESAW (USA) <Monte.K.Matthews@usace.army.mil>
Subject: SAW-2022-00989 (NCDOT / Bridge 267 on Coble Church Road / SR 3336 over Climax Creek / Guilford County /
Div 7)
Good Afternoon,
Your Pre-Construction Notification (PCN) RGP request has been received, assigned action IDSAW-2022-00989 and
forwarded to Dave Bailey for further processing,
Please refer to the action ID in all correspondence.
Thank you,
Josephine Schaffer
2
From: laserfiche@ncdenr.gov <laserfiche@ncdenr.gov>
Sent: Wednesday, April 27, 2022 5:23 PM
To: NCDOT_REG <NCDOT_REG@usace.army.mil>
Cc: SAW-PCN-RG <SAW-PCN-RG@usace.army.mil>
Subject: \[Non-DoD Source\] PCN - Guilford - DOT
A new project has been received on 4/27/2022 5:21 PM for Coble Church Rd Bridge Replacement. The link below will
take you to the project folder.
https://edocs.deq.nc.gov/Laserfiche/index.aspx?db=WaterResources#id=2303172;view=browse
This email was automatically generated by Laserfiche workflow. Please do not respond to this email address, as
responses aren’t monitored.
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.
3