HomeMy WebLinkAboutFW_ 191+00 update
Carpenter,Kristi
From:Vorwerk, Paul J
Sent:Wednesday, June 16, 2021 4:02 PM
To:Johnson, Jay B
Cc:Mcmannen, Brad T; Steffens, Tom; Ward, Garcy; Lane, Heather C; Lane, Stephen;
Horner, Kenneth V
Subject:FW: 191+00 update
Attachments:IMG_0114.jpg; IMG_0115.jpg; IMG_0117.jpg; IMG_0118.jpg
Jay,
Attached are pics from today of the area that was breached by last Fridays storm
near sta 191+00. The contractor fixed this area and has been working on getting
the shoulders ready for seeding, which they hope to have completed by the end of
the week. Seeders have been delayed due to the daily rain showers and are
scheduled to be on site tomorrow to address this and other slopes. Please let me
know if you have any others questions or concerns.
Thanks,
Paul
From: Chapman, Joseph L <jlchapman@ncdot.gov>
Sent: Wednesday, June 16, 2021 12:41 PM
To: Vorwerk, Paul J <pvorwerk@ncdot.gov>
Subject: 191+00 update
Get Outlook for iOS
Email correspondence to and from this sender is subject to the N.C. Public Records Law and may be disclosed to third parties.