[External] NOV-2022-LV-0260 Nature Trail NC0043257
Friday, May 13, 2022 11:26:55 AM
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to Report Spam.
Mr. Zhang,
This email is in response to the aforementioned NOV for exceedance of the NH3 limit 2/28/22. The plant
was beset with issues due to problems with the blowers and the pump station. Both were repaired but the
bio-mass suffered during the disruption. We have worked continuously to bring the facility back into
compliance. We repaired the blowers and the lift station pumps the beginning of March.
At no time we lost any solids or discharged untreated waste into our receiving stream. We could not
sufficiently treat the waste to the degree our permit required.
Please contact me if you have any questions.
Matthew Raynor,
Environmental Director
Matthew Raynor, Director
REE Va. Inc.
524 Meadow Ave. Loop
Banner Elk, NC 28604
919/270-4831 Cell
828/733-5028 Office