Loading...
HomeMy WebLinkAboutDA00517 Precon MinutesSTATE OF NORTH CAROLINA DEPARTMENT OF TRANSPORTATION Roy COOPER GOVERNOR April 11, 2022 Contract: DA00517 WBS No: 1713P.1.R.98 T.I.P. No.: NONE Description: Replacement of Bridge #97 Over Tributary of Meherrin River. Mr. Justin Timmos Dellinger Inc. PO Box 929 Monore, NC 28111 Subject: Preconstruction Conference Minutes Dear Mr. Timmons: J. ERIC BOYETTE SECRETARY A virtual preconstruction conference was held on Monday, April 11, 2022, at 2:00 P.M. Environmental Issues: Kyle Barnes reviewed the Army Corps of Engineers Permit. Garcy Ward reviewed the 401 Water Quality Certification. Andy Blankenship and Paul Williams discussed erosion control issues. The contractor will use a commercial site as the borrow source and a commercial site as the waste site if needed. The contractor should notify the Army Corps of Engineers of any endangered species or historical properties that may be encountered. All equipment shall be kept maintained and care should be taken to avoid contamination of stream waters from fluids, fuels, etc. No staging of equipment of any kind is permitted in waters of the U.S. or protected riparian buffers. The contractor will maintain NPDES inspection records and immediately report any violations to the Engineer, who will notify DWR within 24 hrs. of becoming aware of any violations. The tentative start date is May 2, 2022. The completion date for this project ICT 1 is 120 days from start date but must completed no later than August 31, 2022. Mailing Address: Telephone: (252) 332-4514 Location: NC DEPARTMENT OF TRANSPORTATION Fax: (252) 332-3040 230 NC 42 WEST AHOSKIE DISTRICT OFFICE Customer Service: 1-877-368-4968 AHOSKIE, NC 27910 230 NC 42 WEST AHOSKIE, NC 27910 Website: www.ncdot.gov Direct contact between curing concrete and stream water shall be avoided. Highly visible fencing shall be placed at the outer wetland boundaries before clearing begins, and silt fence should be installed at the toe of slopes. Only coir fiber matting is allowed in riparian areas. The use of matting which contains a nylon mesh grid is prohibited. A turbidity curtain will be required if driving or drilling activities occur within the stream channel, on the stream bank, or within 5 feet of the top of bank. Concrete washout structures will be required on this project. Brooks Braswell discussed contract and plan issues. Contract/Plan Issues: The date of availability for this project is March 16, 2022, and completion date is August 31, 2022. Liquidated damages are $700.00 per calendar day. Brooks discussed the Major and Specialty items in the contract and the base index price for fuel. Final surface testing is not required on this project. Clearing on this project shall be performed to the limits established by Method " I1" shown on Standard Drawing No. 200.02 of the 2018 Roadway Standard Drawings. The monthly estimate has been set on the 15th of each month. Subcontract approval forms, borrow pit and waste site, along with copies of the subcontracts were requested. CUF assessments will be performed on all DBE subcontractors. Contractor was asked to review the "Notes to Contractor" and made aware of coating on caps and cored slabs. This completes the minutes of the Preconstruction Conference for Contract DA00517 held on Monday, April 11, 2022. Any discrepancies with the contents of these minutes should be submitted in writing to this office. Failure to do so will be an indication of agreement. Sincerely, DocuSigned by: SOF861492B234A5... Edwin W. Rose Assistant Resident Engineer cc: Mr. Sterling D. Baker, PE