Messrs. Owen and Evenhouse,
Bailey, David E SAW <David.E.Bailey2 @usace.army.mil>
Monday, May 12, 2014 10:27 AM
Harold Owen; Chad Evenhouse
Homewood, Sue
Request for Additional Information: Haw River Interceptor, Burlington, Alamance Co., NC;
SAW- 2014 -00852 (UNCLASSIFIED)
2014 -00852 Incomplete Tearsheet.pdf
Thanks for your PCN and attached plans, dated and received 4/16/2014, for the above referenced project. I have
reviewed the information and currently the project as described does not fit the terms and conditions of Nationwide
Permit 12 http: / /www,saw.usace.army.mil/ Portals /59 /docs/ regulatory /regdocs /NWP2012 /NWP12 3- 23.pdf. Please
see the attached document (2014 -00852 Incomplete Tearsheet.pdf) and submit the requested information (via e-mail is
fine) within 30 days of receipt of this Notification, otherwise we may deny verification of the use of the Nationwide
Permit or consider your application withdrawn and close the file.
Also, as requested last week, I would like to schedule a field verification of the Jurisdictional resources in the project
corridor.
Please let me know if you have any questions.
Sincerely,
Dave Bailey
David E. Bailey
Project Manager
US Army Corps of Engineers
CE- SAW -RG -R
3331 Heritage Trade Drive, Suite 105
Wake Forest, North Carolina 27587
Phone: (919) 554 -4884, Ext. 30.
Fax: (919) 562 -0421
Email: David.E.Bailey2 @ usace.army.mil
The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we
continue to do so, please complete the Customer Satisfaction Survey located at http : / /regulatory.usacesurvey.com /.
Classification: UNCLASSIFIED
Caveats: NONE
U.S. ARMY CORPS OF ENGINEERS
WILMINGTON DISTRICT
Action Id. SAW- 2014 -00852 County: Alamance U.S.G.S. Quad: Burlington /Mebane
INCOMPLETE APPLICATION
Property Owner: City of Burlington Agent: Kimley -Horn and Associates
attn: Harold Owen attn: Chad Evenhouse
Address: 425 South Lexington Avenue Address: 3001 Weston Parkway
Burlington, N.C. 27215 Cary, N.C. 27513
Location/Description of Proposed Activity: The project is located on the west side of the Haw River between
US 70 Bypass and Riverside Drive in Burlington, Alamance County, North Carolina. Latitude 36.099450 N,
Longitude - 79.379159 W. The applicant has submitted a Preconstruction Notification (PCN) application for 5
total crossings in order to replace existing 42" and 15" gravity sewer lines with 42" and 16" gravity sewer
lines, respectively, resulting cumulatively in 155 linear feet of temporary stream impacts, 0.3273 acre of
temporary riparian, non - riverine wetland impacts, and 0.226 acre of permanent conversion of forested to
herbaceous wetlands.
Type of Permit Applied For (check one): IP ❑ NWP ® GP ❑
Applicable law: Section 404 of the Clean Water Act®; Section 10, Rivers and Harbor Act ❑
YOUR APPLICATION IS INCOMPLETE AND CANNOT BE PROCESSED UNTIL THE FOLLOWING
INFORMATION IS RECEIVED (CHECK ALL THAT APPLY):
❑ Your application form has not been completed and/or signed (see remarks)
❑ Under the conditions of the Nationwide Permit, mitigation is required for your project. The mitigation
proposal submitted with your application is insufficient. (see remarks.)
❑ Your application did not include a statement explaining how avoidance and minimization for losses of
waters of the U.S. were achieved on the project site. (see remarks)
❑ Your submitted project plans or maps were insufficient, too large, or not legible (see remarks).
❑ Your application did not include a delineation of affected special aquatic sites, including wetlands, vegetated
shallows, and riffle and pool complexes as required.
❑ You must submit a copy of your application to the NC Wildlife Resources Commission (WRC) since your
proposed work is in a designated trout water county (see remarks section below for the address of your WRC
representative)
® Other (see remarks below).
"Please reference the PCN submitted by Kimley -Horn and Associates dated and received 4/16/2014.
REMARKS:
1. Your PCN included impacts to wetlands, streams, and open waters, however these jurisdictional boundaries
have not been verified by the USACE. Please schedule a time for an on -site verification with the USACE.
2. According to the plans, rip rap is proposed for Impacts 1 and 4; however this is not mentioned in the PCN.
Please include these impacts as permanent in the PCN (although they would not be considered a loss of
Waters). Also, please explain why rip is not proposed for Impacts 2, 3, and 5.
3. According to the plans, the utility lines are buried for Impacts 4 and 5; however they are not buried for
Impact 1 -3. Please explain how Impact 1 -3 will avoid impeding flow, so as to comply with Nationwide
Permit Condition # 2. Please note that, based on the plans, Impact 3 appears to have the effect of
permanent fill.
4. Per Regional Condition # 4.1.8 please provide a plan to restore and re- vegetate wetland areas cleared for
construction. Note that Fescue grass shall not be used.
5. Please confirm that, in wetlands, the top 6 to 12 inches of the trench will be backfilled with topsoil from the
trench, as required in the Nationwide Permit 12 description.