Loading...
HomeMy WebLinkAbout20170067 Ver 4_2016-01608 NWP 39 Tearsheet - Re-verification_20220511U.S. ARMY CORPS OF ENGINEERS WILMINGTON DISTRICT Action Id. SAW-2016-01608 County: Rockingham U.S.G.S. Quad: NC-Bethany GENERAL PERMIT (REGIONAL AND NATIONWIDE) VERIFICATION Permittee:NTE Carolinas II Attn: Brian Romero Address:24 Cathedral Place, Suite 600 Saint Augustine, FL 32084 Size (acres) ~157.1 Nearest Town Wentworth Nearest Waterway Little Jacobs Creek River Basin Roanoke USGS HUC 03010103 Coordinates 36.333252, -79.833382 Location description: The project is located between NC 65 and New Lebanon Church Road, just west of Ernest Drive, near Reidsville, Rockingham County, North Carolina. Description of projects area and activity: This verification authorizes the permanent discharge of fill material into 0.04 acre (227 linear feet) of stream channel (all a loss of waters of the US from culvert fill) and the temporary discharge of fill material into 0.01 acre (80 linear feet) of stream channel (construction access/dewatering), necessary for the installation of two road crossings for access to a natural gas fired, combine cycle power plant known as the NTE Reidsville Energy Center. Applicable Law(s): ܈Section 404 (Clean Water Act, 33 USC 1344) ܆Section 10 (Rivers and Harbors Act, 33 USC 403) Authorization: NWP 39 (2021) Commercial and Institutional Developments *Reverification of the use of NWP 39, initially issued on 7/28/2017. SEE ATTACHED NWP GENERAL, REGIONAL, AND/OR SPECIAL CONDITIONS Your work is authorized by the above referenced permit provided it is accomplished in strict accordance with the attached Conditions, your application signed and dated 3/28/2022, and the enclosed plans Figure 2 (Facility Layout) and Figure 5 (Culvert Sections), dated 6/7/2017 and 7/19/2017, respectively. Any violation of the attached conditions or deviation from your submitted plans may subject the permittee to a stop work order, a restoration order, a Class I administrative penalty, and/or appropriate legal action. This verification will remain valid until the expiration date identified below unless the nationwide and/or regional general permit authorization is modified, suspended or revoked. If, prior to the expiration date identified below, the nationwide and/or regional general permit authorization is reissued and/or modified, this verification will remain valid until the expiration date identified below, provided it complies with all requirements of the modified nationwide permit. If the nationwide and/or regional general permit authorization expires or is suspended, revoked, or is modified, such that the activity would no longer comply with the terms and conditions of the nationwide permit, activities which have commenced (i.e., are under construction) or are under contract to commence in reliance upon the nationwide and/or regional general permit, will remain authorized provided the activity is completed within twelve months of the date of the nationwide and/or regional general permit’s expiration, modification or revocation, unless discretionary authority has been exercised on a case-by-case basis to modify, suspend or revoke the authorization. Activities subject to Section 404 (as indicated above) may also require an individual Section 401 Water Quality Certification. You should contact the NC Division of Water Resources (telephone 919-807-6300) to determine Section 401 requirements. For activities occurring within the twenty coastal counties subject to regulation under the Coastal Area Management Act (CAMA), prior to beginning work you must contact the N.C. Division of Coastal Management. This Department of the Army verification does not relieve the permittee of the responsibility to obtain any other required Federal, State or local approvals/permits. If there are any questions regarding this verification, any of the conditions of the Permit, or the Corps of Engineers regulatory program, please contact David E. Bailey at (919) 554-4884 X 30 or David.E.Bailey2@usace.army.mil. Corps Regulatory Official: _____________________________________________________Date: 05/11/2022 Expiration Date of Verification: 3/14/2026 Date: 2022.05.11 14:04:45 -04'00' SAW-2016-01608 SPECIAL CONDITIONS 1. In order to compensate for impacts associated with this permit, mitigation shall be provided in accordance with the provisions outlined on the most recent version of the attached Compensatory Mitigation Responsibility Transfer Form. The requirements of this form, including any special conditions listed on this form, are hereby incorporated as special conditions of this permit authorization. 2. Please note that future impacts and/or phases of the NTE Reidsville Energy Center commercial/ industrial development, and related activities associated with Corps Action ID: SAW-2016-01608, may be considered part of a single and complete project; these impacts may be considered cumulative with impacts authorized during earlier phases with respect to compensatory mitigation and Nationwide Permit thresholds. Water intakes and outfall running to and from the Reidsville Energy Center, as well as associated utility lines, are among the activities considered part of the Reidsville Energy Center single and complete project. Current cumulative impacts to waters of the US for the NTE Reidsville Energy Center single and complete project include a total loss of 0.04 acre (227 linear feet) of stream channel/waters of the US. Corps Regulatory Official: ______________ ______ ______ Date: 05/11/2022 Expiration Date of Verification:3/14/2026 The Wilmington District is committed to providing the highest level of support to the public. To help us ensure we continue to do so, please complete the Customer Satisfaction Survey located at https://regulatory.ops.usace.army.mil/customer-service-survey/. Copy furnished: Sue Homewood, NCDEQ-DWR, 450 W. Hanes Mill Rd, Suite 300, Winston Salem NC 27105 Date: 2022.05.11 14:04:24 -04'00' U.S.ARMYCORPSOFENGINEERS WilmingtonDistrict Page1of2FormDateJuly7,2020 CompensatoryMitigationResponsibilityTransferForm  Permittee:NTECarolinasII,Attn:BrianRomero ActionID:SAWͲ2016Ͳ01608 ProjectName:ReidsvilleEnergyCenter/NTECarolinas/4673NC65/Reidsville/RockinghamCountyCounty:Rockingham  InstructionstoPermittee:ThePermitteemustprovideacopyofthisformtotheMitigationSponsor,eitheranapproved MitigationBankortheNorthCarolinaDivisionofMitigationServices(NCDMS),whowillthensigntheformtoverifythe transferofthemitigationresponsibility.OncetheSponsorhassignedthisform,itisthePermittee’sresponsibilitytoensure thatWilmingtonDistrictProjectManageridentifiedonpagetwoisinreceiptofasignedcopyofthisformbeforeconducting authorizedimpacts,unlessotherwisespecifiedbelow.IfmorethanoneMitigationSponsorwillbeusedtoprovidethe mitigationassociatedwiththepermit,oriftheimpactsand/orthemitigationwilloccurinmorethanone8ͲdigitHydrologic UnitCode(HUC),multipleformswillbeattachedtothepermit,andtheseparateformsforeachSponsorand/orHUCmust beprovidedtotheappropriateMitigationSponsors.  InstructionstoSponsor:TheSponsorverifiesthatthemitigationrequirements(credits)shownbelowhavebeenreleased andareavailableattheidentifiedsite.Bysigningbelow,theSponsorisacceptingfullresponsibilityfortheidentified mitigation,regardlessofwhethertheyhavereceivedpaymentfromthePermittee.Oncetheformissigned,theSponsor mustupdatethebankledgerandprovideacopyofthesignedformandtheupdatedledgertothePermittee,theProject Managerwhoissuedthepermit,theBankProjectManager,andtheDistrictMitigationOffice(seecontactinformationon page2).TheSponsormustalsocomplywithallreportingrequirementsestablishedintheirauthorizinginstrument.  PermittedImpactsandCompensatoryMitigationRequirements  PermittedImpactsRequiringMitigation*:8ͲdigitHUCandBasin:03010103,RoanokeRiverBasin StreamImpacts(linearfeet)WetlandImpacts(acres) WarmCoolColdRiparianRiverineRiparianNonͲRiverineNonͲRiparianCoastal 227      *Ifmorethanonemitigationsponsorwillbeusedforthepermit,onlyincludeimpactstobemitigatedbythissponsor.  CompensatoryMitigationRequirements:8ͲdigitHUCandBasin:03010103,RoanokeRiverBasin StreamMitigation(credits)WetlandMitigation(credits) WarmCoolColdRiparianRiverineRiparianNonͲRiverineNonͲRiparianCoastal 454     MitigationSiteDebited:NCDMS (Listthenameofthebanktobedebited.Forumbrellabanks,alsolistthespecificsite.ForNCDMS,listNCDMS.IftheNCDMS acceptanceletteridentifiesaspecificsite,alsolistthespecificsitetobedebited).  SectiontobecompletedbytheMitigationSponsor  StatementofMitigationLiabilityAcceptance:I,theundersigned,verifythatIamauthorizedtoapprovemitigation transactionsfortheMitigationSponsorshownbelow,andIcertifythattheSponsoragreestoacceptfullresponsibilityfor providingthemitigationidentifiedinthisdocument(seethetableabove),associatedwiththeUSACEPermitteeandAction IDnumbershown.Ialsoverifythatreleasedcredits(and/oradvancecreditsforNCDMS),asapprovedbytheWilmington District,arecurrentlyavailableatthemitigationsiteidentifiedabove.Further,IunderstandthatiftheSponsorfailstoprovide therequiredcompensatorymitigation,theUSACEWilmingtonDistrictEngineermaypursuemeasuresagainsttheSponsorto ensurecomplianceassociatedwiththemitigationrequirements.  MitigationSponsorName:  NameofSponsor’sAuthorizedRepresentative:    SignatureofSponsor’sAuthorizedRepresentativeDateofSignature U.S.ARMYCORPSOFENGINEERS WilmingtonDistrict Page2of2 ConditionsforTransferofCompensatoryMitigationCredit: x OncethisdocumenthasbeensignedbytheMitigationSponsorandtheDistrictisinreceiptofthesignedform,the Permitteeisnolongerresponsibleforprovidingthemitigationidentifiedinthisform,thoughthePermitteeremains responsibleforanyothermitigationrequirementsstatedinthepermitconditions. x Constructionwithinjurisdictionalareasauthorizedbythepermitidentifiedonpageoneofthisformcanbeginonlyafter theDistrictisinreceiptofacopyofthisdocumentsignedbytheSponsor,confirmingthattheSponsorhasaccepted responsibilityforprovidingthemitigationrequirementslistedherein.WhenNCDMSprovidesmitigationforauthorized impactsconductedbytheNorthCarolinaDepartmentofTransportation(NCDOT),constructionwithinjurisdictionalareas mayproceeduponpermitissuance;however,acopyofthisformsignedbyNCDMSmustbeprovidedtotheDistrict within30daysofpermitissuance.NCDOTremainsfullyresponsibleforthemitigationuntiltheDistricthasreceivedthis form,confirmingthattheSponsorhasacceptedresponsibilityforprovidingthemitigationrequirementslistedherein. x SignedcopiesofthisdocumentmustberetainedbythePermittee,MitigationSponsor,andintheUSACEadministrative recordsforboththepermitandtheBank/ILFInstrument.ItisthePermittee’sresponsibilitytoensurethattheDistrict ProjectManager(addressbelow)isprovidedwithasignedcopyofthisform. x Ifchangesareproposedtothetype,amount,orlocationofmitigationafterthisformhasbeensignedandreturnedto theDistrict,theSponsormustobtaincaseͲbyͲcaseapprovalfromtheDistrictProjectManagerand/orNorthCarolina InteragencyReviewTeam(NCIRT).Ifapproved,highermitigationratiosmaybeapplied,aspercurrentDistrictguidance andanewversionofthisformmustbecompletedandincludedintheDistrictadministrativerecordsforboththepermit andtheBank/ILFInstrument.  Comments/AdditionalConditions:AletterfromNCDMS,dated3/18/2022,confirmingtheyarewillingandabletoaccept theapplicant’scompensatorymitigationresponsibilitywasprovided.        ThisformisnotvalidunlesssignedbelowbytheDistrictProjectManagerandbytheMitigationSponsoronPage1.Once signed,theSponsorshouldprovidecopiesofthisformalongwithanupdatedbankledgerto:1)thePermittee,2)the DistrictProjectManagerattheaddressbelow,3)theBankManagerlistedinRIBITS,and4)theWilmingtonDistrict MitigationOffice,3331HeritageTradeDrive,Suite105,WakeForest,NC27587(orbyemailtoSAWMIT@usace.army.mil). QuestionsregardingthisformoranyofthepermitconditionsmaybedirectedtotheDistrictMitigationOffice.  USACEProjectManager:DavidE.Bailey USACEFieldOffice:RaleighRegulatoryOffice USArmyCorpsofEngineers 3331HeirtageTadeDrive,Suite105 WakeForest,NorthCarolina27587 Email:David.E.Bailey2@usace.army.mil    May11,2022 WilmingtonDistrictProjectManagerSignatureDateofSignature  CurrentWilmingtonDistrictmitigationguidance,includinginformationonmitigationratios,functionalassessments,and mitigationbanklocationandavailability,andcreditclassifications(includingstreamtemperatureandwetlandgroupings)is availableathttp://ribits.usace.army.mil. Date: 2022.05.11 14:01:49 -04'00' 1?35-?17((QHUJ\?(FR?3&1?)LJXUHV?)LJXUH)DFLOLW\/D\RXW?² FIGURE 2. FACILITY LAYOUT Source: NTE: Mott Macdonald Site Arrangement, 2017. ),*85( July 20, 2017 Page 5 Temporary diversions will be required for culvert installation. The two stream crossing locations are along the plant access road and the switchyard crossing from the power island. See Drawing 334954NR-CSK-101 (Figure 5) sections A and B. Work will be conducted in accordance with NC Department of Environmental Quality (DEQ), NC Department of Transportation (NC DOT), and USACE regulations. The streams will be blocked during construction by use of a temporary impervious dike approximately 20 feet upstream of the entrance to the permanent culvert. A second impervious dike will be located approximately 20 feet down stream of the exit of the permanent culvert. The flow will be diverted to a location beyond the construction zone via a pumped diversion, piped diversion, or fabric lined diversion channel consistent with the attached diagrams from the NC DOT Best Management Practice (BMP) for Construction and Maintenance Activities. Construction will involve resurfacing the stream bed to a suitable foundation for the culvert. Minimal excavation is expected due to a rocky stream bed. The slope of the culvert will match existing grade at approximately 2% grade. No riprap will be installed in the stream bed beyond the exit of the culvert or any other identified areas of high velocity. The culvert will be covered in fill, road bed material and paved. All materials and tools used in construction will be removed after completion. Temporarily disturbed area will be fully restored after construction, see Table 1 for quantities. Table 1 Culvert Location Length (ft) Approximate Width (ft) Temporary Area of Disturbance (ft^2) Total Stream Permanent Culvert Temporary Disturbance UT102 68 28 40 3 120 UT3 229 189 40 7 280 Action ID Number: SAW-2016-01608 County: Rockingham Permittee: NTE Carolinas II (Attn: Brian Romero) Project Name: Reidsville Energy Center / NTE Carolinas / 4673 NC 65 / Reidsville / Rockingham County Date Verification Issued: 05/11/2022 Project Manager: David E. Bailey Upon completion of the activity authorized by this permit and any mitigation required by the permit, sign this certification and return it to the following address: US ARMY CORPS OF ENGINEERS WILMINGTON DISTRICT Attn: David E. Bailey Raleigh Regulatory Office U.S Army Corps of Engineers 3331 Heritage Trade Drive, Suite 105 Wake Forest, North Carolina 27587 or David.E.Bailey2@usace.army.mil Please note that your permitted activity is subject to a compliance inspection by a U. S. Army Corps of Engineers representative. Failure to comply with any terms or conditions of this authorization may result in the Corps suspending, modifying or revoking the authorization and/or issuing a Class I administrative penalty, or initiating other appropriate legal action. I hereby certify that the work authorized by the above referenced permit has been completed in accordance with the terms and condition of the said permit, and required mitigation was completed in accordance with the permit conditions. _______________________________________ ______________________ Signature of Permittee Date SAW-2016-01608 A. Determination of Jurisdiction: 1.܆ There are waters, including wetlands on the above-described project area that may be subject to Section 404 of the Clean Water Act (CWA) (33 USC § 1344) and/or Section 10 of the Rivers and Harbors Act (RHA) (33 USC § 403). This preliminary determination is not an appealable action under the Regulatory Program Administrative Appeal Process (Reference 33 CFR Part 331). However, you may request an approved JD, which is an appealable action, by contacting the Corps district for further instruction. Please note, if work is authorized by either a general or nationwide permit, and you wish to request an appeal of an approved JD, the appeal must be received by the Corps and the appeal process concluded prior to the commencement of any work in waters of the United States and prior to any work that could alter the hydrology of waters of the United States. 2.܆ There are Navigable Waters of the United States within the above-described project area subject to the permit requirements of Section 10 of the Rivers and Harbors Act (RHA) (33 USC § 403) and Section 404 of the Clean Water Act (CWA) (33 USC § 1344). This determination may be relied upon for a period not to exceed five years from the date of this notification, provided there is no change in law or our published regulations or new information that warrants revision of this determination. 3.܆ There are waters, including wetlands within the above-described project area that are subject to the permit requirements of Section 404 of the Clean Water Act (CWA) (33 USC § 1344). This determination may be relied upon for a period not to exceed five years from the date of this notification, provided there is no change in law or our published regulations or new information that warrants revision of this determination. 4. A jurisdiction determination was not completed with this request. Therefore, this is not an appealable action. However, you may request an approved JD, which is an appealable action, by contacting the Corps for further instruction. 5.܈ The jurisdictional areas within the above-described project area have been identified under a previous action. Please reference jurisdictional determination issued 4/28/2017. Action ID: SAW-2016-01608.