HomeMy WebLinkAboutSW6220203_Plansheet C1.1 - Notes_20220225LEGEND
EXISTING DESCRIPTION PROPOSED
-- -- PROPERTY LINE -- --
-- -- ADJACENT PROPERTY LINE -- --
-- -- LOT LINE -- --
RIGHT OF WAY --- ---
CENTERLINE
FLOOD PLAIN - -
LIMITS OF CONSTRUCTION
LIMITS OF DISTURBANCE
SWALE / STREAM FLOWLINE
OVERFLOW RELIEF PATH
FENCE LINE x x x
EASEMENT -----------
EDGE OF PAVEMENT
VERTICAL CURB AND GUTTER
MOUNTABLE CURB AND GUTTER
CONCRETE SIDEWALK
--------------------
ASPHALT SIDEWALK
HANDICAP PARKING
SIGHT TRIANGLE
-o SIGN(S) -w-w- T
25 PARKING COUNT INDICATOR 2s
255 vPo VEHICLES PER DAY INDICATOR 55 VPD
4' TEST PIT Q�
{ MONITORING WELL
-350- - MAJOR CONTOUR 350
-----350-- MINOR CONTOUR 350
GRADE BREAK
<> RIDGELINE <>
f52 F� f5236 F� SPOT ELEVATION f52 FG f5236 F�
RIP RAP 9D
w WATER LINE w
❑"' ® WATER METER ❑"" OM
IM WATER VALVE a 0
WATER REDUCER
J + WATER FITTINGS - J -j- +
FIRE HYDRANT
ss SANITARY LINE ss
►� SANITARY MANHOLE ►�
• SANITARY CLEANOUT •
STORM SEWER PIPE
® STORM SEWER MANHOLE 0
g 0 STORM SEWER INLET g f
STORM SEWER FLARED END SECTION
® STORM SEWER HEADWALL
ou ou OVERHEAD UTILITY ou ou
E E UNDERGROUND ELECTRIC E E
OHE OVERHEAD ELECTRIC 0HE- OHE
UTILITY POLE 0
STREET LIGHT
CATV CAN CABLE TV SERVICE QAT„CAT„
T T TELECOM SERVICE _T-T
Fo Fo FIBER OPTIC SERVICE Fo Fo
G NATURAL GAS SERVICE c
0 TREE0
TREE LINE
�Ic WETLANDS
LEGEND NOTES
1. THIS IS A STANDARD SHEET, THEREFORE SOME ABBREVIATIONS MAY APPEAR ON THIS SHEET AND
NOT BE USED ON THE PROJECT.
2. ADDITIONAL LEGENDS AND NOTES MAY BE FOUND ON OTHER SHEETS ASSOCIATED WITH THIS PLAN.
THESE LEGENDS AND NOTES ARE TO BE REFERENCED IN ADDITION TO THIS STANDARD SHEET.
ABBREVIATIONS
A AREA OF ARC
AASHTO AMERICAN ASSOCIATION OF STATE HWY &
TRANS. OFFICIALS
AB AS BUILT
AC ACRE
AD ALGEBRAIC DIFFERENCE IN GRADE
AE ACCESS EASEMENT
ADJ ADJACENT
AGGR AGGREGATE
AHD AHEAD
ANSI AMERICAN NATIONAL STANDARDS INSTITUTE
ANGLE POINT
APT APPROXIMATE
APPROX ARCHITECTURAL
ARCH ASPHALT
ASPH AMERICAN SOCIETY FOR TESTING AND
ASTM MATERIALS
AMERICAN WATER WORKS ASSOCIATION
AWWA
BREADTH
B BACK OF CURB
BOC BASEMENT FLOOR
BF BUILDING
BLDG BENCHMARK
BM BEST MANAGEMENT PRACTICES
BMP (WATER QUALITY)
BLOW OFF VALVE
BOV BEARING
BRG BUILDING RESTRICTION LINE
BRL BEGINNING VERTICAL CURVE ELEVATION
BVCE BEGINNING VERTICAL CURVE STATION
BVCS BOTTOM OF WALL
BW
CENTER CORRECTION ON VERTICAL CURVE
c,e RUNOFF COEFFICIENT
C CABLE TELEVISION
CATV CURB AND GUTTER
C&G CATCH BASIN
CB CALIFORNIA BEARING RATIO
CBR CENTER TO CENTER
CC COLORADO DEPT. OF TRANSPORTATION
CDOT CUBIC FEET
CF CUBIC FEET PER SECOND
CFS CURB AND GUTTER (REVERSE SLOPE)
CG(R) CHORD
CH CHORD BEARING
CHBRG CAST IRON PIPE
CIP CENTERLINE
CL CLEAR
CLR CUBIC METERS
CM CORRUGATED METAL PIPE
CMP CUBIC METERS PER SECOND
CMS RUNOFF CURVE NUMBER
CN CONTINUOUS
CONT CLEAN OUT
CO CONCRETE
CONC CURB STOP
CS COURT
CT CENTER
CTR CONTROL LINE
CTRL CUBIC YARD
CY
DEPTH
D DRAINAGE AREA
DA DEED BOOK
DB DIVERSION DIKE
DID DETAIL
DET DIAMETER
DIA DUCTILE IRON PIPE
DIP DROP INLET
DI DISTANCE
DIST DOMESTIC LINE
DL DROP MANHOLE
DM DOMESTIC
DOM DRIVE DRAIN
DR DRAINAGE
DRN DRAINAGE AREA
DRNG DOWN SPOUT
DS DWELLING UNITS
DU DRAWING
DWG DRIVEWAY
D/W DELTA
A
EASTING/EAST
E EACH
EA EAST BOUND LANE
EBL EROSION CONTROL
EC EROSION CONTROL BLANKET
ECB EDGE OF GUTTER
EG ENERGY GRADIENT LINE
EGL ELEVATION
EL ELECTRIC
ELEC ELEVATION
ELEV ENGINEER
ENGR ENTRANCE
ENT EDGE OF ASPHALT
EOA EDGE OF CONCRETE
EOC EDGE OF PAVEMENT
EOP EQUIPMENT
EQUIP EASEMENT
ESMT EXISTING TO BE DEMOLISHED
ETD EXISTING TO REMAIN
ETR EXISTING TO BE RELOCATED
ETRL EXISTING TO BE REPLACED
ETRP ENDING VERTICAL CURVE ELEVATION
EVCE ENDING VERTICAL CURVE STATION
EVCS END WALL
EW EXISTING
EX ENVIRONMENTAL QUALITY CORRIDOR
EQC
FIRE LINE
F FLOOR AREA RATIO
FAR FACE OF CURB
FOC FLOOR DRAIN
FD FLARED END SECTION
FES FIRST FLOOR OR FINISH FLOOR
FF FINISH GRADE
FG FIRE HYDRANT
FH FLOW LINE
FL FOUNDATION
FND FOYER
FOY FLOOD PLAIN
FP FEET PER SECOND
FPS FIRE SERVICE OR FACTOR OF SAFETY
FS FOOT OR FEET
FT
GAS
G GARAGE
GAR GRADE BREAK
GB GROSS FLOOR AREA
GFA GUARD RAIL OR GRATE INLET
GR GATE VALVE
GV
HEAD
H HANDICAP
HC HORIZONTAL BEND
HB HOT BITUMINOUS PAVEMENT
HBP HYDRAULIC GRADE LINE
HGL HORIZONTAL
HORZ HIGH POINT
HP HAND RAIL
HR HEIGHT
HT HEADWATER
HW
RAINFALL INTENSITY
I INSIDE DIAMETER OR IDENTIFICATION
ID INVERT ELEVATION
IE INCH
IN INVERT
INV IRON PIPE
IP IRON PIPE FOUND
IPF IRON PIPE SET
IPS IRRIGATION
IRR
JUNCTION BOX
JB JOINT
JN T
K SIGHT DISTANCE COEFFICIENT OR
RATE OF VERTICAL CURVATURE
Ke CULVERT ENTRANCE LOSS COEFFICIENT
L LENGTH
LAT LATERAL
LCG LIMITS OF CLEARING & GRADING
LF LINEAR FEET
LIP LIP OF PAN
LL LOWER LEVEL
LOS LINE OF SIGHT
LP LOW POINT
LS LOADING SPACE
LT LEFT
M MONUMENT FOUND
MAX MAXIMUM
ME MATCH EXISTING
MECH MECHANICAL
MH MANHOLE
MI MILE
MIN MINIMUM
MISC MISCELLANEOUS
MPH MILES PER HOUR
MS MEDIAN STRIP
MSL MEAN SEA LEVEL
N NORTHING/NORTH
N/A NOT APPLICABLE
NBL NORTH BOUND LANE
N/F NOW OR FORMERLY
NFA NET FLOOR AREA
NO. & # NUMBER
NTS NOT TO SCALE
OC ON CENTER
OBJ OBJECT
OD OUTSIDE DIAMETER
OH OVERHANG
O/H OVERHEAD
OHC OVERHEAD CABLE
OHE OVERHEAD ELECTRIC
OHT OVERHEAD TELEPHONE
P PERIMETER
R PROPERTY LINE
P&P PLAN AND PROFILE
PC POINT OF CURVATURE
PCC POINT OF COMPOUND CURVATURE
PCR POINT OF CURB RETURN
PCEP POINT OF CURVE EDGE OF PAVEMENT
PCTC POINT OF CURVATURE TOP OF CURB
PI POINT OF INTERSECTION
PG PAGE
PGL POINT OF GRADE LINE
PRC POINT OF REVERSE CURVATURE
PRELIM PRELIMINARY
PROP PROPOSED
PT POINT OF TANGENCY
PUE PUBLIC UTILITY EASEMENT
PVC POLYVINYL CHLORIDE PIPE OR
POINT OF VERTICAL CURVATURE
PVI POINT OF VERTICAL INTERSECTION
PVT POINT OF VERTICAL TANGENCY
PVMT PAVEMENT
PVRC POINT OF VERTICAL REVERSE CURVE
Q (cfs) AMOUNT OF RUNOFF (FLOW RATE)
R RADIUS
RCP REINFORCED CONCRETE PIPE
RDCR REDUCER
RD ROAD OR ROOF DRAIN
REINF REINFORCED
REQD REQUIRED
RET RETAINING
REV REVISION
RGP ROUGH GRADING PLAN
RMA RESOURCE MANAGEMENT AREA
ROM REMOTE OUTSIDE MONITOR
RPA RESOURCE PROTECTION AREA
RR RAILROAD
RT RIGHT
RTE ROUTE
R/W & ROW RIGHT OF WAY
S SPEED OR SLOPE
SAN SANITARY SEWER
SANMH SANITARY SEWER MANHOLE
SBL SOUTH BOUND LANE
SCH SCHEDULE
SD SIGHT DISTANCE
SEC SECTION
SEW SEWER
SF SQUARE FEET
SH SHOULDER
SP SPACE OR SITE PLAN
SPEC SPECIFICATIONS
STA STATION
STD STANDARD
STK STACK
STM STORM SEWER
STMMH STORM SEWER MANHOLE
STIR STRUCTURE
SVC SERVICE
S/W SIDEWALK
SWM STORM WATER MANAGEMENT
Sx CROSS SLOPE
SY SQUARE YARD
T TANGENT
TB TOP OF BANK OR TEST BORING
TBR TO BE REMOVED
TOC TOP OF CURB
Tc TIME OF CONCENTRATION
TEL TELEPHONE
TEMP TEMPORARY
TH TEST HOLE
TOF TOP OF FOUNDATION
TOP TOP OF PIPE
TIP TEST PIT OR TREE PROTECTION
TW TOP OF WALL OR TAILWATER
TYP TYPICAL
UE UTILITY EASEMENT
UG UNDERGROUND
UGE UNDERGROUND ELECTRIC
UGT UNDERGROUND TELEPHONE
UGC UNDERGROUND CABLE
UD UNDERDRAIN
UL UPPER LEVEL
UP UTILITY POLE
USGS US GEOLOGICAL SURVEY
UTIL UTILITY
V OR VOL VOLUME
V OR VEL VELOCITY
VAN HANDICAPPED VAN PARKING SPACE
VB VERTICAL BEND
VC VERTICAL CURVE
VF VERTICAL FOOT
W WEIGHT OR WIDTH
WBL WEST BOUND LANE
WL WATER LINE
WM WATER METER
W/M OR WM WATER MAIN
W/TB WITH THRUST BLOCK
WSEL WATER SURFACE ELEVATION
WV WATER VALVE
XING CROSSING
XF TRANSFORMER
I YARD INLET
YR YEAR
GENERAL NOTES
GENERAL NOTES (CONT.
1.
UTILITY CONFLICTS: ALL EXISTING UTILITIES SHOWN WERE COMPILED USING THE BEST AVAILABLE INFORMATION AND FIELD OBSERVATION. BOWMAN
CONSULTING INC. DOES NOT GUARANTEE THE LOCATION OF UNDERGROUND UTILITIES SHOWN HEREON. CONTRACTOR TO BE RESPONSIBLE FOR FIELD
41.
THE CONTRACTOR SHALL CAREFULLY EXAMINE THE SITE AND MAKE ALL INSPECTIONS NECESSARY IN ORDER TO DETERMINE THE FULL EXTENT OF THE
VERIFYING THE LOCATION OF AND PROTECTING ALL EXISTING UTILITIES, INCLUDING THOSE NOT SHOWN OR SHOWN INCORRECTLY ON THE PLANS. ANY
WORK REQUIRED TO MAKE THE PROPOSED WORK CONFORM TO THE DRAWINGS AND SPECIFICATIONS. THE CONTRACTOR SHALL SATISFY HIMSELF AS TO
DAMAGE TO EXISTING UTILITIES SHALL BE REPAIRED IN A TIMELY FASHION TO THE SATISFACTION OF THE APPROPRIATE GOVERNING AGENCY AND THE
THE NATURE AND LOCATION OF THE WORK, CONDITIONS, AND CONFIRMATION AND CONDITION OF EXISTING GROUND SURFACE AND THE CHARACTER OF
OWNER OF THE IMPACTED UTILITY AT THE CONTRACTOR'S EXPENSE.
THE EQUIPMENT AND FACILITIES NEEDED PRIOR TO AND DURING EXECUTION OF THE WORK. THE CONTRACTOR SHALL SATISFY HIMSELF AS TO THE
CHARACTER, QUANTITY AND QUALITY OF SURFACE AND SUBSURFACE MATERIALS OR OBSTACLES TO BE ENCOUNTERED. ANY INACCURACIES OR
2.
ALL MATERIALS AND WORKMANSHIP SHALL BE IN CONFORMANCE WITH THE LATEST STANDARDS AND SPECIFICATIONS FOR THE APPROPRIATE
DISCREPANCIES BETWEEN THE DRAWINGS AND SPECIFICATIONS MUST BE BOUGHT TO THE OWNER'S ATTENTION IN ORDER TO CLARIFY THE EXACT
GOVERNING AGENCY. THE CONTRACTOR SHALL HAVE IN HIS POSSESSION AT THE JOB SITE AT ALL TIMES THE APPROPRIATE GOVERNING AGENCY'S
NATURE OF THE WORK TO BE PERFORMED PRIOR TO THE COMMENCEMENT OF ANY WORK.
PUBLIC WORKS MANUAL, ALL APPROVED EASEMENT AGREEMENTS, AND ONE (1) SIGNED COPY OF THE PLANS AS APPROVED BY THE APPROPRIATE
GOVERNING AGENCY. THE CONTRACTOR SHALL OBTAIN WRITTEN APPROVAL FROM THE APPROPRIATE GOVERNING AGENCY FOR ANY VARIANCE TO THE
42.
THE CONTRACTOR WILL BE RESPONSIBLE FOR ANY DAMAGE TO THE EXISTING ROADS AND UTILITIES WHICH OCCURS AS A RESULT OF THE PROJECT
ABOVE DOCUMENTS.
CONSTRUCTION WITHIN OR CONTIGUOUS TO THE EXISTING RIGHT-OF-WAY.
3.
CONTRACTOR SHALL OBTAIN, AT HIS OWN EXPENSE, ALL APPLICABLE CODES, LICENSES, STANDARDS, SPECIFICATIONS, PERMITS, BONDS, ETC., WHICH
43.
ALL STREET CUT AND PATCH WORK IN PUBLIC RIGHT-OF-WAY REQUIRED FOR UTILITIES INSTALLATION SHALL BE PERFORMED IN STRICT ACCORDANCE
ARE NECESSARY TO PERFORM THE PROPOSED WORK.
WITH CITY, COUNTY, AND/OR APPROPRIATE GOVERNING AGENCY STANDARDS AND SPECIFICATIONS.
4.
THE CONTRACTOR SHALL BE SOLELY AND COMPLETELY RESPONSIBLE FOR CONDITIONS AT AND ADJACENT TO THE JOB SITE INCLUDING THE SAFETY
44.
THE APPROVAL OF THIS PLAN SHALL IN NO WAY GRANT PERMISSION FOR THE CONTRACTOR TO TRESPASS ON OFF -SITE PROPERTIES.
OF ALL PERSONS AND PROPERTY DURING PERFORMANCE OF THE WORK. THIS REQUIREMENT SHALL APPLY CONTINUOUSLY AND NOT BE LIMITED TO
NORMAL WORKING HOURS AND MUST COMPLY WITH OSHA REGULATIONS.
45.
THE APPROVAL OF THESE PLANS SHALL IN NO WAY RELIEVE THE CONTRACTOR OF COMPLYING WITH OTHER APPLICABLE LOCAL, STATE, AND FEDERAL
REQUIREMENTS.
5.
IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO NOTIFY THE OWNER/DEVELOPER AND ENGINEER OF ANY PROBLEM CONFORMING TO THE
APPROVED PLANS FOR ANY ELEMENT OF THE PROPOSED IMPROVEMENTS PRIOR TO ITS CONSTRUCTION.
46.
THESE PLANS MAKE NO REPRESENTATION AS TO THE SUBSURFACE CONDITIONS AND THE PRESENCE OF SUBSURFACE WATER OR THE NEED FOR
SUBSURFACE DRAINAGE FACILITIES.
6.
THE CONTRACTOR SHALL REPAIR ANY EXCAVATIONS OR PAVEMENT FAILURES CAUSED BY HIS/HER CONSTRUCTION.
47.
THE CONTRACTOR IS RESPONSIBLE FOR ARRANGING ALL NECESSARY INSPECTIONS.
7.
THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REMOVAL AND REPLACEMENT OF ALL MATERIALS WITHIN DEDICATED RIGHT-OF-WAY AND ALL
MATERIALS AND WORKMANSHIP SHALL MEET THE ROADWAY DESIGN AND CONSTRUCTION STANDARDS OF THE APPROPRIATE GOVERNING AGENCY.
48.
EMERGENCY VEHICLE ACCESS SHALL BE MAINTAINED DURING ALL PHASES OF CONSTRUCTION.
8.
THE CONTRACTOR SHALL NOTIFY THE LOCAL JURISDICTION AT LEAST 24 HOURS PRIOR TO THE START OF CONSTRUCTION. THE APPROPRIATE FIRE
49.
ALL FINISHED GRADING, SEEDING, SODDING OR PAVING SHALL BE DONE IN SUCH A MANNER TO PRECLUDE THE PONDING OF WATER.
DEPARTMENT SHALL BE NOTIFIED AT LEAST 48 HOURS IN ADVANCE OF ANY STREET CLOSURES AND IN THE EVENT THAT ANY FIRE HYDRANTS ARE
TO BE TEMPORARILY REMOVED FROM SERVICE. THE CONTRACTOR SHALL ALSO BE RESPONSIBLE FOR PROVIDING AT LEAST 48 HOURS ADVANCED
50.
THE ENGINEER SHALL NOT HAVE CONTROL OVER OR CHARGE OF AND SHALL NOT BE RESPONSIBLE FOR CONSTRUCTION MEANS, METHODS,
NOTICE OF ANY NEED TO SHUT DOWN ANY PORTION OF THE EXISTING WATER SYSTEM AND FOR OBSERVATIONS AND/OR INSPECTIONS REQUIRED.
TECHNIQUES, SEQUENCES OR PROCEDURES OR FOR SAFETY PRECAUTIONS AND PROGRAMS IN CONNECTION WITH THE WORK SHOWN ON THESE PLANS.
THE ENGINEER SHALL NOT BE RESPONSIBLE FOR THE CONTRACTOR'S SCHEDULES OR FAILURE TO CARRY OUT THE WORK. THE ENGINEER IS NOT
9.
THE CONTRACTOR SHALL PROVIDE ALL SIGNS, BARRICADES, FLAGMEN, LIGHTS OR OTHER DEVICES NECESSARY FOR SAFE TRAFFIC CONTROL IN
RESPONSIBLE FOR ACTS OR OMISSIONS OF THE CONTRACTOR, SUBCONTRACTORS, OR THEIR AGENTS OR EMPLOYEES, OR OF ANY OTHER PERSONS
ACCORDANCE WITH THE CURRENT EDITION OF THE MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES AND AS MODIFIED BY THE COLORADO
PERFORMING PORTIONS OF THE WORK.
SUPPLEMENT TO THE MUTCD. A TRAFFIC CONTROL PLAN SHALL BE SUBMITTED TO AND APPROVED BY THE APPROPRIATE GOVERNING AGENCY PRIOR
TO THE ISSUANCE OF ANY CONSTRUCTION PERMIT FOR WORK WITHIN THE RIGHT-OF-WAY.
51.
CONTRACTOR SHALL BE RESPONSIBLE FOR THE DIGGING OF TEST HOLES PRIOR TO BEGINNING OF ANY CONSTRUCTION ON THE PROJECT. IF CONFLICTS
ARE DISCOVERED AS A RESULT OF TEST HOLE FINDINGS, NOTIFY OWNER'S REPRESENTATIVE IMMEDIATELY.
10.
THE CONTRACTOR SHALL CONTACT THE UTILITY NOTIFICATION CENTER OF COLORADO AT 1-800-922-1987 AT LEAST 2 BUSINESS DAYS PRIOR TO
CONSTRUCTION. THE CONTRACTOR SHALL COORDINATE ALL CONSTRUCTION ACTIVITIES WITH ANY AFFECTED UTILITY COMPANY.
52.
EXCAVATION SUPPORT SYSTEMS SHALL CONFORM TO THE PROVISIONS OF OSHA CONSTRUCTION STANDARD 29 CFR PART 1926 SUBPART P, OR
CURRENT EDITION.
11.
THE CONTRACTOR SHALL OBTAIN COPIES OF THE "SOILS AND INVESTIGATION" REPORT FROM GEOTECHNICAL ENGINEER ALONG WITH THE "PAVEMENT
THICKNESS DESIGN REPORT". THE CONTRACTOR MUST HAVE COPIES OF SAME ON THE SITE AT ALL TIMES.
53.
AT LOCATIONS WHERE THE FINAL SURFACE COURSE OF ASPHALT PAVEMENT IS TO BE FEATHERED INTO THE EXISTING SURFACE COURSE, THE
EXISTING SURFACE COURSE IS TO BE SCABBLED TO A MINIMUM DEPTH OF 1" AND A TACK COAT APPLIED PRIOR TO FINAL PAVING TO INSURE A
12.
THE CONTRACTOR IS REQUIRED TO PROVIDE AS -CONSTRUCTED HORIZONTAL AND VERTICAL CONSTRUCTION INFORMATION, INCLUDING THE LOCATIONS
SMOOTH, WELL BONDED JOINT.
OF ALL SANITARY LINES AND SERVICES, WATER LINES AND SERVICES, AND OTHER UTILITY LINES AND SERVICES TO THE ENGINEER FOR PREPARATION
OF AS -BUILT DOCUMENTS.
54.
ANY NEW PAVEMENT OPENED TO TRAFFIC SHALL RECEIVE A TACK COAT PRIOR TO PLACEMENT OF ANY OVERLYING ASPHALT COURSE.
13.
LIMITS OF CONSTRUCTION EASEMENTS AND RIGHTS -OF -WAY SHALL BE DELINEATED WITH TEMPORARY STAKING BY THE CONTRACTOR. SAFETY FENCING
55.
ALL SIDEWALKS TO BE 4" THICK CONCRETE UNLESS OTHERWISE SHOWN ON THE PLAN.
SHALL BE PER APPROPRIATE GOVERNING AGENCY.
56.
ALL DEMOLITION SHALL BE PERFORMED IN STRICT COMPLIANCE WITH THE APPROPRIATE GOVERNING AGENCY.
14.
WHERE EXCAVATION IS REQUIRED UNDER EXISTING ASPHALT OR CONCRETE PAVEMENT, THE EXISTING PAVEMENT SHALL BE SAW CUT IN A MANNER TO
EFFECT A SMOOTH, STRAIGHT -CUT EDGE. ASPHALT PATCH SHALL BE PER APPROPRIATE GOVERNING AGENCY STANDARDS.
57.
ALL APPLICABLE EROSION AND SEDIMENT CONTROL MEASURES SHALL BE INSTALLED PRIOR TO COMMENCING DEMOLITION.
15.
REFER TO FINAL RECORDED PLAT FOR ACTUAL LOT, TRACT, PARCEL, AND EASEMENT LOCATIONS AND DESIGNATIONS.
58.
ITEMS SHOWN TO BE RELOCATED SHALL BE CAREFULLY REMOVED AND STORED BY THE CONTRACTOR UNTIL SUCH TIME AS THEY CAN BE PLACED IN
THEIR NEW LOCATION. CONTRACTOR SHALL VERIFY THESE ITEMS WITH THE OWNER, PRIOR TO CONSTRUCTION.
16.
THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE REMOVAL AND REPLACEMENT OF ALL MATERIALS WITHIN DEDICATED RIGHT-OF-WAYS AND ALL
MATERIALS AND WORKMANSHIP SHALL MEET THE ROADWAY DESIGN AND CONSTRUCTION STANDARDS OF THE APPROPRIATE GOVERNING AGENCY.
59.
CONTRACTOR SHALL COORDINATE REMOVAL OR RELOCATION OF ALL EXISTING UNDERGROUND AND OVERHEAD ELECTRICAL, TELEPHONE AND CABLE TV
LINES AND REMOVAL OF UTILITY POLES, PEDESTALS AND TRANSFORMERS WITH UTILITY COMPANIES AND WITH DEVELOPER PRIOR TO DEMOLITION.
17.
THE CONTRACTOR SHALL PROTECT ALL ADJACENT PROPERTY TO THE PROJECT WORK SITE (SEE THE EROSION CONTROL PLAN). THE CONTRACTOR
SHALL OBTAIN ALL PERMITS NECESSARY (IF APPLICABLE) TO COMPLETE THE CONSTRUCTION AND SHALL COMPLY WITH ALL LOCAL, STATE AND
60.
CONTRACTOR SHALL BE RESPONSIBLE FOR ADJUSTMENTS AND/OR RECONSTRUCTION OF ALL UTILITY COVER (MANHOLE FRAMES AND COVERS, VALVE
FEDERAL REGULATIONS.
BOX COVERS, ETC.) TO MATCH THE FINISHED GRADES OF THE AREAS EFFECTED BY THE CONSTRUCTION.
18.
WATER WILL BE PROVIDED BY THE CONTRACTOR TO KEEP WIND EROSION IN CHECK. USE OF WATER AS A DUST PREVENTATIVE SHALL NOT BE PAID
61.
THE CONTRACTOR MUST HAVE THE APPROVED CONSTRUCTION DRAWINGS IN POSSESSION PRIOR TO THE START OF CONSTRUCTION. AT LEAST ONE (1)
FOR SEPARATELY, BUT INCLUDED IN THE COST OF THE WORK.
COPY OF THE APPROVED PLANS, WITH REVISIONS, MUST BE KEPT ON -SITE AT ALL TIMES.
19.
ANY SETTLEMENT OR SOIL ACCUMULATIONS BEYOND THE PROPERTY LIMITS DUE TO GRADING OR EROSION SHALL BE REPAIRED IMMEDIATELY BY THE
62.
ALL HANDICAP RAMPS SHALL BE BUILT IN ACCORDANCE WITH THE MOST CURRENT EDITION OF THE APPROPRIATE GOVERNING AGENCY STANDARDS,
CONTRACTOR.
CDOT STANDARDS, AND CURRENT ADA REQUIREMENTS.
20.
ANY CONSTRUCTION DEBRIS OR MUD TRACKING IN THE PUBLIC RIGHT-OF-WAY RESULTING FROM THIS DEVELOPMENT SHALL BE REMOVED IMMEDIATELY
63.
THE STORM DRAIN, STORMWATER MANAGEMENT AND WATER QUALITY FACILITIES MUST BE MAINTAINED BY THE CONTRACTOR UNTIL SUCH TIME AS
BY THE CONTRACTOR. THE CONTRACTOR SHALL IMMEDIATELY FIX ANY EXCAVATIONS OR PAVEMENT FAILURES CAUSED BY THE DEVELOPMENT AND
THEY ARE NOT ONLY 100% COMPLETE , BUT ALSO THAT 100% OF THE DRAINAGE AREA TO EACH FACILITY IS PERMANENTLY STABILIZED. SEED AND
SHALL PROPERLY BARRICADE THE SITE UNTIL CLEAN UP OR REPAIR IS COMPLETE.
MULCH DOES NOT CONSTITUTE STABILIZATION IN TERMS OF THE CONTRACTOR MAINTENANCE OF THE STORM DRAIN STORMWATER MANAGEMENT AND
WATER QUALITY FACILITIES. ALL STORM DRAIN, STORMWATER MANAGEMENT AND WATER QUALITY FACILITIES SHALL BE TURNED OVER TO THE OWNER
21.
IT WILL BE THE CONTRACTOR'S RESPONSIBILITY TO GRADE STREET CORES, RIGHT-OF-WAY TEMPLATES, AND LOTS ACCORDING TO GRADING
COMPLETELY CLEAN AND FREE FROM ANY CONSTRUCTION RELATED SEDIMENT OR DEBRIS.
INSTRUCTIONS SHOWN ON PLANS.
64.
THE CONTRACTOR IS RESPONSIBLE FOR INSURING THAT ALL ADA ACCESSIBLE SIDEWALKS MAINTAIN SLOPES NOT TO EXCEED 5% LONGITUDINALLY AND
22.
STREET CONTOURS SHOWN AT PROPOSED STREET LOCATIONS REPRESENT FINISHED GRADE ELEVATION TO TOP OF ASPHALT.
2% CROSS SLOPES. SLOPES AT ACCESSIBLE PARKING SPACES AND ACCESS AISLE SHALL BE A MAXIMUM OF 2%, AND THE MANEUVERING CLEARANCE
AT EXTERIOR ENTRANCES SHALL HAVE A MAXIMUM SLOPE OF 2%.
23.
COMPACTION FILL MATERIAL SHALL BE COMPACTED ACCORDING TO THE APPROPRIATE GOVERNING AGENCY REGULATIONS AND THE RECOMMENDATIONS
OF THE GEOTECHNICAL ENGINEER.
65.
DURING CONSTRUCTION, NO TEMPORARY CONNECTIONS TO FIRE HYDRANTS MAY BE MADE WITHOUT THE EXPRESS AUTHORIZATION OF THE UTILITY
OWNER.
24.
TOLERANCE ROUGH GRADING: TOLERANCE SHALL BE +/- 0.1 FEET.
25.
IT IS THE CONTRACTOR'S RESPONSIBILITY TO MAKE SURE ALL APPROPRIATE PERMITS FOR STORM WATER DISCHARGES ASSOCIATED WITH
CONSTRUCTION ACTIVITY HAVE BEEN OBTAINED PRIOR TO GRADING. CONTRACTOR SHALL BE RESPONSIBLE FOR THE INSTALLATION OF ALL TEMPORARY
WATER DIVERSION/CONTROL DEVICES AND EROSION CONTROL DEVICES NECESSARY TO PROTECT ADJACENT PROPERTIES, WATERWAYS AND PUBLIC
RIGHT-OF-WAY. CONTRACTOR IS RESPONSIBLE FOR THE MAINTENANCE OF SAID DEVICES THROUGHOUT CONSTRUCTION AND UNTIL THE PERMANENT
GENERAL EROSION CONTROL NOTES
PROTECTION NECESSARY HAS BEEN COMPLETED.
1.
THE CONTRACTOR SHALL REMOVE ALL SEDIMENT, MUD AND CONSTRUCTION DEBRIS THAT MAY ACCUMULATE IN THE FLOWLINES AND PUBLIC
26.
IT IS THE CONTRACTOR'S RESPONSIBILITY TO OBTAIN THE MOST CURRENT APPROVED ARCHITECTURAL/
RIGHTS -OF -WAY OF THE APPROPRIATE GOVERNING AGENCY AS A RESULT OF THIS CONSTRUCTION PROJECT. SAID REMOVAL SHALL BE CONDUCTED IN
MECHANICAL/ELECTRICAL/PLUMBING/STRUCTURAL PLANS AND COORDINATE SAME WITH THE SITE PLAN, PRIOR TO BEGINNING CONSTRUCTION
A TIMELY MANNER.
OPERATIONS.
2.
THE CONTRACTOR SHALL PREVENT SEDIMENT, DEBRIS AND ALL OTHER POLLUTANTS FROM ENTERING THE STORM SEWER SYSTEM DURING ALL
27.
WHEN DURING THE COURSE OF CONSTRUCTION, ANY OBJECT OF AN UNUSUAL NATURE IS ENCOUNTERED, THE CONTRACTOR SHALL CEASE WORK IN
DEMOLITION AND CONSTRUCTION OPERATIONS THAT ARE A PART OF THIS PROJECT. THE CONTRACTOR SHALL BE HELD RESPONSIBLE FOR REMEDIATION
THAT AREA AND IMMEDIATELY NOTIFY THE OWNER, APPROPRIATE GOVERNING AGENCY, AND/OR THE ARCHITECT/ENGINEER.
OF ANY ADVERSE IMPACTS TO ADJACENT WATERWAYS, WETLANDS, ETC., RESULTING FROM WORK DONE AS A PART OF THIS PROJECT.
28.
THE EXISTING UNDERGROUND UTILITIES SHOW HEREON ARE BASED UPON AVAILABLE INFORMATION. THE CONTRACTOR SHALL BE RESPONSIBLE FOR
3.
ALL DISTURBED AREAS MUST BE HYDRO -MULCHED W/ TACKIFIER AFTER FINAL GRADE IS REACHED ON ANY PORTION OF THE SITE NOT OTHERWISE
DETERMINING THE EXACT LOCATION OF ALL UTILITIES BEFORE COMMENCING WORK AND FOR ANY DAMAGES WHICH OCCUR BY HIS FAILURE TO LOCATE
PERMANENTLY STABILIZED.
OR PRESERVE THESE UNDERGROUND UTILITIES. IF DURING CONSTRUCTION OPERATIONS THE CONTRACTOR SHOULD ENCOUNTER UTILITIES OTHER THAN
IN THOSE SHOWN ON THE PLANS, HE SHALL IMMEDIATELY NOTIFY THE ENGINEER AND TAKE NECESSARY AND PROPER STEPS TO PROTECT THE
4.
THE CONTRACTOR SHALL INSURE THAT ALL LOADS OF CUT AND FILL MATERIAL IMPORTED TO OR EXPORTED FROM THIS SITE SHALL BE PROPERLY
FACILITY AND ASSURE THE CONTINUANCE OF SERVICE.
COVERED TO PREVENT LOSS OF THE MATERIAL DURING TRANSPORT ON PUBLIC RIGHTS -OF -WAY.
29.
ALL STEPS WITH THREE OR MORE RISERS SHALL HAVE HAND RAILS, PER LOCAL CODE.
5.
THE USE OF REBAR, STEEL STAKES, OR STEEL FENCE POSTS TO STAKE DOWN STRAW OR HAY BALES; OR TO SUPPORT SILT FENCE USED AS AN
EROSION CONTROL MEASURE; IS PROHIBITED. THE USE OF OSHA APPROVED COLORED WARNING CAPS ON REBAR OR FENCE POSTS USED WITH
30.
A SMOOTH GRADE SHALL BE MAINTAINED FROM THE CENTERLINE OF EXISTING ROAD TO PROPOSED CURB AND GUTTER AND/OR PROPOSED EDGE OF
EROSION CONTROL MEASURES IS NOT ACCEPTABLE.
PAVEMENT TO PRECLUDE THE FORMING OF FALSE GUTTERS AND/OR THE PONDING OF ANY WATER IN THE ROADWAY. REMOVE AND RECONSTRUCT
EXISTING PAVEMENT AND/OR CURB AS DICTATED BY FIELD CONDITIONS TO PROVIDE POSITIVE DRAINAGE AT TIE -IN -POINTS.
6.
IF STOCKPILES ARE LOCATED WITHIN 100 FEET OF A DRAINAGE WAY, ADDITIONAL SEDIMENT CONTROLS SUCH AS TEMPORARY DIKES OR SILT FENCE
SHALL BE REQUIRED.
31.
OVERLAY OF EXISTING PAVEMENT SHALL BE MINIMUM OF 1 1/2 INCH DEPTH; ANY COST ASSOCIATED WITH PAVEMENT OVERLAY, OR THE MILLING OF
7
APPROVED EROSION AND SEDIMENT CONTROL "BEST MANAGEMENT PRACTICES" SHALL BE MAINTAINED AND KEPT IN GOOD REPAIR FOR THE DURATION
EXISTING PAVEMENT TO OBTAIN REQUIRED DEPTH, SHALL BE ASSUMED BY THE CONTRACTOR.
OF THE PROJECT. AT A MINIMUM, THE CONTRACTOR OR HIS AGENT SHALL INSPECT ALL BMP'S WEEKLY AND AFTER SIGNIFICANT PRECIPITATION
32.
ALL RIGHT-OF-WAY DEDICATED FOR PUBLIC USE SHALL BE CLEAR AND UNENCUMBERED.
EVENTS. ALL NECESSARY MAINTENANCE AND REPAIR SHALL BE COMPLETED IN A TIMELY MANNER. ACCUMULATED SEDIMENT AND DEBRIS SHALL BE
REMOVED FROM A BMP WHEN THE SEDIMENT LEVEL REACHES ONE HALF THE HEIGHT OF THE BMP OR, AT ANY TIME THAT SEDIMENT OR DEBRIS
33.
AN AIR QUALITY PERMIT SHALL BE OBTAINED IF REQUIRED.
ADVERSELY IMPACTS THE FUNCTION OF THE BMP. A BUILDUP OF EXCESSIVE SEDIMENT OCCURRING IN FLAT AREAS, BEHIND STRAW BALES, AND
BEHIND SILT FENCES WILL BE REMOVED PROMPTLY. DISLOCATED STRAW BALES AND COLLAPSED OR TORN SILT FENCES WILL BE IMMEDIATELY
34.
ANY LIGHTING SHOWN HEREON IS AS SPECIFIED BY THE CLIENT AND IS INCLUDED FOR INFORMATION PURPOSES ONLY, AS DIRECTED BY THE OWNER
REPAIRED.
AND/OR PUBLIC AGENCY REQUIREMENTS. BOWMAN CONSULTING GROUP, LTD. HAS NOT PERFORMED THE LIGHTING DESIGN, AND THEREFORE DOES NOT
WARRANT AND IS NOT RESPONSIBLE FOR THE DEGREE AND/OR ADEQUACY OF ILLUMINATION ON THIS PROJECT.
8
THE CLEANING OF CEMENT TRUCK DELIVERY CHUTES SHALL OCCUR IN A PREDEFINED CONTAINMENT AREA. THE DISCHARGE OF WATER CONTAINING
CEMENT TO THE STORM SEWER SYSTEM IS PROHIBITED.
35.
THE CONTRACTOR WILL BE REQUIRED TO NOTIFY ALL RESIDENCES WITHIN VICINITY OF THE PROPERTY BOUNDARY TEN (10) DAYS PRIOR TO ANY
9.
EROSION BALES SHALL BE PLACED SUCH THAT RUNOFF WILL NOT FLOW BETWEEN, AROUND OR UNDER BALES. BALES TO BE ANCHORED WITH 2" X 2"
BLASTING IN ACCORDANCE WITH THE APPROPRIATE GOVERNING AGENCY REQUIREMENTS.
X 3' WOODEN STAKES OR TWO PER BALE.
36.
NO BLASTING SHALL BE PERMITTED WITHIN 25' OF EXISTING UTILITY LINES OR STRUCTURES. BLASTING TO BE EXTENDED 25, BEYOND PROPOSED
10.
WHEN TEMPORARY SEDIMENT AND EROSION CONTROL MEASURES ARE TO BE REMOVED, ANY SILT AND SEDIMENT DEPOSITS SHALL BE REMOVED AND
STRUCTURES IF CONDITIONS WARRANT FUTURE EXTENSIONS.
SPREAD EVENLY IN OPEN AREAS.
37.
ALL RETAINING WALLS 4' IN HEIGHT AND OVER (MEASURED FROM BOTTOM OF FOOTER TO TOP OF WALL) REQUIRE A SEPARATE BUILDING PERMIT.
11.
12.
BEST MANAGEMENT PRACTICES (BMP) DETAILS SHOWN ON THESE PLANS ARE CONCEPTUAL ONLY. ADJUST AS NECESSARY TO FIT FIELD CONDITIONS.
38.
THE APPROVAL OF THIS PLAN DOES NOT CONSTITUTE THE APPROVAL OF FUTURE WORK.
13.
TEMPORARY SEDIMENT BASINS SHALL BE USED DURING CONSTRUCTION TO CONTAIN ALL RUNOFF FROM THE SITE. IF TRENCH DEWATERING OR GROUND
39.
ALL HANDICAPPED SPACES SHALL HAVE AN ABOVE GRADE IDENTIFICATION SIGN MEETING APPROPRIATE GOVERNING AGENCY STANDARDS.
WATER REMOVAL IS REQUIRED, THE SEDIMENT POND OR OTHER APPROVED MEANS SHALL BE USED TO DETAIN ALL WATER PUMPED BY THESE
OPERATIONS.
40.
WHERE A PROPOSED PIPE CROSSES OR PARALLELS A STREET OR DRIVE AISLE, THE ASPHALT SHALL BE NEATLY SAWCUT TO FULL DEPTH. AFTER
14.
THE CONTRACTOR SHALL SUBMIT A SCHEDULE OF CONSTRUCTION, GRADING AND LANDSCAPING, INCLUDING THE NAME AND 24 HOUR PHONE NUMBER
INSTALLATION OF THE PIPE, THE ROADWAY SHALL BE PATCHED IN ACCORDANCE WITH THE APPROPRIATE GOVERNING AGENCY STANDARDS.
OF THE RESPONSIBLE PARTY TO CONTACT REGARDING ANY EROSION OR SEDIMENT PROBLEM TO THE APPROPRIATE GOVERNING AGENCY PRIOR TO
BEGINNING ANY CONSTRUCTION.
15.
EROSION CONTROL MEASURES TO BE COORDINATED WITH CONSTRUCTION MANAGER.
16.
EROSION AND SEDIMENT CONTROL SHALL BE INSTALLED IN ACCORDANCE WITH REGULATIONS OF THE APPROPRIATE GOVERNING AGENCY.
0
01
J
cz
c
O
co
CD r-
LO
O
czLO
U Ir
N
CDz
�
o"t
Cc
a m
z
.� (
C/)
rn
co Nt
E LL
co
Ccu O
E
w
J
Q
(i
0
0
m
z
lLLJ
V
UJI
C)
z
Q
c/i
Q
z
z_
O
J
F___
o
-
U
Lu
m
r1%
z
o
Q
0
�
cf)O
LLLu
o
O
Q
�
O
Q
z
J
Q
Lu
z
Lu
0
PRELIMINARY
DO NOT
USE FOR
C0 T
y� f
"
It
0GINS
�
W EL
. , ..IL
PLAN STATUS
-9-22 11ST SUBMISSION
DATE
DESCRIPTION
RG
DESIGN
RG
DRAWN
CHKD
SCALE
H: 1 " = 30'
V: N/A
OB No.
TSD-058-011
DATE FEBRUARY 9, 2022
-ILE No.
SHEET C 1 .1
Cad file name: P:\058-Rhetson Companies\011-DG-
Plans\Construction Documents\058-011-NTS.dwq