August 27, 2007
Halifax County
DWQ Project No. 20071418
NC 4/48
State Project No. 46840
APPROVAL of 401 WATER QUALITY CERTIFICATION and TAR-PAMLICO BUFFER AUTHORIZATION
with ADDITIONAL CONDITIONS
Mr. Ricky E. Greene, Jr, P.E., Division Engineer
NCDOT, Division 4
PO Box 3165
Wilson, NC 27895-3165
Dear Mr. Greene:
You have our approval, in accordance with the conditions listed below, for the following impacts for the purpose of
adding a turning lane to NC 4/48 in Halifax County:
Stream Impacts in the Tar-Pamlico River Basin
Site Permanent Fill in Intermittent Stream
linear ft Total Stream Impact
linear ft
22+90 20 20
Total 20 20
Total Stream Impact for Project: 201inear feet.
Tar-Pamlico Riparian Buffer Impacts
Site Zone 1 minus =Zone 1 Zone 1 Buffer Zone 2 minus =Zone 2 Zone 2 Buffer
Impact Wetlands Buffers (not Mitigation Impact
~ Wetlands Buffers Mitigation
(sq ft) in Zone 1 wetlands) Required ' (sq ft) in Zone 2 (not Required (using
(sq ft) (sq ft) (using 3:1 ratio) (sq ft) wetlands) 1.5:1 ratio)
s ft
1 839 0 839 N/A 495 0 495 N/A
Totals 839 0 839 0 495 0 495 0
* n/a =Total for Site is less than 1/3 acre and 150 linear feet of impact, no mitigation required
Total Buffer Impact for Project: 1,334 square feet.
The project shall be constructed in accordance with your application dated received August 14, 2007. After
reviewing your application, we have decided that these impacts are covered by General Water Quality Certification
Number 3627 and 3634. This certification corresponds to the Nationwide Permit 14 and Nationwide Permit 33
issued by the Corps of Engineers. This approval is also valid for the Tar-Pamlico Riparian Buffer Rules (15A
NCAC 2B.0259). In addition, you should acquire any other federal, state or local permits before you proceed with
your project including (but not limited to) Sediment and Erosion Control, Non-Discharge and Water Supply
Watershed regulations. This approval will expire with the accompanying 404 permit.
No°e Carolina
Transportation Permitting Unit ~tllCQ~~1,J
1650 Mail Service Center, Raleigh, North Carolina 27699-1650
2321 Crabtree Boulevard, Suite 250, Raleigh, North Carolina 27604
Phone: 919-733-17861 FAX 91 9-733-6893 1 1ntemet: http:llh2o.enr.state.nc.us/ncwetlands
An Equal OpportunitylAffirmative Action Employer - 50% Recycled110% Post Consumer Paper
~~ ~NAT~-R Michael F. Easley, Governor
`O~ ~ QG William G. Ross Jr., Secretary
North Carolina Department of Environment and Natural Resources
~ ~~ Coleen Sullins, Director
>_ ~ ~ Division of Water Quality
p 'C
This approval is valid solely for the purpose and design described in your application (unless modified below).
Should your project change, you must notify the DWQ and submit a new application. If the property is sold, the
new owner must be given a copy of this Certification and approval letter, and is thereby responsible for complying
with all the conditions. If total wetland fills for this project (now or in the future) exceed one acre, or of total
impacts to streams (now or in the future) exceed 1501inear feet, compensatory mitigation may be required as
described in 15A NCAC 2H .0506 (h) (6) and (7). For this approval to remain valid, you must adhere to the
conditions listed in the attached certification as well as those listed below.
Conditions of Certification:
1. Placement of culverts and other structures in waters, streams, and wetlands shall be placed below the elevation of
the streambed by one foot for all culverts with a diameter greater than 48 inches, and 20 percent of the culvert
diameter for culverts having a diameter less than 48 inches, to allow low flow passage of water and aquatic life.
Design and placement of culverts and other structures including temporary erosion control measures shall not be
conducted in a manner that may result in dis-equilibrium of wetlands or streambeds or banks, adjacent to or
upstream and down stream of the above structures. The applicant is required to provide evidence that the
equilibrium is being maintained if requested in writing by DWQ. If this condition is unable to be met due to
bedrock or other limiting features encountered during construction, please contact the NC DWQ for guidance on
how to proceed and to determine whether or not a permit modification will be required.
2. Riprap should not be placed in the active thalweg channel or placed in the streambed in a manner that precludes
aquatic life passage. Bioengineering boulders or structures should be properly designed, sized and installed.
3. For any streams being impacted due to site dewatering activities, the site shall be graded to its preconstruction
contours and revegetated with appropriate native species. .
4. All stormwater runoff shall be directed as sheetflow through stream buffers at nonerosive velocities, unless
otherwise approved by this certification.
5. All riparian buffers impacted by the placement of temporary fill or clearing activities shall be restored to the
preconstruction contours and revegetated. Maintained buffers shall be permanently revegetated with non-woody
species by the end of the growing season following completion of construction. For the purpose of this condition,
maintained buffer areas are defined as areas within the transportation corridor that will be subject to regular DOT
maintenance activities including mowing. The area with non-maintained buffers shall be permanently revegetated,
with native woody species before the next growing season following completion of construction.
6. Pursuant to NCAC 15A 2B.0259(6), sediment and erosion control devices shall not be placed in Zone 1 of any
Tar-Pamlico Buffer without prior approval by the NCDWQ. At this time, the NCDWQ has approved no sediment
and erosion control devices in Zone 1, outside of the approved project impacts, anywhere on this project. Moreover,
sediment and erosion control devices shall be allowed in Zone 2 of the buffers provided that Zone 1 is not
compromised and that discharge is released as diffuse flow.
7. If concrete is used during construction, a dry work area should be maintained to prevent direct contact between
curing concrete and stream water. Water that inadvertently contacts uncured concrete should not be discharged to
surface waters due to the potential for elevated pH and possible aquatic life and fish kills.
8. During the construction of the project, no staging of equipment of any kind is permitted in waters of the U.S., or
protected riparian buffers.
9. The dimension, pattern and profile of the stream above and below the crossing should not be modified.
Disturbed floodplains and streams should be restored to natural geomorphic conditions.
N~o~ecr~Carolina
Transportation Permitting Unit ~VattlCUlly
1650 Mail Service Center, Raleigh, North Carolina 27699-1650
2321 Crabtree Boulevard, Suite 250, Raleigh, North Carolina 27604
Phone: 919-733-17861 FAX 919-733-689311nternet: http://h2o.enr.state.nc.uslncwetlands
An Equal Opportunity/Affirmative Action Employer- 50% Recycled110% Post Consumer Paper
~ ~Nar~ Michael F. Easley, Governor
-d~O r'7 pG William G. Ross Jr., Secretary
North Carolina Department of Environment and Natural Resources
fi) ~ Coleen Sullins, Director
~_ ~ Division of Water Quality
G1 -r
10. The use of rip-rap above the Normal High Water Mark shall be minimized. Any rip-rap placed for stream
stabilization shall be placed in stream channels in such a manner that it does not impede aquatic life passage.
11. All work in or adjacent to stream waters shall be conducted in a dry work area. Approved BMP measures from
the most current version of NCDOT Construction and Maintenance Activities manual such as sandbags, rock berms,
cofferdams and other diversion structures shall be used to prevent excavation in flowing water.
12. Heavy equipment shall be operated from the banks rather than in the stream channel in order to minimize
sedimentation and reduce the introduction of other pollutants into the stream.
13. All mechanized equipment operated near surface waters must be regularly inspected and maintained to prevent
contamination of stream waters from fuels, lubricants, hydraulic fluids, or other toxic materials.
14. No rock, sand or other materials shall be dredged from the stream channel except where authorized by this
certification.
15. Discharging hydroseed mixtures and washing out hydroseeders and other equipment in or adjacent to surface
waters is prohibited.
16. A copy of this Water Quality Certification shall be posted on the construction site at all times. In addition, the
Water Quality Certification and all subsequent modifications, if any, shall be maintained with the Division Engineer
and the on-site project manager.
17. The outside buffer, wetland or water boundary located within the construction corridor approved by this
authorization shall be clearly marked by highly visible fencing prior to any land disturbing activities. Impacts to
areas within the fencing are prohibited unless otherwise authorized by this certification.
18. Upon completion of the project, the NCDOT Division Engineer shall complete and return the enclosed
"Certification of Completion Form" to notify DWQ when all work included in the 401 Certification has been
completed.
19. Native riparian vegetation must be reestablished within the construction limits of the project by the end of the
growing season following completion of construction.
20. There shall be no excavation from, or waste disposal into, jurisdictional wetlands or waters associated with this
permit without appropriate modification. Should waste or borrow sites be located in wetlands or streams,
compensatory mitigation will be required since that is a direct impact from road construction activities.
21. Erosion and sediment control practices must be in full compliance with all specifications governing
the proper design, installation and operation and maintenance of such Best Management Practices in
order to protect surface waters standards:
a. The erosion and sediment control measures for the project must be designed, installed, operated, and
maintained in accordance with the most recent version of the North Carolina Sediment and Erosion
Control Planning and Design Manual.
b. The design, installation, operation, and maintenance of the sediment and erosion control measures
must be such that they equal, or exceed, the requirements specified in the most recent version of the
North Carolina Sediment and Erosion Control Manual. The devices shall be maintained on all
construction sites, borrow sites, and waste pile (spoil) projects, including contractor-owned or leased
borrow pits associated with the project.
Nao e~Carolina
Transportation Permitting Unit d vu~uCa~~l~
1650 Mail Service Center, Raleigh, North Carolina 27699-1650
2321 Crabtree Boulevard, Suite 250, Raleigh, North Carolina 27604
Phone: 919-733-1786 /FAX 919-733-6893 /Internet: htto:/!h2o.enr.state.nc.uslncwetlands
An Equal OpportunitylAffirmative Action Employer - 50% Recycled110% Post Consumer Paper
~/aj'~ Michael F. Easley, Governor
~ ~^ ~ William G. Ross Jr., Secretary
\Q~" QG North Carolina Department of Environment and Natural Resources
~ ~~ Coleen Sullins, Director
>_ _ ..,{ Division of Water Quality
D 'C
c. For borrow pit sites, the erosion and sediment control measures must be designed, installed, operated,
and maintained in accordance with the most recent version of the North Carolina Surface Mining
Manual.
d. The reclamation measures and implementation must comply with the reclamation in accordance with
the requirements of the Sedimentation Pollution Control Act.
22. Sediment and erosion control measures shall not be placed in wetlands or waters unless otherwise approved by
this Certification. If placement of sediment and erosion control devices in wetlands and waters is unavoidable, they
shall be removed and the natural grade restored upon completion of the project.
If you do not accept any of the conditions of this certification, you may ask for an adjudicatory hearing. You must
act within 60 days of the date that you receive this letter. To ask for a hearing, send a written petition that conforms
to Chapter 150B of the North Carolina General Statutes to the Office of Administrative Hearings, 6714 Mail Service
Center, Raleigh, N.C. 27699. This certification and its conditions are final and binding unless you ask for a
hearing. This letter completes the review of the Division of Water Quality under Section 401 of the Clean Water
Act. If you have any questions, please contact Rob Ridings at (919) 733-9817.
Si ely,
~'J't-
~`
Coleen Sullins,
Director
Attachments (General Certification and Certificate of Completion form)
cc: Jamie Guerrero, Division 4 Environmental Officer
William Wescott, US Army Corps of Engineers, Washington Field Office
Travis Wilson, NC Wildlife Resources Commission
File Copy
NoSthCarolina
Transportation Permitting Unit lltllCll~~l~
1650 Mail Service Center, Raleigh, North Carolina 27699-1650
2321 Crabtree Boulevard, Suite 250, Raleigh, North Carolina 27604
Phone: 919-733-17861 FAX 919-733-6893 / Internet: http://h2o.enr.state.nc.us/ncwetlands
An Equal Opportunity/Affirmative Action Employer - 50% Recycled/10% Post Consumer Paper
QF W ATER
~ ~
~ _ -.l
DWQ Project No.:
Applicant:
Project Name:
Date of Issuance of 401 Water Quality Certification:
Michael F. Easley, Governor
William G. Ross Jr., Secretary
North Carolina Department of Environment and Natural Resources
Coleen Sullins, Director
Division of Water Quality
County:
Certificate of Completion
Upon completion of all work approved within the 401 Water Quality Certification or applicable Buffer Rules, and
any subsequent modifications, the applicant is required to return this certificate to the 401 Transportation Permitting
Unit, North Carolina Division of Water Quality, 1650 Mail Service Center, Raleigh, NC, 27699-1650. This form
may be returned to DWQ by the applicant, the applicant's authorized agent, or the project engineer. It is not
necessary to send certificates from all of these.
Applicant's Certification
I, ,hereby state that, to the best of my abilities, due care and diligence
was used in the observation of the construction such that the construction was observed to be built within substantial
compliance and intent of the 401 Water Quality Certification and Buffer Rules, the approved plans and
specifications, and other supporting materials.
Signature:
Agent's Certification
Date:
I, ,hereby state that, to the best of my abilities, due care and diligence
was used in the observation of the construction such that the construction was observed to be built within substantial
compliance and intent of the 401 Water Quality Certification and Buffer Rules, the approved plans and
specifications, and other supporting materials.
Signature:
Engineer's Certification
Partial Final
Date:
I, , as a duly registered Professional Engineer in the State of North
Carolina, having been authorized to observe (periodically, weekly, full time) the construction of the project,for the
Permiee hereby state that, to the best of my abilities, due care and diligence was used in the observation of the
construction such that the construction was observed to be built within substantial compliance and intent of the 401
Water Quality Certification and Buffer Rules, the approved plans and specifications, and other supporting materials.
Signature
Date
Registration No.
Nao e~Carolina
Transportation Permitting Unit ~UfllCllt'~l,~
1650 Mail Service Center, Raleigh, North Carolina 27699-1650
2321 Crabtree Boulevard, Suite 250, Raleigh, North Carolina 27604
Phone: 919-733-1786 /FAX 919-733-68931 Internet: http:!/h2o.enr.state.nc.us/ncwetlands
An Equal Opportunity/Affirmative Action Employer - 50% Recycled/10% Post Consumer Paper