HomeMy WebLinkAboutDN00496 Pre-Construction Meeting Minutes SignedROY COOPER
GOVERNOR
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
April 271h1,2022
J. ERIC BOYETTE
SECRETARY
CONTRACT NO:
DNO0496
TIP NO:
N/A
FEDERAL:
STATE FUNDED
WBS ELEMENT NO:
17BP.14.R.177
COUNTY:
HAYWOOD
DESCRIPTION:
GRADING, DRAINAGE, PAVING, TRAFFIC CONTROL,
BRIDGE, AND RETAINING WALL
LOCATION:
AT BRIDGE NO.237 OVER SORRELLS CREEK ON SR 1129
(LITTLE EAST FORK RD) IN HAYWOOD COUNTY
SUBJECT:
Phillip Creasman
Buckeye Bridge LLC
PO Box 1367
Canton, NC 28716
Dear Mr. Creasman,
Pre -Construction Meeting — 04/27/2022
This letter is to serve as a summary of the construction meeting that was conducted on
04/27/2022. Please review the following summary and let us know if you find any
discrepancy.
In Attendance:
Nathan Tanner (NCDOT) — Resident Engineer
David Moore (RK&K)
Brittany Haskett (NCDOT) — HiCams Technician
Joshua Christ (Camp Daniel Boone)
John Nixon (Camp Daniel Boone)
Andrew Fulkerson (Buckeye) — Project Manager
Phillip Creasman (Buckeye) — Project Manager
Lee Sheppard (NCDOT) — Roadside Environmental
Kevin Mitchell (NCDWR) — Environmental Specialist
Mailing Address.
NC DEPARTMENT OF TRANSPORTATION
DIVISION 14 - DISTRICT 2
178 HENRY BIRD RD.
WHITTIER, NC 28789-7646
Telephone. 828497-7333
Fax. 828497-6095
Customer Service. 1-877-3684968
Website: ncdagov
Location:
178 HENRY BIRD RD.
WHITTIER, NC 28789-7646
d STATFa
a
�s 'ywaa�' •
vQ.rrd�
STATE OF NORTH CAROLINA
DEPARTMENT OF TIANSPORTATION
Roy COOPER J. ERIC BOYETTE
GOVERNOR SECRETARY
General Items:
Progress Schedule: Received
Letter Authorizing Supplemental Agreements: Received
Subcontract Requests: Pending
Material Suppliers: Received
Monthly Estimate End Date: 15th
Buy American Letter: Received
Representing the Department as Project Engineer will be TBD. The Project Inspector
will be TBD.
For the Contractor, the Project Manager will be Phillip Creasman. The Project
Superintendent will be Tad Carpenter. The Traffic Control Coordinator will be
Andrew Fulkerson. The Certified Erosion Control Supervisor will be TBD.
Project Schedule/Contractor Schedule:
Date of Availability: March 21 st, 2022
Completion Date: 180 days after the completion of ICT # 1
The Contractors Plan of Operation Start Dates:
TBD — Late August/Early September
Contract/Plan Review:
Liquidated Damages are $200 per day.
ICT # 1:
Liquidated damages are $700 per day.
ICT #2:
Liquidated damages are $1,500 per day.
DBE goal of 3.0% was met.
The contractor was reminded that materials cannot be used in the work until they have
been approved, tested, or certified.
The contractor was reminded that an OSHA competent person must be on the project at
all times.
Mailing Address:
NC DEPARTMENT OF TRANSPORTATION
DIVISION 14 - DISTRICT 2
178 HENRY BIRD RD.
WHITTIER, NC 28789-7646
Telephone. 828497-73 33
Fax: 828497-6095
Customer Service. 1-877-3684968
Website. ncdot.gov
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
Roy COOPER
GOVERNOR
J. ERIC BOYETTE
SECRETARY
Utility Comments:
• Utilities are complete with the exception of one pole remaining to be removed
within the next couple of weeks.
Right of Way Comments:
• No R.O.W. issues.
General Comments:
• Make sure if you have issues meeting commitments, document all communication
early and often, so that if you fail to meet the committed amounts, we can go
through the good faith effort to replace.
• If you plan to use a drone (follow guidelines)
• Please review the idle equipment guidelines in the contract
• Make sure tracks on equipment are clean upon arrival to the project and get
proper permits if it crosses state lines (Pest/Plant Quarantine)
• Make sure that a Level II certified person is always onsite to assist with erosion
control implementation
• Our inspectors will fill out the NPDES forms, make sure your level II person does
the inspection as well and reviews the NPDES afterwards.
• The NPDES forms are to be kept onsite at all times with a set of up to date as -
built plans.
• Stage seed early and often to help achieve 80% vegetation after work has been
completed
• Seed changes to make — Add hard fescue to native seeding mix (recommend 20lbs
per acre)
• Someone from roadside environmental will be performing a monthly inspection
and any corrections will be provided to inspector to communicate said changes to
contractor.
• *Please make sure that corrections provided are addressed in a timely manner and
not left to be an issue for next month's inspection.
• This contract has a lawn type appearance special provision.
Mailing Address:
NC DEPARTMENT OF TRANSPORTATION
DIVISION 14 — DISTRICT 2
178 HENRY BIRD RD.
WHITTIER, NC 28789-7646
Telephone: 828-497-7333
Fax: 828497-6095
Customer Service: 1-877-3684968
Website: ncdot.gov
�$rATFa
dCl
�ysaab
u
'fin ManA' ��
va.w.d
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
Roy COOPER
GOvERNOR
J. ERIC BOYETTE
SECRETARY
• Concrete washouts will be required and will need to be built per the spec (bags
are acceptable)
• Make sure to follow submittal requirements in the contracts whereas the proper
units listed, Geotech and structures, are emailed in a timely manner to provide
sufficient time to review. (Please CC David and Nathan so that we can track the
progress)
• Make sure that anyone operating a crane is certified to do so and has their card
present during operating. Please provide the inspector onsite with a copy so that
they can record it in Shareplus.
• Please make note that creek water will not be allowed to be used in the production
of grout. Water for miscellaneous uses will need to be from an approved source.
• Asbestos assessment has already been completed for this project.
• Please inform project inspector of guardrail and pipe deliveries prior to them
getting onsite so that they can have our M&T rep inspect necessary materials
before they are installed. You do not want to dig up pipe for inspection.
• Please let the inspector onsite know of any anticipated night or weekend work so
that we can staff the project properly.
• We need to coordinate with Camp Daniel Boone when they have events to limit
traffic jams and backups.
• Please note that if areas are used as a staging area, we would need a reclamation
plan if any ground disturbing activity takes place in that area off of right-of-way.
• Pond already drained.
• Kevin Mitchell to do monthly inspections.
• Self report any sediment loss or oil spills.
• Do not use earth material to construct Impervious Dikes (if needed)
• Inside limits of project and SHIPPO — contractor to park equipment on property
owners property if permitted.
• Less traffic from September on to Camp Daniel Boone.
• Phase I — SA for temporary signals instead of using the stop/yield TCP.
• Very little weekend traffic on driveway that's getting relocated.
• Keep traffic in roadway work completed in Phase I for Phase II traffic pattern.
Mailing Address.
NC DEPARTMENT OF TRANSPORTATION
DIVISION 14 — DISTRICT 2
178 HENRY BIRD RD.
WHITTIER, NC 28789-7646
Telephone: 828497-7333
Fax. 828497-6095
Customer Service: 1-877-3684968
Website: ncdot gov
ASfA q,
O ysac�
Ww
STATE OF NORTH CAROLINA
DEPARTNMNT OF TRANSPORTATION
Roy COOPER J. ERIC BOYETTE
GOVERNOR SECRETARY
These minutes are completed as noted. Any discrepancies to the content of the minutes
should be provided in writing to the Resident Engineer. If no discrepancies are noted, this
will indicate concurrence with the minutes as noted.
Sincerely,
Nathan anner
Division 14 District 2 Resident Engineer
Mailing Address:
NC DEPARTMENT OF TRANSPORTATION
DIVISION 14 — DISTRICT 2
178 HENRY BIRD RD.
WHITTIER, NC 28789-7646
Telephone: 828497-7333
Fax: 828497-6095
Customer Service: 1-877-3684968
Website: ncdot.Ro_v