August 15, 2007
Beaufort County
DWQ Project No. 20070864 v.2
TIP B-4018
MODIFICATION of APPROVAL of 401 WATER QUALITY CERTIFICATION and TAR-PAMLICO RIVER BUFFER
AUTHORIZATION with ADDITIONAL CONDITIONS
Dr. Gregory J. Thorpe, PhD., Manager
Planning & Environmental Branch
N.C. Department of Transportation
1548 Mail Service Center
Raleigh, North Carolina, 27699-1548
Dear Dr. Thorpe:
You have our approval, in accordance with the attached conditions and those listed below, for the following impacts:
Wetlands Buffer Buffer
Streams
Site Number (acres)
Temporary Temporary Temporary Zone 1
(square ft) Zone 2
(square ft) (acres)
Fill Excavation Hand Clearin
TIP B-4018 < 0.01 0.01 0.02 3,736 1,226 < 0.001
Net Total Im acts 0.03 acres 4,962 ft <0.001
The project shall be constructed in accordance with your application dated June 28, 2007 for the purpose of replacing Bridge
Number 104 over Broad Creek on NC 32 in Beaufort County. All the authorized activities and conditions associated with the
original Water Quality Certification dated July 2, 2007 and all subsequent modifications still apply except where superceded
by this certification. After reviewing your application, we have decided that these impacts are covered by General Water
Quality Certification Number 3627. This certification corresponds to General Permit 31, issued by the Corps of Engineers.
This approval is also valid for the Tar-Pamlico River Buffer Rules (15A NCAC 2B .0259). In addition, you should acquire
any other federal, state or local permits before you proceed with your project including (but not limited to) Sediment and
Erosion Control, Non-Discharge and Water Supply Watershed regulations. This approval will expire with the accompanying
404 permit issued by the US Army Corps of Engineers (this supercedes Condition 19 of General Certification 3627 issued
March 19, 2007).
This approval is valid solely for the purpose and design described in your application (unless modified below). Should your
project change, you must notify the DWQ and submit a new application. If the property is sold, the new owner must be given
a copy of this Certification and approval letter, and is thereby responsible for complying with all the conditions. If total
wetland fills for this project (now or in the future) exceed one acre, or total impacts to streams or buffers (now or in the
future) exceed 150 linear feet, compensatory mitigation may be required as described in 15A NCAC 2H .0506 (h) (6) and (7).
For this approval to remain valid, you must adhere to the conditions listed in the attached certification.
l.) Upon completion of the project, the NCDOT Division Engineer shall complete and return the enclosed "Certification of
Completion Form" to notify DWQ when all work included in the 401 Certification has been completed.
2.) The permittee and its authorized agents shall conduct its activities in a manner consistent with State water quality
standards (including any requirements resulting from compliance with §303(d) of the Clean Water Act) and any other
appropriate requirements of State and Federal law. If DWQ determines that such standards or laws are not being met
(including the failure to sustain a designated or achieved use) or that State or federal law is being violated, or that further
conditions are necessary to assure compliance, DWQ may reevaluate and modify this certification.
N. C. Division of Water Quality 943 Washington Square Mall Washington, N.C. 27889 Telephone (252) 946-6481
FAX (252) 946-9215 Internet: www.ncwaterquality.org
An Equal OpportunitylAffirmative Action Employer - 50% Recycledl10% Post Consumer Paper
No e hCarolina
~atrrra!!~
3.) The permittee will need to adhere to all appropriate in-water work moratoriums (including the use of pile driving or
vibration techniques) prescribed by the NC Wildlife Resources Commission, the US Fish and Wildlife Service, and
National Marine Fisheries Service. No in-water work is permitted between February 15 and June 15 of any year, without
prior approval from the NC Division of Water Quality and the NC Wildlife Resources Commission. In addition, the
permittee shall conform with the NCDOT policy entitled "Stream Crossing Guidelines for Anadromous Fish Passage
(May 12, 1997) at all times.
4.) Erosion and sediment control practices must be in full compliance with all specifications governing the
proper design, installation and operation and maintenance of such Best Management Practices in order to
protect surface waters standards:
a. The erosion and sediment control measures for the project must be designed, installed, operated, and
maintained in accordance with the most recent version of the North Carolina Sediment and Erosion
Control Planning and Design Manual.
b. The design, installation, operation, and maintenance of the sediment and erosion control measures must be
such that they equal, or exceed, the requirements specified in the most recent version of the North Carolina
Sediment and Erosion Control Manual. The devices shall be maintained on all construction sites, borrow
sites, and waste pile (spoil) projects, including contractor-owned or leased borrow pits associated with the
project.
c. For borrow pit sites, the erosion and sediment control measures must be designed, installed, operated, and
maintained in accordance with the most recent version of the North Carolina Surface Mining Manual.
d. The reclamation measures and implementation must comply with the reclamation in accordance with the
requirements of the Sedimentation Pollution Control Act.
5.) Pursuant to NCAC 15A 2B.0259 (6), temporary sediment and erosion control devices shall be allowed in Zones 1 and 2
of the Tar-Pamlico Buffer provided that sediment and erosion control for upland areas is addressed to the maximum
extent practical outside the buffer.
6.) If concrete is used during construction, a dry work area should be maintained to prevent direct contact between curing
concrete and stream water. Water that inadvertently contacts uncured concrete should not be discharged to surface
waters due to the potential for elevated pH and possible aquatic life and fish kills.
7.) During the construction of the project, no staging of equipment of any kind is permitted in waters of the U.S., or
protected riparian buffers.
8.) The dimension, pattern, and profile of the stream above and below the crossing should not be modified. Disturbed
floodplains and streams should be restored to natural geomorphic conditions.
9.) The use of rip-rap above the Normal High Water Mark shall be minimized. Any rip-rap placed for stream stabilization
shall be placed in stream channels in such a manner that it does not impede aquatic life passage.
10.) Heavy equipment may be operated within the stream channels however, its usage shall be minimized.
11.) All mechanized equipment operated near surface waters must be regularly inspected and maintained to prevent
contamination of stream waters from fuels, lubricants, hydraulic fluids, or other toxic materials.
12.) No rock, sand or other materials shall be dredged from the stream channel except where authorized by this certification.
13.) Discharging hydroseed mixtures and washing out hydroseeders and other equipment in or adjacent to surface waters is
prohibited.
14.) All fill slopes located in jurisdictional wetlands shall be placed at slopes no flatter than 3:1, unless otherwise authorized
by this certification.
15.) The outside buffer, wetland or water boundary located within the construction corridor approved by this authorization
shall be clearly marked by highly visible fencing prior to any land disturbing activities. Impacts to areas within the
fencing are prohibited unless otherwise authorized by this certification.
16.) Native riparian vegetation must be reestablished within the construction limits of the project by the end of the growing
season. following completion of construction.
17.) There shall be no excavation from, or waste disposal into, jurisdictional wetlands or waters associated with this permit
without appropriate modification. Should waste or borrow sites be located in wetlands or streams, compensatory
mitigation will be required since that is a direct impact from road construction activities.
18.) All stormwater runoff shall be directed as sheetflow through stream buffers at nonerosive velocities, unless otherwise
approved by this certification.
19.) All riparian buffers impacted by the placement of temporary fill or clearing activities shall be restored to the
preconstruction contours and revegetated. Maintained buffers shall be permanently revegetated with non-woody species
by the end of the growing season following completion of construction. For the purpose of this condition, maintained
buffer areas are defined as areas within the transportation corridor that will be subject to regular DOT maintenance
activities including mowing. The area with non-maintained buffers shall be permanently revegetated, with native woody
species before the next growing season following completion of construction.
20.) Strict adherence to the most recent version of NCDOT's Best Management Practices For Bridge Demolition and
Removal approved by the US Army Corps of Engineers is a condition of the 401 Water Quality Certification.
21.) The jetting of piles is not authorized without prior written approval from the NC Division of Water Quality.
22.) Bridge deck drains should not discharge directly into the stream. Stormwater should be directed across the bridge and
pre-treated through site-appropriate means (grassed swales, pre-formed scour holes, vegetated buffers, etc.) before
entering the stream. Please refer to the most current version. of Stormwater Best Management Practices.
23.) The post-construction removal of any temporary bridge structures must return the project site to its preconstruction
contours and elevations. The impacted areas shall be revegetated with appropriate native species.
24.) A copy of this Water Quality Certification shall be posted on the construction site at all times. In addition, the Water
Quality Certification and all subsequent modifications, if any, shall be maintained with the Division Engineer and the on-
site project manager.
If you do not accept any of the conditions of this certification, you may ask for an adjudicatory hearing. You must act within
60 days of the date that you receive this letter. To ask for a hearing, send a written petition that conforms to Chapter 150B of
the North Carolina General Statutes to the Office of Administrative Hearings, P.O. Box 27447, Raleigh, N.C. 27611-7447.
This certification and its conditions are final and binding unless you ask for a hearing.
This letter completes the review of the Division of Water Quality under Section 401 of the Clean Water Act. If you have any
questions, please contact Garcy Ward at (252) 948-3922.
m r y,
n,~n._ °/
___. .
for oleen H. Sullins
Director, Division of Water Quality
Attachment
cc: Wilmington District Corps of Engineers
William Wescott, US Army Corps of Engineers, Washington Field Office
Steve Sollod, DCM, 1638 Mail Service Center, Raleigh, NC 27699
Jay Johnson, Division 2 Environmental Officer, NCDOT
Garcy Ward, NC DWQ, Washington Regional Office
Central Files
File copy
o~o~ wAT ~RQ~
r
~_ ~
O '~
DWQ Project No.:
Applicant:
Project Name:
Date of Issuance of 401 Water Quality Certification:
County:
Certificate of Completion
Upon completion of all work approved within the 401 Water Quality Certification or applicable Buffer Rules, and
any subsequent modifications, the applicant is required to return this certificate to the 401/Wetlands Unit, North
Carolina Division of Water Quality, 1621 Mail Service Center, Raleigh, NC, 27699-1621. This form may be
returned to DWQ by the applicant, the applicant's authorized agent, or the project engineer. It is not necessary to
send certificates from all of these.
Applicant's Certification
I, ,hereby state that, to the best of my abilities, due care and diligence
was used in the observation of the construction such that the construction was observed to be built within substantial
compliance and intent of the 401 Water Quality Certification and Buffer Rules, the approved plans and
specifications, and other supporting materials.
Signature:
Date:
Agent's Certification
I, ,hereby state that, to the best of my abilities, due care and diligence
was used in the observation of the construction such that the construction was observed to be built within substantial
compliance and intent of the 401 Water Quality Certification and Buffer Rules, the approved plans and
specifications, and other supporting materials.
Signature:
Engineer's Certification
Partial Final
Date:
I, , as a duly registered Professional Engineer in the State of North
Carolina, having been authorized to observe (periodically, weekly, full time) the construction of the project, for the
Permittee hereby state that, to the best of my abilities, due care and diligence was used in the observation of the
construction such that the construction was observed to be built within substantial compliance and intent of the 401
Water Quality Certification and Buffer Rules, the approved plans and specifications, and other supporting materials.
Signature Registration No.
Date
N~o e~Cazolina
Transportation Permitting Unit ~ "`tura~~1~
1650 Mail Service Center, Raleigh, North Carolina 27699-1650
2321 Crabtree Boulevard, Suite 250, Raleigh, North Carolina 27604
Phone: 919-733-1786/ FAX 919-733-689311ntemet: htta://h2o.enr.state.nc.us/ncwetlands
Michael F. Easley, Governor
William G. Ross Jr., Secretary
North Carolina Department of Environment and Natural Resources
Coleen H. Sullins Director
Division of Water Quality
An Equal Opportunity/Affirmative Action Employer- 50% Recycled/10% Post Consumer Paper