HomeMy WebLinkAboutNC0036196_Authorization to Construct_20040423NPDES DOCUMENT SCANNING COVER SHEET
NPDES Permit:
NC0036196
Clark Creek WWTP
Document Type:
Permit Issuance
Wasteload Allocation
Authorization to Construct (AtG
Permit Modification
Complete File - Historical
Engineering Alternatives (EAA)
Correspondence
Owner Name Change
Instream Assessment (67b)
Speculative Limits
Environmental Assessment (EA)
Document Date:
April 23, 2004
This document is printed on reuse paper - ignore any
content on the resrerxse side
0
C)
Michael F. Easley, Govemor
State of North Carolina
William G. Ross, Jr., Secretary
Department of Environment and Natural Resources
Alan W. Klimek, P.E., Director
Division of Water Quality
April 23, 2004
Mr. Martin Wilson, Director of Utilities
City of Newton
P.O. Box 550
Newton, North Carolina 28658
Subject: Authorization to Construct Permit Issuance
ATC Number 0036196A01
Newton WWTP
NPDES Permit NC0036196
Catawba County
Dear Mr. Wilson:
A request for an Authorization to Construct (ATC) was received by the Division February 4,
2004, and final plans and specifications for this project have been reviewed and found to be
satisfactory. Authorization is hereby granted for the improvements to the City of Newton's
Wastewater Treatment Plant (WWTP). The majority of the permit authorizes the
renovation/refurbishment of existing treatment units. In general, this ATC allows:
• The replacement of screening/conveying at the influent pump station,
• The replacement of internal equipment in the reactor (primary) clarifiers,
• The replacement of internal equipment in secondary clarifiers no. 1 and 2,
• The renovation of the effluent filters and control system,
• The replacement of the existing chlorine system and the addition of dual feed SO2
dechlorination (retaining the same chlorine detention time),
• The installation of septage storage tank/receiving station,
• The replacement of lime slurry tanks,
• The installation of thickener mechanisms/equipment in place of the existing sludge storage
tanks,
• and all additional piping, and appurtenances.
Once construction under this ATC has been completed and an Engineer's Certificate has been
submitted, the permittee is authorized to operate the units listed above, with permitted limits as
specified in the 1VPDES permit issued December 6, 2002. This Authorization to Construct permit
does not modify the existing design low of 5.0 MGD for the Newton WWTP. The Division of Water
Quality approves this project in terms of compliance with NPDES limits; we defer to the City of
Newton and their consultants for approval of structural integrity, etc. of the various treatment
units, as well as compliance with any other required programs.
This Authorization to Construct is issued in accordance with NPDES Permit No.
NC0036196 issued December 6, 2002, and shall be subject to revocation unless the wastewater
treatment facilities are constructed in accordance with the conditions and limitations specified in
the permit.
The sludge generated from these treatment facilities must be disposed of in accordance
with G.S. 143-215.1 and in a manner approved by the North Carolina Division of Water Quality.
In the event that the facilities fail to perform satisfactorily, including the creation of
nuisance conditions, the Permittee shall take immediate corrective action, including those as may
be required by this Division, such as the construction of additional or replacement wastewater
treatment or disposal facilities.
North Carolina Division of Water Quality
1617 Mail Service Center
Raleigh, North Carolina 27699-1617
(919) 733-7015
FAX (919) 733-0719
On the Internet at http://h2o.enr.state.nc.us/
Mr. Wilson
Page 2
The Mooresville Regional Office, telephone number (704) 663 - 1699, shall be notified
at least forty-eight (48) hours in advance of operation of the installed facilities so that an in -place
inspection can be made. Such notification to the regional supervisor shall be made during the
normal office hours from 8:00 a.m. until 5:00 p.m. on Monday through Friday, excluding State
Holidays.
Upon classification of the facility by the Certification Commission, the Permittee shall
employ a certified water pollution control treatment system operator to be in responsible charge
(ORC) of the water pollution control treatment system. The operator must hold a certificate of the
type and grade at least equivalent to or greater than the classification assigned to the water
pollution control treatment system by the Certification Commission. The Permittee must also
employ a certified back-up operator of the appropriate type and grade to comply with the
conditions of Title 15A, Chapter 8G, .0202. The ORC of the facility must visit each Class I facility
at least weekly and each Class II, III, and IV facility at least daily, excluding weekends and
holidays, and must properly manage and document daily operation and maintenance of the facility
and must comply with all other conditions outlined in Title 15A, Chapter 8G, .0204. Once the
facility is classified, the Permittee must submit a letter to the Certification Commission which
designates the operator in responsible charge within: (A) Sixty calendar days prior to wastewater
being introduced into a new system or (B) within 120 calendar days of the following, (i) after
receiving notification of a change in the classification of the system requiring the designation of a
new ORC and back-up ORC or (ii) a vacancy in the position of ORC or back-up ORC.
A copy of the approved plans and specifications shall be maintained on file by the
Permittee for the life of the facility.
The Operational Agreement between the Permittee and the Environmental Management
Commission is incorporated herein by reference and is a condition of this Permit. Noncompliance
with the terms of the Operational Agreement shall subject the Permittee to all sanctions provided
by G. S. 143-215.6 for violation of or failure to act in accordance with the terms and conditions of
this Permit.
Failure to abide by the requirements contained in this Authorization to Construct may
subject the Permittee to an enforcement action by the Division of Water Quality in accordance
with North Carolina General Statute 143-215.6A to 143-215.6C.
The issuance of this Authorization to Construct does not preclude the Permittee from
complying with any and all statutes, rules, regulations, or ordinances which may be imposed by
other government agencies (local, state, and federal) which have jurisdiction.
Upon completion of construction and prior to operation of this permitted facility, a
certification must be received from a professional engineer certifying that the permitted facility has
been installed in accordance with the NPDES Permit, this Authorization to Construct and the
approved plans and specifications. Mail the Certification to the NPDES Unit, Division of Water
Quality, 1617 Mail Service Center, Raleigh, NC 27699-1617.
One (1) set of approved plans and specifications is being forwarded to you. If you have any
questions or need additional information, please contact Ms. Susan A. Wilson, P.E., telephone
number (919) 733-5083, extension 510.
cc: Central Files
NPDES Unit. Permit File
Mooresville Regional Office,
Mr. Charles Willis. Jr., P.E.
Sincerely,
Alan W. Klimek, P.E.
Water Quality
Willis Engineers
1520 South Boulevard
Charlotte, NC 28203
j
Mr. Wilson
Page 3
Engineer's Certification
I, , as a duly registered Professional Engineer in the State of
North Carolina, having been authorized to observe (periodically, weekly, full time) the construction
of
the project, for the
Project Name Location
Permittee hereby states that, to the best of my abilities, due care and diligence was used in the
observation of the following installations:
• The replacement of screening/conveying at the influent pump station,
• The replacement of internal equipment in the reactor (primary) clarifiers,
• The replacement of internal equipment in secondary clarifiers no. 1 and 2,
• The renovation of the effluent filters and control system,
• The replacement of the existing chlorine system and the addition of dual feed SO2
dechlorination (retaining the same chlorine detention time),
• The installation of septage storage tank/receiving station,
• The replacement of lime slurry tanks,
• The installation of thickener mechanisms/equipment in place of the existing sludge storage
tanks,
• and all additional piping, and appurtenances.
Once construction under this ATC has been completed and an. Engineer's Certificate has been
submitted, the permittee is authorized to operate the units listed above, with permitted limits as
specified in the NPDES permit issued December 6, 2002. This Authorization to Construct permit
does not modify the existing design flow of 5.0 MGD for the Newton WWTP. The Division of Water
Quality approves this project in terms of compliance with NPDES limits; we defer to the City of
Newton and their consultants for approval of structural integrity, etc. of the various treatment
units, as well as compliance with any other required programs.
Signature _ Registration No.
Date
Mail this Certification to the
NPDES Unit
DENR/DWQ
1617 Mail Service Center
Raleigh, NC 27699-1617