HomeMy WebLinkAboutNCC221312_ESC Approval Submitted_20220405ROY COOPER
Governor
ELIZABETH S. BISER
Secretary
BRIAN WRENN
Director
NORTH CAROLINA
Environmental attatd{ry
March 28, 2022
LETTER OF APPROVAL
Resource Environmental Solutions, LLC
Daniel Ramsay, General Manager
3600 Gleenwood Avenue, Suite 100
Raleigh, NC 27612
RE: Project Name: Dugout Stream and Wetland Mitigation Site
Acres Approved: 34
Project ID: CUMBE-2022-126
County: Cumberland, City: Fayetteville
Address: Upton Tyson Road
River Basin: Cape Fear
Stream Classification: Other
Submitted by: Ann Frasier
Date Received by LQS: March 4, 2022
Plan Type: Environmental Mitigation
Dear Mr. Ramsay:
n
The subject erosion and sedimentation control plan has been approved
mu t belfiled a
Sedimentation Pollution Control Act (hereinafter Act) states that thisp
minimum of 30 days (15 days for revised plans) prior to the activity and the approving authority -
ptari
must approve or disapprove the submitted plan within 30 days (15 dau hori for r failsto approve:
receipt of G.S. 113A-54.1. The Act further states that if the approving a sY erv.od, the lan
or disapprove the submitted plan within the 30-day (15 days for revised plans) at the �obslte:.
will be deemed approved. The enclosed Certificate of Approval must be posted dat, hf no` land
This plan approval shall expire three (3) y
ears following the date of app
disturbing activity has been undertaken, as is required by Title 15A NCAC 4B 0129
As of April 1, 2019, all new construction activities are requirekpw
an electronic Notice of Intent (NOI) form requesting a Certificate of Coverage ( b��F R
under the NCG010000 Conan
struction Stormwater General Permitau°b h l o T
submitted and COC issued prior to the commencement of any
be accessed at de nc ovs ;
the above -named project. The NOT form may
about the NOI form to Annette Lucas at Ann cue Iu°a
direct questionseke xh
Paul Clark at paul.clark ncd.enr. ov. After you submit a compk
you within three b:�usinessi'das
Form, a COC will be emaiied to y
not charge a fee for coverage under the NCG01 pernllt Ho
g
�f
el"NK", 7000`�-'�
NorthCarolina Dept
payetteville"Al•y 410..433..'+300
ura!Asr�As V
2019, a $100 fee will be charged annually. This fee is to be sent to the DEMLR
Stormwater Central Office staff in Raleigh. Title 15A NCAC 4B .0118(a) and the
NCG01 permit require that the following documentation be kept on file at the job site:
1. The approved E&SC plan as well as any approved deviation.
2. The NCG01 permit and the COC, once it is received.
3. Records of inspections made during the previous 30 days.
Also, this letter gives the notice required by G.S. 113A-61.1(a) of our right of periodic
inspection to insure compliance with the approved plan.
North Carolina's Sedimentation Pollution Control Act is performance -oriented, requiring
protection of existing natural resources and adjoining properties. If, following the
commencement of this project, the erosion and sedimentation control plan is inadequate
to meet the requirements of the Sedimentation Pollution Control Act of 1973 (North
Carolina General Statute 113A-51 through 66), this office may require revisions to the
plan and implementation of the revisions to insure compliance with the Act.
Acceptance and approval of this plan is conditioned upon your compliance with Federal
and State water quality laws, regulations, and rules. In addition, local city or county
ordinances or rules may also apply to this land -disturbing activity. This approval does
not supersede any other permit or approval.
Please note that this approval is based in part on the accuracy of the
information provided in the Financial Responsibility Form, which you provided. You
are requested to file an amended form if there is any change in the information
included on the form. This permit allows for a land -disturbance, as called for on the
application plan, not to exceed the approved acres. Exceeding the acreage will be a
violation of this permit and would require a revised plan and additional application
fee. Any addition in impervious surface, over that already noted on the approved
plan, would also require a revised plan to verify the appropriateness of the erosion
control measures and the stormwater retention measures. (GS 113A-54.1(b)). In
addition, it would be helpful if you notify this office of the proposed starting date for
this project. Please notify us if you plan to have a preconstruction conference.
Your cooperation is appreciated.
Sincerely,
4C 3 ...
Chris Baker
Assistant Regional Engineer
DEMLR - Fayetteville Regional Office
Enclosures: Certificate of Approval
cc: Ann Mullen, P. E., Resources Environmental Solutions, LLC — email copy
Joseph Stanton, City of Fayetteville Permit Office — email copy
Fayetteville Regional Office