HomeMy WebLinkAboutNCC200626_NOT Closeout Documents_20220329THECITYOF
ASHEVILLE
CERTIFICATE OF COMPLETION
fol.
SEDIMENT AND EROSION CONTROL
Hilliard Park LLC
302 Dahlonega St.
Cumming, GA 30040
RE: Project Name: 360 Hilliard Ave
Project Address: 360 Hilliard Ave
Permit Number: 18-05006
Inspection Date: February 10, 2022
Inspector: Gary Jarvis
DaVelopmerrl 5andea Daluutmont
City of Asheville
PO BOX 7140
Asheville, NC 28802
This document certifies that the project has been inspected by a City of Asheville Site
Engineering Inspector, and the final grading inspection has been approved.
The approved final grading inspection certifies that the land disturbing activity for the above
referenced project is complete, and the temporary sedimentation and erosion control measures
have been removed, all permanent measures installed and that the site has been satisfactorily
stabilized sufficient to restrain erosion, per the approved plan.
The project is in compliance and released under the SPCA. Termination of coverage under the
NPDES General Stormwater Permit for Construction Activities must be requested by the
permittee via a Notice of Termination (NOT). The NOT is available at: deq.nc.govNCGO1
Please note that this correspondence must be uploaded as part of completing the NOT process.
Monte Clampett, CESSWI, CPII
Site Inspection & Zoning Enforcement Supervisor