This permit issued to Richard Garrigan authorizes the development of 1.25 acres of land in Samsara
Estates at 4050 Chaprai Drive for SFD construction in New Hanover County. This permit issued on February 21,
2022 is subject to compliance with the application and site drawings, all applicable regulations and special
conditions and notes set forth below. Any plan modifications must be approved by this office prior to field
changes.
It is understood by the applicant that a representative of New Hanover County's Engineering Department
may inspect the site at any time following the issuance of this Permit. A copy of the approved Soil Erosion
Control Plan as well as any approved deviations, this permit, a rain gauge, a copy of the NCG01 permit, a copy of
the Certificate of Coverage (COC) from the State and copies of the Combined Self -Monitoring and Self -Inspection
Reports must be available at all times at the site.
Failure to execuite the provisions of this permit and the approved Soil Erosion Plan, or any other provisions
of the New Hanover County Soil Erosion and Sedimentation Control Ordinance, may result in immediate legal
action by the County to the limits prescribed by the Ordinance. If the measures outlined on the approved Soil
Erosion Control Plan and this Permit prove insufficient, additional Erosion Control measures can and will be
required which in turn will be considered provisions of this Permit. This Permit does not preclude any other
permits or approvals necessary for beginning or completing this development. Approval of an erosion control
plan is conditioned on the applicant's compliance with Federal and State laws, regulations, and rules. It is the
Permittee's responsibility to obtain all necessary permits and approvals.
SPECIAL CONDITIONS
(THESE CONDITIONS MUST BE FOLLOWED IN ADDITION TO THE PLANS AND SPECIFICATIONS)
*All the soil erosion control measures will be installed as the site is cleared and maintained throughout
construction. These include silt fence, a construction entrance, concrete washout, and all NCG01 regulations for
lot 19 at 4050 Chapra Drive.
**Note the required separate NCG01 permit that requires concrete washouts and other NCG01 regulations.
*Silt fence stakes must be steel and will be placed six feet apart without wire reinforcement or eight feet apart
with wire reinforcement. Silt fence is not allowed as inlet protection.
*Tree Removal Permits and/or Approvals are required from the City of Wilmington and/or New Hanover County
PRIOR to clearing of the site.
*This permit does not preclude any permits or approvals which may be necessary such as City of Wilmington or
New Hanover County, INC DEMLR, C.A.M.A., and/or the US Army Corps. of Engineers, DEM Solid Waste or any
other agencies.
*No sediment shall leave the site in suspension of water.
(Continued) - Page Two
Permit# GP 04-22
*If plan revisions are necessary, you must submit a copy to this office for approval prigr to any field changes.
*If soil is brought onto this site or removed from this site, it must come from or be taken to an approved or
permitted site, to be identified to this office rp for to being brought onsite or removal from the site.
*All City and/or County and State drainage and stormwater requirements will be adhered to.
*If these measures fail to adequately control erosion, more restrictive measures will be required.
*If any phase of grading ceases for more than 90 calendar days, the site will be temporarily stabilized.
*All slopes must be stabilized within 21 calendar days of any phase of activity.
The approval of an erosion control plan is conditioned on the applicant's compliance with Federal and State
Water Quality laws, regulations, and rules.
*Note the required rates for seed, lime, fertilizer, and mulch in your seeding specifications.
*Enclosed is a Combined Self -Monitoring and Self -Inspection Form that meets the requirements of both the
NPDES Stormwater Permit for Construction Activities, NCG 010000 reporting and the Land Resources Self -
Inspection Program that satisfies the requirements of the Sedimentation Pollution Control Act. These are
mentioned below with specific requirements for each program. These reports are the responsibility of the
property owner. They require a rain gauge onsite, inspections and reporting every 7 calendar days and within
24 hours of every 1.0-inch rain per 24-hour period and at specific phases of construction. Additional copies of
this Combined Construction Inspection Report can be found at http://portal.ncdenr.org/web/ir/erosion .
Reports must be available onsite at all times. If you have questions, please contact New Hanover County
Engineering (910) 798-7139 or the Land Quality Section at the NC DEMLR Regional office at (910) 796-7215.
*Note the NPDES information from the State for sites disturbing 1 acre or more and the reporting
requirements. All NEW projects permitted after August 3, 2011 must include the following surface water
withdrawal locations and stabilization requirement designations on the plan in order to qualify for coverage
under the most recent NPDES Construction General Permit. All settling basins must have outlet structures that
withdraw water from the surface, with the exception of basins or traps that have a drainage area of less than 1
acre. The NPDES permit also requires ground cover within 15 calendar days on disturbed flat areas and ground
cover within 7 calendar days on all areas within HQW Zones, perimeter dikes, swales, ditches, perimeter slopes
and all slopes steeper than 3:1. Exceptions include slopes that are 10 feet or less in length and not steeper than
2:1 which must be stabilized within 14 calendar days and slopes greater than 50 feet which must be stabilized
within 7 calendar days. It requires inspections of all erosion control measures and reporting every 7 days and
within 24 hours of every 1.0-inch rain event in a 24-hour period. This permit also includes other new
requirements which are listed in the text of the NPDES Stormwater Discharge Permit for Construction Activities,
which is included with the original copy of each land -disturbing permit.
*Note the Land Resources Self Inspection Program Requirements. This program is separate from the NPDES
reporting and requires inspection and documentation after each phase of construction. These phases include:
Installation of perimeter erosion control measures, Clearing and Grubbing of existing ground cover, Completion
of any phase of grading of slopes or fills, Installation of storm drainage facilities, Completion of construction or
development, Establishment of permanent ground cover sufficient to restrain erosion and any Deviation from
the approved plan.
(Continued) - Page Three
Permit# GP 04-22
*Pre -construction meetings are optional. Contact Beth E. Wetherill at (910) 798-7139 to set up a meeting prior
to land -disturbing activity onsite. If you do not choose to have a preconstruction meeting prior to starting work
on site, you should contact us when activity begins and again when the initial measures have been installed.
This Permit will expire one year from date of issue
if no construction activity begins on site. This permit
may not be amended or transferred to another party
without approval of this office.
_ 7e" .
Beth Furr
Erosion Control Inspector/New Hanover County
Acknowledgment of receipt of Permit
6ourn�an-
By (please print)