HomeMy WebLinkAbout20141053 Ver 1_401 Application_201408271
71/3
L
Scoping Meeting Minutes for 17BP.8.R.61 (Bridge 439) held 08/16/13
1. Let Date September 23, 2014.
2. SEPI responsible for Roadway Design, Bid Documents, Right of Way acquisition Hydraulic
Design, Erosion Control, Permit Drawings, Traffic Control Plans and an environmental Pre -
Construction Notification (PCN).
3. DOT will be responsible for Structure Design, Structure General drawings, Geotechnical
Investigations, Speed Study, Surveying /Base Map Preparation, Utility Coordination and
Permit Application
4. Per field review a 2 barrel 10'x9', cast in place RCBC is proposed at a 450 skew.
Sills are anticipated in both barrels. A low flow channel to match the existing stream width
will be maintained to the greatest extent practicable.
5. A PCN will be required for this option due to stream impacts.
6. Overhead and buried utilities crossing the creek were observed
7. Not on a bike route
8. Not High Quality Water; no state stormwater permit required.
9. Speed limit posted at 40 mph
10. Existing bridge is on a horizontal curve; roadway will need to be superelevated.
11. Bridge 440 and 439 in Randolph County will be put under the same contract.