HomeMy WebLinkAboutFSM worksheet_230271NORTH CAROLINA DEPARTMENT OF TRANSPORTATION
FIELD SCOPING MEETING WORKSHEET
Design Build Process
TIP No.: N/A
WBS No.: BP6.R008
Field Scoping Meeting Date: 2/17/2022
Division: 6
Location: Virtual with individual site visits prior to FSM
Route (US/NC/SR): SR 1818 (Neils Eddy Rd)
County: Columbus
Project Description: Structure No. 230271 over Mill Creek on SR 1818 (Neils Eddy Rd)
Tier: Sub-Regional
Funding: TBD
Municipality: N/A
Attendees
Name
Phone No.
Email
Division Project Manager
Christy Huff
910-364-0682
chuff@ncdot.gov
Division Bridge Program Manager
Adam Britt
910-364-0603
atbritt@ncdot.gov
Assistant Division Bridge Program Manager
Jason Hatfield
910-364-0603
jrhatfield@ncdot.gov
Division Construction Engineer
Rusty Marsh
910-364-0600
rmarsh@ncdot.gov
Division Bridge Maintenance
Mike Fisher
910-364-0670
mdfisher@ncdot.gov
Bridge Maintenance Supervisor
Gary Hilburn
910-642-4388
gdhilburn@ncdot.gov
District Engineer
Ken Clark
910-642-3760
klclark2@ncdot.gov
Columbus County Maintenance Engineer
Barry Gelezinsky
910-642-7597
bwgelezinsky@ncdot.gov
Division Environmental Officer
Greg Price
910-364-0683
gwprice2@ncdot.gov
Division 6 Environmental Specialist II
Chris Underwood
910-364-0603
csunderwood@ncdot.gov
Water Resources
Hannah Sprinkle
910-796-7306
Hannah.sprinkle@ncdener.gov
Division Utility Coordinator
Rick Bounds
910-639-7345
rbounds@ncdot.gov
Hydraulics Engineer
Craig Lee
919-707-6708
cjlee@ncdot.gov
KCI
Charlie Flowe
919-926-4126
Charlie.flowe@kci.com
KCI
Liz Phipps
919-278-2473
Liz.phipps@kci.com
KCI
Leah Young
919-278-2487
Leah.young@kci.com
KCI
Barry Smith
919-278-2503
Barry.smith@kci.com
KCI
Bryan Hough
919-278-2468
Bryan.hough@kci.com
ECS
Mohammed Mulla
Existing Features
Feature Bridged: Mill Creek
Bridge Clear Deck Width: N/A (Ft.)
Approach Roadway width: 20 (Ft.)
Culvert Length: 63’ along CL of pipe (Ft.)
Deck Width (Out To Out): N/A (Ft.)
Water Depth: 3 (Ft.) fill depth 3.2 Ft
Height Bed-To-Crown: 13 (Ft.)
Year Built: 1985
Posted: SV - NP
TTST - NP
Superstructure: N/A
Substructure: N/A
Pier Type: N/A
Type of Structure: 3 LINES OF 12' X 7.8' STEEL PLATE ARCH, 62'6" ALONG CENTERLINE OF PIPE
Historic High Water (Elev. to the Existing Structure):
PRI:
DP: 0
SR: 99.82
School Bussing crossings per day: 2, Must leave county for detour
Posted Speed Limit Vicinity: 45 mph
Detour
Off-Site
Stage Construction
New Alignment
On-site
If Off-Site, Description Of Detour Route: SR 1421 to SR 1422 to SR 1419 to SR 1820
Approximate Length Of Detour? 7.6 miles; (5.4 additional miles)
Improvements Needed To Road(s) On Detour? Strengthening of SR 1818 to eliminate posting will be required.
Div. Traffic Eng. Recommend Off-site detour signing? Trailblazing with Street/Road names
Improvements Needed To Bridges On Detour? No
Are future plans for upgrading this roadway either at or in the vicinity of this project? No
Are Bridges On Detour Currently Programmed? No
Are There EMS Or Business Access Issues? NO EMS issues. There are trucking companies at the end of SR 1818
Are There Any Railroad Crossings On Detour? Yes, Railroad Tracks 0.5 miles from culvert
Should Work Zone Pedestrian Access Be Maintained During Construction? No
Utilities
Overhead Utility Lines In Conflict
Power Transmission Lines In Conflict
Telephone In Conflict
Cable Lines In Conflict
Fiber Optic In Conflict
Water In Conflict
Sewer In Conflict
Natural Gas In Conflict
Other In Conflict
Based on the past history near this project site, what is the Estimated Time Required to complete Utility Adjustments? Months
Is There Any Future Utility Construction Anticipated In The Project Area: Yes/No
Is A FEMA Buy-Out Property Being Impacted:
Environmental
Wetlands At Site: Yes
Comments:
Endangered Species In County: Four listed fauna – Northern Long-eared Bat, RCW, Alligator, Wood Stork. One listed flora – Cooley’s Meadowrue
T&E species effect: None likely
Trout Watershed: No
CAMA County: No
Primary Nursery Area: No
Moratoria: None
Which species: Cape Fear
Duration: No
Permits discussion:
Water Quality Classification:
303d:
Coast Guard Permit? No
Drainage Basin:
Riparian Buffer Rules: Yes/No
Is The Project Site In Or Near Any Of The Following:
National Forest: No
Wildlife Refuge: No
State, County, Or Local Park: No
Wild And Scenic River: No
Airport: No
Recreation or Power Generation: No
Water Supply Reservoir: No
Nutrient Sensitive Waters: No
Public Use Boat Ramp: No
Cemeteries: No
VAD/Farmland Protection: No
Game Lands: No
Known Or Potential Historic Properties In The Area: No
Architecture: No Survey
Archaeology: No survey
Is the Bridge Structure Itself, or any part thereof, considered Historic: No
Impacts to a Church, Community Center, Or Other Public Facility? No
Are there any potential Environmental Justice Issues? No
Is this a Statewide Bicycle Route or a Local Non-Marked Bicycle Route: No
Comments:
Geotechnical
Are There Any Historical and/or Vibration Sensitive Structures Near By? No
Comments:
Are There Any Known Landfills and/or Geo-environmental Hazard Sites at/or Within Close Proximity To The Project Site? No
Comments:
Are Any Impacts Anticipated To Natural Springs Or Artesian Wells? No
Comments:
Possible Foundation Type: H-piles
End Bents: Galvanized H-Piles Interior Bents:
Geotechnical firm will provide their own traffic control for field investigations.
Hydraulics
FEMA Approval? Yes. There is a Limited Detail Study. (FCS Needed)
Is There Unusual Scour Potential? No
Is Protection Needed? Standard
Are Banks Stable? Yes
Is Protection Needed? Standard
Appreciable Amount Of Large Debris? No
Placement Of Bents In The Water Be Allowed: N/A
Where: N/A
Structure Type: 60’ to 65’ Cored Slab
Superstructure Type: 24” Cored Slab
Culvert size: N/A
Length Of Structure: 60’ to 65’
Min. Number of Barrels: N/A
Span Arrangement: N/A
Add’l Comments: Flumes are preferred over piping across road; Offsets waived; Do not skew – prefer 90 degree. For structure layout, use 5’ offsets and 1:5:1 slopes.
Items To Be Discussed / Resolved At FSM By Attendees
Off-Site
Stage Construction
New Alignment
On-site
Environmental Document Prepared by: KCI (Reviewed & Submitted by DEO)
Federal CE Checklist State Minimum Criteria Checklist prepared by KCI
ADT: 780 vpd (per SIR)
NHS: No
Tier: Sub-Regional
Func. Class: Local Rural
Bridge Min. Clear Deck Width Recommended by Div.: 30’-10” ft CRW (Out to Out dimension 33 ft)
Roadway lane width: 10 ft lanes. 3’ Paved shoulders
Pave to face of guardrail and taper 8:1 to travel lane/paved shoulder? Pave to the face of Guardrail
Min. Pavement Surface Course: 3” S9.5B (2 lifts)
4” B25.0C
Existing Roadway: 20’
Pavement Marking: Thermo
Pavement Markers: Raised reflective
Will Railroad Involvement Be Required: No
Method of Clearing: II Modified
Truck Percentage: 6% per BIR
Reasonable Safe Speed per SIR: 55 mph
Existing posting = 45 mph, Design speed 50 mph
R/W by? NCDOT
R/W monuments? Pin & Cap
Salvageable materials: No
Contact Person/number:
Deliver to:
Removal of previous structure remnant abutments/piers: None
Sequencing priority in construction? N/A
Let Date: 6/5/2024 Production schedule will be accelerated to allow for the possibility of earlier let. Data collection
Comments: Data collection by NCDOT. Document preparation by KCI team.
ORD will not be required on this project.
To Do’s:
Scope-Schedule Meeting to take place March 22, 2022.