Loading...
HomeMy WebLinkAboutSW6211203_Design Calculations_20220310Sform wofer Monogement Reporf Mo rc h 10, 2022 McCain Gas Station NC Hwy 211 Hoke County, NC Prepared for: Double D Engineering, PLLC 150 S. Page Street Southern Pines, NC 28387 910-684-8646 Prepared by: Bowman 4006 Barrett Drive, Suite 104 Raleigh, NC 27609 (919) 553-6570 FIRM# F-1445 CA SEAL ❑51571 = TABLE OF CONTENTS OVERVIEW FIGURES SOILS SURVEY & SOIL INFORMATION USGS TOPOGRAPHIC MAP FEMA FIRM MAP WATER SURFACE CLASSIFICATIONS HUC NOAA POINT PRECIPITATION FREOUENCY ESTIMATES SHWT REPORT WATER QUANTITY -INFILTRATION BASIN DRAINAGE AREA MAP DESIGN SUPPLEMENT CN VALUES PRE -DEVELOPMENT HYDROGRAPHS POST -DEVELOPMENT HYDROGRAPHS TIME VS. VOLUME (STORAGE) TIME VS. ELEVATION (STAGE) ELEVATION -VOLUME -FLOW SUMMARY SCM SUMMARY TIME OF CONCENTRATION OVERVIEW This report contains the storm water management overview for the proposed gas station site on NC Hwy 211 in Hoke County. The project site is currently a gas station. The proposed site consists of 5.096 acres and approximately 3.69 acres will be disturbed as part of this project for the construction of the site improvements. The proposed site is located in Flood Zone `X' as shown on FEMA FIRM Panel 3710848600J with an effective date of 10/17/06. Flood zones are subject to change by FEMA. There are no existing stream or wetland features on the proposed property. The drainage area consists of 14,822sf (0.34 ac) off —site area that will be considered 100% BUA. The drainage area also consists of 10,993sf of existing impervious area that will be future NCDOT roadway. The proposed storm water management facility (infiltration basin) outlined in this report has been designed for post —development peak attenuation to treat the impervious areas of the development. The Infiltration Basin is designed to capture a drainage area of 3.43 ac with an impervious area of 2.10 ac. The balance of the site is open space and will by—pass the proposed SCM, The SCM are designed to treat a 1.0" storm event. Impervious Area Summary — Infiltration Basin Parking 56,714 1.30 Sidewalk 1910 0.04 Building 7,000 0.16 Future Impervious NCDOT 10,993 0.25 Off -Site 14,822 0.34 Total IA to Pond 91,439 2.10 The County Soils Survey indicates that Blaney Loamy Sand soils are present on the site. FIGURES 3V Y4S N 35' Y39'N Hydrologic Soil Group —Hoke County, North Carolina 3 — 3 Map Scale: 1:1,480If rated al A pd patrat (8.5" x 11') dxct. Meters N 0 2D 40 80 12'D � Fed 0 50 100 20D 300 Map pro]edbn: Web Mmallor Oxnercoordrotes: WGS84 Edgetl6: UTM Zane 17N WGS84 35° Y 48' N 35° Y 39' N l IND,•, Natural Resources Web Soil Survey 10/14/2021 Conservation Service National Cooperative Soil Survey Page 1 of 4 0 z w 0 w J IL N N M `7 m o_ C _ 0 n m 'U Z O U O L 41 3 E 1� y p ta 2 •C C a (,1 m 0 n tm U (p —0C n a 0 0 mW £ N O l0 .0 E (Li'Q @ M— O-'O l6 (6 N lD w N l0 O' n N 3 d (A U N .O O 3 O N C N E m c 3 L N 2 N U O N N Z N N N ...� 7 L a)N U N 3 w O« t N C d N 7 N Q U pN N L 2 O 3 E E V W m QL Cj M Q C` O N Q 10 (N�ppQ U (p O N L N C N O O O- N N Ui N 9 o E n m u ° w C o 0 3 o n ui 10 m E > > o o v _ C> C 3 U O 0 >. N U C w O E w pp n N O n E �` m N .� L C (0 O t -0 O N 2 Z 0 0 N 7 41 U O jq O L w 3 O C U (A v a u°'i E N d N (p C C T N-0 d O n 3 U N � L l6 N (n N N — Z O n� N N fA 2— O Y N N N O n C U f0 L w (O V 3 J O N n C O O = t O 10 - ,O N (0 .00 l6 � Q V N f/1 W N o N o ~ N N T >. 'O 'uj N d U N 4p1 N f0 Q! 016 a 3 (n UI l0 Ol T W 3 �_ w w 3 C �cu �p E 3 U V O 3 >. C 3 0 N � C Unl 0 (/1 g C w w 0.S C l0 w c °1 �Ii a> N > >, m p pn °� v E m a� �' m m 3p o0 a.w m a�i N (n °' E$ am L ?O C '� C O U W E_ U N N 0 d E d (nU C�7 f0 O N L U ^2 O.'OQ 10 L o 0 3 CO (n O �? (n� (0 p �N L 0 O t f- 0.9 N m > N o N C � 'O N 3 L a � O 0 U1 O N O O i m OE'a � O m o O L a m w in � o m U U 0 Z (5 o O � S 1 -01 � L c ©■ a o a LLCL 0 v v o n � a � s C a)oC _ O N C C O p0p�� O O Q O T y @ C 0f e e rn m d Q 1 a m m U 0 z of Q a m m U O Z Q a m C V) (A Q Hydrologic Soil Group —Hoke County, North Carolina Hydrologic Soil Group Map unit symbol Map unit name Rating Acres in AOI Percent of AOI BaB Blaney loamy sand, 2 to C 8 percent slopes Totals for Area of Interest Description 5.5 I 100,0% 5.51 100.0% Hydrologic soil groups are based on estimates of runoff potential. Soils are assigned to one of four groups according to the rate of water infiltration when the soils are not protected by vegetation, are thoroughly wet, and receive precipitation from long -duration storms. The soils in the United States are assigned to four groups (A, B, C, and D) and three dual classes (A/D, B/D, and C/D). The groups are defined as follows: Group A. Soils having a high infiltration rate (low runoff potential) when thoroughly wet. These consist mainly of deep, well drained to excessively drained sands or gravelly sands. These soils have a high rate of water transmission. Group B. Soils having a moderate infiltration rate when thoroughly wet. These consist chiefly of moderately deep or deep, moderately well drained or well drained soils that have moderately fine texture to moderately coarse texture. These soils have a moderate rate of water transmission. Group C. Soils having a slow infiltration rate when thoroughly wet. These consist chiefly of soils having a layer that impedes the downward movement of water or soils of moderately fine texture or fine texture. These soils have a slow rate of water transmission. Group D. Soils having a very slow infiltration rate (high runoff potential) when thoroughly wet. These consist chiefly of clays that have a high shrink -swell potential, soils that have a high water table, soils that have a claypan or clay layer at or near the surface, and soils that are shallow over nearly impervious material. These soils have a very slow rate of water transmission. If a soil is assigned to a dual hydrologic group (A/D, B/D, or C/D), the first letter is for drained areas and the second is for undrained areas. Only the soils that in their natural condition are in group D are assigned to dual classes. Rating Options — -Aggregation Method: Dominant Gflndition Component Percent Cutoff.- None Specified USDA Natural Resources Conservation Service Web Soil Survey National Cooperative Soil Survey 10/14/2021 Page 3 of 4 � �o J Q E2 C O Q N O J m a o 3 3 d � s J h a Q a s (0 ° J`� o ¢oo v c a m LL m w 0 0 Q o X O a N N U U m 0 m N LL O L C O O O N2 m N ° U° N.L. V 0 0 X m p0 w 0 Z mQ O Cal O J J y N C 0 0 d' m LL 0 w �Q m m ° LL Y Y U o m Q L 3 3 Q L e L J o m J c m m m �N� Z � ooam LLU QJQ w w 0 LL LL p Q o pC = oa o ai a wa Qi JC)cc aaxa �2 Qo �- U J N aQ wo i N Inx rLL 0 = �CL a co L 2 N m a c p m N O m o c� b0 N a °o E lwi c m c m C m o N m E a 'D'am ° m m c m na0 J-OE ao Co o O m U) -0 o o ~ C.c m O C O o Y j O m O J °� D 'N O O N m J D 76 r w E m Q m N N y m D N E m E>N) cCmo o> E o aCm> cUm .vM O NU :E Q o :E 2 a 10 eE m 0 Ea U N m 0) 0 iN EamEN Ocm c m N - a N O N a a m Tmm mYN.00 m _00 aNm+ m wwFmanmJ aIEcumOi y m O O E OL > Nm ONNE> ° O a> Q Jm U U 0] J x 0 Z yN w E N� a C_ m mN Ta m_ '• Cm I I c 3 c aL+ aco t m 3 E m D a ao Omm° ° 1 -_ I 11 E=0oNa '0 CCN) N a a c m z o J N m 0 0 E a Pi c c U) J U)x U) w w id O o EN amEm Lm>Z- - mJania m c co Jd2m w w� z o o m Ta m `Lm) N pY c m Q U w0Q G- m VNU E E u O .U m E m e m OQ E m m t "' co QU) tE m0 �EEw a wmo .E a Ftm m 3 D S 0N a� 00 u- o Io N 0 0 LO 0 0 A 0 LO N f-) a 0 G LD u 0 - Y E 2 Lt t L Gt75 y� i to cn L1 " C o �� 10/14/21, 9:56 AM Precipitation Frequency Data Server NOAA Atlas 14, Volume 2, Version 3 Location name: Raeford, North Carolina, USA' r1-4 Latitude: 35.0462°, Longitude:-79.3388' ���{I► Elevation: 462.95 tr Ij 'source: ESRI Maps " source: USGS POINT PRECIPITATION FREQUENCY ESTIMATES G M Bonnin, D Martin, 8 Lin, T. Partybok, M.Yekta, and D Riley NOAA, National Weather Service, Silver Spring, Maryland PF tabular I PF graphical I Maps & aerials PF tabular PDS-based point precipitation frequency estimates with 90% confidence intervals (in inches)1 Average recurrence interval (years) puration 0 2 0 10 25 50 100 2001 500 1000 5 min 0.437 1 0.516 0.602 0.666 0.742 0.796 0.848 0.897 0.956 1.00 (0.398-0.483 0.471-0.570 0.548.0.664 ( 0 605-0.733 0-671.0.815 0.718-0.874 0.761-.0.930 0 800-0.983 0.846-1.051 (0.880 1.10 0.699 0.826 0.963 1.07 1.18 1.27 1.35 1.42 1.51 1.58 10arlin (0 636-0.771) J(0.753-0.912 0.878-1.06 (0 967-1.1 7 1.07-1.30) 1.21-1.48 (1 27-1.56) 1(1 34-1.66 1.39-1.73 0.873 1.04 1.22 1.35 1.50 1.61 1.70 1.79 1.90 1.98 15-rrlin (0.796-0,963)1(0946-115 111-135) 122-1.49 136-1.65 1.45-176 153-1.87 160-1.97 168-2.09 1.74-217 30{T1in 3 744) 1 09��32 (� 3141368) (1 58 191) [1.779515) (2.01 2F-272Z (? S 72G5 P 34-286) 2 49,0G j (2.6a33 (2 2 3152} 1.49 1.80 2.22 2.54 2.96 3.28 3.60 3.92 4.35 4.68 60 min 1 36-1 Cu(1164.1 99 (2 02-2 45 (2.31 B0 . fir _3.25 2 967.50 3 22.3 94 3 50-4_^L 9 3 64 4 4 11-5 14 2-hr 1.75 1.58-1 95 2.12 2.65 1 (240.2.66) 3.07 (2 77-3 41) 3.62 11 (3.24-4.02) 4.05 (3 62-4 50) 4.49 [3.99.4.99} 4.94 (4 36-5.48) 5.54 1(4 84-6 1 6.02 5 22-6.68) 3-hr 1.85 2.24 11 2.82 1 3.28 1 3.92 4.44 4.97 5.53 6.32 6.96 (1 67-2 07) 1 (2 03-2 50) 11 (2.55-.3.15) 1 (2.96.3.66) 1 (3.51.4.36) 1 (4.39-5.52) (4 85-6 14) (6.48.7 01) 1(5 96-T 72) 6-hr 2 0 2045 2 2--2796) 3.05-3.73) f3.54-4.34 (4.215019) 4 5-5 88) 5 30-6 84 5 8777036 8.8.48844 7 5 9832) 2.60 3.14 3.99 4.67 5.64 6.44 7.28 8.19 9.49 10.6 12-hr (2 35-2 89) (2 85-3 50 3 604 43 4- 1-5.18 5.04-6.23 5 71-7 10 6.40=8 02 7 12.9.01] 6.12-10.4 [$.90-11 6 24-hr 3.05 3.69 4.67 5.44 6.51 7.36 8.23 10.4 11.4 (2.83-3.31 (3 42-4 01 4.32-5.0G r (5.02-a.89 5.98-7.04 G 74-7.95 (7.52.8.90 8 [9.4f 11 2 10.3-12.3 2�ay F-7355- E11) (3 30 3583) (3 98 4862 4.99-5 79 5.78 6472 6. 54299 7 0 9700 (B 57-310 1 .(9 (10 7- 2.S) (11 6- 3 8) 3.77 4.64 5.66 6.55 7.77 8.74 9.75 10.8 12.2 13.3 3-day (3 51-4 04) 4 23-4 87 5.27=6 07 (6.09.7.02) 1 (7 20-8 32 8.D7-9.37 8 97-10.4 9 88-11,6 11 1-13.1] j1.2.1-14.3} 3.98 4.79 5.94 6.86 8.12 9.12 10.2 11.2 12.7 13.8 4�ay 3 73-4 26 4 48-5 12 (5 55.6 34) (E.40.7 31) 1 (7 54-8 66) {6 45.9.73 9 37-10,6 10 3-12 0 (11 6-13.6) 11(12 6-14.8 7�ay 4.61 5.52 6.76 7.75 9.10 10.2 11.3 12.4 14.0 15.2 (4 32-4 93) (5 16-5 90) (6 31-7-23) (7.2-6:28) (6.46.9 73) ( 9.45.10.]) (10 4-12 1) ( 11.5-13.3) (12 8-15 0) (13.9-16.4) 7-77377F-7-6- 0 10-day 74-15 4 g85962 5.93 fi070 7. 58108 6. 0 9316 (9.3P 10.6 10(4- 1.8 11 4-13.0 1214-14.2 13 6 (1416 1 41 8.41 9.99 11.2 12.9 14.2 15.5 16.8 18.6 20.1 20�iay ? 5.7 7 53 7 95-8.92)P�(11 2-10 8 10.6-11.9) 12 1-13 7 13.3-15.0 14 5-16 4 (15 7-17.9 ) 17.119 B 18 5-21.3 30-day ( 8.83 B 35 9.34 10.4 2.2 9 85-11 05-12.9 13.5 12 7-14.3 6 15.3 14 4-16 16.6 15 7-17 G 18.0 16 9-19 1 19.3 18 1-20.5 21.1 19.7-22.5 22.5 21.0.24.0 45�1ay 0.1) (10 6 111.6) (12 4-13.8) 413-15.9) (1516 5) [1715--19.5) (18.8 .1 2 6) (21 4� 4 1 23214 6.1 (24.3-27.5) 60{iay 9--16 8.24.4 12 7- 4 1 14 5 1fi 9- B 7 1814-20.5 2024- 2 7 (21 23.3-26 0 24262 6 2624.29 7 2728--1.3 Precipitation frequency (PF) estimates in this table are based on frequency analysis of partial duration series (PDS). umbers in parenthesis are PF estimates at lower and upper bounds of the 90% confidence interval The probability that precipitation frequency estimates (for a given duration and average recurrence interval) will be greater than the upper bound (or less than the lower bound) is 5% Estimates at upper bounds are not checked against probable maximum precipitation (PMP) estimates and may be higher than currently valid PMP values Please refer to NOAA Atlas 14 document for more information Back to Top PF graphical https://hdsc.nws.noaa.gov/hdsc/pfds/pfds_printpage.html?lat=35.0462&Ion=-79.3388&data=depth&units=english&series=pds 1/4 Scott Cole, NCLSS 312 Copples Road Ext Asheboro, NC 27205 (336) 460-4554 Double D Engineering, PLLC Attn: Mr, Lee Humphrey 150 S. Page Street Southern Pines, NC 28387 September 21, 2021 Re: Seasonal High -Water Table Identification and Soil Infiltration Rates: Proposed McCain Gas Station; Hoke County NC Parcel (Altparno) 19186 (6797 Aberdeen Road, Raeford, NC) Soil conditions and infiltration rates were evaluated and measured on the above -referenced property within the proposed storm water BMP device. Work was conducted in accordance with Parts A-2 and C-1 of the North Carolina Department of Environmental Quality Stormwater Design Alamual. Soil samples were evaluated with a hand auger. SEASONAL HIGH WATER TABLE IDENTIFICATION Seasonal High Water Table depth is determined by field evaluation for soil wetness conditions which are indicated by the presence of redoximorphic (redox) features with a chroma of 2 or less (in Munsell color notation) in mottles or the horizon matrix. Colors of chroma 2 or less due to relic minerals from parent material (underlying rock), anaerobic activity created by placement of fill material, or soil textural class transitions (perched water) are not considered as indicators for seasonal high water. Upon determination of SHWT depth, an additional 6" will be deducted fi-om the observed depth to account for capillary fringe water movement above the SHWT. Stormwater infiltration trenches are designed to ensure the lowest point is at least two feet above the Seasonal High Water Table (SHWT). The SHWT for this r7rolect was not observed within 15' of the around surface. Soil conditions evaluated to elevation 4221. SATURATED HYDRAULIC CONDUCTIVITY (K at) Soils evaluated across most of this property are typical of those within the Blaney Loamy Sand series (BaB). These are deep, well drained, moderately permeable soils often found on side slopes and narrow ridges. Infiltration rates were measured to determine if soil conditions were suitable for the installation of stormwater infiltration trenches. Infiltration rates were measured using a Johnson Constant Head Permeameter. Measurements were recorded at varying intervals until equilibrium was reached. A summary of observations within the proposed Stormwater BMP Device is shown in the table below, BMP Device Site Test Location SHWT Munsell Color Ksat 4l Ksat #2 (feet below Notation round surface 1 Not Observed N/A 0-4' 4'-15' within 15' of Loamy Sand I Loamy Sand ! ground surface Sand Sandy Loam 18" / hour 10" / hour Scott Cole, NCLSS 312 Copples Road Ext Asheboro, NC 27205 (336) 460-4554 CONCLUSION Field evaluation of hydraulic conductivity provides estimations of soil infiltration rates; however, methods used to measure these rates can influence the results. Side walls of the bore hole are "smeared" by the soil auger as the hole is prepared and loose soil in the bottom of the hole is placed in suspension when water is applied; both of these factors negatively influence water infiltration rates. To help overcome these issues, after excavation of each infiltration trench, it is recommended the trench bottom and sidewalls be raked and dusted with pulverized limestone. These are practices that have been in place within the on -site wastewater industry to help loosen the soil and aid in restoration of soil structure. I am pleased to be of service in this matter and can be contacted at your convenience should you have any questions concerning infonnation within this report. Thank ou, Scott Cole North Carolina Licensed Soil Scientist eoK sNKLQ e�� a� ��7262� C; Ink Vn CPI r 458 \:7A 4 Parcel: 1918.6 At IL Isis 1 OjA0 no shwt pp BMP Site SHWT: Not Observed within 115'of surface Solt 8C Ksat 0-4 Loamy Sand I Sand: 25" 1 hour z ■Ksat 4-15' Loamy Sand I Sandy Loam: 10" hour N �9,JkNkKtl 12 '6 1 inch = 100 feet _ AFC 470 f •_. z" F C � ti. R - + s.4fr r.a shwl 9 �0 { ` BMP Site SHWT: Not Observed within 15' of surface r+. ��o IL :• I Ksat 0-4' Loamy Sand/ Sand: 25" / hour '0 ' " Ksat 4-15Loamy Sand f Sandy Loam: 101 hour J ryNK Y' � 1 inch = 100 feet° Source: Esri Maxar,GI •ye. Earthslar Geografhics C'�lE:=r. ir? i,it "' �I_' i =•. WATER QUANTITY -INFILTRATION BASIN SUPPLEMENT-EZ COVER PAGE FORMS LOADED PROJECT INFORMATION 1 Project Name McCain Gas Station 2 Pro'ect Area (ac) 5.096 3 Coastal Wetland Area (ac) _ 4 Surface Water Area (ac)_ 5 Is this project High or Low Density? High 6 Does this project use an off -site SCM? No COMPLIANCE WITH 02H .1003(4) 7 Width of vegetated setbacks provided feet N/A 8 Will the vegetated setback remain vegetated? N/A 9 If BUA is proposed in the setback, does it meet NCAC 02H.1003(4)(c-d)? _ No 10 Is streambank stabilization proposed on this project? No NUMBER AND TYPE OF SCMs: 11 Infiltration System 1 0 12 Bioretention Cell 13 Wet Pond 0 14 Stormwater Wetland 0 15 Permeable Pavement 0 16 Sand Filter 0 17 Rainwater Harvesting RWH) 0 18 Green Roof 0 19 Level Spreader -Filter Strip (IS-FS) 0 20 Disconnected Impervious Surface (DIS) 0 21 Treatment Swale 0 22 Dry Pond 0 23 StormFilter 0 0 24 Silva Cell 25 Bayfilter 0 26 Filterra 0 FORMS LOADED DESIGNER CERTIFICATION 27 Name and Title: Carlo Pardo, PE Bowman North Carolina, Ltd. 4006 Barrett Drive, Suite 104 28 Organization: 29 Street address: City, State, Zip: 30 Raleigh, NC 27609 919-553-6570 cpardo@bowman.com 31 Phone number(s): _ Email: 32 Certification Statement: I certify, under penalty of law that this Supplement-EZ form and all supporting information were prepared under my direction or supervision; that the information provided in the form is, to the best of my knowledge and belief, true, accurate, and complete; and that the engineering plans, specifications, operation and maintenance agreements and other supporting information are consistent with the information provided here. �����ltliililll11j11 ESS _ SEAL 051571 - T 3 lo% Date DRAINAGE AREAS 1 Is this a hi h density project? Yes 2 If so, number of drainage areas/SCMs 1 3 Does this project have low density areas? No 4 If so. number of low density draina a areas 0 5 Is all/part of this project subject to previous rule versions? No FORMS LOADED DRAINAGE AREA INFORMATION Ent re Site 1 4 Type of SCM - Infiltration Basin 5 Total drainage area (sq ft) 221969 sf 149468 6 Onsite drainage area (sq ft 134646 7 Offsite drainage area (sq ft 14822 8 Total BUA in project (sq ft) 65624 sf 91439 sf 9 New BUA on subdivided lots (subject to permitting) (sq ft 10permitting) New BUA not on subdivided lots (subject to s 11 Offsite BUA (sq ft 14822 sf 12 Breakdown of new BUA not on subdivided lots: Parking (sq ft 56714 sf 56714 sf Sidewalk (sq ft 1910 sf 1910 sf Roof (sq ft) 7000 sf 7000 sf Roadway s ft Future (sq ft) 10993 sf Other, please specify in the comment box below (sq ft 13 New infiltrating permeable pavement on subdivided lots (sq ft 14 New infiltrating permeable pavement not on subdivided lots s ft 15permitting) Existing BUA that will remain (not subject to s ft 13158 sf 16 Existing BUA that is already permitted (sq ft 17 Existing BUA that will be removed (sq ft 2091 sf 2091 sf 18 Percent BUA 29.56% 61.2% 19 Design storm inches 1.0 in 20 Design volume of SCM (cu ft) 7481 cf 21 Calculation method for design volume Simple Method ADDITIONAL INFORMATION Please use this space to provide any additional information about the 22 drainage area(s): Entire Site: Existing 19,988 sf Impervious Area Future: Existing Impervious area that will be future NCDOT roadway INFILTRATION SYSTEM 1 Drainage area number 1 2Minimum required treatment volume (cu ftl 7481 cF�� 3 Is the SCM sized to treat the SW from all surfaces at build -out? Yes 4 Is the SCM located away from contaminated soils? Yes 5 What are the side slopes of the SCM (H:V or enter "Vertical' for trenches)? 3:1 6 Does the SCM have retaining walls, gabion walls or other engineered side slopes? No 7 Are the inlets, outlets, and receiving stream protected from erosion (10-year storm)? Yes 8 Is there an overflow or bypass for inflow volume in excess of the design volume? Yes 9 lWhat is the method for clewatering the SCM for maintenance? Pump (preferred) 10 If applicable, will the SCM be cleaned out after construction? Yes 11 Does the maintenance access comply with General MDC (8)? Yes 12 Does the drainage easement comply with General MDC (9)? Yes 13 If the SCM is on a single family lot, does (will?) the plat comply with General MDC (10)? N/A 14 Is there an O&M Agreement that complies with General MDC (11)? Yes 15 Is there an O&M Plan that complies with General MDC (12)? Yes 16 Does the SCM follow the devicespecific MDC? Yes 17 lWas the SCM designed by an NC licensedprofessional? Yes INFIITRATW W CVSTFM Mnr FRnm NH _inrl 18 1 Proposed slope of the subgrade surface (%) 0% 19 Are terraces or baffles provided? No 20 T e of retreatment: Forebay Isnf/a Onto 21 Was the soil investigated in the footprint and at the elevation of the infiltrations stem? Yes 22 SHWT elevation fmsl < 422.0 23 Depth to SHWT per soils re ort (in) > 15ft 24 Ground elevation at boring in soils report (fmsl) 437.00 25 Is a detailed hydrogeologic study attached if the separation is between 1 and 2 feet? N/A 26 ISoil infiltration rate in/hr 9.00 27 j Factor of safety (FS) (2 is recommended): 2.00 Elevations 29 Bottom elevation (fmsl) 436 ft 30 Storage elevation (fmsl) 437.3 ft 31 By ass elevation (fmsl) 439.4 ft For Basins Dnl 32 Bottom surface area ft2 5311511 33 Store a elevation surface area (ft) 6560. ft Fnr Trenches Only 34 Length (ft) 35 Width (ft) 36 Perforated pipe diameter, if applicable (inches) 37 Number of laterals 38 Total length of perforated piping 39 Stone type, if applicable 40 Stone porosity (%) 41 Is stone free of fines? 42 Is the stone wrapped in geotextile fabric? 43 Has at least one inspection port been provided? volumesiurawaown 44 Design volume of SCM (cu ft) 7481 cf 45 1 Time to draw down hours 3.7 hrs ADDITIONAL INFORMATION 46 Please use this space to provide any additional information about the infiltration system(s): Line 26-The infiltration rate was intentially lowered to half of the 18 in/hr to account for cloaainc of the soils that will haooen over time. nfiltration 1 11:11 AM 3/10/2022 3, Bowman North Carolina, Ltd. McCain Gas Station, Raeford, Hoke County, NC Curve Number Calculation (CN) Pre -Developed Conditions Drainage Area (acres 5.41 Existing Soil Grau s Soil Group Map Symbol C BaB Existing Land Uses: Land Use Description Wooded - Good Stand Open Space - Good Stand Impervious -Gravel Impervious -Parking Soil Description Acres Percent of DA Blaney Loamy Sand 5.41 100, Existing Soil GmiT Acres Curve # Wer�ghted CN C 3.66 74 50.1 C 1.00 77 14.2 C 0.17 90 2.8 C 0.58 98 10,5 Cumulative Curve # = 77.6 Bowman North Carolina, Ltd. McCain Gas Station, Raeford, Hoke County, NC Curve Number Calculation (CN) Post -Developed Conditions Drainage Area (acres L 3.43 Existing Soil Groups. Sod Group Map Symbol Soil Description Acres Percent of DA C BaB Blaney Loamy Sand 3.43 100% Proposed Land Uses: Land Use Description Existing Soil Group Acres Curve # Weti hted CN Wooded - Good Stand C 0.39 74 8.4 Open Space - Good Condition C 0.94 77 21.1 Impervious Area -Existing C 0.41 98 11.7 Impervious Area -Proposed C 1.69 98 48.3 Cumulative Curve # = 89.5 Bowman North Carolina, Ltd. McCain Gas Station, Raeford, Hoke County, NC Curve Number Calculation (CN) Post -Developed Conditions Bypass Drainage Area (acres) 1.98 Existina Soil Grouvs Soil Grouo Map Symbol Soil Description Acres Percent of DA ! C BaB Blaney Loamy Sand 1.98 100% Proposed Land Uses' Land Use Description Existing Soil Group Acres Curve # Weighted CN Wooded - Good Stand C 0.41 74 15.3 Open Space - Good Condition C 1.30 77 50.6 Impervious Area C 0.27 98 13.4 Cumulative Curve # = 79.2 Infiltration Basin Design Site Information Sub Area Location: Drainage To Infiltration Basin Drainage Area (DA) = 3,43 Acres 149468 sf Impervious Area (IA) = 2.10 Acres 91439 sf Percent Impervious (1) = 61.2 % Required Water Quality Volume Design Storm = 1 inch Determine Rv Value = 0.05 + .009 (1) = 0.60 in/in Water Quality Volume = 0.172 ac-ft Water Quality Volume = 7,481 cf Water Quality Volume = 0.601 inches of runoff NOAA 1- ear, 24-hour event = 3.05 inches Minimum Surface Area SA = (12-FS"DV)/(K"T) Factor of Safety (FS) = 2 Design Volume (DV) = 7480.7 cf Hydraulic Conductivity of Soil = 9.00 in/hr Max Dewatering Time = 72 hours SA = 277.1 sf Drawdown Time T = FS - (DV`12)/(K*SA) Factor of Safety (FS) = 2 Design Volume (DV) = 7480.7 cf Hydraulic Conductivity of Soil = 9.00 in/hr Surface Area Provided = 5385 sf Drawdown Time = 3.7 hours Z STAGEJSTORAGE TABLE INFILTRATION BASIN STAGE ELEVATION CONTOUR INCREMENTAL TOTAL (FT) (FT) AREA (SF) STORAGE (CF) STORAGE (CF) 0.0 436.0 5385 0 0 1.0 43ZO 6275 5830 5830 1.3 437.3 6560 1925 7755 (WOv) 2.0 438.0 7230 4827 12582 3.0 439.0 8235 7733 20314 4.0 440.0 9300 8768 29082 5.0 441.0 10420 9860 38942 STORMWATER MANAGEMENT DESIGN INFILTRATION BASIN RIVER BASIN: LUMBER RECEIVING STREAM: MOUNTAIN CREEK STREAM INDEX: 14-2-16-(2) STREAM CLASS: C HUC: 03040203 POND DESIGN SUMMARY DRAINAGE AREA TO POND: 3.43 ACRES SITE IMPERVIOUS AREA TO POND: 1.69 ACRES OFF -SITE DESIGN IMPERVIOUS AREA TO POND: 0.41 ACRES TOTAL DESIGN IMPERVIOUS AREA TO POND: 2.10 ACRES PRE -DEVELOPED POST -DEVELOPED POST -DEVELOPED POST -DEVELOPED POST -DEVELOPED THROUGH POND BYPASS COMBINED DRAINAGE AREA: 3.43 AC 3.43 AC 1.98 AC CURVE NUMBER: 77.6 89.5 79.2 INFILTRATION RATE: 9.0 IN/HR 1.0" STORM EVENT: 0.818 CFS 0.000 CFS 1-YEAR STORM EVENT: 8.767 CFS 11.25 CFS 0.000 CFS 3.498 CFS 3.498 CFS 2-YEAR STORM EVENT: 12.52 CFS 14.42 CFS 0.000 CFS 4.927 CFS 4.927 CFS 10-YEAR STORM EVENT: 23.82 CFS 23.05 CFS 0.000 CFS 9.137 CFS 9.137 CFS 1 DO -YEAR STORM EVENT: 42.80 CFS 36.64 CFS 18.08 CFS 16.12 CFS 34.20 CFS ■ ■ � Bqm ( ■;� � / - ■ ■ _ - _/ « (� k UNDISMED 1N_SrrU - > - � J.% g ■ &-© 2 /| § § � � k/� •§ � � §k§ §f 2 � § §|§ | §§| } �d§ ■ §2& , - ! m�<VANS G2 k � k Hydrograph Report Hydraflow Hydrographs Extension for AutoCADO Civil 3D® 2009 by Autodesk, Inc. v6.066 Wednesday, Nov 3, 2021 Hyd. No. 3 Post Through SCM Hydrograph type = Reservoir Peak discharge = 18.08 cfs Storm frequency = 100 yrs Time to peak = 12.03 hrs Time interval = 2 min Hyd. volume = 16,757 cuft Inflow hyd. No. = 2 - SCM Post -Developed Reservoir name = BMP Pond Max. Elevation = 440.20 ft Max. Storage = 30,902 cuft Storage Indication method used. Exfiltration extracted from Outflow. Hydrograph Discharge Table ( Printed values - 1.00% of Qp ) Time Inflow Elevation Clv A Clv B Clv C PfRsr Wr A Wr B Wr C Wr D Exfil Outflow (hrs) cfs ft cfs cfs cfs cfs cfs cfs cfs cfs cfs cfs 11.93 36.64 << 439.58 ----- ----- ----- ----- 2.052 ----- -- -- 1.845 2.052 11.97 35.13 439.96 ----- ----- -_--- --- 10.89 ----- ----- ----- 1.928 10.89 12.00 27.39 440.15 ----- - ---- ----- 16.94 ----- ----- _--- 1.973 16.94 12.03 17.15 440.18 << ----- ----- ----- --- 18.08 ----- ----- ----- 1.981 18.08 << 12.07 9.404 440.12 ----- ----- ----- ----- 15.77 ----- ----- ----- 1.965 15.77 12.10 5.826 440.01 ----- ----- - --- ---- 12.49 ----- -_--- ----- 1.941 12.49 12.13 4.776 439.91 ---- ----- ----_ ----- 9.492 ----- - --- ----- 1.918 9.493 12.17 4.570 439.83 ----- ----- -- -- - -- 7.426 ----- ----- ----- 1.900 7.426 12.20 4.376 439.78 ---- ----- ----- _- - 6.018 ----- ----- ----- 1.888 6.018 12.23 4.181 439.73 _---- ----- ----- -- -- 5.031 ----- ----- ----- 1.878 5.031 12.27 3.987 439.70 -- -- ----- ----- 4.263 ----- ----- ---- 1.871 4.263 12.30 3.792 439.67 - - ----- ----- ----- 3.736 ----- - - ----- 1.865 3.736 12.33 3.596 439.65 ----- ----- -_--- ----- 3.288 ----- - -- ----- 1.860 3.288 12:37 3.401 439.63 ----- - -- --- -- 2.901 ----- ----- ----- 1.855 2.901 12.40 3.205 439.61 ----- ---- -_-- - -- 2.560 ----- ----- - 1.851 2.560 12.43 3.009 439.60 -- - -- ----- ----- 2.268 ----- ----- - - 1.848 2.268 12.47 2.813 439.58 ----- -- ----- ----- 2.044 ----- - -- - 1.845 2.044 12.50 2.616 439.57 --_-- - - ----- ----- 1.825 ----- ----- ----- 1.841 1.825 12.53 2.435 439.55 ---- - -- ---- ----- 1.612 ----- ----- 1.838 1.612 12.57 2.300 439.54 ----- ----- ----- ----- 1.410 ----- --- - 1.835 1.411 12.60 2.214 439.53 ----- ----- ----- ----- 1.226 ----- -- __ 1.833 1.226 12.63 2.160 439.52 ----- ----- - ----- 1.064 ----- - ----- 1.830 1.064 12.67 2.115 439.51 ----- ----- ----- ----- 0.923 ----- ----- ----- 1.828 0.923 12.70 2.070 439.50 ----- ----- ----- ----- 0.810 ----- ----- ----- 1.826 0.810 12.73 2.026 439.49 ----- ----- ----- ----- 0.747 ----- - _ ----- 1.825 0.747 12.77 1.981 439.48 ----- ----- ----- ----- 0.687 ----- --- ----- 1.823 0.687 12.80 1.936 439.48 ----- - _-- ----- ----- 0.628 ---- ----- ----- 1.821 0.628 12.83 1.892 439.47 ----- ----- -_- ----- 0.571 ----- ----- ----- 1.820 0.571 12.87 1.847 439.46 ----- ----_ ----- ----- 0.516 ----- ----- ----- 1.818 0.516 12.90 1.802 439.46 ----- ----- ----- ----- 0.461 ----- ----- ---- 1.817 0.461 12.93 1.757 439.45 ----- ----- ----- ----- 0.408 ----- ----- ----- 1.815 0.408 12.97 1.713 439.44 ----- ------ ----- ----- 0.356 ----- ----- ----- 1.814 0.356 13.00 1.668 439.44 ----- --- --- 0.305 ----- ----- ----- 1.813 0.305 13.03 1.625 439.43 ----- ----- ----- 0.255 ----- ----- ----- 1.811 0.255 13.07 1.589 439.43 -- -- - ----- ----- 0.206 ----- ----- ---- 1,810 0.206 End use .l-hrs 11/1/21, 3:26 PM ECMDS 7.0 NORTH AMERICAN GREEN SPILLWAY ANALYSIS > > > Grass Spillway North American Green 5401 St. Wend el -Cynthia na Rd. Poseyville, Indiana 47633 Tel. 800.772.2040 > Fax 812.867.0247 - www.nagreen.com ECMDS v7.0 Name Grass Spillway Discharge 18.08 Peak Flow Period 1.5 Channel Slope 0.3333 Channel Bottom Width 10 Low Flow Liner Retardence Class C 6-12 in Vegetation Type Mix (Sod and Bunch) Vegetation Density Very Good 80-95% Soil Type Sandy Loam (GM) Shoremax - Class C - Mix (Sod & Bunch) - Very Good 80-95% Normal Permissible Calculated Safety Staple Phase Reach Discharge Velocity Mannings N Remarks Depth Shear Stress Shear Stress Factor _ Pattern Shoremax w/ Straight 18.08 cfs 10.24 ft/s 0.18 ft 0.026 8.5 Ibs/ft2 3.67 Ibs/ft2 2.32 STABLE F P300 Unvegetated Underlying Straight 18.08 cfs 10.24 ft/s 0.18 ft 0.026 5.68 Ibs/ft2 3.55 Ibs/ft2 1.6 STABLE F Substrate Shoremax w/ Straight 18.08 cfs 9.79 ft/s 0.18 ft 0.028 14 Ibs/ft2 3.84 Ibs/ft2 3.64 STABLE F P300 Reinforced Vegetation Underlying Straight 18.08 cfs 9.79 ft/s 0.18 ft 0.028 8.5 Ibs/ft2 3.71 Ibs/ft2 2.29 STABLE F Substrate https:Hecmds.com/project/139235/spillway-analysis/213335/show 1 /1 Z O Q W J W � < J J_ d V) Z W m Y Z Z m O W W W J O W [L O F- Z O � O 2� a Q z ��\ W z 32 U 3ti to Q N V) N t0 3 of m o ig: 2 ca C3 W M Z � M O —i Kj 03 0 U L cy 00 O 7-7 00 Acc C- _Z _ Z n- J Cn p L` z C) w Cj_ X C> W O F Q Z_ J Z � J N p LL- Z O LLJ CL O C) M I I z O Q J W Q I J_ 0_ Sl J Q F— W z Q Z J J � w J z = V) m U V) Q 2 I� C1 W Q p w M C) r - — - Le) U O Z p QW O ME z Pond Report Hydra Flow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2022 Thursday, 03 / 10 / 2022 Pond No. 1 - BMP Pond Pond Data Contours -User-defined contour areas. Average end area method used for volume calculation. Begining Elevation = 436.00 ft Stage / Storage Table Stage (ft) Elevation (ft) Contour area (sgft) Incr. Storage (cuft) Total storage (cuft) 0.00 436.00 5,385 0 0 1.00 437.00 6,275 5,830 5,830 1.30 437.30 6,560 1,925 7,755 2.00 438.00 7,230 4,827 12,582 3.00 439.00 8,235 7,733 20,314 4.00 440.00 9,300 8,768 29,082 5.00 441.00 10,420 9,860 38,942 Culvert / Orifice Structures Weir Structures [A] [B] [C] [PrfRsr] [A] [B] [C] [D] Rise (in) Inactive Inactive Inactive Inactive Crest Len (ft) = 10.00 0.00 0.00 0.00 Span (in) = 0.00 0.00 0.00 0.00 Crest El. (ft) = 439.40 0.00 0.00 0.00 No. Barrels = 0 0 1 0 Weir Coeff. = 2.60 3.33 3.33 3.33 Invert El. (ft) = 0.00 0.00 0.00 0.00 Weir Type = Broad --- --- --- Length (ft) = 0.00 0.00 0.00 0.00 Multistage = No No No No Slope (%) = 0.00 0.00 0.00 n/a N-Value = 013 .013 .013 n/a Orifice Coeff. = 0.60 0.60 0.60 0.60 Exfil.(in/hr) = 9.000 (by Contour) Multistage = n/a No Yes No TW Elev. (ft) = 0.00 Note: Culvert/Orifice outflows are analyzed under inlet (ic) and outlet cc) control Weir risers checked for orifice conditions (ic) and submergence (s) Stage (ft) Stage I Discharge V Vv0.00 6.00 - Total Q 12.00 18.00 24.00 30.00 36.00 42.00 48.00 54.00 Elev (ft) 441.00 440.00 439.00 438.00 437.00 436.00 60.00 Discharge (cfs) Hydrograph Summary Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D0 by Autodesk, Inc. v2022 Hyd. No. i Hydrograph type (origin) Peak flow (cfs) Time interval (min) Time to Peak (min) Hyd. Inflow volume hyd(s) (cult) Maximum elevation (ft) Total strge used (cuft) Hydrograph Description 1 SCS Runoff 8.767 2 722 23,105 -•••- SCM Pre -Developed 2 SCS Runoff 11.25 2 716 23,197 -- --- ------ SCM Post -Developed 3 Reservoir 0.000 2 854 0 2 437.61 9,886 Post Through SCM 4 SCS Runoff 3.498 2 722 9,172 ------ ----- ------ SCM Post -Developed Bypass 6 SCS Runoff 0.818 2 146 3,527 ------ -- - --- 1.0 Post -Developed to SCM 7 Reservoir 0.000 2 210 0 6 436.18 1,059 1.0inPostThrough SCM Infiltration.gpw Return Period: 1 Year Thursday, 03 / 10 / 2022 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2022 Hyd. No. 1 SCM Pre -Developed Hydrograph type = SCS Runoff Storm frequency = 1 yrs Time interval = 2 min Drainage area = 5.410 ac Basin Slope = 0.0 % Tc method = Total precip. = 3.05 in Storm duration = 24 hrs Thursday, 03 / 10 / 2022 Peak discharge = 8.767 cfs Time to peak = 722 min Hyd. volume = 23,105 cuft Curve number = 77.6 Hydraulic length = 0 ft Time of conc. (Tc) = 10.40 min Distribution = Type II Shape factor = 484 SCM Pre -Developed Q (cfs) Hyd. No. 1 -- 1 Year Q (cfs) 10.00 10.00 8.00 8.00 6.00 6.00 4.00 4.00 2.00 2.00 000 000 0 U0 240 MO 480 600 720� 840 960 —fb8d 1200 1320 1440 1564 Hyd No. 1 Time (min) 3 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 31D® by Autodesk, Inc. v2022 Hyd. No. 2 SCM Post -Developed Hydrograph type = SCS Runoff Peak discharge Storm frequency = 1 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 3.430 ac Curve number Basin Slope = 0.0 % Hydraulic length Tc method Time of conc. (Tc) Total precip. = 3.05 in Distribution Storm duration = 24 hrs Shape factor Q (cfs) 12.00 10.00 MIX .M 4.00 2.00 0.00 �120 Hyd No. 2 SCM Post -Developed Hyd. No. 2 -- 1 Year 240 -:5,60 480 Thursday, 03 / 10 / 2022 = 11.25 cfs = 716 min = 23,197 cuft = 89.5 = Oft = 5.00 min = Type II = 484 Q (cfs) 12.00 10.00 MM H. it 4.00 2.00 0.00 �b0 840 __960 TOO ---- f2UG i'20 Time (min) 4 Hydrograph Report Hydraflow Hydrographs Extension for AutodeskO Civil 3D® by Autodesk, Inc. v2022 Hyd. No. 3 Post Through SCM Hydrograph type = Reservoir Storm frequency = 1 yrs Time interval = 2 min Inflow hyd. No. = 2 - SCM Post -Developed Reservoir name = BMP Pond Storage Indication method used. Exfiltration extracted from Outflow. Q (cfs) 12.00 10.00 M . Me 4.00 2.00 111150 � Peak discharge Time to peak Hyd. volume Max. Elevation Max. Storage Post Through SCM Hyd. No. 3 -- 1 Year Thursday, 03 / 10 / 2022 = 0.000 cfs = 854 min = 0 cuft = 437.61 ft = 9,886 cuft Q (cfs) 12.00 10.00 6.00 4.00 2.00 0 -240 -36C 480-- 600 720 840 960 1080 -1200' 1-320- _1440- -1560- 1680 Time (min) Hyd No. 3 Hyd No. 2 Total storage used = 9,886 cult 6 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2022 Hyd. No. 4 SCM Post -Developed Bypass Hydrograph type = SCS Runoff Storm frequency = 1 yrs Time interval = 2 min Drainage area = 1.980 ac Basin Slope 0.0 % Tc method - Total precip. = 3.05 in Storm duration = 24 hrs Q (cfs) 4.00 3.00 2.00 1.00 Thursday, 03 / 10 / 2022 Peak discharge = 3.498 cfs Time to peak = 722 min Hyd. volume = 9,172 cuft Curve number = 79.2 Hydraulic length = 0 ft Time of conc. (Tc) = 10.00 min Distribution = Type II Shape factor = 484 SCM Post -Developed Bypass Hyd. No. 4 -- 1 Year Q (Cfs) 4.00 3.00 2.00 1.00 000 T'2 .2.40 3fi0__ 480 509�T2 �dt7��Q�109{1 1200 1320- -1440 1 Hyd No. 4 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc, v2022 Hyd. No. 6 1.0 Post -Developed to SCM Hydrograph type = SCS Runoff Storm frequency = 1 yrs Time interval = 2 min Drainage area = 3.430 ac Basin Slope = 0.0 % Tc method - Total precip. = 1.00 in Storm duration = 6.00 hrs 7 Thursday, 03 / 10 / 2022 Peak discharge = 0.818 cfs Time to peak = 146 min Hyd. volume = 3,527 cuft Curve number = 89.5 Hydraulic length = 0 ft Time of conc. (Tc) = 5.00 min Distribution = SCS 6-Hr Shape factor = 484 1.0 Post -Developed to SCM Q (cfs) Hyd. No. 6 -- 1 Year Q (cfs) 1.00 0.90 0.80 0.70 0.60 0.50 0.40 0.30 0.20 0.10 0.00 0 �0 Hyd No. 6 1.00 0.90 0.80 - 0.70 0.60 0.50 0.40 0.30 0.20 0.10 0.00 12fj —18b 240 .301�360 420 Time (min) 8 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2022 Hyd. No. 7 1.0inPost Through SCM Hydrograph type = Reservoir Peak discharge Storm frequency = 1 yrs Time to peak Time interval = 2 min Hyd. volume Inflow hyd. No. = 6 - 1.0 Post -Developed to SCWax. Elevation Reservoir name = BMP Pond Max. Storage Storage Indication method used. Exfiltration extracted from Outflow Thursday, 03 / 10 / 2022 = 0.000 cfs = 210 min = 0 cuff = 436.18 ft = 1,059 cuft RIME IIMM RIME 1. MIME mm� NICE 0.30 0.20 NEI 'WIli 0 E 4V Time (min) Hyd No. 7 Hyd No. 6 I Total storage used = 1,059 cult 10 Hydrograph Summary Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2022 Hyd. I Hydrograph Peak Time Time to Hyd. Inflow Maximum Total Hydrograph No. type flow interval Peak volume hyd(s) elevation strge used Description (origin) (cfs) 12.52 (min) 2 (min) 720 (cuft) ------ (ft) - (cuft) 1 SCS Runoff 32,707 SCM Pre -Developed 2 SCS Runoff 14.42 2 716 30,110 ------ -- SCM Post -Developed 3 Reservoir 0.000 2 920 0 2 438.09 13,313 Post Through SCM 4 SCS Runoff 4.927 2 720 12,819 ------ — - — SCM Post -Developed Bypass 6 SCS Runoff 0.000 2 n/a 0 ---- - 1.0 Post -Developed to SCM 7 Reservoir 0.000 2 n/a 0 6 436.00 0.000 1.0inPost Through SCM Infiltration.gpw Return Period: 2 Year Thursday, 03 / 10 / 2022 11 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2022 Hyd. No. 1 SCM Pre -Developed Hydrograph type = SCS Runoff Storm frequency = 2 yrs Time interval = 2 min Drainage area = 5.410 ac Basin Slope = 0.0 % Tc method = Total precip. = 3.69 in Storm duration = 24 hrs Q (Cfs) 14.00 12.00 10.00 • 11 4.00 2.00 0.00 0 120 240 Hyd No. 1 Peak discharge Time to peak Hyd. volume Curve number Hydraulic length Time of conc. (Tc) Distribution Shape factor SCM Pre -Developed Hyd. No. 1 -- 2 Year Thursday, 03 / 10 / 2022 = 12.52 cfs = 720 min = 32,707 cuft = 77.6 = Oft = 10.40 min = Type II = 484 Q (cfs) 14.00 iVA1111 10.00 . 11 4.00 2.00 0.00 360 480 600 720 840 960 1080 1200 1320 1440 1560 Time (min) Hydrograph Report 12 Hydraflow Hydrographs Extension for Aulodesk® Civil 3D® by Autodesk, Inc. v2022 Thursday, 03 / 10 / 2022 Hyd. No. 2 SCM Post -Developed Hydrograph type = SCS Runoff Peak discharge = 14.42 cfs Storm frequency = 2 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 30,110 cuft Drainage area = 3.430 ac Curve number = 89.5 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method - Time of conc. (Tc) = 5.00 min Total precip. = 3.69 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 SCM Post -Developed Q (cfs) Hyd. No. 2 -- 2 Year Q (cfs) 15.00 15.00 12.00 - 12.00 9.00 9.00 6.00 6.00 3.00 3.00 0.00 0.00 1 0 240 36 480 _66o no 840 960 96801260 1320 Hyd No. 2 Time (min) 13 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2022 Hyd. No. 3 Post Through SCM Hydrograph type = Reservoir Peak discharge Storm frequency = 2 yrs Time to peak Time interval = 2 min Hyd. volume Inflow hyd. No. = 2 - SCM Post -Developed Max. Elevation Reservoir name = BMP Pond Max. Storage Storage Indication method used. Exfiltration extracted from Outflow. Post Through SCM Hyd. No. 3 -- 2 Year 12.00 • II MIN MI Thursday, 03 / 10 / 2022 = 0.000 cfs = 920 min = 0 cuft = 438.09 ft = 13,313 cuft Q (cfs) 15.00 12.00 • II . II 3.00 0.00 -L-- - 1 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 1680 Time (min) — Hyd No. 3 Hyd No. 2 . Total storage used = 13,313 cuft 14 Hydrograph Report Hydraflow Hydrographs Extension for Aulodesk® Civil 3D® by Autodesk, Inc. v2022 Hyd. No. 4 SCM Post -Developed Bypass Hydrograph type = SCS Runoff Storm frequency = 2 yrs Time interval = 2 min Drainage area = 1.980 ac Basin Slope = 0.0 % Tc method - Total precip. = 3.69 in Storm duration = 24 hrs Q (cfs) 5.00 - 4.00 3.00 2.00 1.00 Thursday, 03 / 10 / 2022 Peak discharge = 4.927 cfs Time to peak = 720 min Hyd. volume = 12,819 cuft Curve number = 79.2 Hydraulic length = 0 ft Time of conc. (Tc) = 10.00 min Distribution = Type II Shape factor = 484 SCM Post -Developed Bypass Hyd. No. 4 -- 2 Year Q (cfs) 5.00 4.00 3.00 2.00 1.00 M 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Hyd No. 4 Time (min) 17 Hydrograph Summary Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2022 Hyd. No. Hydrograph type (origin) Peak flow (cfs) Time interval (min) Time to Peak (min) Hyd. volume (cult) Inflow hyd(s) Maximum elevation (ft) Total strge used (cuft) Hydrograph Description 1 SCS Runoff 23.82 2 720 61,796 --- — - SCM Pre -Developed 2 SCS Runoff 23.05 2 716 49,585 ------ - — SCM Post -Developed 3 Reservoir 0.000 2 746 0 2 439.34 23,328 Post Through SCM 4 SCS Runoff 9.137 2 720 23,742 -•-- — — - SCM Post -Developed Bypass 6 SCS Runoff 0.000 2 n/a 0 -•---• --- - 1.0 Post -Developed to SCM 7 Reservoir 0.000 2 n/a 0 6 436.00 0.000 1.OinPost Through SCM Infiltration.gpw Return Period: 10 Year Thursday, 03 / 10 / 2022 18 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2022 Hyd. No. 1 SCM Pre -Developed Hydrograph type = SCS Runoff Storm frequency = 10 yrs Time interval = 2 min Drainage area = 5.410 ac Basin Slope = 0.0 % Tc method = Total precip. = 5.44 in Storm duration = 24 hrs Q (cfs) 24.00 20.00 16.00 12.00 8.00 4.00 0.00 Thursday, 03 / 10 / 2022 Peak discharge = 23.82 cfs Time to peak = 720 min Hyd. volume = 61,796 cuft Curve number = 77.6 Hydraulic length = 0 ft Time of conc. (Tc) = 10.40 min Distribution = Type II Shape factor = 484 Q (cfs) 24.00 20.00 16.00 12.00 8.00 4.00 0.00 0 120 246 360 480 600 720 840 960 1080 1200 1320 1440 1560 - Hyd No. 1 Time (min) SCM Pre -Developed Hyd. No. 1 -- 10 Year 19 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2022 Thursday, 03 / 10 / 2022 Hyd. No. 2 SCM Post -Developed Hydrograph type = SCS Runoff Peak discharge = 23.05 cfs Storm frequency = 10 yrs Time to peak = 716 min Time interval = 2 min Hyd. volume = 49,585 cuft Drainage area = 3.430 ac Curve number = 89.5 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = Time of conc. (Tc) = 5.00 min Total precip. = 5.44 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 Q (cfs) 24.00 20.00 16.00 12.00 8.00 4.00 SCM Post -Developed Hyd. No. 2 -- 10 Year Q (cfs) 24.00 20.00 16.00 12.00 8.00 4.00 0 120 240 360 480 600 720 840 966 1080 1200- Hyd No. 2 -- Time (min) 20.00 16.00 12.00 1 4.00 KIN 20 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2022 Thursday, 03 / 1012022 Hyd. No. 3 Post Through SCM Hydrograph type = Reservoir Peak discharge = 0.000 cfs Storm frequency = 10 yrs Time to peak = 746 min Time interval = 2 min Hyd. volume = 0 cuft Inflow hyd. No. = 2 - SCM Post -Developed Max. Elevation = 439.34 ft Reservoir name = BMP Pond Max. Storage = 23,328 cuft Storage Indication method used. ExFltration extracted from Outflow. Q (cfs) 24.00 0 120 240 364 480 600 7 Hyd No. 3 Hyd No. 2 Post Through SCM Hyd. No. 3 -- 10 Year Q (cfs) 24.00 20.00 16.00 12.00 4.00 0.00 20 840 960 1080 1200 E3 0 Time (min) Total storage used = 23,328 cult Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2022 Hyd. No. 4 SCM Post -Developed Bypass Hydrograph type = SCS Runoff Peak discharge Storm frequency = 10 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 1.980 ac Curve number Basin Slope = 0.0 % Hydraulic length Tc method = Time of conc. (Tc) Total precip. = 5.44 in Distribution Storm duration = 24 hrs Shape factor Q (cfs 10.00 4.00 2.00 SCM Post -Developed Bypass Hyd. No. 4 -- 10 Year 0.00 120 240 Hyd No. 4 21 Thursday, 03 / 10 / 2022 = 9.137 cfs = 720 min = 23,742 cult = 79.2 = Oft = 10.00 min = Type II = 484 Q (cfs) 10.00 ME 4.00 2.00 VAT.>• 360 480 600 720 846 660 1080 1200 1320 1440 1560 Time (min) 24 Hydrograph Summary Report Hydraflow Hydrographs Extension for Autodesk0 Civil 3D® by Autodesk, Inc. v2022 Hyd. Hydrograph No. type (origin) Peak flow (cfs) Time interval (min) Time to Peak (min) Hyd. volume (cuft) Inflow hyd(s) Maximum elevation (ft) Total strge used (cuft) Hydrograph Description 1 SCS Runoff 42.80 2 720 112,534 -••- SCM Pre -Developed 2 SCS Runoff 36.64 2 716 81,386 - - — SCM Post -Developed 3 Reservoir 18.08 2 722 16,756 2 440.18 30,901 Post Through SCM 4 SCS Runoff 16.12 2 720 42,590 ---- ----- — SCM Post -Developed Bypass 6 SCS Runoff 0.000 2 n/a 0 - --- — -- --- 1.0 Post -Developed to SCM 7 Reservoir 0.000 2 n/a 0 6 436.00 0.000 1.OinPost Through SCM Infiltration.gpw Return Period: 100 Year Thursday, 03 / 10 / 2022 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D0 by Autodesk, Inc. v2022 Hyd. No. 1 SCM Pre -Developed Hydrograph type = SCS Runoff Storm frequency = 100 yrs Time interval = 2 min Drainage area = 5.410 ac Basin Slope = 0.0 % Tc method = Total precip. = 8.23 in Storm duration = 24 hrs Q (cfs) 50.00 40.00 30.00 20.00 10.00 0 00 25 Thursday, 03 / 10 / 2022 Peak discharge = 42.80 cfs Time to peak = 720 min Hyd. volume = 112,534 cuft Curve number = 77.6 Hydraulic length = 0 ft Time of conc. (Tc) = 10.40 min Distribution = Type II Shape factor = 484 SCM Pre -Developed Hyd. No. 1 -- 100 Year Q (cfs) 50.00 40.00 30.00 20.00 10.00 _ 0.00 0 120 240 360 480 600 720 840 960 1080 1200 1320 1440 1560 Hyd No. 1 Time (min) 26 Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2022 Hyd. No. 2 SCM Post -Developed Hydrograph type = SCS Runoff Peak discharge Storm frequency = 100 yrs Time to peak Time interval = 2 min Hyd. volume Drainage area = 3.430 ac Curve number Basin Slope = 0.0 % Hydraulic length Tc method = Time of conc. (Tc) Total precip. = 8.23 in Distribution Storm duration = 24 hrs Shape factor Q (cfs) 40.00 30.00 20.00 10.00 0.00 SCM Post -Developed Hyd. No. 2 -- 100 Year Thursday, 03 / 10 / 2022 = 36.64 cfs = 716 min = 81,386 cuft = 89.5 = Oft = 5.00 min = Type II = 484 0 120 240 360 480 6fl0 720 840 W 1fJ80 Hyd No. 2 Q (cfs) 40.00 30.00 20.00 10.00 �"_ 0.00 1200 Time (min) Hydrograph Report Hydraflow Hydrographs Extension for Autodesk® Civil 3D® by Autodesk, Inc. v2022 Hyd. No. 3 Post Through SCM Hydrograph type = Reservoir Storm frequency = 100 yrs Time interval = 2 min Inflow hyd. No. = 2 - SCM Post -Developed Reservoir name = BMP Pond Storage Indication method used. Exfiltration extracted from Outflow. Q (cfs) 40.00 30.00 20.00 10.00 0.00 120 Hyd No. 3 M Peak discharge Time to peak Hyd. volume Max. Elevation Max. Storage Post Through SCM Hyd. No. 3 -- 100 Year Hyd No. 2 360 27 Thursday, 03 / 10 / 2022 = 18.08 cfs = 722 min = 16,756 cuft = 440.18 ft = 30,901 cuft Q (cfs) 40.00 30.00 20.00 10.00 _ _ 0.00 480 600 720 840 I Total storage used = 30,901 cult Time (min) Hydrograph Report 28 Hydraflow Hydrographs Extension for Autodesk a0 Civil 3D® by Autodesk, Inc. v2022 Thursday, 03 / 10 / 2022 Hyd. No. 4 SCM Post -Developed Bypass Hydrograph type = SCS Runoff Peak discharge = 16.12 cfs Storm frequency = 100 yrs Time to peak = 720 min Time interval = 2 min Hyd. volume = 42,590 cuft Drainage area = 1.980 ac Curve number = 79.2 Basin Slope = 0.0 % Hydraulic length = 0 ft Tc method = Time of conc. (Tc) = 10.00 min Total precip. = 8.23 in Distribution = Type II Storm duration = 24 hrs Shape factor = 484 SCM Post -Developed Bypass Q (cfs) Hyd. No. 4 -- 100 Year Q (cfs) 18.00 - 18.00 15.00 12.00 15.00 9.00 12.00 - 9.00 6.00 6.00 3.00 0.00 3.00 0.00 0 120 240 360 480 600 720 :84.0 960 1080 1200 1320 1440 1560 Hyd No. 4 Time (min) mm § � § ,! {» ! �k ! I ) ! |E | J! t !| � § k7 ! i# k § 7 E � 2 )& §• 2 - ]( � 4 |� ii! ! §2 � § � � §� §|7 k!§ Project Name Riprap Dissipater #1 Date McCain Gas Station Sept. 2021 DID Project No. Location Double D Engineering, PLLC DD2114 Hoke County, NC 150 S. Page Street Calculated By Southern Pines, NC 28387 JLH (910) 684-8646 Checked By JLH STORM DESIGN: 25 Year BACKGROUND: Use the E&S Control Planning & Design Manual, Section 8.06. REFERENCE: (NCDE-WR, 1993) Step 1. Minimum Tailwater Condition Step 2. D-o = 18 in. D-o = 1.50 ft. Q-25 = 16.33 cfs d-50 = 0.5 ft. L-a = 15 ft. Step 3. 3*D-o = 4.50 ft, W = 16.50 ft. Step 4. d-max 0.75 ft. d-max 9 in. Step 5. Thickness = 1.13 ft Thickness = 14 in. IDESIGN DIMENSIONS: Pipe diameter in inches Pipe diameter in feet Pipe outlet (from drainage calculations) from Figure 8.06 a from Figure 8.06 a 3 times the outlet pipe diameter Pipe diameter + Apron length Maximum Stone Diameter (1.5*d-50) in inches Maximum Stone Diameter (1.5*d-50) in feet Min. Apron Thickness With Filter Fabric (1.5*d-max) in feet Min. Apron Thickness With Filter Fabric (1.5*d-max) in inches Apron Dimensions Rlprap Length Width 3*D-o Thick Class 15 17 5 241n. 1 TERMINOLOGY: Q25 = 25-Year Design Storm, Peak Discharge, (cfs) D-o = Pipe Diameter, (in. & ft.) d-50 = Mean Stone Diameter of Rip -Rap, (ft.) L-a = Length of Rip -Rap Apron, (ft.) 3'D-o = Width of Rip -Rap Apron @ Pipe Outlet, (ft.) W = Width of Rip -Rap Apron @ End of Apron, (ft.) d-max = Maximum Stone Diameter of Rip -Rap, (ft, & in.) Thickness = Thickness of Rip -Rap Apron With Filter Fabric, (ft. &in.)