Farkas, Jim J
From:Farkas, Jim J
Sent:Sunday, August 1, 2021 4:51 PM
To:Craig Grimmer; Kiker, Matthew
Subject:Re: \[External\] RE: SW210301 - Cresswind Phase 2
10 am on Monday works for me
From: Craig Grimmer <cgrimmer@kolter.com>
Sent: Sunday, August 1, 2021 1:52 PM
To: Kiker, Matthew <kiker.m@tandh.com>; Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Subject: Re: \[External\] RE: SW210301 - Cresswind Phase 2
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an attachment to
Report Spam.
Ten works for me
From: Kiker, Matthew <kiker.m@tandh.com>
Sent: Sunday, August 1, 2021 1:43:16 PM
To: Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Cc: Craig Grimmer <cgrimmer@kolter.com>
Subject: Re: \[External\] RE: SW210301 - Cresswind Phase 2
\[External Email\]
Jim - my bad. I meant Monday. Could you possibly do 10? Sorry for the confusion
Sent from my iPhone
On Aug 1, 2021, at 7:36 AM, Farkas, Jim J <Jim.Farkas@ncdenr.gov> wrote:
Sure
From: Kiker, Matthew <kiker.m@tandh.com>
Sent: Saturday, July 31, 2021 7:25 PM
To: Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Cc: Craig Grimmer <cgrimmer@kolter.com>
Subject: RE: \[External\] RE: SW210301 - Cresswind Phase 2
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to Report Spam.
Jim – can you do tomorrow at 11 am?
1
MATTHEW KIKER, PE | Project Manager
THOMAS & HUTTON
p 980-521-5999
e kiker.m@tandh.com
a 1020 Euclid Avenue | Charlotte, NC 28203
vCard | Website | LinkedIn | Facebook | Twitter | Instagram
PRIVILEGED AND CONFIDENTIAL: This electronic message and any attachments are confidential property of
Thomas & Hutton. The information is intended only for the use of the person to whom it is addressed. Any
other interception, copying, accessing, or disclosure of this message is prohibited. If you have received this
message in error, please immediately notify Thomas & Hutton and purge the message received. Do not
forward this message without permission.
From: Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Sent: Wednesday, July 28, 2021 10:42 AM
To: Kiker, Matthew <kiker.m@tandh.com>
Subject: RE: \[External\] RE: SW210301 - Cresswind Phase 2
Yes, we can either have a Teams call or you can call my office phone (I’m back in the office Monday –
Thursday). I’m free anytime today, tomorrow, or Friday.
Timewise, I don’t think that it will set the project back much, if any (most of the comments for Phases 2
& 3 had to deal with correctly showing that an SCM from one project will be treating BUA on another
project, so those comments would not need to be addressed). The Application and Supplement-EZ Form
would need to be tweaked (essentially combining them). You can keep the two separate calculation
books and even plan sets (I’ll combine them into a single set). It wouldn’t cost anything extra to do
combine these projects into a single one (We would just rename one of the projects “Cresswind Phases
2 & 3” and close out the other project. I’d explain everything that needs to be done to combine the
projects in the request for additional information letter).
This review took longer than I would have liked (between vacation and moving back to the office, I got a
little bogged down with the reviews), but subsequent reviews should be closer to 30 days.
While the developer is waiting for approval, they can do clearing, grubbing, grading, etc. (any
construction activities that do not include placing BUA).
Let me know what time works for you for the meeting.
Jim Farkas
Environmental Engineer
North Carolina Department of Environmental Quality
Division of Energy, Mineral, & Land Resources – Stormwater Program
512 N. Salisbury Street
1612 Mail Service Center
Raleigh, NC 27699-1612
(919) 707-3646
Jim.Farkas@ncdenr.gov
<image001.png>
2
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
Based on the current guidance to minimize the spread of COVID-19, the Department of Environmental
Quality has adjusted operations to protect the health and safety of the staff and public. Many
employees are working remotely or are on staggered shifts. To accommodate these staffing changes, all
DEQ office locations are limiting public access to appointments only. Please check with the appropriate
staff before visiting our offices, as we may be able to handle your requests by phone or email. We
appreciate your patience as we continue to serve the public during this challenging time.
From: Kiker, Matthew <kiker.m@tandh.com>
Sent: Wednesday, July 28, 2021 9:26 AM
To: Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Subject: RE: \[External\] RE: SW210301 - Cresswind Phase 2
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to Report Spam.
I am open to that idea but would need to better understand the timing implications for the developer.
They are hoping to get started on Phase 2 as soon as they can.
Can we setup a call to discuss?
MATTHEW KIKER, PE | Project Manager
THOMAS & HUTTON
p 980-521-5999
e kiker.m@tandh.com
a 1020 Euclid Avenue | Charlotte, NC 28203
vCard | Website | LinkedIn | Facebook | Twitter | Instagram
PRIVILEGED AND CONFIDENTIAL: This electronic message and any attachments are confidential property of
Thomas & Hutton. The information is intended only for the use of the person to whom it is addressed. Any
other interception, copying, accessing, or disclosure of this message is prohibited. If you have received this
message in error, please immediately notify Thomas & Hutton and purge the message received. Do not
forward this message without permission.
From: Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Sent: Wednesday, July 28, 2021 9:24 AM
To: Kiker, Matthew <kiker.m@tandh.com>
Subject: RE: \[External\] RE: SW210301 - Cresswind Phase 2
I don’t remember if we discussed permitting Phase 2 & 3 of this project together, but is that something
that you are interested in? It would probably make the submission/permitting/design simpler since you
wouldn’t need to worry about the “intermediateness” (ensuring that the Phase 2 design works
irrespective of whether or not Phase 3 ever gets built) of the Phase 2 design.
Let me know.
-Jim
3
From: Kiker, Matthew <kiker.m@tandh.com>
Sent: Tuesday, July 27, 2021 4:58 PM
To: Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Cc: cgrimmer@kolter.com
Subject: \[External\] RE: SW210301 - Cresswind Phase 2
Importance: High
CAUTION: External email. Do not click links or open attachments unless you verify. Send all suspicious email as an
attachment to Report Spam.
Good afternoon Jim,
I just wanted to reach out to see if you had received this package to review and if you had any
questions.
Please feel free to let me know if you need additional information.
Thanks!
MATTHEW KIKER, PE | Project Manager
THOMAS & HUTTON
p 980-521-5999
e kiker.m@tandh.com
a 1020 Euclid Avenue | Charlotte, NC 28203
vCard | Website | LinkedIn | Facebook | Twitter | Instagram
PRIVILEGED AND CONFIDENTIAL: This electronic message and any attachments are confidential property of
Thomas & Hutton. The information is intended only for the use of the person to whom it is addressed. Any
other interception, copying, accessing, or disclosure of this message is prohibited. If you have received this
message in error, please immediately notify Thomas & Hutton and purge the message received. Do not
forward this message without permission.
From: Kiker, Matthew
Sent: Wednesday, June 2, 2021 4:27 PM
To: Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Cc: Cannon, Katie <cannon.k@tandh.com>; cgrimmer@kolter.com
Subject: RE: SW210301 - Cresswind Phase 2
Please disable any popup blockers and click the following link to download your files (this link will not work on
mobile devices):
https://ftp.thomasandhutton.com:443/AHT/AHT_UI/public/index.html#/password?package=IpFkgUpkiD7HviwkW
x3rEHaokgZjkvayvcB9o9n5HwGeJAoQy4wFDuIJ3SBCzCuy2YtNaVA%2bS9Cm%2ffpQnEuXrVtlVcC6DCpP%2bxRDrFm
1n%2bk%3d
Good afternoon Jim,
Please use the link to download the revised documents for Cresswind Phase 2. These have also been
uploaded digitally with hardcopies to follow via mail this week.
Let us know if you any questions as you proceed with the review.
Thanks!
MATTHEW KIKER, PE | Project Manager
4
THOMAS & HUTTON
p 980-521-5999
e kiker.m@tandh.com
a 1020 Euclid Avenue | Charlotte, NC 28203
vCard | Website | LinkedIn | Facebook | Twitter | Instagram
PRIVILEGED AND CONFIDENTIAL: This electronic message and any attachments are confidential property of
Thomas & Hutton. The information is intended only for the use of the person to whom it is addressed. Any
other interception, copying, accessing, or disclosure of this message is prohibited. If you have received this
message in error, please immediately notify Thomas & Hutton and purge the message received. Do not
forward this message without permission.
From: Farkas, Jim J <Jim.Farkas@ncdenr.gov>
Sent: Monday, April 19, 2021 8:41 AM
To: Kiker, Matthew <kiker.m@tandh.com>; cgrimmer@kolter.com
Cc: Moore, James <james.moore@ncdenr.gov>
Subject: SW210301 - Cresswind Phase 2
Good Morning,
The Division of Energy, Mineral and Land Resources (DEMLR), received a Stormwater Management
th
Permit Application for the subject project on March 10, 2021. A review of that information has
determined that the application is not complete. Attached is a letter describing the items that need to
be submitted. If you have any questions, please feel free to contact me. My contact information is listed
below (I’ll be teleworking so email is the preferred way to reach me).
Thank you,
Jim Farkas
Environmental Engineer
North Carolina Department of Environmental Quality
Division of Energy, Mineral, & Land Resources – Stormwater Program
512 N. Salisbury Street
1612 Mail Service Center
Raleigh, NC 27699-1612
(919) 707-3646
Jim.Farkas@ncdenr.gov
<image001.png>
Email correspondence to and from this address is subject to the
North Carolina Public Records Law and may be disclosed to third parties.
Based on the current guidance to minimize the spread of COVID-19, the Department of Environmental
Quality has adjusted operations to protect the health and safety of the staff and public. Many
employees are working remotely or are on staggered shifts. To accommodate these staffing changes, all
DEQ office locations are limiting public access to appointments only. Please check with the appropriate
staff before visiting our offices, as we may be able to handle your requests by phone or email. We
appreciate your patience as we continue to serve the public during this challenging time.
5