Loading...
HomeMy WebLinkAbout20171559 Ver 3_USACE Public Notice_20211119US Army Corps Of Engineers Wilmington District PUBLIC NOTICE Issue Date: November 19, 2021 Comment Deadline: December 6, 2021 Corps Action ID Number: SAW-2015-01268 The Wilmington District, Corps of Engineers (Corps) received a revised application from the Greensboro -Randolph Megasite Foundation, Inc. seeking Department of the Army authorization to discharge dredged or fill material into waters of the United States, associated with the construction of the Greensboro - Randolph Megasite (GRMS), an approximate 1,000-acre automotive storage battery manufacturing, production, and assembly facility. The proposed project includes off -site transportation and utility improvements. The proposed project site is located adjacent to US Highway 421 in Liberty, Randolph County, North Carolina. The District previously published a public notice for a proposed advanced automotive manufacturing facility at this location/site on December 18, 2018. Due to the large number of permit drawing plans associated with this proposal, they are not included with this Public Notice. This Public Notice is available on the Wilmington District Web site at https://www.saw.usace.army.mil/Missions/Regulatory-Permit-Program/Public- Notices/ Applicant: Greensboro -Randolph Megasite Foundation, Inc. Mr. Jim Melvin 324 W. Wendover Ave. Suite 207 Greensboro, North Carolina 27408 AGENT (if applicable): HDR Ms. Vickie Miller 555 Fayetteville St, Suite 900 Raleigh, North Carolina 27601 Authority The Corps evaluates this application and decides whether to issue, conditionally issue, or deny the proposed work pursuant to applicable procedures of the following Statutory Authorities: ® Section 404 of the Clean Water Act (33 U.S.C. 1344) Version 7.8.2014 Page 1 ❑ Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403) ❑ Section 103 of the Marine Protection, Research and Sanctuaries Act of 1972 (33 U.S.C. 1413) Location Location Description: The project area is composed of the proposed GRMS, and the proposed utility and transportation improvement sites. The GRMS is located in northern Randolph County approximately two miles northwest of the Town of Liberty and east of the Town of Julian. The site is generally bounded by Old US 421 to the north, Julian Airport Road to the west, Troy Smith Road to the east, and US Highway 421 to the south. The proposed route for the water and sewer utilities would begin at the Bora Drive, Liberty Road intersection and follow Liberty Road southeast to the northern portion of the GRMS. At the intersection with Julian Airport Road, the water main continues along Old US 421 to the north of the site while the force main sewer alignment continues along Julian Airport Road. The force main alignment proceeds southeast along US 421 to the intersection with Starmount Road. The force main follows Starmount Road to a stream crossing where a proposed pump station would be located. The proposed route for the electrical transmission line would extend from the existing Duke Energy corridor west of Hockett Road and north of the Hockett Road, Whitt Hunt Road intersection. It would cross Old Climax Road, Hunting Lodge Road, NC 22, Old Red Cross Road and Shiloah Road to the proposed site. The proposed transportation improvements would be located along US 421 on, and adjacent to, the southwestern portion of the GRMS site. Specifically, the transportation improvements would include roadway widening and new interchanges. These improvements would be located immediately south of the Julian Airport Road, Crutchfield Farm Road intersection and extending southward to Shiloh Road, at the Browns Meadow Road, US 421 intersection and along the Shiloh Road, US 421 intersection, immediately south of Dodsons Lake. Project Area (acres): 1858 Nearest Town: Liberty Nearest Waterways: Sandy Creek and Dodsons Lake River Basin: Cape Fear 03030003 and 03030002 Latitude and Longitude: 35.894610N,-79.627378W Version 7.8.2014 Page 2 Existing Site Conditions The project area is located in the Cape Fear watershed (HUCs 03030003 and 03030002) and includes perennial and intermittent streams, adjacent wetlands, open water ponds, and Dodsons Lake. Surface waters flow to six named waterbodies that occur within the project area. These waterbodies are: Little Polecat Creek, Sandy Creek, Dodsons Lake, North Prong Stinking Quarter Creek, Climax Creek, and Big Alamance Creek. North Prong Stinking Quarter Creek, Climax Creek, and Big Alamance Creek drain to the Haw River (HUC 03030002). Polecat Creek, Sandy Creek, and Dodsons Lake drain to the Deep River (HUC 03030003). The project area contains approximately 59,747 feet of perennial streams and approximately 16,659 feet of intermittent streams. Substrate in these streams ranged from silt/sand to cobble/gravel and Ordinary High Water Mark (OHWM) indicators included natural lines impressed on the banks, shelving, matted down vegetation, disturbed leaf litter, sediment deposition, wrack lines, sediment sorting, and bank scour. Open water within the project area consists of ponds (totaling approximately 34 acres) and Dodsons Lake (approximately 53 acres). All but two ponds within the project area are hydrologically connected by unnamed tributaries to named waterbodies. Water Quality Classifications for the named tributaries are as follows: Little Polecat Creek: WS-III; HQW Sandy Creek: WS-III Dodsons Lake: WS-III North Prong Stinking Quarter Creek: WS-IV; NSW Climax Creek: WS-IV; NSW Big Alamance Creek: WS-IV; NSW Water Quality Classification referenced above and pertinent to the waters listed above are defined as the following: • Class C (C) refers to waters protected for uses such as secondary recreation, fishing, wildlife, fish consumption, aquatic life including propagation, survival and maintenance of biological integrity, and agriculture. Secondary recreation includes wading, boating, and other uses involving human body contact with water where such activities take place in an infrequent, unorganized, or incidental manner; • Water Supply III (WS-III) refers to waters used as sources of water supply for drinking, culinary or food processing purposes where a more protective WS-I or WS-II classification is not feasible. These waters are also protected for Class C uses. WS-III waters are typically in low to moderately developed watersheds; • Water Supply IV (WS-IV) refers to waters used as sources of water supply for drinking, culinary or food processing purposes where a WS-I, WS-II or WS-III Version 7.8.2014 Page 3 classification is not feasible. These waters are also protected for Class C uses. WS-IV waters are generally in moderately to highly developed watersheds or Protected Areas; • High Quality Waters (HQW) is a supplemental classification intended to protect waters which are rated excellent based on biological and physical/chemical characteristics through Division monitoring or special studies, primary nursery areas designated by the Marine Fisheries Commission, and other functional nursery areas designated by the Marine Fisheries Commission; • Nutrient Sensitive Waters (NSW) is a supplemental classification intended for waters needing additional nutrient management due to being subject to excessive growth of microscopic or macroscopic vegetation; The project area contains approximately 23.7 acres of wetlands. Differences in jurisdictional areas listed in the December 2018 Public Notice and this Public Notice result from additional site visits and a revised waters/wetlands delineation for the development site. The revised waters/wetlands delineation has been reviewed by the Corps. The North Carolina Wetland Assessment Method (NC WAM) and the North Carolina Stream Assessment Method (NC SAM) were used to assess the functions and values of a representative sampling of wetlands and streams throughout the project area. Common NC WAM wetland types within the project area include Riverine Swamp Forest, Non -Tidal Freshwater Marsh, Headwater Forest and Bottomland Hardwood Forest. Most of the streams within the project area received a medium overall NC SAM rating. Wetlands within the project area are small (average wetland size is 0.3 acre). Most of these wetlands are headwater forests located adjacent to first order tributaries. Overall NC WAM ratings were medium for the majority of wetlands onsite. Land use within the site and along the associated infrastructure improvements consists predominately of agricultural fields, residential property, and forested land. Soils on the GRMS are classified as indicated by the map and table below: Version 7.8.2014 Page 4 Version 7.8.2014 Page 5 Map Unit Symbol Map Unit Name Percent of Property (approximate) Farmland Rating Hydric Rating (%) ApB Applinq sandy loam, 2 to 6 percent slopes 3.0% All areas are prime farmland 0 ApC Appling sandy loam, 6 to 10 percent slopes 1.0% Farmland of statewide importance 0 CcB Cecil sandy loam, 2 to 8 percent slopes 0.2% All areas are prime farmland 0 ChA Chewacla loam, 0 to 2 percent slopes, frequently flooded 0.4% Prime farmland if drained and either protected from flooding or not frequently flooded during the growing season 5 HeB Helena sandy loam, 2 to 6 percent slopes 9.9% All areas are prime farmland 0 HeC Helena sandy loam, 6 to 10 percent slopes 3.3% Farmland of statewide importance 0 A4aC Mecklenburg loam, 8 to 15 percent slopes 1.2% Farmland of statewide importance 0 MeB2 Mecklenburg clay loam, 2 to 8 percent slopes, moderately eroded 1.9% All areas are prime farmland 0 VaB Vance sandy loam, 2 to 8 percent slopes 7.3% All areas are prinie farmland 0 VaC Vance sandy loam, 8 to 15 percent slopes 5.0% Farmland of statewide importance 0 W Water 3.6% 0 WpC Wilkes-Poindexter-Wynott complex, 8 to 15 percent slopes 7.9% Not prime farmland 0 WtB Wynott-Enan complex, 2 to 8 percent slopes 3.2% Farmland of statewide importance 0 WtC Wynott-Enan complex, 8 to 15 percent slopes 8.3% Farmland of statewide importance 0 WvB2 Wynott-Enan complex, 2 to 8 percent slopes, moderately eroded 34.2% Farmland of statewide importance 0 WvC2 Wynott-Enan complex, 8 to 15 percent slopes, moderately eroded 9.6% Farmland of statewide importance 0 Totals for Area of Interest 100.O% Source USDA-NRCS 2017b Applicant's Stated Purpose The applicant's stated purpose is to establish an automotive storage battery manufacturing, production, and assembly facility with utilities (electricity, water, sewer, roads, and rail) that is expected to generate employment and economic benefits for the Project Region, including roughly 2,000-4,000 mostly skilled and semi -skilled manufacturing jobs, an increase in the local tax base, and new payroll to circulate within Randolph County and the City of Greensboro. Project Description The overall project involves the construction of a —1,000 acre development site, with plans for the construction of buildings, parking lots and utilities. The overall project includes roadway interchanges, rail, water, sewer and powerline infrastructure. Implementation of the proposed project would result in direct and indirect impacts to streams, wetlands, and open water. The development site Version 7.8.2014 Page 6 would result in permanent impacts to 6,626 linear feet of intermittent stream, 30,426 linear feet of perennial stream, 9.07 acres of wetlands, and 21.54 acres of open water. Approximately,1,686 linear feet of perennial and intermittent streams, 0.37 acre of wetlands and 0.78 acre of open waters would be indirectly impacted. The development site would also result in temporary impacts to 332 linear feet of perennial stream and 109 linear feet of intermittent stream. No buffer impacts would result from the development site because streams impacted by the site are in the Deep River watershed and are not subject to Jordan Lake Buffer Rules. Transportation and utility improvements associated with the project would result in permanent impacts to an additional 0.575 acre of wetlands, 0.50 acres of open water, 1,400 linear feet of intermittent stream, and 2,692 linear feet of perennial stream. Transportation and utility improvements associated with the project would result in temporary impacts to an additional 165 linear feet of intermittent stream and 126 linear feet of perennial stream and 0.45 acre of wetlands. Zone 1 and Zone 2 buffer impacts associated with offsite utilities are anticipated along streams subject to the Jordan Lake Buffer Rules; however, these impacts are anticipated to be exempt because buffer impacts are equal to or less than 40 linear feet with a proposed maintenance corridor equal to or less than 10 feet in width at jurisdictional crossings (See table below). Project Component Temporary Stream (LF) Permanent Stream (LFj Wetland (AC.) Open Water (AC) P Total I P Total Temporary Permanent Permanent Main Site 109 332 441 6626 30426 37052 0 9.07 21.54 Transportation 6 D 0 1290 2609 3899 0 0.305 6.5 Water/Sever 165 126 291 11D 83 193 0.33 0.19 0 Electric Utilities D D 0 0 0 0 0.12 O.08 0 Total 274 458 732 8026 33118 41144 0.45 9.645 22.04 Total Stream Impacts 41,876 Total Wetland Impacts 10.095 Total Open Water Impacts 22,04 indirect Impacts 0 Cr 1478 204 1E86 0 3. , o Avoidance and Minimization The applicant provided the following information in support of efforts to avoid and/or minimize impacts to the aquatic environment: Several alternatives were evaluated during the design process in an effort to avoid and minimize impacts to jurisdictional resources within the site and along the proposed infrastructure extensions. The developer has attempted to avoid and minimize impacts to water resources by designing perpendicular road and utility crossings, where feasible, and utilizing erosion control Best Management Practices (BMPs) to minimize impacts associated with offsite sedimentation. Version 7.8.2014 Page 7 Compensatory Mitigation The applicant offered the following compensatory mitigation plan to offset unavoidable functional loss to the aquatic environment: Mitigation for impacts to streams/wetlands would be accomplished through payment to the North Carolina Division of Mitigation Services (NCDMS). The applicant has stated that total permanent direct and indirect impacts associated with the proposed project development (including utilities and transportation improvements) would be mitigated at ratios of 1:1 or 2:1 depending upon the stream/wetland qualitative assessment scores of the waters using the North Carolina Stream Assessment Method (NCSAM) and North Carolina Wetland Assessment Method (NCWAM). The applicant has provided a conditional acceptance letter from the NCDMS for 42,639 If of warm stream impacts and 9.75 acre of riparian wetland impacts. The letter states that NCDMS proposes to provide the required mitigation credits in the Cape Fear 03030002 and 03030003 Hydrologic Unit Codes (HUCs) . Essential Fish Habitat The Corps' determination is that the proposed project would not effect EFH or associated fisheries managed by the South Atlantic or Mid Atlantic Fishery Management Councils or the National Marine Fisheries Service. ® This notice initiates the Essential Fish Habitat (EFH) consultation requirements of the Magnuson -Stevens Fishery Conservation and Management Act. Implementation of the proposed project would not impact marine substrate, estuarine substrate, water columns, emergent wetlands, submerged aquatic vegetation, artificial reefs, hardbottoms utilized by various life stages of the following species: coastal migratory pelagics, corals, golden crab, shrimp, snapper grouper, spiny lobster, Atlantic highly migratory species. Our initial determination is that the proposed action would not have a substantial individual or cumulative adverse impact on EFH or fisheries managed by Fishery Management Councils and the National Marine Fisheries Service (NMFS). Our final determination relative to project impacts and the need for mitigation measures is subject to review by and coordination with the NMFS. ❑ The Corps will consult under the Magnuson -Stevens Act and will not make a permit decision until the consultation process is complete. ❑ The Corps has initiated consultation the Magnuson -Stevens Act and will not make a permit decision until the consultation process is complete. Version 7.8.2014 Page 8 Cultural Resources Pursuant to Section 106 of the National Historic Preservation Act of 1966, Appendix C of 33 CFR Part 325, and the 2005 Revised Interim Guidance for Implementing Appendix C, the District Engineer consulted district files and records and the latest published version of the National Register of Historic Places and initially determines that: ❑ Should historic properties, or properties eligible for inclusion in the National Register, be present within the Corps' permit area; the proposed activity requiring the DA permit (the undertaking) is a type of activity that will have no potential to cause an effect to an historic properties. ® No historic properties, nor properties eligible for inclusion in the National Register, are present within the Corps' permit area; therefore, there will be no historic properties affected. The Corps subsequently requests concurrence from the SHPO (or THPO). ❑ Properties ineligible for inclusion in the National Register are present within the Corps' permit area; there will be no historic properties affected by the proposed work. The Corps subsequently requests concurrence from the SHPO (or THPO). ❑ Historic properties, or properties eligible for inclusion in the National Register, are present within the Corps' permit area; however, the undertaking will have no adverse effect on these historic properties. The Corps subsequently requests concurrence from the SHPO (or THPO). ❑ Historic properties, or properties eligible for inclusion in the National Register, are present within the Corps' permit area; moreover, the undertaking may have an adverse effect on these historic properties. The Corps subsequently initiates consultation with the SHPO (or THPO). ❑ The proposed work takes place in an area known to have the potential for the presence of prehistoric and historic cultural resources; however, the area has not been formally surveyed for the presence of cultural resources. No sites eligible for inclusion in the National Register of Historic Places are known to be present in the vicinity of the proposed work. Additional work may be necessary to identify and assess any historic or prehistoric resources that may be present. The District Engineer's final eligibility and effect determination will be based upon coordination with the SHPO and/or THPO, as appropriate and required, and with full consideration given to the proposed undertaking's potential direct and indirect effects on historic properties within the Corps-indentified permit area. Version 7.8.2014 Page 9 Endangered Species Pursuant to the Endangered Species Act of 1973, the Corps reviewed the project area, examined all information provided by the applicant and consulted the latest North Carolina Natural Heritage Database. Based on available information: ❑ The Corps determines that the proposed project would not affect federally listed endangered or threatened species or their formally designated critical habitat. ® The Corps determines that the proposed project may affect federally listed endangered or threatened species or their formally designated critical habitat. The Corps reviewed this project in accordance with (IAW) the NLEB Standard Local Operating Procedures for Endangered Species (SLOPES) between the USACE, Wilmington District, and the Asheville and Raleigh U.S. Fish and Wildlife Service (Service) Offices, and determined that the action area for this project is located outside of the highlighted areas/red 12-digit HUCs and activities in the action area do not require prohibited incidental take; as such, this project meets the criteria for the 4(d) rule and any associated take is exempted/excepted. ® By copy of this public notice, the Corps initiates consultation under Section 7 of the ESA and will not make a permit decision until the consultation process is complete. ❑ The Corps is not aware of the presence of species listed as threatened or endangered or their critical habitat formally designated pursuant to the Endangered Species Act of 1973 (ESA) within the project area. The Corps will make a final determination on the effects of the proposed project upon additional review of the project and completion of any necessary biological assessment and/or consultation with the U.S. Fish and Wildlife Service and/or National Marine Fisheries Service. Other Required Authorizations The Corps forwards this notice and all applicable application materials to the appropriate State agencies for review. North Carolina Division of Water Resources (NCDWR): ❑ The applicant did not provide or satisfy all 9 elements required for a complete 401 certification request. Therefore, the 401 Certification process has not started. The Corps will generally not make a final permit decision until the NCDWR issues, denies, or waives the state Certification as required by Section 401 of the Clean Water Act (PL 92-500). Version 7.8.2014 Page 10 ® The Corps will generally not make a final permit decision until the NCDWR issues, denies, or waives the state Certification as required by Section 401 of the Clean Water Act (PL 92-500). The NCDWR received a complete application for this project on July 28, 2021. Additional information regarding the 401 Certification may be reviewed at the NCDWR Central Office, 401 and Buffer Permitting Unit, 512 North Salisbury Street, Raleigh, North Carolina 27604-2260. All persons desiring to make comments regarding the application for a 401 Certification should do so, in writing, by December 10, 2021 to: NCDWR Central Office Attention: Mr. Paul Wojowski, 401 and Buffer Permitting Unit (USPS mailing address): 1617 Mail Service Center, Raleigh, NC 27699- 1617 Or, (physical address): 512 North Salisbury Street, Raleigh, North Carolina 27604 North Carolina Division of Coastal Management (NCDCM): ❑ The application did not include a certification that the proposed work complies with and would be conducted in a manner that is consistent with the approved North Carolina Coastal Zone Management Program. Pursuant to 33 CFR 325.2 (b)(2) the Corps cannot issue a Department of Army (DA) permit for the proposed work until the applicant submits such a certification to the Corps and the NCDCM, and the NCDCM notifies the Corps that it concurs with the applicant's consistency certification. As the application did not include the consistency certification, the Corps will request, upon receipt, concurrence or objection from the NCDCM. ® Based upon all available information, the Corps determines that this application for a Department of Army (DA) permit does not involve an activity which would affect the coastal zone, which is defined by the Coastal Zone Management (CZM) Act (16 U.S.C. § 1453). Evaluation The decision whether to issue a permit will be based on an evaluation of the probable impacts including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably Version 7.8.2014 Page 11 foreseeable detriments. All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, flood plain values (in accordance with Executive Order 11988), land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership, and, in general, the needs and welfare of the people. For activities involving the discharge of dredged or fill materials in waters of the United States, the evaluation of the impact of the activity on the public interest will include application of the Environmental Protection Agency's 404(b)(1) guidelines. Commenting Information The Corps of Engineers is soliciting comments from the public; Federal, State and local agencies and officials, including any consolidated State Viewpoint or written position of the Governor; Indian Tribes and other interested parties in order to consider and evaluate the impacts of this proposed activity. Any comments received will be considered by the Corps of Engineers to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects and the other public interest factors listed above. Comments are used in the preparation of an Environmental Assessment (EA) and/or an Environmental Impact Statement (EIS) pursuant to the National Environmental Policy Act (NEPA). Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider the application. Requests for public hearings shall state, with particularity, the reasons for holding a public hearing. Requests for a public hearing shall be granted, unless the District Engineer determines that the issues raised are insubstantial or there is otherwise no valid interest to be served by a hearing. The Corps of Engineers, Wilmington District will receive written comments pertinent to the proposed work, as outlined above, until 5pm, December 6, 2021. Comments should be submitted to Andrew Williams, Raleigh Regulatory Field Office, 3331 Heritage Trade Drive, Suite 105 , Wake Forest, North Carolina 27587, at (919) 554-4884 extension 26 or at andrew.e.williams2@usace.army.mil. Version 7.8.2014 Page 12 Legend AJD Boundary Feet 10,000 RANDOLP., Pleasant Garden Stone/Camp P oleo°\ vJ Nal= Forel oiacnsourg Winston-Salem 0 P I E NORTH Iiterll CAROLINA Charlotte NFoaYFI Miles 80 Greensboro Durham p Rody Mount N T R alelgh o Greer. Fayetteville 0 Lumcee Sere. H O0� Jacksonville 0 FEZ ?es n Forest Oaks Climax OI` Project Site 1 n`I 01 I r. xF Roc i," ..Pro Hat I Liberty Sta Saar Creek Golf C lue Cedegck Park ,eal, Gxeev. i, 9;att CANE CREEK MOUNTAINS Snow Camp Maras Gxe ALAI• CHA 0 yJ VICINITY MAP FIGURE 1 at *mart. IMMUZPIMIL. Legend AJD Boundary Feel 1200, AERIAL PHOTOGRAPHY MAP Legend ��Ov n AJD Boundary Feet 2,000 n sboro ays High Point P. an dole fr • �GI.ILFnkD C RANDDLPR nuton ham aro • USGS TOPOGRAPHIC MAP FIGURE 3 A Legend n Q AJD Boundary 1 J 1% Annual Chance Flood Hazard Feet 1,200 FEMA FLOODPLAIN MAP FIGURE PAo ��NOAR.1 IMERaIANGE IN __Wm an Ma i ainipi Imitrin sza LP' IcjI 111 / \� 04, \ ey \ o HUTY I—r--I GRAPHIC SCALE 11T GREENSBORO RANDOLPH MEGASITE FOUNDATION GREENSBORO RANDOLPH MEGASITE RANDOLPH COUNTY, NORTH CAROLINA OVERALL SITE PLAN 01X-04 • 1 RD 3riMajirm...um sal -01X05 111,1,01X-06 --1-,- 01X-07 01X-08 .4 gl ii II 01X-5-09 �` 01X-10 01X-11 01X-12 i 01X-13 II ' 01X-14 01X-15 !01 X-16 1 I 1IX-17, , Y 01X-18 N. 01X-19� '1 01X-20� 01X21 1, 5 01X-222� / � 01X-23 01X-24 II I. \� � VA -, wjmi 01 X-25 -- 01X-26 L N UMMEMEM LEGEND EXISTING WETLAND EXISTING POND EXISTING PERENNIAL STREAM EXISTING INTERMITTENT STREAM PERMANENT WETLAND IMPACT TEMPORARY WETLAND IMPACT PERMANENT POND IMPACT PERMANENT STREAM IMPACT TEMPORARY STREAM IMPACT 0 2000' 4000' SCALE: 1"= 2000' HUH engineering Me of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 01X-01 Wetland Impacts Impact Number Sheet Number Wetland ID Let. (decimal degrees) Long. (decimal degrees) Type of Impact Type of Wetland (Cowardin) Area of Permanent Impact (acres) Area of Temporary Impact (acres) W5.1 5 W38 35.899726 -79.639533 Fill PFO 0.03 0 W5. 2 5 W40A 35.899484 -79.637939 Fill PFO 0.04 0 W6. 1 6 W5 35.900708 -79.631982 Fill PFO 0.13 0 W6.2 6 W5 35.90116 -79.631542 Fill PFO 0.19 0 057. 1 7 W22 35.899693 -79.621614 Fill PFO 0.15 0 W8. 1 8 W21 35.899757 -79.617328 Fill PFO 0.24 0 W8. 2 9 W23 35.899944 -79.619257 Fill PFO 0.25 0 W9. 1 9 W40A 35.899385 -79.637886 Fill PFO 0.02 0 W9. 2 9 W408 35.89895 -79.637536 Fill PFO 0.02 0 W9.3 9 W37 35.898692 -79.637031 Fill PFO 0.14 0 W9.4 9 W43 35.898455 -79.638564 Fill PFO 0.05 0 W9.5 9 W45 35.897286 -79.638822 Fill PFO 0.01 0 W11.1 11 W6 35.895595 -79.628154 Fill PFO 0.02 0 W11.2 W11.3 11 11 W7 W8 35.895927 35896215 -79.626777 -79626185 Fill Fill PFO PFO 0.06 005 0 0 W11.4 11 W22 35.899311 -79.621553 Fill PFO 0.16 0 W12.1 12 W22 35.899009 -79.620748 Fill PFO 0.07 0 W12.2 12 W20 35.898556 -79.619025 Fill PFO 0.10 0 W12.3 12 W21 35.899209 -79.618469 Fill PFO 0.09 0 W12.4 12 W24 35.897575 -79.618322 Fill PFO 0.22 0 W13.1 13 W18A 35.893583 -79.638916 Fill PFO 0.13 0 W13.2 13 W19 35.893997 -79.63887 Fill PFO 0 14 0 W13.3 13 WB 35.891922 -79.638696 Fill PFO 0.07 0 Wetland Impacts Impact Number Sheet Number Wetland ID Lat. (decimal degrees) Long. (decimal degrees) Type of Impact Type of Wetland (Cowardin) Area of Permanent Impact(acres) Area of Temporary Impact(acres) W14.1 14 W9 35.891063 -79.63342 Fill PFO 0.34 0 W14. 2 14 W12 35.892202 -79.631077 Fill PFO 0.26 0 W15. 1 15 W35 35.891018 -79.624455 Fill PEM 0.25 0 W15. 2 15 W25 35.893418 -79.622393 FIII PFO 0.24 0 W16. 1 16 W28 35.890797 -79.616121 FIII PFO 0.05 0 W16.2 16 W31 35.892481 -79.615397 Fill PFO 0.54 0 W16.3 16 HDR WG 35.890983 -79.620098 Fill PEM 0.11 0 W16. 4 16 HDR WH 35.892429 -79.619589 Fill PFO 0.67 0 W17. 1 17 W44 35.889785 -79.638849 Fill PFO 0.03 3 W17. 2 17 W3 35.888035 -79.636276 FIII PFO 0.26 0 W18.1 18 W9 35.890581 -79.633293 Fill PFO 0.07 0 W18.2 18 W10 35.889553 -79. 63211 Fill PFO 0.16 0 W18. 3 18 W13 35.887305 -79. 6319 Fill PFO 0.14 0 W18.4 18 W3 35.888035 -79.636276 Fill PFO 0.00 0 W19.1 19 W34 35.889395 -79.624701 FIII PFO 0.24 0 W19.2 19 W14 35.888443 -79.625216 Fill PFO 0.12 0 W19.3 19 HDRWF 35.888548 -79.621506 Fill PFO 0.15 0 W20.1 20 W28 35.8901 -79.616452 Fill PFO 0.78 0 W20. 2 20 W32 35.88899 -79.618632 Fill PFO 0.19 0 W20.3 20 HDR WE 1'35.888498 l'-79.619415 Fill PFO 1.84 0 W23.1 23 WW 35.88402 -79.625738 Fill PEM 0.15 0 W24. 1 24 HDR WB 35.884777 -79.61877 Fill PFO/PEM 0.12 0 Total 9.07 0 NOTE: 1. ALL FEATURES ARE WITHIN DEEP RIVER WATERSHED. HUH engineering Me of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE 10/13/2021 SHEET 01X-02 Stream Impacts Impact Number Sheet Number Stream ID Lat (decimal degrees) Long. (decimal degrees) Type of Impact Perennial (P) or Intermitten t (I) Average Stream Width (feet) Permanent Impact Length (linear feet) Temporary Impact Length (linear feet) Impact Area (square feet) S5.1 5 SK 35.900393 -79.636643 641 P 2 25 0 50 S5.2 5 S45 35.899868 -79.636795 Fill P 4 492 0 1968 S5.3 6 S15 35.901476 -79.643903 Fill P 5 34 39 195 S6.1 6 S7 35.899976 -79.631308 Fill P 3 633 0 1899 S6.2 6 S1 35.900243 -79.629132 Fill P 4 485 0 1939 S7.1 7 S5 35.899765 -79.627353 641 1 4 203 0 812 S8.1 8 S22 35.899567 -79.617489 Fill P 3 79 0 237 S9.1 9 543/S438 35.898866 -79.63863 641 P 4 768 0 3072 S9.2 9 S45 35.898184 -79.63787 Fill P 4 2363 0 9452 S9.3 9 S51 35.899288 -79.63773 Fill I 3 81 0 243 S9.4 9 S48 35.898246 -79.643552 Fill I 3 45 55 165 S10.1 10 S1 35.8963 -79.629864 Fill P 4 2191 0 8762 S10.2 10 S7 35.898253 -79.630498 Fill P 3 1092 0 3276 S10.3 10 S4 35.89849 -79.628489 Fill P 4 65 0 260 S10.4 10 SA 35.897881 -79.628559 Fill I 3 116 0 348 S10.5 10 S9 35.89546 -79.629054 Fill I 4 601 0 2404 S10.6 10 S8 35.897307 -79.631058 Fill I 3 588 0 1764 S11.1 11 S4 35.898854 -79.62792 Fill P 4 323 0 1292 S11.1 11 S4 35.899 -79.6277 Fill I 4 455 0 1820 S11.2 11 SA 35.897975 -79.628114 Fill I 3 175 0 525 S11.3 11 S9 35.895803 -79.627567 F01 1 4 758 0 3032 S11.4 11 S20 35.89911 -79.621146 Fill P 3 124 0 372 S11.5 11 S5 35.899273 -79.62751 F81 1 4 163 0 652 S12.1 12 S20 35.898865 -79.619771 Fill P 3 949 0 2847 S12.2 12 S22 35.899087 -79.618008 Fill P 3 330 0 990 S12.3 12 S21 35.896637 -79.618448 Fill P 4 1689 0 6756 S12.4 12 S23 35.897961 -79.618066 F81 1 3 76 0 228 S13.1 13 S45 35.892807 -79.639112 Fill P 4 2140 0 8560 S13.2 13 SY 35.893981 -79.638491 F01 I 3 107 0 321 014.1 14 S1 35.893918 -79.630228 Fill P 4 1419 0 5676 Stream Impacts Impact Number Sheet Number Stream ID Lat (decimal degrees) Long. (decimal degrees) Type of Impact Perennial (P) or Intermitten t(I) Average Stream Width (feet) Permanent Impact Length (linear feet) Temporary Impact Length (linear feet) Impact Area (square feet) S15.1 15 S25 35.893404 -79.621706 Fill P 3 410 0 1230 015.2 15 026 35.893629 -79.621324 Fill 1 3 163 0 489 S15.3 15 HDR S9 35.890773 -79.623656 Fill 1 3 222 0 666 S16.1 16 025/S250 35.893092 -79.620224 Fill P 3 541 0 1623 016.2 16 035 35.891276 -79.615761 Fill P 4 483 0 1932 016.3 16 021 35.892261 -79.619717 Fill P 4 1918 0 7671 S17.1 17 S45 35.889256 -79.639931 Fill P 4 861 65 260 017.2 17 044 35.889771 -79.639514 Fill P 3 756 0 2268 018.1 18 0128 35.8868 -79.632719 Fill P 3 162 0 486 S18.2 18 51 35.886749 -79.63223 Fill P 4 752 0 3009 018.3 18 511 35.887125 -79.631796 Fill P 3 232 0 696 019.1 19 HDR S9 35.888223 -79.624394 Fill 1 3 1484 0 4451 S20.1 20 S35 35. 889298 -79.617801 Fill P 4 1443 0 5772 020.2 20 021 35.890149 -79.619916 Fill P 4 1728 0 6912 020.3 20 HDR 09 35.88684 -79.619587 Fill 1 3 417 0 1251 S20.4 20 S30 35.887667 -79.616619 Fill P 3 1708 45 135 S20.5 20 S31 35. 888347 -79.614963 Fill 1 3 29 54 162 S20.5 20 S31 35. 888347 -79.614963 Fill P 3 187 0 561 S22.1 22 S1 35.885936 -79.633011 Fill P 4 406 41 164 S23.1 23 S17 35.883641 -79.626236 Fill P 3 572 55 165 024.1 24 021 35.885824 -79.619151 Fill P 4 346 0 1384 S24.2 24 S30 35.884555 -79.619164 Fill P 3 2240 40 120 024.3 24 HDR S4 35.885421 -79.619586 Fill 1 4 450 0 1800 024.4 24 HDR 03 35.884454 -79.618546 Fill P 3 412 0 1236 024.4 24 HDR 03 35.884454 -79.618546 Fill 1 3 422 0 1266 024.5 24 HDR 05 35.884665 -79.619115 Fill 1 3 71 0 213 S26.1 26 HDR S2 35.881433 -79.618688 Fill P 3 68 47 141 Perennial Total 30,426 332 93,368 Intermittent Total 6,626 109 22,612 Stream Impact Total 37,052 441 115,980 NOTE: 1. ALL FEATURES ARE WITHIN DEEP RIVER WATERSHED. HUH engineering Inc of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE 10/13/2021 SHEET 01X-03 Open Water Impacts Impact Number Sheet Number Name of Waterbody Lat. (decimal degrees) Long. (decimal degrees) Permanent (P) or Temporary (7) Type of Impact Waterbody Type Impact Area (acres) P5.1 5 P6 35.901573 -79. 639568 P Fill Pond 0.17 P5.2 5 P7 35.900787 -79. 639578 P Fill Pond 1.39 P5.3 5 P8 35.899457 -79.639504 P Fill Pond 0.02 P5.4 5 P2 35.9007 -79.643849 P Fill Pond 1.35 P6.1 6 P10 35.9015 -79.632445 P Fill Pond 2.02 P7.1 7 P11 35.899804 -79.626451 P Fill Pond 0.17 P9.1 9 P8 35.899102 -79.639228 P Fill Pond 0.42 P11.1 11 P11 35.899425 -79.626452 P Fill Pond 0.05 P13.1 13 P9 35.892186 -79.638263 P Fill Pond 0.20 P14.1 14 P13 35.891276 -79.631086 P Fill Pond 3.77 P16.1 16 PC 35.893643 -79.614573 P Fill Pond 0.81 P17.1 17 P16 35.887874 -79.636668 P Fill Pond 0.39 P17.2 17 P17 35.887099 -79.637608 P Fill Pond 1.37 P18.1 18 P13 35.890413 -79.631492 P Fill Pond 1.88 P18.2 18 P15 35.888409 -79.631574 P Fill Pond 6.32 P18.3 18 P14 35.890026 -79.633032 P Fill Pond 1.21 Total 21.54 Indirect - Stream Impacts Impact Number Sheet Number Stream ID Lat (decimal degrees) Long. (decimal degrees) Type of Impact Perennial (P) or Intermittent (I) Average Stream Width (feet) Permanent Impact Length (linear feet) Temporary Impact Length (linear feet) Impact Area (square feet) 56.2 6 51 35.9005 -79.629 Indirect P 4 208 0 832 56.3 6 S1 35.8971 -79.6295 Indirect I 4 632 0 2528 S6.4 6 S2 35.9014 -79.6285 Indirect I 3 256 0 768 S7.2 7 S2 35.9014 -79.6285 Indirect 1 3 378 0 1134 S5.3 5 643A 35.9019 -79.6400 Indirect I 3 212 0 636 Total 1686 0 5898 Indirect - Open Water Impacts Impact Number Sheet Number Name of Waterbo dy Lat (decimal degrees) Long. (decimal degrees) Penman nt (P) or Tempora ry (T) Type of Impact Waterbody Type Impact Area (acres) P5.5 5 P5 35.9024 -79.6401 P Indirect Pond 0.09 P7.2 7 P12 35.9027 -79.627 P Indirect Pond 0.69 Total 0.78 Indirect- Wetland Impacts Impact Number Sheet Number Wetland ID Lat (decimal degrees) Long. (decimal degrees) Type of Impact Type of Wetland (Cowardin) Area of Permanent Impact (acres) Area of Temporary Impact (acres) W7.2 7 WA 35.902 -79.6281 Indirect PFO 0.01 0 W6.3 6 W1 35.9011 -79.6287 Indirect PFO 0.07 0 W5.3 5 W39 35.9024 -79.6405 Indirect PFO 0.29 0 Total 0.37 0 NOTE: 1. ALL FEATURES ARE WITHIN DEEP RIVER WATERSHED. HUH engineering Inc of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE 10/13/2021 SHEET 01X-04 OHE c` PROPOSED DUKE ENERGY 500kV CORRIDOR 5 -, I r l /J L. / 7s; / / / / / tt .�--: 5hr L042, R__------------- NORFOLK SOUTHERN RAILROAD _-_ _� .ry—T� \ '-1L/r am -am 'T ��_ =�`-4 P5.5✓_�_ /L� L e �NON-JURISDICT ONAL �\ \ O I / .--"Ti-\ POND (PA), 0.08 AC. OHE - j �) i \ >9HEi OHE ti� 1 1 ,OH� 1 ti „ `L � ti 11 A ( �/55.3 Y-�-�' \ \ \ l \ \ \yam 1 Io$ W5.1 `- 7 l•,`- s zV ) A e — ��—b II w Jm 1 ,/ II "',^ L--E-- T { j 55.1 P5.3 MATCHLINE - SEE SHEET 9 FOR CONTINUATION W52 S5.2 z U GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ 555 Fayetteville Street, Suite 900 PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE 10/13/2021 SHEET 01x-05 1 // o I z z OHE z 0 - oI 2 ORFOLK S UTHERN RAILRQAD- �� / .OT�-2hD _ �� _ NORFOLK SQUTHERN RAILROAD— 56.1J PROPOSED DUKE ENERGY 500kV CORRIDOR / ) F / )/ / S6.3 )\ MATCHLINE- SEE SHEET 10 FOR CONTINUATION 5612 1. MTI N GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND Wetland Impacts KEY MAP Impact Site re ID from PJD Impact TYv Permanent ImpactAreaC TempP�arr Impact Area Fli Fli Total 0.32 Pond Impacts Impact Site Feature ID Dom POD Impact Type Pemlaoent Impact Area (AC) P6.1 P10 2 02 Total Perennial Stream mpacta Impact Site Feature ID from PJD Impact Type Pennanent Impact Length (LF) Temporary Impact Length (LP) 56.1 57 Fill 633 58.2 S1 086 Total 1118 Fdlrect - 5 ream Imps to Impact Stle Feature ID Wm PJD Impact TTPT Permanent Impact Length () Temporary Impact Length CJ 56.2 Fil 208 56.3 Indirect 632 drect 256 Total 1058 Wlirect- Wetland Imp cts Impact te S W6.3 Total Feature D fromPOD KEY MAP Wi TTPT Impact Indirect NOT TO SCALE Permanent Impact Area (AC) 0.07 0.07 Temporary Impact Area (AC) 0 200' 400' SCALE: 1"= 200' HUH engineering Me of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 01X-06 —� 1I I w� l ��II`��tr/ OLD 421 RD� RAJ Ir / /2 \ I \ 1 \ L / / \\‘ S7.2 �� �� /ll 1 //_,,/ P7.2 s, e• ) Ii // / PROPOSED DUKE y ThFY ( / / �SENERGY OkV �L/ / / CORRIDOR ��Rq/��A_ 'f` !`s/ F O'9� 0 i2—\ /"�,� - A / i �/ / A OHE OHE M OHE OHE MATCHLINE - SEE SHEET 11 FOR CONTINUATION GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Wetland Imp,. Impact Feature 0 horn PJD Troat Permanent Impact 22 Imps, Area Total Pend Impact Feature 0 from P30 Permanent A l Total Intermit.. Stream Im a. Impact Feature 0 ,mpact Permanent Impact J Length 571 55 Total Inrllre:t - stream impacts Impact Feature 0 from P30 Impact TYPe Permanent Impact; Impact Tempora„ Indrect PPP Total PPP Indirect - peo water lmpama Impact Feature ID from P30 mpact Permanent Impact Area AC) Indirect Total ®®EIZAIMMIMO KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ HUH engineering Inc or. Carolinas NCBELS License Number F-0116 PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/132021 01X-07 WI w rn w I ORFp K$OUT 1ERN RAILROAD I- 1� ) (- /)12 OL q v __ - J I iti \\`\\\\ 1 // - I/ / J - _! / / / - A- � 1 )) 1 --� `1/ _--' -- /}! \ to PROPOSED DUKE ENERGY500kV l . A . ',i� / o'\ \ .--/ \ CORRIDOR J/*rp�:��� A LWSc2)e w�\ _'\ r- HE ss `' OHE \\ Sal i OHE ss � w MATCHLINE- SEE SHEET 12 FOR CONTINUATION GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Wetland Impacts re ID fiomn PJD W23 Perennial otream hpacis Impact Site yen V08.2 Type Perrin nt Impact (AC) r Temporary Impact Area (AC) Fil 0.23 Total 0.49 P let ac aentpre D mP3o Impact Permanent Impact Length () Temporary Impact Length () 58.1 522 Fil KEY MAP NOT TO SCALE Total 0 200' 400' SCALE: 1"= 200' HUH engineering Me of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 01X-08 I II I I. 1 1 S9.4 7 J• MATCHLINE - SEE SHEET 5 FOR CONTINUATION W9.1 " r S9.3 P9.1 PROPOSED GRADING PROPOSED GRADING W9.4 S9.2 MATCHLINE - SEE SHEET 13 FOR CONTINUATION S9.2 PROPOSED INTERIOR RAIL LINES GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Pa Impact Site 1779.6 1199.4 Feature 10 horn ND a. impacts pSites act WIOA MOB Feature 10 horn KID Feature ID horn ND Impact TYPe Impact type Total Up a.m. Aryan) Impacts Impact Type St n Im acts FOOL. ID hom PLO Impact TYPe P(AC) ra Temporary Impact Length (LP) Temporary Impact Length M1F) Permanent ImpactacmAme 0 Al Impact Area Permanem Impact Length lJ 768 2363 3131 Permanent Impact Length 126 0 200' 400' SCALE: 1"= 200' HUH engineering Inc °Mlle Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 01x-09 MATCHLINE - SEE SHEET 9 FOR CONTINUATION MATCHLINE - SEE SHEET 6 FOR CONTINUATION PROPOSED INTERIOR RAIL LINES PROPOSED GRADING BROWNS MEADOW RD PROPOSED GRADING MATCHLINE - SEE SHEET 14 FOR CONTINUATION GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Perennial Stream Impacts Impact Site Feature ID tom NO Impact Type Permanent ImpactLength (LF) Temporary Impact Length (LF) Z 165 S10.3 54 Fill Total 3348 htermittent Stream Impacts Impact Site Feature 10 horn ND Impact Type germanent Impact Length (LF) Temporary Impact Length (LF) S164 SA FIII 116 S10.6 38 FIII 601 310.6 SO Fill 680 Total 1305 X i KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' HUH engineering Me of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 01x-10 MATCHLINE - SEE SHEET 10 FOR CONTINUATION MATCHLINE - SEE SHEET 7 FOR CONTINUATION S11.5 P 11.1 , S11.1 INTERMITTENT L—�, 511.4 \S11.1 PERENNIAL S11.2 PROPOSED GRADING GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Wetland /Tweets Feature ID from PJO Permanent Impett Area (AG) Temporary Impact Area (AG) 8811 0.02 006 W8 0 05 W114 W22 0LI6 Total 0.29 Z Pond Impacts O Z 0 0 I7 I7 Z U Q 12 MATCHLINE - SEE SHEET 15 FOR CONTINUATION Impact Site Feature ID from ND Impact Type Permanent Impact Area (AP) P111 Pit 0.05 Total 005 Perennial Stream impacts mpact Site Feature ID from PJD impact Type PermanenE Impact Lerfgth (LFI Temporary impact Length (LF) S11.1 S4 Fiil 323 Sit 4 SPO Flil 124 Total Intamtltten re cte im�ct SRe Featum ID from NO Impact Typo Permanent Impact Length dr, temporary Impact Length (lF) S111 S4 Fiil 455 S1t 2 SA F/il 175 O 5113 SO Fiil 758 511.5 56 Fiil 163 O Total 1551 O 4 / 0 200' 400' KEY MAP SCALE: 1"= 200' NOT TO SCALE HUH engineering Inc of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 01x-11 W12.1 S12.1 W12.2 W12.4 MATCHLINE - SEE SHEET 8 FOR CONTINUATION PROPOSED GRADING 2.3 MATCHLINE- SEE SHEET 16 FOR CONTINUATION ` o •` N • \ Ns, PROPOSED DUKE 4 ENERGY 500kV CORRIDOR GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Wetland Impacts Impact Site Feature ID four PM Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) W12.1 W22 FIII 0.07 0 W12.2 W20 FIII 0.10 0 W12.3 W21 FIII 0.09 0 W12.4 W24 FIII 0.22 0 Total 0.47 0 PerennlelStream Imp is Impact Site Feature ID tom ND Impact Type Permanent Impact Length (LF) Temporary Impact Length (LF) 512.1 520 FIII 949 0 5122 522 FIII 330 0 512.3 521 FIII 1689 0 Total 2968 0 htenmittenl Stream Impacts Impact Site Feature ID tom ND Impact Type Permanent Impact Length (LF) Temporary Impact Length (LF) 5124 523 FIII 76 0 Total 76 0 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' HUH engineering I ne of the Carolinas F)1 PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE 10/13/2021 SHEET 01X-12 11 t 11 PROPOSED \ \ 11 1 1 POWER DISTRIBUTION ll(111 LINE TO SITE 1 /----\'./ rt /1 r 1 �� l ///���_////l t 1 i / / /// / / / / 1 l ( f ///////��' 1 V Al 1 77 1/11// //`v v \-vvv1v' vAv�1 1)11////Z11)(/�_�7 v 1I11111/ 1111/1J7 /� '�\ )1 I I) li 1//� \}11111J�l �I / /� �' 1 �-IJ/�1i/Li,II 7111\Ili'\\\\�i-, MATCHLINE - SEE SHEET 9 FOR CONTINUATION 11 1 1 — MATCHLINE - SEE SHEET 17 FOR CONTINUATION ) S13.1 PROPOSED GRADING VE - SEE SHEET 14 FOR CONTINUATI GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Wetland Impacts Impact Site Feature ID tom PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) W13.1 W18A Fill 0.13 0 W13.2 W19 Fill 0.14 0 W13.3 W8 Fill 0.07 0 Total 0 34 0 Pond Impacts Impact Site Feature ID tom PJD Impact Type Permanent Impact Area (AC) P13.1 P9 Fill 0.20 Total 020 Perennial Stream Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Length (LF) Temporary Impact Length (LF) S131 Sits Flo 2140 0 Total 2140 0 Ftennittent Stream Ira acts Impact Site S132 Feature ID from PJD SY Impact Type Fill KEY MAP NOT TO SCALE Total Permanent Impact Length (LF) 107 107 Temporary Impact Length (LF) 0 200' 400' SCALE: 1"= 200' HUH engineering Me of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE 10/13/2021 SHEET 01X-13 MATCHLINE - SEE SHEET 13 FOR CONTINUATION N MATCHLINE - SEE SHEET 10 FOR CONTINUATION PROPOSED GRADING Jgc,IL MATCHLINE - SEE SHEET 18 FOR CONTINUATION GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Wetland Impacts Impact Site Feature ID from PJD Impact Type Pannone Impact Area (AC) Temporary Impact Area (AC) W14.1 W9 FIII 0.34 0 W14.2 W12 Fill 0.20 0 Total C90 0 Pond Impacts Impact Site Feature ID from PJD Impact Type Pemtanera Impact Area (AC) P14.1 P13 FIII 3.17 Total 3.17 Perennlel Stream enpacts Impact Site Feature ID from PJD Impact Type Permanent Impact length (LF) Temporary Impact Length (LP) 314.1 S1 Fill 1419 0 Total 1419 0 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' HUH engineering Me of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 01X-14 MATCHLINE - SEE SHEET 14 FOR CONTINUATION MATCHLINE - SEE SHEET 11 FOR CONTINUATION PROPOSED GRADING MATCHLINE - SEE SHEET 19 FOR CONTINUATION 315.3 GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Wetland Impacts Impact Sita Feature ID Awl PJD Impact Type Impact Area (AC) Temporary Impact Area AIWA W35 525 W 16.2 W25 524 Total Perennial Stream Ynpacis Sptet Feature D fromPJD TYPT Impact Permanent Impact Length (LF) Temporary Impact Length (LW 515.1 325 Fil 410 Total 410 Intermittent Strwm Im acts Site homure D PJD Impact Permanent Impact length () Temporary Impact Length C) 5153 NDR 58 222 S15.2 526 Fil 163 Total 385 X i KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' HUH engineering Me of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 01x-15 MATCHLINE— SEE SHEET 12 FOR CONTINUATION PROPOSED INTERIOR RAIL LINES PROPOSED GRADING ui MATCHLINE — SEE SHEET 20 FOR CONTINUATION GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Wetland Impacts Impact Site re ID home PJD Impact Type Permanent ImpactAreaC Temporary P(ct Area AC) Fil Fil V616.3 MDR Vile 0.1 W 16.4 HDR NM Fil 0.67 Total 1.37 Pond Impacts Sitet homPD PaD TYPe Impact Permanent Impact Area (AC) P16.1 PC Fil 0.81 Total 0.81 Perennial stream hpecis Impact 3M rPJD horn Type Permanent ImpactLength (LF TempLmry Impacte F 1Ln9t S16.1 525I526R Fill 541 0 S162 S36 Fill 483 S16.3 321 FIII 1818 Total 2312 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' HUH engineering Me of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 01X-16 MATCHLINE - SEE SHEET 13 FOR CONTINUATION W17.1 MATCHLINE - SEE SHEET 21 FOR CONTINUATION PROPOSED GRADING GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Wetland Impacts Impact Site re ID homa PJD Impact Pent,Area Impactrea t) Temporary Impact (AD) W 17.2 W3 0.26 Total 0.29 Pond Vimacts Site Feature ID horn PJD ImpactImpact Type Permanent MP (AC)rea P17.1 P16 Fin 0.39 P17.2 P17 Fill 1.37 Total 1.76 Perennial Aram, Ynpacis Impact Site Feature ID horn PJD Impact Type Permanent Impact length (LF) Temporary Impact Length (LF) 6,1 .5 Fill 861 65 517.2 5A4 FIII 756 Total 1617 65 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' HUH engineering Me of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 01X-17 W18.1 7 o' I / o �/ W 2 L Z 0 m z O zI z z 0 0 ce OI ,..I • P18.3 S18.1 MATCHLINE - SEE SHEET 14 FOR CONTINUATION W18.2 S18.2 S18.2 P18.1 S 8.2 W18.3 S18.3 MATCHLINE - SEE SHEET 22 FOR CONTINUATION P18.2 N 7 aVetland Impacts z O O O PROPOSED GRADING Iw W W Z F 2 GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Impact Site Feature hemPJD Impact Type Permanent .pact Area (AC) Temporary ImpactArea 15118.1 VV. Fil 0.07 W18.3 8813 Fill 0.14 16118.4 1/63 Fill 0.005 Total 0.37 0 Pond Imp Is Impact Site Fealure ID horn PJD Impact Tvv Permanent Impact Area P18.1 P13 1 88 P18.2 P15 Fil 6.32 P18.3 P14 Fil Total 0.41 Perennial Stream impacts Impact Site Feature ID horn PJD Impact Type Permanent Impact length (LF) Temporary Impact Length (LF) S18.1 S128 FIII 162 S18.2 S1 FIII 752 S18.3 S11 Fill 232 0 Total 11. 0 X i KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' HUH engineering Inc of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 01X-18 MATCHLINE - SEE SHEET 18 FOR CONTINUATION MATCHLINE - SEE SHEET 15 FOR CONTINUATION MATCHLINE - SEE SHEET 23 FOR CONTINUATION GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Wetland Impacts Site Feature ID from PJD Impact Type Pennane Impact Area (AC) Temporary knpact Area (AC) W19.1 W34 Fill 0.24 0 W19.2 W14 Fill 0.12 0 W19.3 HDR WF Fill 0.15 Total 0 51 Merrnittent Stream impacts Impact Site Feature ID from PHI Impact Type Permanent Impact Length (LF) Temporary Impact Length (LF) S19.1 HDR S9 FIII 1484 0 Total 1484 0 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' HUH engineering Me of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS OATS 10/13/2021 SHEET 01x-19 z O Z z 0 0 17 rn Z MATCHLINE- SEE SHEET 16 FOR CONTINUATION MATCHLINE - SEE SHEET 24 FOR CONTINUATION 4 • 520.5 ( N ®GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Wetland Impacts Impact Site Feature ID flour PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) W20.1 4828 Fill 078 W20.2 4832 Fill 0.19 13120.3 HDR WE F"'Total 2.80 Memident Stream Impacts Impact Site Feature ID firm PJD Impct Type Permanent Impact Length (LF) Temporary Impact Length (LF) S20.3 HDR S9 FIII 417 S20.5 531 Fig 9 Total 443 50. Perennial Stream Impacts Site firm PJD Type Impact Length Impact Length S20.2 S21 Fill 1738 S204 S30 Fill 1708 45 S20.5 331 FI8 187 Total SOW 45 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' HUH engineering Me of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 01X-20 MATCHLINE - SEE SHEET 17 FOR CONTINUATION F)1 HUH engineering Me of the Carolinas e'F2gliefiF0Free""e NCBE LS Leen. Number F 0116 GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP 2) NO JURISDICTIONAL IMPACTS THIS SHEET PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE 10/13/2021 SHEET 01X-21 L-,:- ' . r - _Th , r \ \ t ) �i / 111 / �-i////)J/ / / � ,-/ o 01 //—'tiii/)IqI( Jl ° 7- I), 4),/ -//l,1 ((f �F �' \ J 1 r ) /� ))) ff- /. ///// /�///// / MATCHLINE - SEE SHEET 18 FOR CONTINUATION FEZ HUH engineering Me of the Carolinas GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Impact Site Feature ID from PJD Impact Type Permanent Impact Length (LF) Temporary Impact Length (LF) S22. 1 S1 HI 406 41 Total 406 41 PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE 10/13/2021 SHEET 01X-22 S23.1 MATCHLINE - SEE SHEET 19 FOR CONTINUATION W23.1 NON -JURISDICTIONAL POND (PB), 0.98 AC. //---_7 / .I /, / ---, NON -JURISDICTIONAL _ WETLAND (HDR WD), 0.02 AC. -� _ — p MATCHLINE - SEE SHEET 25 FOR CONTINUATION GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) W23.1 WW Fill 0.15 0 Total 0.15 5 00 Impact Site Feature ID from PJD Impact Type Permanent Impact Length (LF) Temporary Impact Length (LF) S23.1 S17 Fill 573 55 Total 573 55 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' HUH engineering Me of the Carolinas F)1 PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE 10/13/2021 SHEET 01X-23 524.3 524.2 S24.1 524.2 S24.5 MATCHLINE- SEE SHEET 20 FOR CONTINUATION W24.1 S24.4 PERENNIAL 524.2 i S24.2 PROPOSED INTERIOR RAIL LINES 524.4 INTERMITTENT PROPOSED GRADING MATCHLINE-SEE SHEET 26 FOR CONTINUATION GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP Shetland Impacts Impact Site home PJD Impact Penn[ Area .pactArea C' Temporary a Impact(AD) INN 1 HT. WS Total Perennial Stream Impacts Impact Site Feature homPJD Type Permanent Impact� gth (LF) Temporary ImpactLang. (LF) S24.4 HDR S3 FII 412 Total 23412 40 htmmittent Stream Impacts Impact Site Feature ID horn PJD Impact Type Permanent Impact Length (LF) Temporary Impact Length (LF) S24.3 HDR S4 Fill 450 S24.4 HDR S3 Fill 422 5..5 HDR S5 FIII 21 0 Total .3 0 irtr KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' HUH engineering Me of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 01X-24 MATCHLINE— SEE SHEET 23 FOR CONTINUATION ( ) NON —JURISDICTIONAL ) POND (PB), 0.08 AC. HUH engineering Me of the Carolinas FEZ GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE 10/13/2021 SHEET 01X-25 MATCHLINE- SEE SHEET 24 FOR CONTINUATION 1 1 i — — —� Air %� \\ _\\\*\\\,l\\` N GENERAL NOTES: 1) SEE SHEET 1 FOR LEGEND AND KEY MAP 2) NO JURISDICTIONAL IMPACTS THIS SHEET Perennial Stream Impa is Impact Site Feature ID from PJD Impact Type Permanent Impact Length (LF) Temporary Impact Length (LF) S26.1 HDR S2 Fill 68 47 Total 68 47 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' HUH engineering Me of the Carolinas FEZ PROJECT GRMS SITE PLAN JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 01X-26 Legend „r n Expanded Interchange Study Area tg000 Pleasant Garden ?ON -Winston-Salem o Greensboro Durham p o ocky Mount P ! E N T GRaleigh NORTH tear: CAROLINA Charlotte Faau Miles 80 of ayeneville Greene, Croe W., salsa Jadsonvrlea auFr.O Forest Oaks Climax 41 oY °ek Oo` I yank vQ on9 e0�� �px Transportation Improvements . ul ul µ. I.P °ng CO" R uneny I 4 Cedamck Park 9litt CANE CREEK MOUNTAINS Sroty Camp 0a' cte VICINITY MAP FIGURE 1 aY' i�M�"J♦� Legend Transportation Improvements Feet 2.000 FIGURE 2 Legend nExpanded Interchange Study Area Feet 1,600 J AERIAL PHOTOGRAPHY MAP FIGURE 3 v ao Legend . n Expanded Interchange Study Area 1 1 o Feet a000 • c . • t,. • HI[I I, P.---Int r—� 0 Miles 15 / - 1. .160diel. ' ,:__-/---\1 V • - - GCrLFexj CO . )• USGS TOPOGRAPHIC MAP FIGURE 4 Legend QExpanded Interchange Study Area NRCS Soils Feet 1600 ApB -Appling sandy loam, 210 6 percent slopes ApC -Appling sandy loam, 6 to 10 percent slopes CbC - Call6on-Misenheimer complex, 6to 10 percent slopes CcC - Cecil sandy loam, 8 to 15 percent slopes CeB2- Cecil sandy clay loam, 2 to 8 percent slopes, moderately eroded ChA-Chewacla loam, 0 to 2 percent slopes, frequently flooded CmA- Chewacla and W ehadkee soils, 0 to 2 percent slopes, frequently flooded HeB - Helena sandy loam, 2 to 6 percent slopes HeC - Helena sandy loam, 6 to 10 percent slopes MaC - Mecklenburg loam, 8 to 15 percent slopes MCB2 - Mecklenburg clay loam, 2 to 8 percent slopes, moderately eroded PaC - Pacolet fine sandy loam, 8 to 15 percent slopes RnG - Rion loamy sand, 8 to 15 percent slopes VaB - Vance sandy loam, 2 to 8 percent slopes VaC - Vance sandy loam, 8 to 15 percent slopes W - Water WpC - W lkes-Poindexter-Wynott complex, 8 to 15 percent slopes VNB - Wyno8-Enon complex, 2 to 8 percent slopes VNC - Wyno8-Enon complex, 8 to 15 percent slopes W✓B2 - Wynott-Enoncomplex, 2 to 8 percent slopes, moderately eroded NRCS SOILS MAP FIGURE 7 Legend Virv, ,M gi n �,-11 Expanded Interchange Study Area ,» 1 +� 1%Annual Chance Flood Hazard r-� 0 Feet 1aoo k FEMA FLOODPLAIN MAP N __ - — LEGEND q f,_ L rr _ ) EXISTING WETLAND 102 I v %. '� r EXISTING POND 7�\ N �- , �. - � 0(\ 4 ii � -• i Y �� _- d �a. EXISTING PERENNIAL STREAM EXISTING INTERMITTENT I I oto irr [� Cry STREAM �� 6 PERMANENT WETLAND IMPACT XG kg /1J — TEMPORARY WETLAND IMPACT , Itl ; 4.4 PERMANENTPOND MP C V 6%,.) l� PERMANENT STREAM 4 a \ • A "@'� IMPACT TEMPORARY STREAM \ \o� \ \ KEY MAP IMPACT TRANSPORTATION COORIDOR BOUNDARY NOT TO SCALE F�2 F4i".",er7w"" PROJECT GRMS TRANSPORTATION FACILITIES JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 02X-01 Wetland Impacts Impact Number Sheet Number Wetland ID Lat. (decimal degrees( Long. (decimal degrees) Type of Impact Type of Wetland (Covcardin) Area of Permanent Impact (acres) Area of Temporary Impact (acres) 8912.1 2 WI 35.89383 -79.6541203 Fill PFO 0.018 0 WT4.1 4 WO 35.89289 -79.6543259 Fill PFO 0.0004 0 WT8.1 8 WH 35.87717 -79.6327779 Fill PFO 0.0004 0 WT8.2 8 HDRWC 35.87958 -79.6275104 Fill PEM 0.003 0 9(19.1 9 WSA 35.8751 -29.6281868 Fill PEM 0.035 0 9119.2 9 WS 35.87448 -79.6284527 Fill PFO 0.014 0 9119.3 9 WK 35.8741 -79.6292021 Fill PEM 0.168 0 9119.4 9 WN 35.87394 -79.6260749 Fill PFO 0.066 0 Total 0.305 0 Open Water Impacts Impact Number Sheet Number Open Water ID lat.(decimal degrees) Long. (decimal degrees) Type of Impact Waterbody Type Area of Impact (acres) P78.1 8 P18 35.877735 -79.6378387 Fill Pond 01101 PT8.2 8 P19 35.8780052 -79.6280614 Fill Pond 00066 PT9.1 9 PO 35.8740277 -79.6296036 Fill Pond 0.38 Total 0.90 Stream Impacts Impact Number Sheet Number Stream ID Tat. (decimal degrees( Long. (decimal degrees) Type of Impact Perennial (PER)or Intermittent (INF) Average Stream Width (feet) Permanent Impact Length (linear feet) Temporary Impact Length (linear feet) Impact Area (square feet) ST2.1 2 SE 35.894183 -716546671 Culvert PER 6 32 0 190 ST4.1 4 SE 35.892565 -716541181 Culvert PER 10 584 0 5,845 5T4.2 4 SE1 35.891597 -79.6543983 Culvert PER 5 170 0 850 5143 4 SW 35.890681 -716520941 Culvert INT 4 727 0 2,908 515.1 5 S1 35.891874 -716146361 Culvert PER 3 210 0 629 515.2 5 540 35.891585 -716460359 Culvert INT 3 395 0 L185 516.2 6 SE 35.886469 -79.6414069 Culvert PER 10 21 0 210 516.3 6 SE 35.886031 -79.6134009 Culvert PER 10 8 0 83 ST7.1 7 S17 35.883069 -73.6270705 Culvert PER 3 309 0 927 ST8.1 8 NOR S6 35.879249 -73.6278092 Culvert PER 3 469 0 L406 ST9.1 9 SX 35.875076 -716281908 Culvert PER 3 416 0 L247 ST9.2 9 SO 35.874564 -73.6288686 Culvert PER 5 391 0 L957 ST9.3 9 SS 35.874564 -73.6288686 Culvert INT 3 168 0 505 Perennial Sub -Total 2,609 13342.08 Intermittent Sub -Total 1,290 4998.00 Grand -Total 3,900 r 0 17,940 F�2 PROJECT GRMS TRANSPORTATION FACILITIES JURISDICTIONAL IMPACTS DATE 10/13/2021 SHEET 02X-01A \ \ N \ 44 ---..\ N. N \ 411k_ N N ST2.1 WT2.1 MATCHLINE - SEE SHEET 02X-04 FOR CONTINUATION ledinnalimpnels torn P.10 Cannoned hiped Area VC) Irrnad Nee Fill 0018 TOIRI torn P.10 la Lena. 1,1 larTned Length SE Cadet Total ONTINUATION KEY MAP NOT TO SCALE 0 200 400 SCALE: 1" = 200' F�2 PROJECT GRMS TRANSPORTATION FACILITIES JURISDICTIONAL IMPACTS DATE 10/13/2021 SHEET 02X-02 MATCHLINE - SEE SHEET 02X-02 FOR CONTINUATION \ \ V \ WT4.1 �a A \ \ \\ \ � \ v � vN�� y vv w��zo�, N. \ \ \ \ V \ \ \ \ \ \ ST4.2 \ \� \ \ \ ST4.1 Wet.] impede Endue 11,1. torn RIO Invect Fternanerd hinficl Area enneet Nee Fill Lfolel Paerniel amain Impact Falun In torn ND TYPe nerg �L (L�., SE nen Cieunt Lfolel 1312 Intern.. Stearn Mgr. Falun In torn ND TYPe Rerneneri Irreecl Len. LF syy z 0 z a O \ w N. N. U F L KEY MAP NOT TO SCALE 0 200 400 SCALE: 1" = 200' F�2 Lice. Number: In PROJECT GRMS TRANSPORTATION FACILITIES JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 02X-03 MATCHLINE - SEE SHEET 02X-05 FOR CONTINUATION N torn CD Cannoned Innad Area VC) Terrinnean Irripad Nee (AC) Fill 03 Total Perennial St nem 1 inn CU Crane Ane noon( Leon. 1,1 derma, n 575.1 Cann 2-10 Told 210 Intemehentareern newt Inroad nee torn CD laden( TYPn LM (LFn Told KEY MAP NOT TO SCALE 0 200 400 SCALE: 1" = 200' F�2 PROJECT GRMS TRANSPORTATION FACILITIES JURISDICTIONAL IMPACTS DATE 10/13/2021 SHEET 02X-04 MATCHLINE - SEE SHEET 02X-04 FOR CONTINUATION v V y v 0 v v \ N ST6.3 N Perenn Wear pa, STS SE SE KEY MAP NOT TO SCALE 0 200 400 SCALE: 1" = 200' F�2 PROJECT GRMS TRANSPORTATION FACILITIES JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 02X-05 MATCHLINE - SEE SHEET 02X-07 FOR CONTINUATION Perennial Steam Invect torn P.113 TYW Impact pernnert F11 517 309 Total 309 KEY MAP NOT TO SCALE 0 200 400 SCALE: 1" = 200' F�2 PROJECT GRMS TRANSPORTATION FACILITIES JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 02X-06 MATCHLINE - SEE SHEET 02X-06 FOR CONTINUATION ST8 PT8.1 MATCHLINE - SEE SHEET 02X-08 FOR CONTINUATION impecly Feildue Tom MD Impect Mmmemerd cm TeMPCMYY iAC) Fill WTI, 2 Total MondMmply Feildue Tom MD Impact Type Ame cm Fill Tolel 0.12 SIRE11711mock Feildue rem MD Impact Trim wa a nerrl mm 1,1 110,50 Told KEY MAP NOT TO SCALE 0 200 400 SCALE: 1" = 200' F�2 PROJECT GRMS TRANSPORTATION FACILITIES JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 02X-07 MATCHLINE - SEE SHEET 02X-07 FOR CONTINUATION PT9.1 WT9. ST9.1 WT9.4 L ST9.3 Impeols in* Torn P.10 Au cm Med Pee BAC) 2.1791 INSA Fill 0.64 WS Fill TOIRI Pond mpem Ste torn PM i TYPe Asa IA 1 TOIRI Impact SAB fern P.19 Ana Type lisped LeA2n tw Len. tw SX Al 391 ToDI 1197 Impact Site FeAlue IS lisped torn PM Type Perms. u 1� Len. SISS SS alust 1013 163 KEY MAP NOT TO SCALE 0 200 400 SCALE: 1" = 200' F�2 PROJECT GRMS TRANSPORTATION FACILITIES JURISDICTIONAL IMPACTS DATE SHEET 10/13/2021 02X-08 / Legend — City of Greensboro Wastewater Extension - City of Greensboro Water Extension h Feet 10,000 4 ^�q •az.r�� Pleasant Garden RANDO_p. _ _ nlacx50urg Fore Winston-Salem o Greensboro Durham o P I E N T °R sleigh Ur NORTH Neiza9 CAROLINA Charlotte Faeu Miles 80 0 ockY Mount oayelleyille Luu845tl rse Jadsonvllle 0 Greerm FEZ 9051f Forest Oa I¢ climax om .rm �Qr00 0 `I I c° Qro JWater Extension] Sao Uy Sandy Golf Club Cedeuck Park 9J6X CANE C{REEK MOUNTAINS Snow Camp VICINITY MAP PROPOSED WATER MAIN AND FORCE MAIN SEWER FIGURE 1 Legend City of Greensboro Wastewater Extension — City of Greensboro Water Extension _ Megasite Boundary Fey 2,500 o«vnaa«i SaponiItse Bmlut„on raw: AERIAL PHOTOGRAPHY MAP PROPOSED WATER MAIN AND FORCE MAIN SEWER FIGURE 2 �ITla1D-S� 'Ti \ -Y :1 ' LEGEND - City of Greensboro Wastewater Extension - City of Greensboro Water Extension Megasite Boundary f-� 0 Feet 2,000 6, FEZ ,b. _i -44 USGS QUANDRANGLES: CLIMAX, KIMESVILLE, GRAYS CHAPEL AND LIBERTY PROPOSED WATER MAIN AND FORCE MAIN SEWER FIGURE 3 LEGEND - City of Greensboro Wastewater Extension - City of Greensboro Water Extension 0.2%Annual Chance Flood Hazard 1% Annual Chance Flood Hazard Megasite Boundary Feet 2,500 .assie• Y I \ FEMA FLOODPLAIN MAP PROPOSED WATER MAIN AND FORCE MAIN SEWER FIGURE 6 F�2 iswo '"'eNCBELS License Number F-0116 go PROJECT NE- - ORLD JURISDICTIONAL IMPACTS DATE SHEET 05312018 03X-00 Wetland Impacts Impact Number Sheet Number Wetland ID Lat. (decimal degrees) Long. (decimal degrees) Type of Impact Type of Wetland (Cowardln) Area of Permanent Impact (acres) Area of Temporary Impact (acres) WS5.1 5 W-A-190-1 35.869143 -79.627752 CLEARING PFO 0.11 0.00 WS6.1 6 W-B-181-6 35.870524 -79.628747 CLEARING PEM 0.00 0.07 WS6.2 6 W-B-181-6 35.870986 -79.629054 CLEARING PEM 0.00 0.05 WS8.1 8 W-C-183-3 35.883935 -79.638183 CLEARING PSS 0.00 0.01 W59.1 9 W-D-182-2 35.902671 -79.649545 CLEARING PSS 0.00 0.07 WS9.2 9 W-E-182-3 35.902626 -79.646441 CLEARING PEM/PSS 0.00 0.08 WS9.3 9 W-B-183-1 35.902961 -79.639914 CLEARING PEM 0.00 0.01 WS10.1 10 W-B-183-2 35.903147 -79.636891 CLEARING PEM 0.00 0.01 WS10.2 10 W-D-183-2 35.90319 -79.635919 CLEARING PEM 0.00 0.01 WS11.1 11 W-D-182-4 35.902781 -79.622182 CLEARING PSS 0.00 0.01 WS12.1 12 W-A-182-5 35.901815 -79.618279 CLEARING PEM 0.00 0.01 WS12.2 12 W-A-182-2 35.900386 -79.612446 CLEARING PFO/PEM 0.01 0.00 WS13.1 13 W-C-182-2 35.905386 -79.654074 CLEARING PFO 0.01 0.00 WS14.1 14 W-E-182-2 35.917792 -79668686 CLEARING PFO 0.02 0.00 WS15.1 15 W-E-182-1 35.923044 -79.674129 CLEARING PFO 0.04 0.00 Total 0.19 0.33 F�2 aiswo Street,s ego PROJECT NE- - ORLD JURISDICTIONAL IMPACTS DATE 05_312018 SHEET 03X-01 Stream Impacts Impact Number Sheet Number Stream ID Lat. (decimal degrees) Long. (decimal degrees) Type of Impact Perennial (P) or Intermittent (I) Average Stream Width (feet) Permanent Impact Length (linear feet) Temporary Impact Length (linear feet) Impact Area (square feet) SS5.1 5 S-A-190-4 35.866464 -79.622251 STABILIZATION 1 6 20 20 240 SS5.2 5 S-A-190-4 35.866488 -79.622650 STABILIZATION 1 6 20 20 240 SS5.3 5 S-A-190-2 35.866531 -79.623971 STABILIZATION P 15 21 21 630 SS5.4 5 S-A-190-1 35.868492 -79.627243 STABILIZATION P 15 20 20 600 SS7.1 7 S-A-1S3-2 35.789130 -79.633727 STABILIZATION 1 4 32 21 212 SS7.2 7 S-A-1S3-3 35.882835 -79.636832 STABILIZATION P 4 21 25 184 SSS.1 8 S-C-1S3-1 35.883935 -79.638183 STABILIZATION 1 4 0 41 164 SSS.2 8 S-D-1S3-4 35.886291 -79.641971 STABILIZATION P 7 21 22 301 SS10.1 10 S-D-183-2 35.903195 -79.635911 STABILIZATION 1 3 13 0 39 SS13.1 13 S-B-182-4 35.907172 -79.656435 STABILIZATION 1 4 0 43 172 SS13.2 13 S-E-182-3 35.910407 -79.660758 STABILIZATION 1 4 25 20 180 SS14.1 14 S-E-182-1 35.919983 -79.670978 STABILIZATION P 6 0 38 228 Total 193 291 3,190 F�2 gig Street, ego PROJECT NE- - ORLD JURISDICTIONAL IMPACTS DATE 0513112018 SHEET 03X-02 20' PERM. EASMENT (MIN./ St.....TOP /f OF RANK STREAM it Yl-AP. �`Y vc° mow• �'.. NATURAL GROUND CROSSING Q S• RIP -RAP TYPICAL PIPE PLAN SYNTHETIC FILTER FABRIC TOP OF BANK RIP NAP SHALL NOT OAAINAGE DITCH EXTEND ABOVE NORMAL OR SMALL STREAM HIGH WA TEfl MARK ada. EX. INV. S CREEK o SYNTHETIC FILTER FABRIC (AS PER 3- NCOOT SPEC 81056. TYPE-21 4V CROSSING PIPE IV IB" CLASS I RIP -RAP SECTION A —A NOTES' 1) PERMANENT CROSSING FOR VEHICLE MAINTENANCE EQUIPMENT. 2) CLASS I PIP -RAP TO BE LAID MIN. IB INCHES THICK OVER ENTIRE AREA OF DISTURBANCE (AS DIRECTED BY ENGINEER). 3) CLASS II RIP -RAP USED IN LARGER STREAMS (A5 DIRECTED BY ENGINEER). 4) AS PROJECT IS STABILIZED PLACE SYNTHETIC FILTER FABRIC 6 SPREAD 6.O.L EXISTING EROSION STONE INTO PERMANENT LINER AS SHOWN. ADD STONE AS NEEDED. 5) ANY REQUIRED ARMORING ABOVE NORMAL HIGH WATER MARK SHALL CONSIST OF MATTING OR APPROVED VEGETATIVE COVER. CITY OF GREENSBORO STANDARD PERMANENT CREEK STABILIZATION STD. NO. REV. 0 WITH MAINTENANCE CROSSING 214 03 s7 oB-os' 03-05 I F�2 NCBELS License Number F-0,6 PROJECT NE- - ORLD JURISDICTIONAL IMPACTS DATE 05(31(2018 SHEET 03X-03 PUMP — �y Q d „ PROPOSER EARTH BERM TEMP. CONSTRUCTION (TYP.I STREAM CROSSING �10' MIN. CRIPSRAP G NOTES: 1) Cg0SION STONE TO BE "CLASS I" RIP -RAP UNLESS DESIGNATED DIFFERENTLY ON ONSTRUCTZON PLAN. Ll FLOW—>• � MAP DE SLOPE 2) PIPE SIZE AND AMOUNT NEEDED TO BE DETERMINED BY ENGINEER ON CONSTRUCTION �I Go GAG PLAN. 2N— -- 'A) EMRURNEMROSN OBEDNOEHLON2UONPNSET � �y ey 4) PUMP ANO LINE SIZE TO BE OE ZAslINEO BY THE CONTRACTOR USING. THE BASE FLOW �r%�{• =� �1q- 1 T ��',� • _ �, Ir SHDNN DN THE CONSTRUCTION PLANS. 57 WIDTH OF CONSTRUCTION EASEMENT SMALL BE MINIMIZER BASED UPON FIELD CONOZTZONS. ANY OISGATIONE(SI EXCEEDING 40' MAY REQUIRE ABOITIONAL WATEq QUALITY PERMITTING OR MITIGTION. Q° STREAM FLOWww"'"' •• tiT • ws } ° f°°. CONSTRUCTION SEQUENCE FOR STREAM CROSSING 1) INSTALL PUMP AND LINE TO PUMP FL. FROM AREA UPSTREAM OF TEMPORARY STREAM CRPSSIN6 TO AREA DOWNSTREAM OF CONSTRUCTION AREA. BEGIN PUMPING ANO TEMP. 24' TO 24. CMP CLA55 I" RIP RAP �^ CROSSING. PIPE 5' MIN I 2— E TP i!f+K$6}s } _ { y - E CONTINUING PUMPING WHILE WORKING WITHIN THE STREAM. 21 IWNSTALL UPSTREAM RAM, FIL TER FABRIC. ANO TEMPORARY CMP. COVER PIPE INL FT A FABRIC ANO SAND BAGS AS SHOWN IN INSET WHILE WORKING IN THE STREAM_ ALLOW STREAM FLOW THROUGH CMP. AS SHOWN IN INSET B' WHEN NOT WORKING WITHIN THE STREAM. PROP05E0 EARTH BERM 20' L 10' r MIN. P I o s cr eaV. 3/ INSTALL DOWNSTREAM TEMPORARY STONE DAM AND FILTER FABRIC TO PREVENT BACK FLOW INTO CONSTRUCTION AREA. (TYP.I FaL rc ON ZI TtFAax n PUU 50 CONSTRUCTION EASEMENT NEE NOTE 5) PROPOSER EARTH BEAM PLAN v.) 12 TOP OF FROM MIN. PUMP 4) INSTALL PROPOSED EARTH BERMS ALONG TOP. OF BANK ON EACH SIDE OF THE CONSTRUCTION AREA. 5) INSTALL OEWATERING BASIN OR SILT BAG AT TOP OF BANK. DEBATER CONSTRUCTION AREA BETWEEN TEMPORARY DAM USING THIS BASIN. 6) INST LL THE PO' X 10 SEDIMENT TRAP OR SILT BAC. T/ UPON CONSTRUCTION COMPLETION. REMOVE TEMPORARY DAMS, FILTER FABRIC, ANO ' BANK aM. i'w. aM1s sox TEMPORARY CMP DEPRESS TEMPORARY DAM BOTTOMS INTO STREAM BED UNTILPIP RAP , LEVEL KT. TOP OF FOR IN THE CONSTRUCTIONTPLANS BOTTOM. CONVERT TO 506 STANDARD f214 IF CALLED 5 N AeF { 2TEMP.TO A 42" CMP pJ =i1:.: EM. INV. � TEMPORARY CREEK STONE DAM POLYETHYLENE FABRIC \ \ ON FACE (B ME THICK) as -CROSSING lit PIPE 0) UPON STABILIZATION OF CLEARED AREAS. REMOVE TEMPORARY EARTH BERM SEDIMENT TRAP. ANO DENA TERING BASIN. R W B ...Watt:iv A INSTALL SANDBAGS ZN PIPE INVERT D FABRIC WHILE PUMPING -_� 4000N0 OUgINO CONSTRUCTION IN STREAM.. POL ETHYLENE`FABR CC le PC woo B REMOVE SANDBAGS B FABRIC TO ALLOW FLOW THROUGH PIPE WHEN NOT PUMPING AROUND. SECTION A -A OF a R z OF z 1 ITY OF GREENSBORO C I T Y OF GREENSBORO STANDARD TEMPORARY CREEK STD. NO. REV. STANDARD TEMPORARY CREEK STD. NO. REV. ,• CROSSING DURING CONSTRUCTION 213 0f-91 06-05 03-, 09-05 03-05 CROSSING DURING CONSTRUCTION 213 01-9105-05 03-, 02-05 03-05 F�2 NCBELS License Number F-0,6 PROJECT NE- I ORLD JURISDICTIONAL IMPACTS DATE 05)31)2018 SHEET 03X-04 r ( (� SS5.2 1i 0 of MATCHLINE - SEE SHEET 03X-06 FOR CONTINUATION I SS5.4 Sandy CCeek OLD 421 RD GS KEYMAP Weland Impacts I rrpact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Terporary Impact Area (AC) WS5.1 W-A-190-1 CLEARING 0.11 0.00 Total 0.11 0.00 Perennial Stream Impacts Irrpact Site Feature ID from PJD Impact Type Permanent Impact Length (LF) Temporary Impact Length (LF) 555.3 S-A-190-2 STABILIZATION 21 21 555.4 S-A-190-1 STABILIZATION 20 20 Total 41 41 Intermittent Stream Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Length (LF) Terporary Impact Length (LF) 555.1 S-A-190-4 STABILIZATION 20 20 555.2 S-A-190-4 STABILIZATION 20 20 Total 40 40 f SS5.3 ,1 (II/ VII Jy( pl ))11i1(III—A))1/ J )1111 /(I)I J y))//,yAVv/\��A\0A1 ( \y�v��i yAVAvA \AAVAV/�AAOlam( l`VA( \VAVA 11V11111j111�11 11 V (� itWWI \) IA1 111111 \V'VA 11 VAAt\ / 11A/A A, 1� VAA A �A V1A 11 1A\1 V1. 211 1 1 1 v(I�)i1v�ii)r i(y 7/,// i� \I,I \ 1 / j1,i111 -i///_1/ 1 11(1 7/ 1 A'i1 v 11 �1 2" PUMP 1 I ) ( A �' STATION SS5.1 I 1 A 1 SITE LEGEND `V te( rlt � V l'tt- EXISTING WETLAND EXISTING POND EXISTING PERENNIAL STREAM EXISTING INTERMITTENT STREAM PERMANENT WETLAND IMPACT TEMPORARY WETLAND IMPACT PERMANENT STREAM IMPACT (COG STD. 214 - SEE 03X-03) TEMPORARY STREAM IMPACT (COG STD. 213 - SEE 03X-04) PROPOSED SEWER MAIN PROPOSED WATER MAIN !Iwr/i' STARMOl3NT YtD SR2407 ' l V 1 / It,(1 \ 11 t 1 I// (/ —��) f I� vJ I\ / I V ((I /(/ 1 / 1 A V A.— I ) (I ) 0 I 200' 400' SCALE: 1"= 200' F�2 PROJECT NE- - ORLD JURISDICTIONAL IMPACTS DATE 053112010 SHEET 03X-05 Wetland Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WS6.1 W-B-181-6 CLEARING 0.00 0.07 WS6.2 W-B-181-6 CLEARING 0.00 0.05 Total 0.00 0.12 0200' 400' 2� SCALE: 1"= 200' LEGEND EXISTING WETLAND EXISTING POND EXISTING PERENNIAL STREAM EXISTING INTERMITTENT STREAM PERMANENT WETLAND IMPACT TEMPORARY WETLAND IMPACT PERMANENT STREAM IMPACT (COG STD. 214 - SEE 03X-03) TEMPORARY STREAM IMPACT (COG STD. 213 - SEE 03X-04) PROPOSED SEWER MAIN PROPOSED WATER MAIN 0 2 z F�2 a swo�,s ego NCBELS License Number F-0,6 PROJECT NE- - ORLD JURISDICTIONAL IMPACTS DATE 0513112018 SHEET 03X-06 z SS7.2 REF Perennial Stream Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Length (LF) Temporary Impact Length (LF) SS7.2 S-A-183-3 STABILIZATION 21 25 Total 21 25 Intermittent Stream Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Length (LF) Temporary Impact Length (LF) SS7.1 S-A-183-2 STABILIZATION 32 21 Total 32 21 -24 200' 400' SCALE: 1"= 200' LEGEND EXISTING WETLAND EXISTING POND EXISTING PERENNIAL STREAM EXISTING INTERMITTENT STREAM PERMANENT WETLAND IMPACT TEMPORARY WETLAND IMPACT PERMANENT STREAM IMPACT (COG STD. 214 - SEE 03X-03) TEMPORARY STREAM IMPACT (COG STD. 213 - SEE 03X-04) PROPOSED SEWER MAIN PROPOSED WATER MAIN SS7.1 / r 1 111� ( \1, I I`, �\\\\\\ _ \ E \11A 2 F�2 a swo 1 ego NCB L License Number F-0116 PROJECT NE- - ORLD JURISDICTIONAL IMPACTS DATE 05 312018 SHEET 03X-07 Wetland Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WS8.1 W-C-183-3 CLEARING 0.00 0.01 Total 0.00 0.01 Perennial Stream Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Length (LF) Temporary Impact Length (LF) SS8.2 S-D-183-4 STABILIZATION 21 22 Total 21 22 Intermittent Stream Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Length (LF) Temporary Impact Length (LF) SS8.1 S-C-183-1 STABILIZATION 0 41 Total 0 41 rmAUK�� �� __ SS82 / / %i-i/ J \1V1AV \)�:, IS 1� / ( _ _ �� S HWY 4-21 — __ / -) 0 200' 400' SCALE: 1"= 200' LEGEND Waif SS8.1 EXISTING WETLAND EXISTING POND EXISTING PERENNIAL STREAM EXISTING INTERMITTENT STREAM PERMANENT WETLAND IMPACT TEMPORARY WETLAND IMPACT PERMANENT STREAM IMPACT (COG STD. 214 - SEE 03X-03) TEMPORARY STREAM IMPACT (COG STD. 213 - SEE 03X-04) PROPOSED SEWER MAIN PROPOSED WATER MAIN E VAAIA� �/1�0 WS81 `� -1 X — — I 0 0 0 Z 1 2 Ic I Im F�2 a�swo '"te-°o NCBELS License Number F-0116 PROJECT NE- - ORLD JURISDICTIONAL IMPACTS DATE 0513112018 SHEET 03X-08 \ Impacts on this sheet are within the Haw River Subasin (Cape Fear 02) Wetland Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WS9.1 W-D-182-2 CLEARING 0.00 0.07 WS9.2 W-E-182-3 CLEARING 0.00 0.08 WS9.3 W-B-183-1 CLEARING 0.00 0.01 Total 0.00 0.16 ) ai F�2 a�swo '"te-°o NCBELS License Number F-0116 LEGEND Waif PROJECT NE- - ORLD JURISDICTIONAL IMPACTS EXISTING WETLAND EXISTING POND EXISTING PERENNIAL STREAM EXISTING INTERMITTENT STREAM PERMANENT WETLAND IMPACT TEMPORARY WETLAND IMPACT PERMANENT STREAM IMPACT (COG STD. 214 - SEE 03X-03) TEMPORARY STREAM IMPACT (COG STD. 213 - SEE 03X-04) PROPOSED SEWER MAIN PROPOSED WATER MAIN Z / glfl i��, WS9.33 a_ / 'af DATE 053112018 SHEET 03X-0 ❑ I1 m 0 O 2 C Impacts on this sheet are within the Haw River Subasin (Cape Fear 02) Wetland Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WS10.1 W-B-183-2 CLEARING 0.00 0.01 WS10.2 W-D-183-2 CLEARING 0.00 0.01 Total 0.00 0.02 Intermittent Stream Imp cts Impact Site Feature ID from PJD Impact Type Permanent Impact Length (LF) Temporary Impact Length (LF) SS10.1 S-D-183-2 STABILIZATION 13 0 Total 13 0 LEGEND EXISTING WETLAND EXISTING POND EXISTING PERENNIAL STREAM EXISTING INTERMITTENT STREAM PERMANENT WETLAND IMPACT TEMPORARY WETLAND IMPACT PERMANENT STREAM IMPACT (COG STD. 214 - SEE 03X-03) TEMPORARY STREAM IMPACT (COG STD. 213 - SEE 03X-04) PROPOSED SEWER MAIN i PROPOSED WATER MAIN I0I I I Z wsio.1) 1 �i%'ssio.1�,�64 .!��� 1127 (SR 1006) wS10.2 S 1 ! 1� _I � man = t s ,_ = %��_--� `1� 1 (/ __ �, __f ems.' y®--""`° �X g N �Q IA 3 f. O 0 cr m 1Z C )4 1z co 0 200' 400' SCALE: 1"= 200' z 1 F�2 a:swo sass ego NCBELS License Number F-0,6 PROJECT NE- - ORLD JURISDICTIONAL IMPACTS DATE 053112018 SHEET 03X-10 Impacts on this sheet are within the Haw River Subasin (Cape Fear 02) Wetland Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WS11.1 W-D-182-4 CLEARING 0.00 0.01 Total 0.00 0.01 X-10 FOR CONTINUAT w _ /-: \\V \//r- �V \\ N \\Jiffff J `a 0 200' 400' SCALE- 1"= 200' LEGEND EXISTING WETLAND EXISTING POND ................. EXISTING PERENNIAL STREAM 1/ /r-? 2(r EXISTING INTERMITTENT STREAM PERMANENT WETLAND IMPACT TEMPORARY WETLAND IMPACT PERMANENT STREAM IMPACT (COG STD. 214 - SEE 03X-03) TEMPORARY STREAM IMPACT (COG STD. 213 - SEE 03X-04) PROPOSED SEWER MAIN PROPOSED WATER MAIN HS 33S - 3NI11 (SR 7006)/ .-a _.".,-.,,,ti o 0 ///iy///z 0 F�2 a�swo s'"'ego NCBELS License Number F-0116 PROJECT NE- - ORLD JURISDICTIONAL IMPACTS DATE 0513112018 SHEET 03X-11 11 FOR CONTINUATION Impacts on this sheet are within the Haw River Subasin (Cape Fear 02) Wetland Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WS12.1 W-A-182-5 CLEARING 0.00 0.01 WS12.2 W-A-182-2 CLEARING 0.01 0.00 Total 0.01 0.01 LEGEND WO I P 2 _ue > z //y ��� _ NW'- / ��� �I VA,�1oos)' _.. , i)/ �).Ca D4IAlr�Ra. i 2 EXISTING WETLAND EXISTING POND EXISTING PERENNIAL STREAM EXISTING INTERMITTENT STREAM PERMANENT WETLAND IMPACT TEMPORARY WETLAND IMPACT PERMANENT STREAM IMPACT (COG STD. 214 - SEE 03X-03) TEMPORARY STREAM IMPACT (COG STD. 213 - SEE 03X-04) PROPOSED SEWER MAIN PROPOSED WATER MAIN 0 200' 400' SCALE: 1"= 200' F�2 a swo 1 ego NCB L License Number F-0116 PROJECT NE\ \ ORLD JURISDICTIONAL IMPACTS DATE 05312018 SHEET 03X-12 SS13.2 0 Impacts on this sheet are within the Haw River Subasin (Cape Fear 02) Wetland Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WS13.1 W-C-182-2 CLEARING 0.01 0.00 Total 0 01 0.00 I nternittenl Stream I mpacts Impact Site Feature ID from PJD Impact Type Permanent Impact Length (LF) Temporary Incpat Lenglh (LF) SS13.1 S-B-182-4 STABILIZATION 0 43 0013.2 S-E-182-3 STABILIZATION 25 20 Total 25 63 200' 400' SCALE: 1"= 200' F�2 a swo airs ego NCB L License Number F-0116 LEGEND !!/ ( ``'/,//r ' PROJECT NE- - ORLD JURISDICTIONAL IMPACTS EXISTING WETLAND EXISTING POND EXISTING PERENNIAL STREAM EXISTING INTERMITTENT STREAM PERMANENT WETLAND IMPACT TEMPORARY WETLAND IMPACT PERMANENT STREAM IMPACT (COG STD. 214 - SEE 03X-03) TEMPORARY STREAM IMPACT (COG STD. 213 - SEE 03X-04) PROPOSED SEWER MAIN PROPOSED WATER MAIN likr:14 imp., LAIR mp7s4.( WS13.1 _b TrAw / /// s- .A emu( DATE 05 312018 SHEET 03X-13 Impacts on this sheet are within the Haw River Subasin (Cape Fear 02) Welland Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WS14.1 W-E-182-2 CLEARING 0.02 0.00 Total 0.02 0.00 Pe nial ea cts Impact Site Feature ID from PJD Impact Type Permanent Impact Lengt (LF) Temporary Impact Length (LF) 0014.1 S-E-182-1 STABILIZATION 0 36 Total 0 38 LEGEND EXISTING WETLAND EXISTING POND EXISTING PERENNIAL STREAM EXISTING INTERMITTENT STREAM PERMANENT WETLAND IMPACT TEMPORARY WETLAND IMPACT PERMANENT STREAM IMPACT (COG STD. 214 - SEE 03X-03) TEMPORARY STREAM IMPACT (COG STD. 213 - SEE 03X-04) PROPOSED SEWER MAIN PROPOSED WATER MAIN qli//(l t' V �/� \flRlA 11 / i.,� Ill rlll� I i ii iV�A PC ,/ �\,SS141 1'/ / J\j III 4 Illz /i. A��1\\J� )/�$1 I�r/1 i — r r t I - �� ys T f / fi ? ° A lily l..1Tz, \ �.: ////�� I ip I 200' 400' SCALE: 1"= 200' F�2 555 Fa ahiswo 1 ego NCB L License Number F-0116 PROJECT NE- - ORLD JURISDICTIONAL IMPACTS DATE 05_312018 SHEET 03X-14 Impacts on this sheet are within the Haw River Subasin (Cape Fear 02) Welland Impacts I rrpact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WS15.1 W-E-182-1 CLEARING 0.04 0.00 Total 0.04 0.00 — •` x�o (SyRQ' EXISTING WETLAND EXISTING POND EXISTING PERENNIAL STREAM EXISTING INTERMITTENT STREAM PERMANENT WETLAND IMPACT TEMPORARY WETLAND IMPACT PERMANENT STREAM IMPACT (COG STD. 214 - SEE 03X-03) TEMPORARY STREAM IMPACT (COG STD. 213 - SEE 03X-04) PROPOSED SEWER MAIN PROPOSED WATER MAIN LEGEND Ilir 0 200' 400' 2 SCALE: 1"= 200' z 2 F�2 Street sme-00 772 swoNCB L License Number F-0116 PROJECT NE- - ORLD JURISDICTIONAL IMPACTS DATE 05_312018 SHEET 03X-15 kLegend 1-7StudyArea 5r 0 Feet 10,000 Jamestown iandover Resort .GollG tub Plea sinl Garden >Mal RAND() oBristol }, Forest N' Oea Farah sheville AMarem Blacksburg FZe Winston-Salem o P Gr_ensboro Durham N T Raleigh .Rocky Mount NORTH Green, Na CAROL INA Charlotte Fa.M Gra Mlles 80 A Lumbee Sdtse Jacksonville 0 Lr rone Camp Joy J51f Forest Oalvs Climax t;m Sandy Creek Golf Club 0c Liberly 91411 CANE CREEK Sn Ste VICINITY MAP DUKE ENERGY 100KV TRANSMISSION LINE STUDY AREA FIGURE t Legend n Study Area 0 Feet 3,000 A AERIAL MAP DUKE ENERGY 100KV TRANSMISSION LINE STUDY AREA FIGURE 2 Legend n Study Area 0 Feet 3,000 Miles 25 USGS TOPOGRAPHIC MAP DUKE ENERGY 100KV TRANSMISSION UNE STUDY AREA FIGURE 3 F�2 PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 05252018 SHEET 04X-01 LEGEND EXISTING WETLAND EXISTING POND • - EXISTING PERENNIAL STREAM EXISTING INTERMITTENT STREAM 555555555555555555555555 PERMANENT WETLAND IMPACT TEMPORARY WETLAND IMPACT PERMANENT POND IMPACT PERMANENT STREAM IMPACT TEMPORARY STREAM IMPACT Wetland Impacts Impact Nunber Sheet Nunber Wetland ID Lat. (decimal degrees) Lang. (decimal degrees) Type of Enpact Type of Wetland (Cowardin) Area of Permanent Impact (acres) Area of Temporary Impact (acres) WP6.1 6 WA 35.9088 -79.7334 Clearing PEM1E 0.00 0.04 WP9.1 9 WB 35.9005 -79.7184 Clearing PEM1EIPSSIE 0.00 0.02 WP10.1 10 WG 35.8974 -79.7048 Clearng PEM1E 0.00 0.02 WP11.1 11 WF ( 35.8972 -79.7035 Clearing PEM1E 0.00 0.01 WP11.2 11 WC 35.8971 -79.7003 Clearing PSS 0.00 0 01 WP12.1 12 WH 35.8967 -79.6916 Clearing PEM1EIPSSIB 0.00 0.01 WP13.1 13 WI ( 35.8957 -79.6835 Clearing PEM1E 0.00 0.01 WP22.1 22 W39 35.9023 -79.6405 Clearing PFO 0.08 0 00 Total 0.08 0.12 F�2 PROJECT GRMS DUDE ENERGI CORRIDORS JURISDICTIONAL IMPACTS DATE 05252018 SHEET 04X-02 EXISTING DUKE ENERGY CORRIDOR OHE J SEE NOTE 2 x 0 m SEE NOTE 2 OHE E J OHE PROPOSED DUKE ENERGY 100kV !.\ CORRIDOR 1 • LT] GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL RESOURCES ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILILED FOR CROSSINGS IF NECESSARY. KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 05252018 SHEET 04X-03 L SEE NOTE 2 oy\` 0 O w Iw z UHF \ x J` PROPOSED DUKE ENERGY 100kV / CORRIDOR ' GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL RESOURCES ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILI_ED FOR CROSSINGS IF NECESSARY. KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-04 f, I \ z J F � O U O v I L SEE NOTE 2 wl w x 1 U 2 OHE OHE - --� OHE OHE PROPOSED DUKE - --_____ __- / r .� ENERGY 100kV �/ r I w CORRIDOR / / I w w r z 1 / / I / / / / I / / GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL RESOURCES ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILI_ED FOR CROSSINGS IF NECESSARY. KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERG- CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-05 OHE PROPOSED DUKE ENERGY 100kV CORRIDOR SEE NOTE 2 MATCHLINE - SEE SHEET 7 FOR CONTINUATION GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL STREAMS ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILILED FOR CROSSINGS IF NECESSARY. 3. WETLANDS IN THE PROPOSED DUKE ENERGY CORRIDOR WILL BE HAND CLEARED. Wetland Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WP6.1 WA CLEARING 0.00 004 Total 0.00 0.04 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ a�swo ��rs��e�o PROJECT GRMS DUDE ENERG- CORRIDORS JURISDICTIONAL IMPACTS DATE 0525L2018 SHEET 04X-06 MATCHLINE - SEE SHEET 6 FOR CONTINUATION FEZ PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS NO IMPACTS TO JURISDICTIONAL RESOURCES ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILI_ED FOR CROSSINGS IF NECESSARY. DATE 05252018 SHEET 04X-07 PROPOSED DUKE ENERGY 100kV CORRIDOR z ,U 0 off\ Iw kw \` '` Z NF 2 _ \� \S OHF\I2 GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL RESOURCES ON THIS SHEET. KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-08 I❑ OI Iz Izt z i =I O SEE NOTE 2 ' U L.L3I U 2 WPr1 SEE NOTE 3 Z 0 Im 01 v' 1 z O z Z 0 PROPOSED DUKE ----Im ENERGY 100kV 2 CORRIDOR F. w SEE NOTE 2 It ` HF\ \ toL.ON..\ww\`` IO F 2 GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL STREAMS ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILILED FOR CROSSINGS IF NECESSARY. 3. WETLANDS IN THE PROPOSED DUKE ENERGY CORRIDOR WILL BE HAND CLEARED. Wetland Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WP9.1 WB CLEARING 0.00 0.02 Total 0.00 0.02 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERG- CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-0_ LLI PROPOSED DUKE ENERGY 100kV CORRIDOR WP10.1 SEE NOTE 3 GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL STREAMS ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILILED FOR CROSSINGS IF NECESSARY. 3. WETLANDS IN THE PROPOSED DUKE ENERGY CORRIDOR WILL BE HAND CLEARED. Wetland Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WP10.1 WG CLEARING 0.00 0.02 Total 0.00 0.02 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ a�swo sa�,s��e�o PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-10 I0 z O O O [-El.--OHE w WP11.1 /,/ bj SEE NOTE 3 J z x ¢I 21 PROPOSED DUKE ENERGY 100kV CORRIDOR SEE NOT7SEE NOTE 2 WP11.2 SEE NOTE 3 OHE OHE - 1!! MATCHLINE - SEE SHEET 12 GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL STREAMS ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILILED FOR CROSSINGS IF NECESSARY. 3. WETLANDS IN THE PROPOSED DUKE ENERGY CORRIDOR WILL BE HAND CLEARED. Welland Impacts Irrpact Site Feature ID from PJD Irrpact Type Permanent Impact Area (AC) Temporary I rpacl Area (AC) WP11.1 WF CLEARING 0.00 0.01 WP11.2 WC CLEARING 0.00 001 Total 0.00 0.02 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-11 OHE I zI 2 —__ OHE PROPOSED DUKE ENERGY 100kV CORRIDOR OHE WP12.1 SEE NOTE 3 OHE --4 SEE NOTE 2 SEE NOTE 2 GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL STREAMS ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILILED FOR CROSSINGS IF NECESSARY. 3. WETLANDS IN THE PROPOSED DUKE ENERGY CORRIDOR WILL BE HAND CLEARED Wetland Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WP12.1 WH CLEARING 0.00 0.01 Total 0.00 0.01 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERG- CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-12 SEE NOTE 2 / OHE PROPOSED DUKE ENERGY 100kV CORRIDOR _ GREESON COUNTRY RD z 0 z z 0 In 0 Iw SEE NOTE 2 x Iw I0) _OHE z WP13.1 SEE NOTE 3 r GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL STREAMS ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILILED FOR CROSSINGS IF NECESSARY. PONDS WILL BE SPANNED. 3. WETLANDS IN THE PROPOSED DUKE ENERGY CORRIDOR WILL BE HAND CLEARED. Wetland Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WP13.1 WI CLEARING 0.00 0.01 Total 0.00 001 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-13 MATCHLINE - SEE SHEET 13 FOR CONTINUATION OHE OHE PROPOSED DUKE ENERGY 100kV CORRIDOR OHE II _ SEE NOTE 2 1 \ OHE �� I z O z 0 In to GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL RESOURCES ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILILED FOR CROSSINGS IF NECESSARY. KEY MAP . NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERG- CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-14 SEE NOTE 2 ‘, SEE NOTE 2 OHE OHE PROPOSED DUKE ENERGY 100kV CORRIDOR SEE NOTE 2 0 OHE QHE OHE OHE EXISTING DUKE ENERGY 500kV CORRIDOR GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL RESOURCES ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILILED FOR CROSSINGS IF NECESSARY. KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERG- CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-15 HE PROPOSED DUKE ENERGY 100kV CORRIDOR OHE - - OHE OHE OHE OHE OHE OHE EXISTING DUKE ENERGY 500kV CORRIDOR OHE 0 to In �o OH iw Q 2 GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL RESOURCES ON THIS SHEET. KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-16 1- OHE OHE OHE \, OHE N-O PROPOSED DUKE ENERGY 100kV CORRIDOR EXISTING DUKE ENERGY 500kV CORRIDOR • \OHE OH w I� 2 GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. NO IMPACTS TO JURISDICTIONAL RESOURCES ON THIS SHEET. KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-17 ri MEGASITE PROPERTY BOUNDARY OHE H PROPOSED DUKE ENERGY 100kV CORRIDOR MATCH LINE - SEE SHEET 20 FOR CONTINUATION o ♦ • PROPOSED DUKE ENERGY 500kV CORRIDOR EXISTING DUKE ENERGY 500kV CORRIDOR MATCHLINE GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL RESOURCES ON THIS SHEET. KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-18 SITE GRADING BOUNDARY SITE PAD BOUNDARY Z O I a 1 Z O I' 0 I N Z PROPOSED DUKE ENERGY 100kV CORRIDOR EXISTING DUKE ENERGY 500kV CORRIDOR MEGASITE PROPERTY BOUNDARY I GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL STREAMS ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILILED FOR CROSSINGS IF NECESSARY. plilll�l 1 ir��i` i�/<■ qe. 1' m-/� a , fI-■Ill�f� -01 - •,.." 1 111:1-1� � •� • rill `w/1rR �. ��I 1 �gwrletr � J til i!ri�' & p', L yk.4saft�� i!i+�\ III:wig:ill KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERG- CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-1- CALHOUN DR SHOOTING STAR DR i MATCHLINE - SEE SHEET 21 FOR CONTINUATION 0 z WOODVERY DR MEGASITE PROPERTY BOUNDARY WOODVERY DR I � I Q PROPOSED DUKE ENERGY 500kV CORRIDOR w 0 SEE NOTE 2 w 0 S i I d I l I I n 1 1 �_ - MATCHLINE - SEE SHEET 18 FOR CONTINUATION NN GENERAL NOTES: SEE SHEET 04X-02 FOR LEGEND. NO IMPACTS TO JURISDICTIONAL RESOURCES ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILILED FOR CROSSINGS IF NECESSARY. smoi r!rrt :61 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 05252018 SHEET 04X-20 MEGASITE PROPERTY BOUNDARY 0 II I CALHOUN DR IJ o OL 421_" D_ N NORFOLK SOUTHERN RAILROAD x w w z MATCHLINE - SEE SHEET 20 FOR CONTINUATION OHE OHE SITE GRADING BOUNDARY (RAIL SPUR INTO PAD) - PROPOSED DUKE ENERGY 500kV CORRIDOR GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL RESOURCES ON THIS SHEET. KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-21 � L.J MEGASITE PROPERTY BOUNDARY O OHE i�..�` — r OHE PROPOSED DUKE ENERGY 500kV CORRIDOR WP22.1 SEE NOTE 3 SITE PAD BOUNDARY NORFOLK SOUTHERN RAILROAD OLL _ x rn SEE NOTE 2 OHE OHE w rn L. IZ _-__-U SITE GRADING BOUNDARY 2 -_ E S SITE1•1-�C SHEETS FOR CONTINUATION _- NTINUATION -�--� -�- GENERAL NOTES: SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL STREAMS ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILILED FOR CROSSINGS IF NECESSARY. PONDS WILL BE SPANNED. 3. WETLANDS IN THE PROPOSED DUKE ENERGY CORRIDOR WILL BE HAND CLEARED. Weiland Impacts Impact Site Feature ID from PJD Impact Type Permanent Impact Area (AC) Temporary Impact Area (AC) WP22.1 W39 CLEARING 0.08 0.00 Total 0.08 0.00 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' F�2 PROJECT GRMS DUDE ENERGI CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-22 FOR CONTINUATIO OHE MEGASITE PROPERTY BOUNDARY -1-0LD421 RD SEE NOTE 3 OHE SITE GRADING BOUNDARY SITE PAD BOUNDARY ❑ SEE SITE PLAN IMPam(1,,cm ion En ion ACT SHEETS FOR CON AT N- NORFOLK SOUTHERN RAILROAD PROPOSED DUKE ENERGY 500kV CORRIDOR Z ff O 0 0 O SEE SITE MPACTS SHEETS FOR IMPACTS TO THIS POND Z/ ❑_ Iw sw z x U GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL STREAMS ON THIS SHEET. 3. POND IS NON -JURISDICTIONAL. KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-23 \ SEE NOTE 2 \ z o, zI z 0 oh— w i ) En ow zl x UI2 -,L 0HV PROPOSED DUKE ENERGY 500kV CORRIDOR OHE SITE GRADING BOUNDARY ma ma OHE SITE PAD BOUNDARY ma on on Ina an nini inn inn inn nn nn nn SEE SITE PLAN IMPACT SHEETS FOR CONTINUATION l AfpRFpz <kSp�Thz•zi,„/. C�pq� OHE OHE ma aa-ini nor imi i 0 3 z 0 0 GENERAL NOTES: SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL STREAMS ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILILED FOR CROSSINGS IF NECESSARY. �It�li`��•�A n1l41'1�� 1 i v + ill /�� L ■ �' ! 11 r �m:�t �rt� *III 7 a` mEr.: �Giy! ..,+ t Ihr _,� �■_ KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERG- CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-24 •L- �I DHE w w MEGASITE PROPERTY BOUNDARY NORFOLK SOUTHERN RAILROAD ONE PROPOSED DUKE ENERGY 500kV CORRIDOR z1 • -_ \ I SITE GRADING BOUNDARY U la on r1 SITE PAD BOUNDARY r1 E N IMPACTSHEETS FORNTINUA L r1 SEE SITE IMPACT SHEETS FOR IMPACT TO THIS WETLAND GNE r I O ONE Z GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL STREAMS ON THIS SHEET. n1l41'1�� 1 i ti ■ `• J gFreti� til ri�� r�'` ;mpg 4�I NEr..4aarrti iotr\v��1� KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ a:swo �,s ego PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-25 TINUATION z x F 2 4°42�RD>A MEGASITE PROPERTY BOUNDARY PROPOSED DUKE ENERGY 500kV CORRIDOR SITE GRADING BOUNDARY Io a SITE PAD BOUNDARY o° MATCHLINE - SEE SHEET 27 FOR CONTINUATION GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. NO IMPACTS TO JURISDICTIONAL STREAMS ON THIS SHEET. IIMIC n1l41'1.1 ' i t i�� i�1<A I�i�al Err - illy r _: �� Iln! j LIl 3i ��w7��F� J �rCiiII -_.1 KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERG- CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-26 SEE SITE PLAN IMPACT SHEETS FOR CONTINUATION MATCHLINE - SEE SHEET 26 FOR CONTINUATION SITE PAD BOUNDARY PROPOSED DUKE ENERGY 500kV CORRIDOR SITE GRADING BOUNDARY MEGASITE PROPERTY BOUNDARY 1 1 1 io 1m I 1 1 1 1 0 ❑1. MATCH LINE - SEE SHEET 28 FOR CONTINUATION iliq KFMGNiq <GGp 80UT RO HFRN RgirRoq� GENERAL NOTES: 1. SEE SHEET 04X-02 FOR LEGEND. 2. NO IMPACTS TO JURISDICTIONAL RESOURCES ON THIS SHEET. NVird KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERGD CORRIDORS JURISDICTIONAL IMPACTS DATE 05252018 SHEET 04X-27 z SITE PAD BOUNDARY I z o� w wI U z 1 11 • 1 1 r• MATCHLINE - SEE SHEET 27 FOR CONTINUATION I O QO EXISTING DUKE ENERGY 500kV CORRIDOR MEGASITE PROPERTY BOUNDARY SITE GRADING BOUNDARY /. 1 Jr SEE NOTE 2 F OHE GENERAL NOTES: SEE SHEET 04X-02 FOR LEGEND. NO IMPACTS TO JURISDICTIONAL RESOURCES ON THIS SHEET. STREAM CROSSINGS WILL BE HAND CLEARED AND SPAN BRIDGES WILL BE UTILILED FOR CROSSINGS IF NECESSARY. KEY MAP NOT TO SCALE 0 200' 400' SCALE: 1"= 200' FEZ PROJECT GRMS DUDE ENERG- CORRIDORS JURISDICTIONAL IMPACTS DATE 052512018 SHEET 04X-28