Permit Class Permit Number
EXPRESS 4-22
STATE OF NORTH CAROLINA
Department of Environmental Quality
and
Coastal Resources Commission
for
X Major Development in an Area of Environmental Concern
pursuant to NCGS I I3A-118
X Excavation and/or filling pursuant to NCGS 113-229
Issued to Showboat Investments LLC 8930 NC HWY 39 South, Zebulon, NC 27597
Authorizing development in Carteret County at adito a man-made canal leading to Bogue
Sound at 702-Atlantic Beach Causeway, in Atlantic Beach, as requested in the permittee's application dated _
12/2/21 including attached workplan drawings (8) Cover and Sheets 1-7 all dated 12/2/21.
This permit, issued on January 26, 2022 , is subject to compliance with the application (where
consistent with the permit), all applicable regulations, special conditions and notes set forth below. Any violation
of these terms may be subject to lines, imprisonment or crvu auttuu; or n,ay uauao .===_ -
Upland Development within Urban Waterfront
1) Unless specifically altered herein, this permit authorizes the grading and other land disturbing
activities associated with the development of the above referenced property, including the 8
condominium buildings, driveway, sidewalk and boardwalk along the bulkhead, and other associated
infrastructure, all as expressly and specifically set forth in the attached permit application and
workplan drawings.
Shoreline Stabilization - Bulkhead
2) The bulkhead shall be constructed in accordance with the alignment depicted on the attached
workplan drawings.
(See attached sheets for Additional Conditions)
This permit action may be appealed by the permittee or other
qualified persons within twenty (20) days of the issuing date.
This permit must be accessible on -site to Department
personnel when the project is inspected for compliance.
Any maintenance work or project modification not covered
hereunder requires further Division approval.
All work must cease when the permit expires on
December 31, 2025
In issuing this permit, the State of North Carolina agrees that
your project is consistent with the North Carolina Coastal
Management Program.
Signed by the authority oI the 5ecrerary or "nY auu we �LIWI
of the Coastal Resources Commission.
41/4�
Braxton C. Davis, Director
Division of Coastal Management
This permit and its conditions are hereby accepted.
Signature of Permittee
Showboat Investments LLC. Permit No. 4-22
Page 2 of 3
ADDITIONAL CONDITIONS
3) No open water shall be excavated or filled, even temporarily, outside of the approved bulkhead
alignment.
4) The alignment of the authorized bulkhead shall be staked by the permittee and verified by a
representative of the Division of Coastal Management within a maximum of 30 days prior to the start of
construction.
5) The bulkhead shall be solid and constructed of treated wood, concrete slabs, metal or vinyl sheet piles,
or other suitable materials approved by Division personnel.
6) The bulkhead shall be constructed prior to any backfilling activities.
7) The bulkhead shall be structurally tight so as to prevent seepage of backfill materials through the
structure.
8) This permit does not authorize any excavation waterward of the approved alignment.
9) The fill material shall be clean and free of any pollutants except in trace quantities.
10) Unless altered herein, all backfill material shall be obtained from a high ground source and confined
behind the permitted bulkhead.
11) No backfill material is to be placed within 30 feet of the normal high-water level, except that which will
be used to backfill the area behind the permitted bulkhead.
12) All fill material to be placed below normal high-water level shall be confined behind the permitted
bulkhead.
13) This permit does not authorize any formalized boat slips.
Stormwater Management
14) The Division of Energy, Mineral and Land Resources is currently reviewing a stormwater management
plan permit application to determine if the proposed project is in compliance with North Carolina's
stormwater management rules. If required, the permittee shall receive a Stormwater Management
Permit, and provide a copy of this permit to DCM, prior to the initiation of any development activities
authorized by this permit. Any violation of the permit approved by the DEMLR shall be considered a
violation of this CAMA permit.
Sedimentation and Erosion Control
15) An Erosion and Sedimentation Control Plan modification will be required for this project. If required,
this plan must be filed at least thirty (30) days prior to the beginning of any land disturbing activity.
Submit this plan to the Division of Energy, Mineral and Land Resources, Land Quality Section, 127
Cardinal Drive Extension, Wilmington, NC 28405.
Showboat Investments LLC.
ADDITIONAL CONDITIONS
Permit No. 4-22
Page 3 of 3
16) In order to protect water quality, runoff from construction shall not visibly increase the amount of
suspended sediments in adjacent waters.
17) Appropriate sedimentation and erosion control devices, measures or structures shall be implemented to
ensure that eroded materials do not enter adjacent wetlands, watercourses or properties.
18) A ground cover sufficient to restrain erosion shall be provided within 30 calendar days of any phase of
grading on cut or filled slopes. At a minimum, a silt fence shall be properly installed immediately
landward of the bulkhead cap immediately following completion of backfilling activities.
General
19) This permit shall -not -be assigned, transferred, sold, or otherwise disposed of to a third party without the
written approval of the Division of Coastal Management.
20) All construction debris associated with the removal or construction of the permitted development shall
be contained within the authorized project area and disposed of in an approved upland location.
21) The permittee and/or his or her contractor shall meet with a representative of the Division prior to
project initiation.
NOTE: This permit does not eliminate the need to obtain any additional state, federal or local permits,
approvals or authorizations that may be required.
NOTE: The U.S. Army Corps of Engineers authorized the project by way of Regional General Permit
197800080 (Action ID SAW-2022-00065).
NOTE: The N.C. Division of Water Resources authorized the proposed project by way Water Quality
Certification No. WQC004602 and assigned the project DWR Project No. 1995-1130 v2.
NOTE: Future development of the pennittee's property may require a modification of this permit.
Contact a representative of the Division at (252) 808-2808 prior to the commencement of any
such activity for this determination. The permittee is further advised that many non -water
dependent activities are not authorized within 30 feet of the normal high-water level.
NOTE: An express application processing fee of $2000 was received by DCM for this project.