HomeMy WebLinkAboutNCC220384_Site Plan or Location Map_20220126ITY MAP - N.T.S.
LEGEND
DIVERSION BERM W/ MATTING
DIVERSION BERM (TYP.)
CONSTRUCTION LIMITS (TYP.)
SILT FENCE (TYP.)
CHECK DAM
I'1,.
-,8 � m
GRAVEL BERM
DOSOO
C18�J O%
REINFORCED SILT FENCE OUTLET
TEMPORARY GRAVEL
CONSTRUCTION ENTRANCE
0000
00
INLET PROTECTION
00000
NOTES:
1. CONTRACTOR SHALL VERIFY THE LOCATIONS OF ALL EXISTING
UTILITIES PRIOR TO BEGINNING CONSTRUCTION.
2. ALL WATER & SEWER MAINS, LATERALS AND
APPURTENANCES SHALL BE TESTED IN ACCORDANCE WITH
HOKE COUNTY AND PWC TECHNICAL SPECIFICATIONS.
3. ALL DUCTILE IRON PIPE, IN SANITARY SEWER SERVICE,
SHALL HAVE GRIFFIN "SEWPER" COAT OR PROTECTO 401
LINING
4. STORMWATER FOR THIS PHASE OF THE MIDLANDS WAS
PREVIOUSLY APPROVED BY NCDENR STORMWATER AS PART OF
BEDFORD PHASE ONE (NC STORMWATER PERMIT #:SW6140202)
TEMPORARY SEDIMENT SKIMMER BASINS
TSSB #1
TSSB #2
DRAINAGE AREA
5.84
1.73
DISTURBED AREA
5.84
1.73
REQUIRED STORAGE VOLUME
10507
3119
REQUIRED SURFACE AREA
5881
1746
AVG. LENGTH
150'
80'
AVG. WIDTH
40'
25'
DEPTH
2.0'
2.0'
ACTUAL SURFACE AREA
6000
2000
ACTUAL STORAGE VOLUME
12000
6000
TOP ELEVATION
97.00
100
EMERGENCY SPILLWAY ELEVATION
95.50
98.50
S.A. ELEVATION
95.50
98.5
BOTTOM ELEVATION
93.50
96.50
SKIMMER SIZE
2.5"
1.5"
SKIMMER ORFICE SIZE (DIAMETER)
1.9"
1.2"
EMERGENCY SPILLWAY WIDTH
12'
12'
Q=CIA (C-0.5, 1=6.2)
18.01
5.37
1, s
REINFORCED ILT
FENCE OUTLET
5DOUBLE ROW
SILT FENCE
REINFORCED SILT
FENCE OUTLET
Id III IIII�III
FUTURE SITE
S %/ x / i S 2 I I I/ ST NU `c�FSCM FOR
REINFORCED��rFENCE OUTLET
JJ iI j au am
APRON
7 DAY STABILIZATION EQ'D
TSSB #2
RIP RAP APRON moo,
°
TDB - "F1"
*7 DAY STABILIZATION REQ'D
/ " I\ / I --,W/ / I
REINFORCED SILT -
FENCE OUTLET
P I
II 1
I
x
II� I
REINFORCED SILT
FENCE OUTLET
I
."1
II
TDB - Cl
*7 DAY STABILIZATION REQ'D oo PI: 12+
Q
CONSTRUCTION
LIMITS (TYP.) 00
+
:7Y I
AROLIN "'
I I D
42 568
I �Q
PI: 14+5 10
39
100
99
99
102
/
C�
FFE 104.25
99
�1p1�
0 /
500'
r
0
TDB - "C2"
W/ TURF MATTING ALONG
TDB-C2 (120 S.Y. MAX) (TYP.) gg-
*7 DAY STABILIZATION REQ'D
� 103 ------40 CAR PARKI a3 A S3(9'X20')
10,0 W covv
'oz
ee�e
II I
_
REINFORCED SILT
FENCE OUTLET
I\1 II 1
� II
II
I � .
1
co
I
I
I
I
1
•
I
I
1I
1
I
e
I
1
I ,
REINFORCED SILT
FENCE OUTLET
II
1
I➢4\
.
`10? I5 0
GROUND STABILIZATION
SITE AREA
STABILIZATION
EXCEPTIONS
DESCRIPTION
TIME FRAME
PERIMETER DIKES,
7 DAYS
NONE
SWALES, DITCHES &
SLOPES
HIGH QUALITY
7 DAYS
NONE
WATER ZONES
(HQW)
SLOPES STEEPER
7 DAYS
IF SLOPES ARE 10'
THAN 3:1
OR LESS IN LENGTH
AND ARE NOT
STEEPER THAN 2:1,
14 DAYS ARE
ALLOWED
SLOPES 3:1 OR
14 DAYS
7 DAYS FOR
FLATTER
SLOPES GREATER
THAN 50' IN LENGTH
ALL OTHER AREAS
14 DAYS
NONE (EXCEPT FOR
WITH SLOPES
PERIMETERS AND
FLATTER THAN 4:1
HQW ZONES)
LEGEND
SURVEYED BOUNDARY LINE
MIN. BLDG. SETBACK LINE
LINES NOT SURVEYED
EASEMENT LINES
- CENTERLINE
FENCE
STORM PIPE
OHE OVERHEAD ELEC. LINE
TREE
WETLANDS
TEMPORARY DIVERSION BERM VELOCITY CALCULATIONS
BERM
SIDE
SLOPES
BOTTOM
WIDTH
MIN. DEPTH
(FT)
AREA (AC)
Q-CUMMULATIVE
VELOCITY
(F/S)
LINING
TDB-A1
3:1- 8:1
1'
1'
1.53 AC
4.743 cfs
2.29
NO
TDB-A2
3:1- 8:1
1'
1'
3.579 AC
11.09 cfs
2.89
YES
TDB-B1
3:1- 8:1
1'
1'
0.535 AC
1.4 cfs
2.33
NO
TDB-C1
3:1- 8:1
1'
1'
.467 AC
1.45 cfs
2.16
NO
TDB-C2
3:1- 8:1
1'
1'
1.459 AC
4.53 cfs
2.89
YES
TDB-E1
3:1- 8:1
1'
1'
1.598 AC
4.95 cfs
2.17
NO
TDB-F1
3:1- 8:1
1'
1'
0.226 AC
0.700 cfs
1.88
NO
LIMITS OF CONSTRUCTION
\ / D
v\ TDB - "B1"
o \ 7 DAY STABILIZATION REQ'D
o \
1
339 0 1 '
I1 Rip Rap d so
\ w
C\
I
1
\� o
1 D: - "A I" GRAVELBERM
DAY STABILIZATION REQ ACROSS R/W (TYP-.)
J__ JQLk
i AA -
/IrVIk_
-
IfJ•J/1! 1nM1WIR-i♦'/��
110NA, "Will
r ♦ �
W = is + do
CONSTRUCTION SCHEDULE
(INITIAL CLEARING, GRUBBING & MASS GRADING)
1. Obtain all permits before beginning construction.
2. Install gravel construction entrances at the locations show, then
install all silt fences around the perimeter of the construction area
and 5 feet off of the wetlands to the west.
3. Construct temporary skimmer basin #20 & #30. Maintain existing
skimmer basin #7.
4. Clear and grub, strip topsoil and construct all diversion berms,
check dams and armor the berms noted on the erosion control
plan with turf reinforcement matting.
5. Continue clearing and grubbing of the site as necessary.
6. Seed and mulch all completed diversion berms within 7 days of
their completion.
7. Continue mass grading the site while maintaining all erosion
control measures and diversion berms during the site's grading.
8. After completion of all site grading, re -spread topsoil, fine grade,
seed and mulch all disturbed area that will not be disturbed with
the subdivision's utility work by providing ground cover within 7
to 14 days per NPDES requirements.
RIPRAP OUTLET PROTECTION
TSSB #1
TSSB #2
PIPE SIZE (do)
4
4
Q
0.12 CFS
0.12 CFS
VELOCITY
2.4 FPS
2.4 FPS
3do
12
12
d50
4'
4'
La (CHART MIN.)
6'
6'
PIPE SIZE (do)
7'
7'
THK.
12"
12"
drawn by
LS
checked
JMK
reviewed JMK
date
SEPT-14-2021
job no.
21-2881-01
z
Z
O
O
Z
U
O
a
z
J
0
W
Z
C)
0
z
fx
A
U)
U
z
Z
Q
z
W
LU
m
�
�
a
�
U
W
�
a
U
r�
N
M
c
0
D
0
c
ILD
O
>
Q
4-1
O
,
ti
co
N
U
Z't
T-
L0
4
00
O
O
O
Co
11
LL
�Lo°_'
FINAL RECORD DOCUMENTS (WATER & SEWER)
� 0
O
O
THESE RECORD DOCUMENTS REPRESENT ACTUAL FIELD
L-
m
In Q)
N
SEWER INVERTS AND MANHOLE RIM ELEVATIONS AFTER
C
C
CONSTRUCTION. THEY ALSO INCLUDE FIELD CHECKED
In
O >, O
DISTANCES BETWEEN MANHOLES. THE REVISED PIPE SLOPES
r
M -C-_
V
ARE BASED ON ACTUAL INVERTS AND FIELD DISTANCES. THE
r
LL 0-
J
PLANS HAVE NOT BEEN REDRAWN TO REFLECT THE ACTUAL
FIELD ELEVATIONS, LOCATIONS OR SLOPES.
THE WATER UTILITIES HAVE BEEN BASED ON INFORMATION
Z
PROVIDED BY OTHERS. THE DESIGN PROFESSIONAL HAS NOT
Q
VERIFIED THE ACCURACY AND/OR COMPLETENESS OF THIS
J
INFORMATION AND SHALL NOT BE RESPONSIBLE FOR ANY
W
ERRORS OR OMISSIONS WHICH MAY BE INCORPORATED
p
HEREIN AS A RESULT.
_
FINAL RECORD DOCUMENTS (STORM)
THIS RECORD DOCUMENT REPRESENTS ACTUAL FIELD
GATHERED INFORMATION CONCERNING THE AS CONSTRUCTED
STORM WATER DRAINAGE SYSTEM. THIS INCLUDES THE STORM
DRAIN INVERTS, GRATE ELEVATIONS AND DISTANCES BETWEEN
N
STRUCTURES. ANY REVISED PIPE SLOPES ON THIS PLAN ARE
BASED ON ACTUAL INVERTS AND FIELD DISTANCES. THIS PLAN
HAS BEEN MODIFIED TO INDICATE THE ACTUAL FIELD
w
GATHERED DATA, BUT HAS NOT BEEN REDRAWN TO REFLECT
z
THE ACTUAL LENGTHS OR ELEVATIONS.
0
"All construction to be in accordance with current
W c o
oC
applicable Hoke County, North Carolina Department of
pp Y p
ZZ
u
C)
O
Transportation (NCDOT) and/or Hoke County Utilities
W 0.Standards
and Specifications. ,
scale
1 "=30'
GRAPHIC SCALE
Field Book No.
-30 0 15 30 60 120
( IN FEET )
1 inch = 30 ft.
SHEET
1 OF 1