HomeMy WebLinkAbout20140168 Ver 1_Application_20140220,�„�
� ��� �
STATE OF NORTH CAROLINA
DEPART'MENT' OF TRANSPORTATTON
PAT L. MCCRORY
GOVERNOR
February 20, 2014
Mr. Steven Kichefski
Asheville Regulatory Field Office
US Army Corps of Engineers
151 Patton Avenue, Room 208
Asheville, North Carolina 28801-5006
ANTHONY J. TATA
SacaeTnxv
SUBJECT: Pipe Replacement, SR 1460 (Berea Chwch Quincy Road), Ale�nder CounTy
Dear Mr. Kichefski:
The North Carolina Department of Transportation requests authorization to replace a failing pipe
on SR 1460 (Berea Quincy Road) in Alexander County. NCDOT proposes to replace the existing
60—foot, 72" CMP with a 70-foot, 84" CMP. The existing pipe is on �5% slope and a shallow
scourhole has formed at the pipe ouUet. The new pipe will ba buried per regulation aY the pipe
inlet; however, due to the slope of the pipe and the scour, the new pipe outlet invert will be placed
at slreambed elevarion and the existing scourhole (� 7 ft long) armored with Class II riprap in an
effort to prevent fiirther stream destabilization. Five feet of riprap will be used uound the pipe
inlet and outlet for sYructure sYabilization. (At the outlet, the riprap stabilizarion impacts will be
within the armored scourhole impacts). Due to the site conditions, NCDOT request a waiver
from the Regional Conditions 2(b)(e) permit depth specificarion for the construction of this
project. Temporary cofferdam/bypass pumping system will be used to divert the stream azound
the conshuction site, as needed. Any areas affected by the temporary cofferdam will be restored
to pre-project conditions.
The scope of the work will result in 22 feet of permanent impacts to an unnamed tributary to the
5outh Yadkin River, which is classiiied as a WS-II Watershed, HQW by the N.C. Water QualiTy
Section.
The project is not located within %z mile of any critical watershed area nor is SR 1460 a rural or
urban arterial; therefore, hazardous spill basins are not required. Enclosed is the hazardous spill
basin checklist. This office has conducted a GIS and field survey for the project for historical
sites and threatened/endangered species sites. No sites listed on the National Register of Historic
Places are located in the vicinity of the project nor did there appear to be any eligible structures.
This office has conducted a GIS and field survey for the project threatened/endangered species.
The federally listed species for Alexander County (USFWS listed date September 22, 2010)
include dwarf-flowered heartleaf (Hexastylis nan�ora) and the bog turtle (Glyptemys
muhdenbergie)-(T/SA- Threatened due to similarity of appearance). National Heritage Prograxn
records document the neazest heartleaf location 72 miles south of the proposed project azea. The
SR 1460, Berea Church Quincy Road
Page 2
February 20,2014
heartleaf is usually found on dry to moist ravine slopes (usually north facing and of the
oak-hickory-pine forest type) and in boggy areas near springheads. There is no suitable
habitat in the proposed project azea and no heartleaf species were observed within the
project footprint. No impaci on tlus species is anticipated. Nataral Heritage Program records
document the nearest bog turtle location 2.0 miles northwest of the proposed project area. Bog
turtles are typically found in bogs, marshes, and wet pastures. T/SA species aze not subject to
Section 7 consultation; however, there is no suitable habitat located within the project azea and no
impact on this species is anticipated.
I have enclosed a pre-construction notificarion for a NW#3, sketches of planned activities and
location maps relative to the project.
Project information for the 401 Automated PaymenY Procedure is as follows:
• Work order number: 150465-55120005-12B.200211-3300
• TII'#: NA
• Project Category: $240.00 Fee
If you haue any questions ar concerns please feel free to contact me at (704) 480-9044. Thank
you for your time and consideration on this matter.
Respectfully yours,
Reuben Chandler, P.E.
Acting Division Engineer
Twelfth Division
BY: ` �
Trish Beam
Division 12 Environmental Supervisor
Enclosures
�a�"�wrFqo
� �r
>- y
O T
Office Use Only:
Corps action ID no.
DWQ project no.
Form Version 1.3 Dec 10 2008
Pre-Construction Noti�cation PCN Form
A. A licant Information
1. Processing
1a. Type(s) of approval sought from the
Corps: � Section 404 Permit ❑ Section 10 Permit
1 b. Specify Nationwide Permit (NWP) number: 3 or General Permit (GP) number:
1c. Has the NWP or GP number been verified by the Corps? ❑ Yes � No
1 d. Type(s) of approval sought from the DWQ (check all that apply):
� 401 Water Quality Certification — Regular ❑ Non-404 Jurisdictional General Permit
❑ 401 Water Quality Certifcation — Express ❑ Riparian Buffer Authorization
1 e. Is this notification solely for the record For the record only for DWQ 401 For the record only for Corps Permit:
because written approval is not required? Certification:
❑ Yes � No ❑ Yes � No
1f. Is payment into a mitigation bank or in-lieu fee program proposed for mitigation � Yes � No
of impacts? If so, attach the acceptance letter from mitigation bank or in-lieu
fee program.
1 g. Is the project located in any of NC's twenty coastal counties. If yes, answer 1 h ❑ Yes � No
below.
1 h. Is the project located within a NC DCM Area of Environmental Concern (AEC)? ❑ Yes � No
2. Project Information
2a. Name of project: Pipe Replacement, SR 1460 (Berea Church Quincy Road)
2b. County: Alexander
2c. Nearest municipality / town: Hiddenite
2d. Subdivision name: NA
2e. NCDOT only, T.I.P. or state NA
project no:
3. Owner Information
3a. Name(s) on Recorded Deed: NCDOT Right of Way
3b. Deed Book and Page No.
3c. Responsible Party (for LLC i f
applicable):
3d. Street address:
3e. City, state, zip:
3f. Telephane no.:
3g. Fax no.:
3h. Email address:
Page 1 of 11
PCN Form — Version 1.3 December 10, 2008 Version
4. Applicant Information (if different from owner)
4a. Applicant is: ❑ Agent ❑ Other, specify:
4b. Name: Reuben Chandler (Acting Division Engineer)
4c. Busines s name N.C. Department of Transportation, Division 12
(if applicable):
4d. Street address: 1710 East Marion Street
4e. City, state, zip: Shelby, NC 28151
4f. Telephone no.: 704-450-9020
4g. Fax no.: 704-480-5401
4h. Email address: rchandler@ncdot.gov
5. AgenUConsultant Information (if applicable)
5a. Name: Trish Beam
Sb. Business name N.C. Department of Transportation, Division 12
(if applicable):
5c. Street address: 1710 East Marion Street
5d. City, state, zip: Shelby, NC 28151
5e. Telephone no.: 704-480-9044
5f. Fax no.: 704-480-5401
5g. Email address: pdbeam@ncdot.gov
Page 2 of 11
PCN Form — Version 1.3 December 10, 2008 Version
B. Project Information and Prior Project History
1. Property Identification
1a. Property identification no. (tax PIN or parcel ID): NA
1 b. Site coordinates (in decimal degrees): Latitude: 35.963003 Longitude: - 81.06113
(DD.DDDDDD) (-DD.DDDDDD)
1 c. Property size: <0.10 acres
2. Surtace Waters
2a. Name of nearest body of water (stream, river, etc.) to UT to South Yadkin River
proposed project:
2b. Water Quality Classification of nearest receiving water: WS II, HQW
2c. River basin: Yadki�
3. Project Description
3a. Describe the existing conditions on the site and the general land use in the vicinity of the project at the time of this
application:
Existing pipe on paved secondary road. Landuse in vicinity of bridge is mostly forested.
3b. List the total estimated acreage of all existing wetlands on the property:
0
3c. List the total estimated linear feet of all existing streams (intermittent and perennial) on the property:
100
3d. Explain the purpose of the proposed project:
To replace a deteriorating pipe for the safety of the traveling public.
3e. Describe the overall project in detail, including the type of equipment to be used:
NCDOT proposes to replace an existing 60 -foot 72" CMP with a 70-foot long, 84" CMP with associated riprap for
structure stabilization. The existing pipe is on —5% slope and a shallow scourhole has formed at the pipe outlet. The new
pipe will be buried per regulation at the pipe inlet; however, due to the slope of the pipe and the scour, the new pipe outlet
invert will be placed at streambed elevation and the existing scourhole armored with Class II riprap in an effort to prevent
further stream destabilization. Riprap will be used around the pipe inlet and outlet for structure stabilization. Typical
construction equipment to be used, backhoes, trackhoes, etc.
4. Jurisdictional Determinations
4a. Have jurisdictional wetland or stream determinations by the
Corps or State been requested or obtained for this property /
project (including all prior phases) in the past? ❑ Yes � No ❑ Unknown
Comments: Jurisdictional stream determination made by
Division 12 DEO.
4b. If the Corps made the jurisdictional determination, what type
of determination was made? ❑ Preliminary ❑ Final
4c. If yes, who delineated the jurisdictional areas? AgencylConsultant Company:
Name (if known): Other:
4d. If yes, list the dates of the Corps jurisdictional determinations or State determinations and attach documentation.
5. Project History
5a. Have permits or certifications been requested or obtained for � Yes � No ❑ Unknown
this project (including all prior phases) in the past?
5b. If yes, explain in detail according to "help file" instructions.
Page 3 of 11
PCN Form — Version 1.3 December 10, 2008 Version
6. Future Project Plans
6a. Is this a phased project? ❑ Yes � No
6b. Ifyes, explain.
Page 4 of 11
PCN Form — Version 1.3 December 10, 2008 Version
C. Proposed Impacts Inventory
1. Impacts Summary
1 a. Which sections were completed below for your project (check all that apply):
❑ Wetlands � Streams - tributaries ❑ Buffers
❑ Open Waters ❑ Pond Construction
2. Wetland Impacts
If there are wetland impacts proposed on the site, then complete this question for each wetland area impacted.
2a. 2b. 2c. 2d. 2e_ 2f.
Wetland impact Type of jurisdiction
number— Type of impact Type of wetland Forested (Corps - 404, 10 Area of impact
Permanent (P) or (if known) DWQ — non-404, other) (acres)
Tem ora T
W1 ❑ P � T ❑ Yes ❑ Corps
❑ No ❑ DWQ
W2 � P � T ❑ Yes ❑ Corps
❑ No ❑ DWQ
W3 ❑ P❑ T ❑ Yes ❑ Corps
❑ No ❑ DWQ
W4 ❑ P❑ T ❑ Yes ❑ Corps
❑ No ❑ DWQ
W5 ❑ P❑ T ❑ Yes ❑ Corps
❑ No ❑ DWQ
W6 ❑ P❑ T ❑ Yes ❑ Corps
❑ No ❑ DWQ
2g. Total wetland impacts
2h. Comments:
3. Stream Impacts
If there are perennial or intermittent stream impacts (including temporary impacts) proposed on the site, then complete this
question for all stream sites impacted.
3a. 3 b. 3c. 3 d. 3e. 3f. 3g.
Stream impact Type of impact Stream name Perennial Type of jurisdiction Average Impact
number - (PER) or (Corps - 404, 10 stream length
Permanent (P) or intermittent DWQ — non-404, width (linear
Temporary (T) (INT)? other) (feet) feet)
S1 � P❑ T Increase in pipe Ut to South Yadkin � PER � Corps 5 `10
length River ❑ INT � DWQ
Armoured Ut to South Yadkin � PER � Corps
S2 � P� T scourhole/Riprap River 5 *12
Stabilization ❑ INT � DWQ
Pumping system Ut to South Yadkin � PER ❑ Corps
S3 ❑ P� T for stream 5 40
management River ❑ INT ❑ DWQ
S4 ❑ P❑ T ❑ PER ❑ Corps
❑ INT ❑ DWQ
SS ❑ P � T ❑ PER ❑ Corps
❑ INT ❑ DWQ
S6 ❑ P❑ T ❑ PER ❑ Corps
❑ INT ❑ DWQ
3h. Total stream a�d tributary impacts *22
3i. Comments: *Permanent Impacts: Existing pipe = 60 feet, Proposed Pipe = 70 feet, Armoured Scourhole = 7 feet; Riprap
on streambank at inlet and outlet = 10 feet (impacts at outlet in the same area as the armoured scourhole impacts.
Page 5 of 11
PCN Form — Version 1.3 December 10, 2008 Version
4. Open Water Impacts
If there are proposed impacts to lakes, ponds, estuaries, tributaries, sounds, the Atlantic Ocean, or any other open water of
the U.S. then individually list all open water impacts below.
4a. 4b. 4c. 4d. 4e.
Open water Name of waterbody
impact number — (if applicable) Type of impact Waterbody type Area of impact (acres)
Permanent (P) or
Tem orar T
01 ❑P❑T
02 ❑P❑T
03 ❑P❑T
04 ❑P❑T
4£ Total open water impacts
4g. Comments:
5. Pond or Lake Construction
If ond or lake construction ro osed, then com lete the chart below.
5a. 5b. 5c. Sd. 5e.
Wetland Impacts (acres) Stream Impacts (feet) Upland
Pond ID Proposed use or purpose (acres)
number of pond
Flooded Filled Excavated Flooded Filled Excavated Flooded
P1
P2
Sf. Total
5g. Comments:
5h. Is a dam high hazard permit required?
❑ Yes ❑ No If yes, permit ID no:
5i. Expected pond surface area (acres):
Sj. Size of pond watershed (acres):
5k. Method of construction:
6. Buffer Impacts (for DWQ)
If project will impact a protected riparian buffer, then complete the chart below. If yes, then individually list all buffer impacts
below. If an im acts re uire miti ation, then ou MUST fill out Section D of this form.
6a.
❑ Neuse ❑ Tar-Pamlico ❑ Other:
Project is in which protected basin? ❑ Catawba ❑ Randleman
6b. 6c. 6d. 6e. 6f. 6g.
Buffer impact
number— Reason Buffer Zone 1 impact Zone 2 impact
Permanent (P) or for Stream name mitigation (square feet) (square feet)
Tem orar T im act re uired?
B1 ❑P❑T ❑Yes
❑ No
B2 ❑P�T ❑Yes
❑ No
B3 ❑P❑T ❑Yes
❑ No
6h. Total buffer impacts
6i. Comments:
Page 6 of 11
PCN Form — Version 1.3 December 10, 2008 Version
D. Impact Justification and Mitigation
1. Avoidance and Minimization
1 a. Specifically describe measures taken to avoid or minimize the proposed impacts in designing project.
Existing scourhole to be armored to prevent further stream destabilization.
1 b. Specifically describe measures taken to avoid or minimize the proposed impacts through construction techniques.
2. Compensatory Mitigation for Impacts to Waters of the U.S. or Waters of the State
2a. Does the project require Compensatory Mitigation for ❑ Yes � No
impacts to Waters of the U.S. or Waters of the State?
26. If yes, mitigation is required by (check all that apply): ❑ DWQ ❑ Corps
❑ Mitigation bank
2c. If yes, which mitigat ion option will be used for this
project? ❑ Payment to in-lieu fee program
❑ Permittee Respo�sible Mitigation
3. Complete if Using a Mitigation Bank
3a. Name of Mitigation Bank:
3b. Credits Purchased (attach receipt and letter) Type Quantity
3c. Comments:
4. Complete if Making a Payment to In-lieu Fee Program
4a. Approval letter from in-lieu fee program is attached. ❑ Yes
4b. Stream mitigation requested: linear feet
4c. If using stream mitigation, stream temperature: ❑ warm ❑ cool ❑cold
4d. Buffer mitigation requested (DWQ only): square feet
4e. Riparian wetland mitigation requested: acres
4f. Non-riparian wetland mitigation requested: acres
4g. Coastal (tidal) wetland mitigation requested: acres
4h. Comments:
5. Complete if Using a Permittee Responsible Mitigation Plan
5a. If using a permittee responsible mitigation plan, provide a description of the proposed mitigation plan.
Page 7 of 11
PCN Form — Version 1.3 December 10, 2008 Version
6. Buffer Mitigation (State Regulated Riparian Buffer Rules) — required by DWQ
6a. Will the project result in an impact within a protected riparian buffer that requires ❑ Yes � No
buffer mitigation?
6b. If yes, then identify the square feet of impact to each zone of the riparian buffer that requires mitigation. Calculate the
amount of mitigation required.
6c. 6d. 6e.
Zone Reason for impact Total impact Multiplier Required mitigation
(square feet) (square feet)
Zone 1 3(2 for Catawba)
Zone 2 1.5
6f. Total buffer mitigation required:
6g. If buffer mitigation is required, discuss what type of mitigation is proposed (e.g., payment to private mitigation bank,
permittee responsible riparian buffer restoration, payment into an approved in-lieu fee fund).
6h. Comments:
Page 8 of 11
PCN Form — Version 1.3 December 10, 2008 Version
E. Stormwater Management and Diffuse Flow Plan (required by DWQ)
1. Diffuse Flow Plan
1 a. Does the project include or is it adjacent to protected riparian buffers identifed � Yes � No
within one of the NC Riparian Buffer Protection Rules?
1 b. If yes, then is a diffuse flow plan included? If no, explain why.
Comments: ❑ Yes ❑ No
2. Stormwater Mana ement Plan
2a. What is the overall percent imperviousness of this project? 0%
2b. Does this project require a Stormwater Management Plan? ❑ Yes � No
2c. If this project DOES NOT require a Stormwater Management Plan, explain why: Complies with NCDOT's individual
NPDES permit NCS000250.
2d. If this project DOES require a Stormwater Management Plan, then provide a brief, narrative description of the plan:
❑ Certified Local Government
2e. Who will be responsible for the review of the Stormwater Management Plan? ❑ DWQ Stormwater Program
❑ DWQ 401 Unit
3. Certified Local Government Stormwater Review
3a. In which local government's jurisdiction is this project? NA
❑ Phase II
3b. Which of the following locally-implemented stormwater management programs � NSW
apply (check all that apply): ❑ USMP
❑ Water Supply Watershed
❑ Other:
3c. Has the approved Stormwater Management Plan with proof of approval been ❑ Yes ❑ No
attached?
4. DWQ Stormwater Pro ram Review
❑ Coastal countfes
❑ HQW
4a. Which of the following state-implemented stormwater management programs apply � ORW
(check all that apply): ❑ Session Law 2006-246
❑ Other:
4b. Has the approved Stormwater Management Plan with proof of approval been
attached? ❑ Yes ❑ No
5. DWQ 401 Unit Stormwater Review
5a. Does the Stormwater Management Plan meet the appropriate requirements? ❑ Yes ❑ No
Sb. Have all of the 401 Unit submittal requirements been met? ❑ Yes ❑ No
Page 9 of 11
PCN Form — Version 1.3 December 10, 2008 Version
F. Supplementary Information
1. Environmental Documentation (DWQ Requirement)
1 a. Does the project involve an expenditure of public (federal/state/local) funds or the � yes ❑ No
use of public (federal/state) land?
1 b. If you answered "yes" to the above, does the project require preparation of an
environmental document pursuant to the requirements of the National or State ❑ Yes � No
(North Carolina) Environmental Policy Act (NEPA/SEPA)?
1 c. If you answered "yes" to the above, has the document review been finalized by the
State Clearing House? (If so, attach a copy of the NEPA or SEPA final approval
letter.) ❑ Yes ❑ No
Camments:
2. Violations (DWQ Requirement)
2a. Is the site in violation of DWQ Wetland Rules (15A NCAC 2H .0500), Isolated
Wetland Rules (15A NCAC 2H .1300), DWQ Surface Water or Wetland Standards, ❑ Yes � No
or Riparian Buffer Rules (15A NCAC 2B .0200)?
2b. Is this an after-the-fact permit application? ❑ Yes � No
2c. If you answered "yes" to one or both of the above questions, provide an explanation of the violation(s):
3. Cumulative Impacts (DWQ Requirement)
3a. Will this project (based on past and reasonably anticipated future impacts) result in � yes � No
additional development, which could impact nearby downstream water quality?
3b. If you answered "yes" to the above, submit a qualitative or quantitative cumulative impact anatysis in accordance with the
most recent DWQ policy. If you answered "no," provide a short narrative description.
The project is classified as a minimum criteria checklist project which has low potential for cumulativelindirect impacts and
will not result in additional development which could impact water quality.
4. Sewage Disposal (DWQ Requirement)
4a. Clearly detail the ultimate treatment methods and disposition (non-discharge or discharge) of wastewater generated from
the proposed project, or available capacity of the subject facility.
No wastewater generated from project.
Page 10 of 11
PCN Form — Version 1.3 December 10, 2008 Version
5. Endangered Species and Designated Critical Habitat (Corps Requirement)
5a. Will this project occur in or near an area with federally protected species or � Yes � No
habitat?
Sb. Have you checked with the USFWS concerning Endangered Species Act � yes � No
impacts?
❑ Raleigh
Sc. If yes, ind icate the USFWS Field Office you have contacted.
❑ Asheville
Sd. What data sources did you use to determine whether your site would impact Endangered Species or Designated Critical
Habitat?
NC Natural Heritage Program database.
6. Essential Fish Habitat (Corps Requirement)
6a. Will this project occur in or near an area designated as essential fish habitat? ❑ Yes � No
6b. What data sources did you use to determine whether your site would impact Essential Fish Habitat?
No salt marshes, oyster reefs, or seagrass beds in the vicinity of the project.
7. Historic or Prehistoric Cultural Resources (Corps Requirement)
7a. Will this project occur in or near an area that the state, federal or tribal
governments have designated as having historic or cultural preservation � yes � No
status (e.g., National Historic Trust designation or properties signifcant in
North Carolina history and archaeology)?
7b. What data sources did you use to determine whether your site would impact historic or archeological resources?
The National Register of Historic Places were reviewed for historic sites in the vicinity of the project; however, the pipe
replacement project occurs within a previously impacted area (NC DOT Right of Way).
8. Flood Zone Designation (Corps Requirement)
8a. Will this project occur in a FEMA-designated 100-year floodplain? ❑ Yes � No
8b. If yes, explain how project meets FEMA requirements:
8c. What source(s) did you use to make the floodplain determination? FEMA FIRM panal number: 3710386000E
/7 �a//�- /L ��-�-� '� a a� -�Y
j9c�:�q D�v,'s�o�...�t���--
ApplicanUk§enPs Printed Name ApplicanUAgenYs Signature Date
(Agenfs signature is valid only'rf an authorization letter from the applicant
is rovided.
Page 11 of 11
PCN Form — Version 1.3 December 10, 2008 Version
Z ((1 l0
� p � �
c
H � n �
�' O s C
N i z
n �
Y y S 7p
= m p i
'm x c
� � 3 �
� N �G 3
��p�
ao g �
a
30
�u
'n3
Rj�
`3m
s'°
3
W f�
'7 N
a{
� S
�v
� <.
A
-31- Z
3 �
v
� O
� �
N
� N
e
a
uo�meom
00
m�
n
m
�p
�N �
N N
p0
� r
ao
N�
N
j T P
o �
00
s m ��(
� l.J
Q
w ,j
J �
o Y I
n 1O
C C
R i O
+ �
�
'c a
2 R
N �
A O
A o
N
N �
A '
b
A
�
N
A
�
u
�
9m
:y
4J
FN
09
nx
'no
a£
_ A�
O
o�
ve
mP
�n
m�
2H
2H
20
�r
��'o
O�
cN
o A
s
�
Bereu Church Quincy Rd
Nail sei centerline of Roud
approx. 120' fram ihe centerline
of ihe Rood and culvert
Assumed Nail Elev 100.0
�x
F Y
c�
o N
V n
N 3
P �
3g
rvs
n
Ea
�
i ?�
�a
= A
P -
2 h
o �
—x
V
O
, �
�
�im
sn�
�o 0
N�
o � �^
Oo�
�3 m
OjN
µ�N
��O
3 P
3P
N �
a�
w�
<.
ryP
NN
SR 1460
�
I`
A
nm "'3
c a�
0
A DNa
apOP
o �nrv±
rt
y�P�
3 y -i
1n�
3 no
N�
S
1p O
�
o �^
s�
�'3
m
o m
aa
o°
-�! �
9
N�
ya
no
�a
�
3�a
6�3
>;�
°n3
p��
N O O
�Np_
t0 � O
v: '
o- E.
P �
nv�
'�^�v
c z�
-P�
�mm
~3 N�
O10 3
NOQ
C
dO N
m n
nm o
Pipe Replacement
Berea Church Quency Road, SR 1460
Vicinity Map
�� NaRTry eq 9
Q4 �Po~
q z`I
,,,�����
I
I
0.75 1.5
3 Miles
NCDOT
HA7ARDOUS SPILL BASIN CHECKLIST
Division: 1 �. County: AlPxandPr Project ID: 12B.2002ll
River Basin: Yadkin Bridge No: NA
Route: Pipe Replacement on SR 1460 (Berea Church Ouencv Road�
Stream: UT to South Yadkin River (WS-II HQW)
Water Ouality Criteria:
Stream Crossing Blue Line On USGS
ORW
WSI
WS II,III OR IV, Crossing Within O.Smi of W.S. Critical Area
Roadway Criteria:
Route Designation-
Arterial Urban
Arterial Rural
Additional Site Information:
Is a Hazardous Spill Basin Required?
Yes No
� �
!" Ci
Yes No
� �
Criteria Based Upon NCDOT "Best Management Practices for the
Protection of Surface Waters" (March, 1997).
Yes No
� �
C" �
i �
� �